CN208862508U - A kind of connecting node of power transformation station cable poling turning position - Google Patents
A kind of connecting node of power transformation station cable poling turning position Download PDFInfo
- Publication number
- CN208862508U CN208862508U CN201821789012.7U CN201821789012U CN208862508U CN 208862508 U CN208862508 U CN 208862508U CN 201821789012 U CN201821789012 U CN 201821789012U CN 208862508 U CN208862508 U CN 208862508U
- Authority
- CN
- China
- Prior art keywords
- cable
- sand pit
- steel pipe
- coating steel
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
The utility model discloses a kind of connecting nodes of power transformation station cable poling turning position, to after the completion of solving civil construction in the prior art, the problem of when carrying out cable laying, the positioning of cable pipe is inaccurate, is unsatisfactory for turning of cable radius in cable pipe laying ground.The first coating steel pipe is specially connected below electrical equipment cable connection port, which is arranged perpendicular to ground, and bottom end is protruded into below ground, which is placed in cable sand pit;With ground level and the second coating steel pipe located underground, one end are protruded into cable sand pit, and one end that the second coating steel pipe protrudes into the one end in cable sand pit and the first coating steel pipe protrudes into cable sand pit passes through connection by metal hose;Fine sand is filled in cable sand pit.Beneficial effect includes: that cable pipe position can be accurately positioned in the working procedure requirement for meeting civil construction and cable laying, and meet turning of cable radius in cable pipe laying ground.
Description
Technical field
The utility model relates to electric power project engineering field more particularly to a kind of power transformation station cable poling turning positions
Connecting node.
Background technique
The substation project inner part high and low pressure power cable and control cable of newly-built, enlarging and reconstruction is applied using poling
If mode.The turning radius of cable need to be met in cable pipe laying ground with ground turn fractions;The overground part of cable pipe
Divide and needs to be accurately positioned at electrical equipment connectivity port;Cable pipe need to electrically be set in civil engineering " three supplies and one leveling " staged construction
Standby to be mounted on after civil construction, working procedure causes the positioning of cable pipe is inaccurate even to need to do over again.
Summary of the invention
The utility model embodiment provides a kind of connecting node of power transformation station cable poling turning position, existing to solve
Have in technology after the completion of civil construction, when carrying out cable laying, the positioning of cable pipe is inaccurate, is unsatisfactory for cable pipe laying ground
The problem of middle turning of cable radius.
The utility model embodiment provides a kind of connecting node of power transformation station cable poling turning position, comprising: electrical
The first coating steel pipe is connected below equipment cable connectivity port, which is arranged perpendicular to ground, and bottom end is protruded into
Below ground, which is placed in cable sand pit;With ground level and the second coating steel pipe located underground,
One end is protruded into cable sand pit, and the second coating steel pipe protrudes into the one end in cable sand pit and the first coating steel pipe protrudes into cable sand pit
One end passes through connection by metal hose;Fine sand is filled in cable sand pit.
Preferably, the cable sand pit uses machine brick masonry, cement sand bed is arranged in cable sand pit inner surface and outer surface.
Preferably, the first coating steel pipe, metal hose and the second coating steel pipe form L-type, internal cabling.
Preferably, a length of 1300mm in cable sand pit, width is when the metal hose number for being embedded in sand pit is more than or equal to 3
740mm;When being embedded in the metal hose number in sand pit less than 3, a length of 740mm in cable sand pit, width 640mm.
The beneficial effects of the utility model include: in the working procedure requirement for meeting civil construction and cable laying, and energy is quasi-
It determines position cable pipe position, and meets turning of cable radius in cable pipe laying ground, be suitable for each voltage class substation
Interior, site operation is convenient, can standardized and popularized.
Detailed description of the invention
Fig. 1 is the schematic diagram of the section structure of the vertical ground level in cable sand pit in the utility model;
Fig. 2 is the attachment structure schematic diagram of the power transformation station cable poling turning position in the utility model.
Specific embodiment
The utility model embodiment provides a kind of connecting node of power transformation station cable poling turning position, below in conjunction with
Figure of description is illustrated the preferred embodiment of the utility model, it should be understood that preferred embodiment described herein is only
For instruction and explanation of the utility model, it is not used to limit the utility model.And in the absence of conflict, in the application
Embodiment and embodiment in feature can be combined with each other.
Due to turning of cable radius limit, need by coating steel pipe according to turning of cable radius bend l-shaped, a part with
Original horizontally disposed water gas pipe connects, and is embedded in ground end, and another part vertically extends ground, electrical with needing to connect
Equipment connects;But electrical equipment, after civil construction, such civil engineering is completed preceding just it needs to be determined that good coating steel pipe elevates above the soil
Accurate location, to connect with other power equipments, working procedure causes that cable pipe positioning is inaccurate, and gap is biggish also
It needs to do over again.
Refering to fig. 1 and shown in Fig. 2, a kind of connecting node of power transformation station cable poling turning position, comprising: electrical equipment
The first coating steel pipe 1 is connected below cable connection port, which is arranged perpendicular to ground, and ground is protruded into bottom end
Below face, which is placed in cable sand pit 4;With ground level and the second coating steel pipe located underground
2, one end is protruded into cable sand pit 4, and the second coating steel pipe 2 protrudes into the one end in cable sand pit 4 and the first coating steel pipe 1 protrudes into cable
The one end in sand pit 4 is connected by metal hose 3;Fine sand 5 is filled in cable sand pit 4.The cable sand pit 4 uses machine brick masonry, electricity
Cement sand bed is arranged in 4 inner surface of cable sand pit and outer surface.First coating steel pipe 1, metal hose 3 and the second coating steel pipe 2
Form L-type, internal cabling.Sand pit is protruded into second coating steel pipe one end, and the other end protrudes into cable duct 6;It is embedded in the gold in sand pit
When belonging to 3 number of hose more than or equal to 3, a length of 1300mm in cable sand pit 4, width 740mm;It is embedded in the number of metal hose 3 in sand pit
When mesh is less than 3, a length of 740mm in cable sand pit 4, width 640mm.
Specifically, being positioned according to electric appliance general layout to sand pit, in electrical equipment cable connection port, downward vertical is buried
Cable sand pit 4 is set at pipe;Then according to the quantity of cable pipe, i.e., the first coating steel pipe 1, metal hose in the utility model
3 and second quantity of pipeline that forms of coating steel pipe 2, and according to the size of electrical equipment cable connection port, determine husky
Size is cheated, when the number of cable pipe is more than or equal to 3, using A type cable sand pit 4;When the number of cable pipe is less than 3, using B
Type cable sand pit 4;4 size of A type cable sand pit: 1300 × 740 × H (long × wide × deep);4 size of Type B cable sand pit: 640 ×
740 × H (long × wide × deep).Two kinds of sand pit depth are advisable by turning of cable radius is met.The production method in sand pit: M5 water is used
Cement mortar builds M7.5 machine brick, uses 1:2 cement sand plaster 20mm thick inside and outside sand pit.Fine sand 5 is inserted after cable laying.
To prevent cable in sand pit, can be in sand pit by the cable pipe and attachment of the flat laying of telluric water with the sedimentation of fine sand 5
Foundation of civil work is reliably connected.The cable pipe and ground vertical run laid is put down in sand pit using metal hose 3 and telluric water
Cable pipe connection.According to the requirement of the outside diameter of cable and turning radius, the outer diameter and length of reasonable selection metal hose 3, metal
The internal diameter of hose 3 is slightly larger than the first coating steel pipe 1 and the second coating steel pipe 2.It, can using the good turning performance of metal hose 3
Meet the turning radius requirement of different cables.Over ground installation cable pipe cooperation electrical equipment connectivity port, definitely on
The positioning of poling, the metal hose 3 in ground need to be adjusted flexibly according to laying, do not limit civil construction.
Claims (4)
1. a kind of connecting node of power transformation station cable poling turning position characterized by comprising electrical equipment cable connection
The first coating steel pipe is connected below port, first coating steel pipe is arranged perpendicular to ground, and bottom end is protruded into below ground, institute
The first coating steel pipe bottom end is stated to be placed in cable sand pit;With ground level and the second coating steel pipe located underground, one end is protruded into
In cable sand pit, one end that cable sand pit is protruded into the first coating steel pipe in one end that the second coating steel pipe protrudes into cable sand pit passes through
Connection by metal hose;Fine sand is filled in cable sand pit.
2. the connecting node of power transformation station cable poling turning position as described in claim 1, which is characterized in that the cable
Sand pit uses machine brick masonry, and cement sand bed is arranged in cable sand pit inner surface and outer surface.
3. the connecting node of power transformation station cable poling turning position as described in claim 1, which is characterized in that first is zinc-plated
Steel pipe, metal hose and the second coating steel pipe form L-type, internal cabling.
4. the connecting node of power transformation station cable poling turning position as described in claim 1, which is characterized in that be embedded in sand pit
Metal hose number be more than or equal to 3 when, a length of 1300mm in cable sand pit, width 740mm;It is embedded in the metal hose number in sand pit
When mesh is less than 3, a length of 740mm in cable sand pit, width 640mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821789012.7U CN208862508U (en) | 2018-11-01 | 2018-11-01 | A kind of connecting node of power transformation station cable poling turning position |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821789012.7U CN208862508U (en) | 2018-11-01 | 2018-11-01 | A kind of connecting node of power transformation station cable poling turning position |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208862508U true CN208862508U (en) | 2019-05-14 |
Family
ID=66421793
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821789012.7U Active CN208862508U (en) | 2018-11-01 | 2018-11-01 | A kind of connecting node of power transformation station cable poling turning position |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208862508U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113765031A (en) * | 2021-09-17 | 2021-12-07 | 青岛中车四方轨道车辆有限公司 | Railway vehicle lower line pipe installation module and installation method |
-
2018
- 2018-11-01 CN CN201821789012.7U patent/CN208862508U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113765031A (en) * | 2021-09-17 | 2021-12-07 | 青岛中车四方轨道车辆有限公司 | Railway vehicle lower line pipe installation module and installation method |
CN113765031B (en) * | 2021-09-17 | 2023-03-14 | 青岛中车四方轨道车辆有限公司 | Installation module and installation method for lower line pipe of railway vehicle |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103573274B (en) | Soft foundation shield tunnel subsidence controls steel sleeve grouting and reinforcing device | |
CN103603368B (en) | Diaphragm wall meets the inverse construction method done of underground utilities | |
CN104963705A (en) | Underground space excavating and constructing method | |
CN208862508U (en) | A kind of connecting node of power transformation station cable poling turning position | |
CN101793045A (en) | Concealed laying method of water supply pipeline | |
CN207621488U (en) | Adjustable limited support auxiliary device | |
CN105546213B (en) | A kind of flexible composite pipe rapid construction device and construction method | |
CN105672351A (en) | Construction method of buckling connection type prefabricated ribbed bar concrete comprehensive pipe rack structure | |
CN103669400A (en) | Typical construction method for prefabricated tube bank | |
CN106159475A (en) | Arid geology grounded screen and water conservation fall resistance construction method thereof | |
CN104727339A (en) | Electrical equipment foundation two-step type construction method | |
CN201554042U (en) | Installer for diaphragm wall connector flexible water stops | |
CN108930323B (en) | Pipe jacking construction method | |
CN204343286U (en) | A kind of steel pipe pile support | |
CN203821326U (en) | Force transferring hole structure for arch dam foundation processing | |
CN214994477U (en) | Pipeline changes structure in foundation ditch | |
CN209313032U (en) | A kind of vertical ground structure in power transmission and transformation line | |
CN104314104A (en) | Setting method for deformation joint obliquely crossed with underground box culvert | |
CN112728209B (en) | Construction method for connecting new and old pipes in non-excavation mode | |
CN206157768U (en) | Street piping lane is crossed to underground | |
CN110277661B (en) | Lightning protection grounding construction method capable of continuously maintaining without secondary groove digging | |
CN103114601A (en) | Cut-off method of rapid-hardening high-spray grouting of strong leakage stratum and device thereof | |
CN209001496U (en) | A kind of electric power tunnel push pipe with electro-magnetic screen function | |
CN203947557U (en) | Enclosure wall discharge structure | |
CN205779013U (en) | The transverse drainage of tunnel crag |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |