CN208872285U - A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM - Google Patents

A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM Download PDF

Info

Publication number
CN208872285U
CN208872285U CN201821189637.XU CN201821189637U CN208872285U CN 208872285 U CN208872285 U CN 208872285U CN 201821189637 U CN201821189637 U CN 201821189637U CN 208872285 U CN208872285 U CN 208872285U
Authority
CN
China
Prior art keywords
displacement meter
impervious body
monitoring
earth
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821189637.XU
Other languages
Chinese (zh)
Inventor
张晨亮
王永晖
崔海波
耿贵彪
刘海宇
季祥
刘士佳
夏天倚
葛鹏
张怀远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Beijing Engineering Corp Ltd
Original Assignee
PowerChina Beijing Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Beijing Engineering Corp Ltd filed Critical PowerChina Beijing Engineering Corp Ltd
Priority to CN201821189637.XU priority Critical patent/CN208872285U/en
Application granted granted Critical
Publication of CN208872285U publication Critical patent/CN208872285U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The utility model discloses a kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEMs, including monitoring criteria, flexible displacement meter, pillar, data acquisition device, monitoring criteria are arranged in the metastable impervious body pedestal/basement rock in earth and rockfill dam impervious body bottom end, flexible displacement meter bottom is fixed in monitoring criteria, pillar is cased on the outside of flexible displacement meters more than monitoring criteria, pillar is continuously bonded or close to being placed in impervious body downstream face, make the deformation synchronous with impervious body of flexible displacement meter, flexible displacement meter top is connected on the data acquisition device that dam crest is arranged in.The utility model fundamentally solves the problems, such as that the monitoring data representativeness of earth and rockfill dam impervious body deformation routine monitoring method is poor, precision is low, compared with routine monitoring method, Embedded installation is quality controllable, observation workload is small, high degree of automation, and realizes impervious body 3 d deformation monitoring.

Description

A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM
Technical field
The utility model relates to monitoring of hydraulic engineering field more particularly to a kind of earth and rockfill dam impervious body deformation monitoring systems System.
Background technique
Earth and rockfill dam impervious body plays water blocking antiseep, and impervious body deforms excessive or deformation, impervious body can be made to produce Raw harmfulness crack leads to seepage prevention system defect, to generate seepage abnormality, will cause seepage flow accident when serious;Ministry of Water Resources was once More of whole nation large reservoir accident is arranged, discovery seepage flow accident accounts for 31.7%, therefore impervious body deformation is important monitoring item Mesh.Impervious body deformation is substantially carried out Deflection deformation inspection, when impervious body is the flexible materials core-walls such as soil property or bituminous concrete, It also will do it compressive deformation monitoring.
For impervious body Deflection deformation inspection, inclinometer pipe is buried usually near impervious body, using movable type inclinometer people Work observation or built-in stationary slope level automatic Observation, this monitoring method have following defect: 1. survey line is represented far from impervious body Property is poor.Since impervious body surface is not generally plane, and impervious body in principle cannot be occupied and penetrates, and inclinometer pipe is usual It can not be bent, survey line is approximately straight line, therefore inclinometer pipe is difficult to be bonded impervious body, and survey line is representative poor.2. surveying Inclined tube guide groove is stringent towards requiring, and embedded quality is difficult to ensure.For obtain panel deflection deformation, need to make inclinometer pipe guide groove line with Deflection deformation direction is consistent, otherwise can bring measurement error, and this point is not easily achieved during earth and rockfill dam roller compaction construction, and Inclinometer pipe longer guide groove torsion possibility is bigger, is influenced also bigger, measurement error amendment trouble by reversing when observation.3. artificial Observation process is cumbersome, heavy workload.Relatively multi-measuring point can be set in artificial observation, reduces sag curve error of fitting, but Measuring point quantity is directly proportional to workload, and often in hours, and observation process is cumbersome, inefficient.4. fixing inclinometer in pipe certainly When in-motion viewing is surveyed, measuring point limited amount, observing buoy error is larger, and complex installation process, risk are larger.Every fixed survey in pipe Oblique instrument needs to draw a cable, manages interior narrow space and limits measuring point quantity, general measuring point spacing is 5~10m, sag curve Upper data are discontinuous, connected between inclinometer by flexible member, and the sag curve between two o'clock is generated by fitting, error compared with Greatly;The mechanical fastener quantity for needing to assemble in inclinometer installation process is more, once falling into hole in installation process, is then difficult to It salvages and becomes useless hole.5. can not achieve three-dimensional automatic monitoring.Inclinometer pipe can only carry out the deformation monitoring of its vertical axis direction, To monitor axial deformation, then housing detection punctuate is needed such as to settle magnet ring, it can only be using movable type inclinometer and movable heavy Instrument artificial measurement respectively is dropped, if survey line is smaller with horizontal sextant angle, manual measurement mode is also difficult to carry out.
Utility model content
Technical problem to be solved by the utility model is to provide a kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEMs, whole Succinctly, it is not take up, do not weaken antiseepage phosphor bodies, be bonded or disposed close to impervious body, outlet is simple, and measuring point continuously divides on survey line Cloth can represent impervious body deformation;Quality is easy to control when the monitoring device implements embedded, the data acquisition of monitoring method and Treatment process is not necessarily to manual intervention, high degree of automation, and it is bent can to obtain continuous modification that represent impervious body deformation, high-precision Line realizes impervious body 3 d deformation monitoring.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is: a kind of earth and rockfill dam impervious body deformation Monitoring system, including monitoring criteria, flexible displacement meter, pillar, data acquisition device, monitoring criteria are arranged in earth and rockfill dam impervious body In the metastable impervious body pedestal/basement rock in bottom end, flexible displacement meter bottom is fixed in monitoring criteria, more than monitoring criteria It is cased with pillar on the outside of flexible displacement meter, pillar is continuously bonded or close to impervious body downstream face is placed in, and makes flexible displacement meter and prevents The synchronous deformation of body is seeped, flexible displacement meter top is connected on the data acquisition device that dam crest is arranged in.
The effective aperture of drilling or preformed hole in the monitoring criteria, drilling or preformed hole is greater than flexible displacement meter outer diameter, 70~90mm of aperture, effective hole depth are 1~2m, the fixed flexible displacement meter of injection cement mortar in drilling or preformed hole.
The flexibility displacement meter uses array displacement meter or various dimensions deformation measurement sensor.
The flexibility displacement meter measurement end carries a cable, in cable connection to data acquisition device.
The pillar and flexible displacement meter are mating, and pillar internal diameter is greater than flexible displacement meter 2~4mm of outer diameter, pillar be with Flexible, PE, PVC of inner wall smooth or PPR pipe.
A kind of earth and rockfill dam impervious body deformation monitoring method, comprising the following steps:
(1) in the metastable impervious body pedestal/basement rock internal drilling in earth and rockfill dam impervious body bottom end or preformed hole, by flexible position It moves meter bottom direct-burried and is fixedly arranged at formation monitoring criteria in hole;
(2) flexible displacement meter more than monitoring criteria, housing pillar are continuously bonded or close to being placed in impervious body downstream face, It is allowed to deformation synchronous with impervious body;
(3) flexible displacement meter measurement end cable is connected to data acquisition device, by data acquisition device and mating soft Part obtains impervious body in a manner of wired automatic collection existingly or now wireless automatic collecting or remote automatic acquisition automatically 3 D deformation data are simultaneously handled.
The fitting or close to being placed in impervious body downstream face, it is desirable that be not take up antiseepage phosphor bodies and as close to antiseepage The placement of body downstream face: it for reinforced concrete face rockfill dam, is bonded panel and is placed in panel base mat layered material surface;For drip Green concrete face rockfill dam is placed in the shallow slot on panel base mat layered material surface layer close to panel, keep certain safety away from From avoiding high temperature from damaging flexible displacement meter;For core wall dam, it is bonded core-wall and is placed in core-wall and downstream transition material junction.
The effective aperture of drilling or preformed hole is greater than 70~90mm of flexible displacement meter outer diameter, effective hole in the monitoring criteria Depth is 1~2m, the fixed flexible displacement meter of injection cement mortar in drilling or preformed hole.
The flexibility displacement meter uses array displacement meter or various dimensions deformation measurement sensor, flexible displacement meter measurement end A cable is carried, in cable connection to data acquisition device.
The pillar and flexible displacement meter are mating, and pillar internal diameter is greater than flexible displacement meter 2~4mm of outer diameter, pillar be with Flexible, PE, PVC of inner wall smooth or PPR pipe.
The beneficial effects of the utility model are: survey line can be bonded or dispose close to impervious body, deformation synchronous with impervious body, Fundamentally solve the problems, such as that routine monitoring means are representative poor;Flexible displacement meter is continuously distributed on survey line, can obtain The monitoring data of continuous point, essentially eliminate the error of fitting between point, further improve impervious body deformation curve Representative and precision;When monitoring system implements embedded, towards being easy to control, outlet is simple, and embedded quality is easy to control;The prison Survey method high degree of automation, data acquisition and processing (DAP) process are not necessarily to manual intervention, improve observed efficiency, avoid artificial mistake Difference;Realize impervious body 3 d deformation monitoring;It is not take up, do not weaken antiseepage phosphor bodies, it is logical that seepage flow will not be formed inside impervious body Road brings security risk to antiseepage main body.
Detailed description of the invention
Fig. 1 is the panel dam type drawing in side sectional elevation of the utility model earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM.
Fig. 2 is the core-wall dam type drawing in side sectional elevation of the utility model earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM.
In figure, 1 --- impervious body (asphaltic concrete core wall/panel);2 --- impervious body pedestal/basement rock;3 --- it is flexible Displacement meter;4 --- pillar;5 --- monitoring criteria;6 --- cable;7 --- data acquisition device;8 --- one area of transition zone; 9 --- 2nd area of transition zone;10 --- upstream enrockment;11 --- downstream enrockment;12 --- blotter;13 --- transition zone; 14 --- main enrockment.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, now the utility model is carried out It is further described.It should be appreciated that the specific embodiments described herein are only used to explain the utility model, and do not have to In restriction the utility model.
As shown in Figure 1, 2, the earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM of the utility model, including monitoring criteria 5, flexible position Meter 3, pillar 4, data acquisition device 7 are moved, monitoring criteria 5 are arranged in the metastable impervious body base in earth and rockfill dam impervious body bottom end In seat/basement rock 2, flexible 3 bottom of displacement meter is fixed in monitoring criteria 5, is cased on the outside of flexible displacement meters 3 more than monitoring criteria Pillar 4, pillar 4 are continuously bonded or close to 1 downstream face of impervious body are placed in, and make the deformation synchronous with impervious body 1 of flexible displacement meter 3, Flexible 3 top of displacement meter is connected on the data acquisition device 7 that dam crest is arranged in.
The effective aperture of drilling or preformed hole in the monitoring criteria 5, drilling or preformed hole is greater than 3 outer diameter of flexible displacement meter 70~90mm, effective hole depth are 1~2m, the fixed flexible displacement meter 2 of injection cement mortar in drilling or preformed hole.
The flexibility displacement meter 2 uses array displacement meter or various dimensions deformation measurement sensor.
Flexibility 2 measurement end of displacement meter carries a cable 6, and cable 6 is connected on data acquisition device 7.
The pillar 4 and flexible displacement meter 3 are mating, and 4 internal diameter of pillar is greater than 3 2~4mm of outer diameter of flexible displacement meter, and pillar 4 is With flexible, PE, PVC of inner wall smooth or PPR pipe.
In figure, 12 --- blotter;13 --- transition zone;14 --- main enrockment.
A kind of earth and rockfill dam impervious body deformation monitoring method, comprising the following steps:
(1) in the metastable impervious body pedestal/basement rock internal drilling in earth and rockfill dam impervious body bottom end or preformed hole, by flexible position It moves meter bottom direct-burried and is fixedly arranged at formation monitoring criteria in hole;
(2) flexible displacement meter more than monitoring criteria, housing pillar are continuously bonded or close to being placed in impervious body downstream face, It is allowed to deformation synchronous with impervious body;
(3) flexible displacement meter measurement end cable is connected to data acquisition device, by data acquisition device and mating soft Part obtains impervious body in a manner of wired automatic collection existingly or now wireless automatic collecting or remote automatic acquisition automatically 3 D deformation data are simultaneously handled.
The fitting or close to being placed in impervious body downstream face, it is desirable that be not take up antiseepage phosphor bodies and as close to antiseepage The placement of body downstream face: it for reinforced concrete face rockfill dam, is bonded panel and is placed in panel base mat layered material surface;For drip Green concrete face rockfill dam is placed in the shallow slot on panel base mat layered material surface layer close to panel, keep certain safety away from From avoiding high temperature from damaging flexible displacement meter;For core wall dam, it is bonded core-wall and is placed in core-wall and downstream transition material junction.
Specifically, fitting or close to being placed in impervious body downstream face, it is desirable that be not take up antiseepage phosphor bodies and lean on as far as possible Nearly impervious body downstream face placement: 1. for reinforced concrete face rockfill dam, after the completion of dam slope blotter rolls, panel is poured Before building, selects a good opportunity and monitoring criteria are set in toe board or toe slab downstream basement rock, it is outer along monitoring section laying on base mat layered material surface The flexible displacement meter for covering pillar, pours fitting with panel and is placed in panel bottom surface;2. being needed for bitumen concrete faced rockfill dam Flexible displacement meter and panel are kept into certain safe distance, high temperature is avoided to damage sensor, is specifically ground in dam slope blotter It after the completion of pressure, before panel pours, selects a good opportunity and monitoring criteria is set in the basement rock of panel bottom, on panel base mat layered material surface layer along prison Section excavation shallow slot is surveyed, then the flexible displacement meter of housing pillar is placed in shallow slot bottom depending on field test by groove depth, Simultaneously manual compaction pours with panel close to panel bottom surface and pacifies to dam standard is filled out backfill maximum particle diameter≤50mm graded broken stone material It sets;3. fitting core-wall is placed in core-wall and downstream transition material junction for core wall dam.It specifically can be in current layer core-wall and dam body Before expecting rolling and placement, flexible displacement meter is carried out into protection in the trench and is backfilled, safeguard measure and groove depth are to guarantee to avoid Roller compaction construction and pitch core-wall high temperature damage sensor;After the completion of current layer rolling and placement, flexible displacement meter is carefully dug out, is pasted It closes core-wall and disposes flexible displacement meter, and remaining flexible displacement meter is carried out into protection in the trench again and is backfilled, next layer of repetition A upper layer operation, until dam crest.
Specifically combine example in detail:
As shown in Fig. 2, certain big (2) type Hydropower Project, water retaining structure is rockfill dam with asphalt concrete core, and dam crest is long 219.85m, the wide 15.0m of dam crest, riverbed position maximum height of dam 164.2m, asphaltic concrete core wall maximum height 132.0m, need pair Asphaltic concrete core wall deformation is monitored.This engineering rock-fill dams core-wall bottom is enlarged structure, conventional inclinometer pipe monitoring mode It needs vertically to bury other than enlarged structure, so that survey line is apart from 0.5~0.9m of core-wall surface, in addition inclinometer pipe is routinely embedded square Formula needs to avoid core wall construction mechanical influence, away from 1.5~2m of core-wall bury, due to remote apart from core-wall, inclinometer pipe measure The only deformation in one area of transition zone, can not represent the deformation of core-wall;In addition survey line is up to 132m, and guide groove installation easily twists And deformation, inclinometer pipe are buried quality and are difficult to ensure, using inefficiency when artificial observation, if installation stationary slope level carries out certainly Dynamic monitoring, by interval, 5m is arranged based on 1 measuring point, needs to draw 27 cables, and 16 cables have rule of thumb been drawn in pipe very It is difficult;In terms of survey line representativeness and expected implementation result, conventional inclinometer pipe monitoring method is not suitable for the engineering core-wall deformation monitoring. In order to realize the engineering core-wall deformation monitoring, earth and rockfill dam impervious body deformation monitoring device described in the utility model and side are used Method.The specific implementation process is as follows:
The flexible displacement meter 3 of monitoring device selects array displacement meter, and length is according to the monitoring position bituminous concrete heart The customization of 1 downstream surface survey line length of wall, an included cable 6 can lead to dam crest monitoring station nearby;Pillar 4 uses internal diameter Φ 27mm Flexible PVC pipe, pillar do not constrain array displacement meter and slides in pipe.
Monitoring criteria 5 are arranged on the impervious body pedestal 2 of asphaltic concrete core wall bottom, specifically in asphaltic concrete core wall Vertical hole is bored in the downstream side of bottom enlarged structure on impervious body pedestal after positioning, aperture is Φ 76mm, and effective hole depth is not less than 1.0m uses steel deck-plate closed orifices after the completion of drilling.When asphaltic concrete core wall and one area of downstream transition floor, 8 reclamation level are super When crossing impervious body pedestal about 0.75m, digs out aperture steel deck-plate and open, micro-expansion cement mortar is filled in hole, it will be without shield In the 1m array displacement meter tripping in hole of pipe and fixed, after cement mortar consolidation, hole inner segment displacement meter is as the bituminous concrete heart The monitoring criteria of wall deformation.
The array displacement meter with pillar of the above fitting asphaltic concrete core wall downstream surface placement 50cm long of drilling, and In asphaltic concrete core wall downstream side, vertically roam all around the would is tested through scene temperature to groove is excavated and uses depth 25cm groove, length It paves boundary of works area 1m or more beyond paver downstream side lower hopper, remaining array displacement meter band pillar is laid in slot, And protected using channel steel, so that array displacement meter is not subject to crushing and will not be damaged by asphaltic concrete core wall high temperature.
After carrying out safeguard measure, continue the construction in one area of asphaltic concrete core wall and transition zone.When lifting height reaches To after 50cm or 100cm (the about integral multiple of array displacement meter single-unit length), array displacement meter is carefully dug out, continues to paste The array displacement meter with pillar for closing asphaltic concrete core wall downstream surface placement 50cm or 100cm long backfills groove to working as 25cm below preceding reclamation level simultaneously is compacted reach to fill out dam standard, and remaining array displacement meter band pillar is laid in slot, and is adopted It is protected with channel steel, is then backfilled to current reclamation level.This step is repeated until asphaltic concrete core wall crest level.In figure, 9 --- 2nd area of transition zone;10 --- upstream enrockment;11 --- downstream enrockment.
Array displacement meter is led to monitoring station when dam crest structure is formed to top by dam filing nearby.Data acquisition uses Array displacement meter is connected directly to installation SAAsuite especially by SAAUSB converter by now wired the automatic data collection mode The laptop of software, automatic collection core-wall 3 D deformation data are simultaneously handled.In addition it is provided with SAA232 converter, with side Just engineering monitoring automated system is accessed.
Above-mentioned technical proposal disclosed by the utility model has obtained as follows mixing the utility model has the advantages that solving the high pitch of the engineering The deformation monitoring problem of solidifying soil core wall dam core-wall, obtains the high precision monitor data of continuous point, Monitoring Result representativeness is good; Compared with routine monitoring method, the technical difficulty of Embedded installation is reduced, Embedded installation quality is guaranteed;Realize core-wall 3 d deformation monitoring, and the automatic collection and processing of monitoring data are realized, observation workload is greatly reduced, improves observation Efficiency avoids artificial observation error.
Embodiment described above is merely to illustrate the technical idea and feature of the utility model, and its object is to make ability Technical staff in domain, cannot be only practical to limit with the present embodiment it will be appreciated that the content of the utility model and implement accordingly Novel the scope of the patents, i.e., same changes or modifications made by the revealed spirit of all the utility model, it is practical new still to fall in this In the scope of the patents of type.

Claims (5)

1. a kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM, which is characterized in that including monitoring criteria (5), flexible displacement meter (3), Pillar (4), data acquisition device (7), monitoring criteria (5) are arranged in the metastable impervious body base in earth and rockfill dam impervious body bottom end In seat/basement rock (2), flexible displacement meter (3) bottom is fixed on monitoring criteria (5), flexible displacement meters (3) more than monitoring criteria Outside is cased with pillar (4), pillar (4) continuously fitting or close to impervious body (1) downstream face is placed in, make flexible displacement meter (3) with The synchronous deformation of impervious body (1), flexible displacement meter (3) top is connected on the data acquisition device (7) that dam crest is arranged in.
2. earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM according to claim 1, which is characterized in that on the monitoring criteria (5) The effective aperture of drilling or preformed hole, drilling or preformed hole is greater than flexible displacement meter (3) outer diameter, 70~90mm of aperture, effective hole Depth is 1~2m, the fixed flexible displacement meter (3) of injection cement mortar in drilling or preformed hole.
3. earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM according to claim 1, which is characterized in that the flexibility displacement meter (3) Using array displacement meter or various dimensions deformation measurement sensor.
4. earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM according to claim 1, which is characterized in that the flexibility displacement meter (3) Measurement end carries a cable (6), and cable (6) is connected on data acquisition device (7).
5. earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM according to claim 1, which is characterized in that the pillar (4) and flexibility Displacement meter (3) is mating, and pillar (4) internal diameter is greater than flexibility displacement meter (3) 2~4mm of outer diameter, and pillar (4) is with flexible, inner wall light Sliding PE, PVC or PPR pipe.
CN201821189637.XU 2018-07-25 2018-07-25 A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM Active CN208872285U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821189637.XU CN208872285U (en) 2018-07-25 2018-07-25 A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821189637.XU CN208872285U (en) 2018-07-25 2018-07-25 A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM

Publications (1)

Publication Number Publication Date
CN208872285U true CN208872285U (en) 2019-05-17

Family

ID=66463507

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821189637.XU Active CN208872285U (en) 2018-07-25 2018-07-25 A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM

Country Status (1)

Country Link
CN (1) CN208872285U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109029337A (en) * 2018-07-25 2018-12-18 中国电建集团北京勘测设计研究院有限公司 A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM and monitoring method
CN111678474A (en) * 2020-06-04 2020-09-18 赵德才 Arch bridge owner encircles continuous displacement monitoring devices

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109029337A (en) * 2018-07-25 2018-12-18 中国电建集团北京勘测设计研究院有限公司 A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM and monitoring method
CN111678474A (en) * 2020-06-04 2020-09-18 赵德才 Arch bridge owner encircles continuous displacement monitoring devices

Similar Documents

Publication Publication Date Title
CN103953025B (en) Measure equipment and the method to set up thereof of Deep Thick Soft Ground or covering layer delaminating deposition
CN104696010B (en) Comprehensive treatment method of mine water inrush
CN103046523B (en) Method for monitoring horizontal deformation of foundation pit and slope support
CN104596405B (en) Rain dirty pipe deforming contact real-time monitoring device and method on ground
CN106400768B (en) Collapsible loess tunnel submerging test method
CN104569341A (en) Vacuum preloading and electroosmosis combined testing device and vacuum preloading and electroosmosis combined testing method
CN103485320B (en) U-shaped inclinometer and mounting and embedding method thereof
CN208872285U (en) A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM
CN102797248B (en) Soil moisture meter embedding device and embedding method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN107131862A (en) A kind of face-plate of rockfill dam deformation monitoring device and construction method
CN103644892A (en) Measuring device and method for layered settlement of soil body of deep foundation pit
CN106245481A (en) Roadbed globality and the construction method of stability is kept under complex geological condition
CN105735232A (en) Collapsible loess wellpoint presoaking dynamic compaction replacement method
CN107192427A (en) A kind of foundation soil condition monitoring device and its method
CN109029337A (en) A kind of earth and rockfill dam impervious body DEFORMATION MONITORING SYSTEM and monitoring method
CN110453699B (en) Drainage slide-resistant pile structure of 'rice' -shaped pile core and construction method thereof
CN106480871B (en) A kind of automation settlement monitoring device and method being applicable in Yu Haiyang's land reclamation construction usage
CN108930262A (en) Across high speed subway line construction in shield in a kind of mud
CN209539356U (en) The simulation system that subway station bottom frozen construction influences station structure
CN201876257U (en) Dam foundation settlement meter for extra-large measuring range dam
CN102493810B (en) Grouting construction process of pipeline inclined shaft engineering
CN102519427B (en) Method for observing settlement of full section of widened roadbed
CN115450267B (en) Relay installation and burying structure and method for earth-rock dam settling tube
CN209742911U (en) simulation test device for slurry loss amount in shield synchronous grouting

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant