CN208777996U - A kind of anchor combined unit of fully mechanized mining formula pick branch - Google Patents

A kind of anchor combined unit of fully mechanized mining formula pick branch Download PDF

Info

Publication number
CN208777996U
CN208777996U CN201821359316.XU CN201821359316U CN208777996U CN 208777996 U CN208777996 U CN 208777996U CN 201821359316 U CN201821359316 U CN 201821359316U CN 208777996 U CN208777996 U CN 208777996U
Authority
CN
China
Prior art keywords
support portion
anchorage
oil cylinder
driving
sliding sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201821359316.XU
Other languages
Chinese (zh)
Inventor
谢苗
刘治翔
毛君
卢进南
李玉岐
王鹏飞
董钰峰
张鸿宇
李政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Technical University
Original Assignee
Liaoning Technical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Technical University filed Critical Liaoning Technical University
Priority to CN201821359316.XU priority Critical patent/CN208777996U/en
Application granted granted Critical
Publication of CN208777996U publication Critical patent/CN208777996U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A kind of anchor combined unit of fully mechanized mining formula pick branch, including driving support portion, anchorage support portion, cutting units, scraper portion and bore portion;Anchorage support portion is symmetrically distributed at left and right sides of driving support portion, is leapfroged by driving support portion and anchorage support portion and is realized that step type cooperates, increases fuselage and roadway floor contact area, avoids causing fuselage to fall into roadway floor problem than excessive because being grounded;By being flexibly laid with lateral steel band beam mode, avoids longitudinal roof girder from directly contacting with back, and then avoid repeating to roll problem to back, reduce back second-time breakage and inbreak is dangerous;Pass through the steady drop vibration structural member of setting increasing between driving support portion and anchorage support portion, during coal petrography cutting, make to connect between driving support portion and anchorage support portion even closer, and keep complete machine structure stability higher, to improve vibratory output of the anchor combined unit of fully mechanized mining formula pick branch during coal petrography cutting;Drivage efficiency and safety are further promoted.

Description

A kind of anchor combined unit of fully mechanized mining formula pick branch
Technical field
The utility model belongs to coal mine machinery technical field, more particularly to a kind of anchor combined unit of fully mechanized mining formula pick branch.
Background technique
Currently, existing comprehensive pick equipment mostly uses greatly crawler-type traveling scheme, and track chain presence is easily damaged, repairs Disadvantage that is difficult, being easy skidding and sink;Further more, existing comprehensive pick equipment is to the gib of back using entirety Top beam scheme, and integral top beam is easy to appear the situation not firm to back supporting, and during advance, integral top beam Also back can be carried out to repeat to roll, to increase the danger of top plate second-time breakage and inbreak;In addition, existing comprehensive pick It is larger to equip the vibration generated during coal petrography cutting, will lead to equipment fuselage when serious and sideway phenomenon occur, thus seriously Influence drivage efficiency.
Application No. is 201711288542.3 Chinese patent application, a kind of pick, anchor, the integrated pick Anchor Care of shield are disclosed Machine, by installing gib mechanism additional on existing development machine, and gib mechanism has lifting operating platform and slideway, And jumbolter is installed on slideway, although the safety of worker and equipment can be improved by gib, but still exist The problem of repetition rolls back, and boring mechanism and gib mechanism are each provided on slideway, if working face in the pit Dust Capacity it is larger, a large amount of dust accumulation easily causes slideway stuck, so as to cause can not continue passage the problem of.
Application No. is 201611237498.9 Chinese patent application, a kind of pick, branch, anchor, drill integrated comprehensive pick are disclosed Machine, by arranging Anchor Care equipment, drilling equipment and temporary support device on original machine body of boring machine, so as to dig, prop up, Anchor, brill integrate, but the patent application uses still for crawler-type traveling scheme, thus in the presence of be easily damaged, repair be stranded Problem that is difficult, being easy skidding and sink.
Utility model content
In view of the problems of the existing technology, the utility model provides a kind of fully mechanized mining formula pick branch anchor combined unit, abandons Traditional crawler-type traveling mode solves the problems, such as that top beam repeats to roll to back, reduces back two Secondary broken and inbreak danger effectively improves the vibratory output equipped during coal petrography cutting, and drivage efficiency and driving peace Further promotion also can be obtained in full property.
To achieve the goals above, the utility model adopts the following technical solution: a kind of anchor combined unit of fully mechanized mining formula pick branch, Including driving support portion, anchorage support portion, cutting units, scraper portion and bore portion;The cutting units is located in front of driving support portion, And cutting units is mounted in scraper portion, is crushed by cutting units to coal petrography;The scraper portion is mounted on driving support portion, Coal breakage is collected and is transported by scraper portion;The anchorage support portion is symmetrically distributed in the left and right sides of driving support portion, It is leapfroged by driving support portion and anchorage support portion and realizes that step type cooperates;The bore portion is mounted on anchorage support portion On, anchor hole is processed on palisades by bore portion.
The driving support portion includes driving support portion pedestal, driving support portion outer support sliding sleeve, the interior branch of driving support portion Support sliding sleeve, driving support portion shored oil cylinder and driving support portion longitudinal roof girder;The driving support portion longitudinal roof girder uses three sections Formula structure is divided into longitudinal roof girder before tunneling support portion, driving support portion centre longitudinal roof girder and tunnels longitudinal roof girder after support portion, Longitudinal roof girder rear end is hinged with longitudinal roof girder front end among driving support portion before driving support portion, longitudinal among driving support portion Top beam rear end is hinged with longitudinal roof girder front end after driving support portion;The driving support portion outer support sliding sleeve is packed in pick vertically Into on support portion pedestal, the driving support portion inner support sliding sleeve is vertically installed on the inside of driving support portion outer support sliding sleeve, pick Sliding in driving support portion outer support sliding sleeve into support portion inner support has vertically movable freedom degree;The driving support portion top Support oil cylinder is vertically installed on the inside of driving support portion inner support sliding sleeve, in driving support portion shored oil cylinder top and driving support portion Support sliding sleeve is fixedly connected with, and driving support portion shored oil cylinder bottom end is fixedly connected with driving support portion outer support sliding sleeve;The driving branch Longitudinal roof girder level is packed at the top of driving support portion inner support sliding sleeve among support part;The longitudinal roof girder before the driving support portion Diagonal brace oil cylinder before tunneling support portion is installed between driving support portion outer support sliding sleeve, tunnels diagonal brace oil cylinder one end before support portion It is hinged on before tunneling support portion in the middle part of longitudinal roof girder, the diagonal brace oil cylinder other end is hinged on branch outside driving support portion before tunneling support portion It supports in the middle part of sliding sleeve;Driving support is installed between longitudinal roof girder after the driving support portion and driving support portion outer support sliding sleeve Diagonal brace oil cylinder behind portion, diagonal brace oil cylinder one end is hinged on longitudinal roof girder middle part after driving support portion, driving support after tunneling support portion The diagonal brace oil cylinder other end is hinged in the middle part of driving support portion outer support sliding sleeve behind portion;The anchor combined unit of fully mechanized mining formula pick branch Driver's cabin is located on driving support portion pedestal.
The anchorage support portion includes anchorage support portion pedestal, anchorage support portion outer support sliding sleeve, props up in anchorage support portion Support sliding sleeve, anchorage support portion shored oil cylinder and anchorage support portion longitudinal roof girder;Anchorage support portion longitudinal roof girder uses three sections Formula structure is divided into longitudinal roof girder before anchorage support portion, longitudinal roof girder behind longitudinal roof girder and anchorage support portion among anchorage support portion, Longitudinal roof girder rear end and anchorage support portion, longitudinal roof girder front end, centre are hinged before anchorage support portion, longitudinal among anchorage support portion Top beam rear end is hinged with longitudinal roof girder front end behind anchorage support portion;The anchorage support portion outer support sliding sleeve is packed in anchor vertically On clamped support part pedestal, the anchorage support portion inner support sliding sleeve is vertically installed on the inside of anchorage support portion outer support sliding sleeve, anchor Clamped support part inner support, which slides over, has vertically movable freedom degree in anchorage support portion outer support sliding sleeve;The anchorage support portion top Support oil cylinder is vertically installed on the inside of anchorage support portion inner support sliding sleeve, in anchorage support portion shored oil cylinder top and anchorage support portion Support sliding sleeve is fixedly connected with, and anchorage support portion shored oil cylinder bottom end is fixedly connected with anchorage support portion outer support sliding sleeve;The anchoring branch Longitudinal roof girder level is packed at the top of anchorage support portion inner support sliding sleeve among support part;The longitudinal roof girder before the anchorage support portion Diagonal brace oil cylinder before anchorage support portion, diagonal brace oil cylinder one end before anchorage support portion are installed between anchorage support portion outer support sliding sleeve It is hinged on before anchorage support portion in the middle part of longitudinal roof girder, the diagonal brace oil cylinder other end is hinged on branch anchorage support portion outside before anchorage support portion It supports in the middle part of sliding sleeve;Anchorage support is being installed between longitudinal roof girder and anchorage support portion outer support sliding sleeve behind the anchorage support portion Diagonal brace oil cylinder behind portion, diagonal brace oil cylinder one end is hinged on behind anchorage support portion in the middle part of longitudinal roof girder behind anchorage support portion, anchorage support The diagonal brace oil cylinder other end is hinged in the middle part of anchorage support portion outer support sliding sleeve behind portion;In anchorage support portion pedestal and driving branch Advance passage drive cylinder is installed, passage drive cylinder of advancing is used for as the anchor combined unit of fully mechanized mining formula pick branch between the pedestal of support part Onward impulse is provided.
The bore portion is mounted on anchorage support portion pedestal, is also respectively provided on anchorage support portion pedestal automatically controlled Case, pumping plant, anchorage support portion lateral support oil cylinder and anchorage support portion end support oil cylinder;Anchorage support portion lateral support Oil cylinder is horizontally disposed, and anchorage support portion lateral support oil cylinder one end is hinged on anchorage support portion pedestal, and anchorage support portion is lateral The support cylinder other end is equipped with anchorage support portion lateral support seat;The anchorage support portion end support oil cylinder, which tilts down, to be set It sets, anchorage support portion end support oil cylinder one end is hinged on anchorage support portion pedestal, and anchorage support portion end support oil cylinder is another One end is equipped with anchorage support portion end support seat.
The cutting units includes cutterhead, cutting arm, slide unit and sliding rail;The cutterhead uses horizontal shaft type structure or the longitudinal axis Formula structure;The cutterhead is mounted on cutting arm one end, and the cutting arm other end is connected on slide unit, and cutting arm has relative to slide unit There is rotation freedom degree;Cutting motor is provided in the slide unit;The sliding rail is horizontally arranged in scraper portion, sliding rail and driving Direction is perpendicular;On the slide rail, slide unit has linear movement freedom degree relative to sliding rail for the slide unit installation.
The scraper portion include scraper-type shovel coal mechanism, quarter bend transshipment acitivity, scraper-type transporting coal mechanism, transporting coal mechanism drive Dynamic motor, transporting coal mechanism driving-motor mounting seat and scraper-type transporting coal mechanism mounting seat;The scraper-type mechanism that shovels coal is logical It crosses working face transverse adjusting oil cylinder to be connected with driving support portion pedestal, the scraper-type mechanism that shovels coal passes through and quarter bend transshipment acitivity and scrapes Board-like transporting coal mechanism is connected, and scraper-type transporting coal mechanism is mounted in scraper-type transporting coal mechanism mounting seat;The transporting coal mechanism drives Dynamic motor is used to provide power for scraper-type transporting coal mechanism, and transporting coal mechanism driving-motor is mounted on the installation of transporting coal mechanism driving-motor On pedestal;Mechanism lateral support oil cylinder of shoveling coal is installed in scraper-type mechanism both ends horizontal of shoveling coal, the mechanism that shovels coal laterally is propped up Support oil cylinder one end is packed in scraper-type and shovels coal in mechanism, and it is lateral that the mechanism that the shovels coal lateral support oil cylinder other end is equipped with the mechanism that shovels coal Support base.
The steady drop vibration structural member of increasing is added on the driving support portion pedestal, the steady drop vibration structural member of increasing includes fixing Block, briquetting and down pressing oil cylinder;The fixed block is packed on driving support portion pedestal, and fixed block is hinged with briquetting, under described Compressing cylinder one end is hinged on fixed block, and the down pressing oil cylinder other end is hinged on briquetting, and briquetting has rotation relative to hinge joint Freedom degree, briquetting and anchorage support portion pedestal compression fit.
The application method of the anchor combined unit of fully mechanized mining formula pick branch, includes the following steps:
Step 1: preparing some steel bands at the scene, these steel bands are used as lateral steel band beam;
Step 2: by lateral steel band beam be placed into driving support portion longitudinal roof girder and anchorage support portion longitudinal roof girder it is upper Side;
Step 3: control driving support portion longitudinal roof girder and anchorage support portion longitudinal roof girder rise, and keep driving support portion vertical Back is tightened to by lateral steel band back to top beam and anchorage support portion longitudinal roof girder;
Step 4: control anchorage support portion lateral support oil cylinder and anchorage support portion end support oil cylinder stretch out, and make to anchor Support portion lateral support seat and anchorage support portion end support seat are held out against respectively to tunnel side wall and roadway floor;
Step 5: control down pressing oil cylinder is stretched out, and is pressed to briquetting on anchorage support portion pedestal;
Step 6: starting cutting units and scraper portion carry out cutting operation to coal petrography by cutting units, while passing through scraper portion The scraper-type mechanism that shovels coal the coal breakage after cutting is collected, then the coal breakage being collected into is transferred by quarter bend transshipment acitivity Onto scraper-type transporting coal mechanism, finally by scraper-type transporting coal, mechanism transports coal breakage, and in cutting operation process Starting bore portion, which synchronizes, carries out anchoring operation;
Step 7: lane is individually performed by anchorage support portion longitudinal roof girder at this time in control driving support portion longitudinal roof girder decline Road country rock supports task;
Step 8: control, which is advanced, elapses drive cylinder stretching, and driving support portion is made integrally to move forward a step pitch;
Step 9: control driving support portion longitudinal roof girder rises, and driving support portion longitudinal roof girder is made to pass through lateral steel again Band back is tightened to back;
Step 10: control anchorage support portion longitudinal roof girder decline, while controlling anchorage support portion lateral support oil cylinder, anchoring Support portion end support oil cylinder and down pressing oil cylinder retract, and roadway surrounding rock support is individually performed by driving support portion longitudinal roof girder at this time Task;
Step 11: control, which is advanced, elapses drive cylinder retraction, and anchorage support portion is made integrally to move forward a step pitch;
Step 12: lateral steel band beam is placed into the top of anchorage support portion longitudinal roof girder;
Step 13: control anchorage support portion longitudinal roof girder rises, and anchorage support portion longitudinal roof girder is made to pass through transverse direction again Steel band back is tightened to back, tunnels support portion longitudinal roof girder at this time and longitudinal roof girder recovery in anchorage support portion rises at the same time shape State;
Step 14: step 4 is repeated to step 13, realizes continuously tunneling forward for the fully mechanized mining formula anchor combined unit of pick branch.
The utility model has the beneficial effects that
The anchor combined unit of fully mechanized mining formula pick branch of the utility model, has abandoned traditional crawler-type traveling mode, has used and step Step formula walking manner, increases the contact area of fuselage and roadway floor, avoids and falls into because of ground connection than fuselage caused by excessive The problem of roadway floor;The utility model avoids longitudinal roof girder directly and tunnel by way of being flexibly laid with lateral steel band beam Top plate contact, and then avoid and the problem of rolling is repeated to back, to reduce back second-time breakage and inbreak Danger;The utility model is by the steady drop vibration structural member of setting increasing between driving support portion and anchorage support portion, in cutting coal Make to tunnel connection even closer between support portion and anchorage support portion during rock, and keep the structural stability of complete machine higher, So as to improve vibratory output of equipment during coal petrography cutting;It can make drivage efficiency and driving safety by the utility model Further promoted.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of the anchor combined unit of fully mechanized mining formula pick branch of the utility model;
Fig. 2 is the structural schematic diagram of the driving support portion of the utility model;
Fig. 3 is the structural schematic diagram in the anchorage support portion (with bore portion after equipped) of the utility model;
Fig. 4 is the structural schematic diagram of the cutting units of the utility model;
Fig. 5 is the structural schematic diagram in the scraper portion of the utility model;
Fig. 6 is the structural schematic diagram of the steady drop vibration structural member of increasing of the utility model;
In figure, 1-driving support portion, 2-anchorage support portions, 3-cutting units, 4-scraper portions, 5-bore portions, 6-picks Into support portion pedestal, 7-driving support portion outer support sliding sleeves, 8-driving support portion inner support sliding sleeves, 9-driving support portion tops Oil cylinder is supportted, longitudinal roof girder before 10-driving support portions, 11-tunnel longitudinal roof girders among support portions, indulge after 12-driving support portions Diagonal brace oil cylinder before support portions, diagonal brace oil cylinder after 14-driving support portions, 15-driver's cabins, 16-anchorings are tunneled to top beam, 13- Support portion pedestal, 17-anchorage support portion outer support sliding sleeves, 18-anchorage support portion inner support sliding sleeves, 19-anchorage support portions top Oil cylinder is supportted, longitudinal roof girder before 20-anchorage support portions, longitudinal roof girder among 21-anchorage support portions is indulged behind 22-anchorage support portions To top beam, diagonal brace oil cylinder before 23-anchorage support portions, diagonal brace oil cylinder behind 24-anchorage support portions, 25-advance passage driving oil Cylinder, 26-electric cabinets, 27-pumping plants, 28-anchorage support portion lateral support oil cylinders, 29-anchorage support portion end support oil cylinders, 30-anchorage support portion lateral support seats, 31-anchorage support portion end support seats, 32-cutterheads, 33-cutting arms, 34- Slide unit, 35-sliding rails, 36-scraper-types are shoveled coal mechanism, 37-quarter bend transshipment acitivities, 38-scraper-type transporting coal mechanisms, 39-fortune Coal mechanism driving-motor, 40-transporting coal mechanism driving-motor mounting seats, 41-scraper-type transporting coal mechanism mounting seats, 42-works Make face transverse adjusting oil cylinder, 43-shovel coal mechanism lateral support oil cylinder, and 44-shovel coal mechanism lateral support seat, and 45-increase steady drop vibration Structural member, 46-fixed blocks, 47-briquettings, 48-down pressing oil cylinders, 49-lateral steel band beams.
Specific embodiment
The utility model is described in further detail in the following with reference to the drawings and specific embodiments.
As shown in figs. 1 to 6, the anchor combined unit of a kind of fully mechanized mining formula pick branch, including tunnel support portion 1, anchorage support portion 2, cut Cut portion 3, scraper portion 4 and bore portion 5;The cutting units 3 is located at 1 front of driving support portion, and cutting units 3 is mounted on scraper portion 4 On, coal petrography is crushed by cutting units 3;The scraper portion 4 is mounted on driving support portion 1, by scraper portion 4 to coal breakage It is collected and transports;The anchorage support portion 2 is symmetrically distributed in the left and right sides of driving support portion 1, by tunneling support portion 1 It leapfrogs with anchorage support portion 2 and realizes that step type cooperates;The bore portion 5 is mounted in anchorage support portion 2, passes through bore portion 5 process anchor hole on palisades.
The driving support portion 1 includes driving support portion pedestal 6, driving support portion outer support sliding sleeve 7, tunnels in support portion Support sliding sleeve 8, driving support portion shored oil cylinder 9 and driving support portion longitudinal roof girder;The driving support portion longitudinal roof girder uses Three stage structure, after being divided into longitudinal roof girder 10 before tunneling support portion, driving support portion centre longitudinal roof girder 11 and driving support portion Longitudinal roof girder 12,10 rear end of longitudinal roof girder is hinged with 11 front end of longitudinal roof girder among driving support portion before tunneling support portion, digs 11 rear end of longitudinal roof girder is hinged with 12 front end of longitudinal roof girder after driving support portion among into support portion;Outside the driving support portion Support sliding sleeve 7 is packed in vertically on driving support portion pedestal 6, and the driving support portion inner support sliding sleeve 8 is vertically installed at driving 7 inside of support portion outer support sliding sleeve, driving support portion inner support sliding sleeve 8 have vertical in driving support portion outer support sliding sleeve 7 One-movement-freedom-degree;The driving support portion shored oil cylinder 9 is vertically installed at 8 inside of driving support portion inner support sliding sleeve, driving branch Shored oil cylinder 9 top in support part is fixedly connected with driving support portion inner support sliding sleeve 8, driving 9 bottom end of support portion shored oil cylinder and driving Support portion outer support sliding sleeve 7 is fixedly connected with;11 level of longitudinal roof girder is packed in branch in driving support portion among the driving support portion Support 8 top of sliding sleeve;Driving is installed between longitudinal roof girder 10 before the driving support portion and driving support portion outer support sliding sleeve 7 Diagonal brace oil cylinder 13 before support portion, 13 one end of diagonal brace oil cylinder is hinged on before driving support portion in longitudinal roof girder 10 before tunneling support portion Portion, 13 other end of diagonal brace oil cylinder is hinged on 7 middle part of driving support portion outer support sliding sleeve before tunneling support portion;It is supported in the driving Diagonal brace oil cylinder 14 after tunneling support portion, driving branch are installed between longitudinal roof girder 12 and driving support portion outer support sliding sleeve 7 behind portion 14 one end of diagonal brace oil cylinder is hinged on 12 middle part of longitudinal roof girder after driving support portion behind support part, and diagonal brace oil cylinder 14 is another after tunneling support portion One end is hinged on 7 middle part of driving support portion outer support sliding sleeve;The driver's cabin 15 of the anchor combined unit of fully mechanized mining formula pick branch is located at It tunnels on support portion pedestal 6.
The anchorage support portion 2 includes anchorage support portion pedestal 16, anchorage support portion outer support sliding sleeve 17, anchorage support portion Inner support sliding sleeve 18, anchorage support portion shored oil cylinder 19 and anchorage support portion longitudinal roof girder;Anchorage support portion longitudinal roof girder Using three stage structure, it is divided into longitudinal roof girder 20, anchorage support portion centre longitudinal roof girder 21 and anchorage support before anchorage support portion Longitudinal roof girder 22 behind portion, 21 front end of longitudinal roof girder is mutually cut with scissors among 20 rear end of longitudinal roof girder and anchorage support portion before anchorage support portion It connects, 21 rear end of longitudinal roof girder is hinged with 22 front end of longitudinal roof girder behind anchorage support portion among anchorage support portion;The anchoring branch Support part outer support sliding sleeve 17 is packed in vertically on anchorage support portion pedestal 16, and the anchorage support portion inner support sliding sleeve 18 is pacified vertically Mounted in 17 inside of anchorage support portion outer support sliding sleeve, anchorage support portion inner support sliding sleeve 18 is in anchorage support portion outer support sliding sleeve 17 It is interior that there is vertically movable freedom degree;Anchorage support portion shored oil cylinder 19 is vertically installed at anchorage support portion inner support sliding sleeve 18 Inside, 19 top of anchorage support portion shored oil cylinder are fixedly connected with anchorage support portion inner support sliding sleeve 18, and oil is shored in anchorage support portion 19 bottom end of cylinder is fixedly connected with anchorage support portion outer support sliding sleeve 17;21 level of longitudinal roof girder is packed among the anchorage support portion 18 top of anchorage support portion inner support sliding sleeve;Longitudinal roof girder 20 and anchorage support portion outer support sliding sleeve before the anchorage support portion Diagonal brace oil cylinder 23 before anchorage support portion is installed, 23 one end of diagonal brace oil cylinder is hinged on anchorage support portion before anchorage support portion between 17 In the middle part of preceding longitudinal roof girder 20,23 other end of diagonal brace oil cylinder is hinged in anchorage support portion outer support sliding sleeve 17 before anchorage support portion Portion;After anchorage support portion is installed between longitudinal roof girder 22 and anchorage support portion outer support sliding sleeve 17 behind the anchorage support portion Diagonal brace oil cylinder 24,24 one end of diagonal brace oil cylinder is hinged on 22 middle part of longitudinal roof girder behind anchorage support portion, anchoring branch behind anchorage support portion 24 other end of diagonal brace oil cylinder is hinged on 17 middle part of anchorage support portion outer support sliding sleeve behind support part;The pedestal 16 in the anchorage support portion Advance passage drive cylinder 25 is installed between driving support portion pedestal 6, passage drive cylinder 25 of advancing is used to be fully mechanized mining formula The anchor combined unit of pick branch provides onward impulse.
The bore portion 5 is mounted on anchorage support portion pedestal 16, is also respectively provided on anchorage support portion pedestal 16 Electric cabinet 26, pumping plant 27, anchorage support portion lateral support oil cylinder 28 and anchorage support portion end support oil cylinder 29;The anchoring branch Support part lateral support oil cylinder 28 is horizontally disposed, and lateral support oil cylinder 28 one end in anchorage support portion is hinged on anchorage support portion pedestal 16 On, lateral support oil cylinder 28 other end in anchorage support portion is equipped with anchorage support portion lateral support seat 30;The anchorage support portion End support oil cylinder 29 tilts down setting, and end support oil cylinder 29 one end in anchorage support portion is hinged on anchorage support portion pedestal 16 On, end support oil cylinder 29 other end in anchorage support portion is equipped with anchorage support portion end support seat 31.
The cutting units 3 includes cutterhead 32, cutting arm 33, slide unit 34 and sliding rail 35;The cutterhead 36 uses horizontal axis Formula structure or vertical axis structure;The cutterhead 32 is mounted on 33 one end of cutting arm, and 33 other end of cutting arm is connected to slide unit 34 On, cutting arm 33 has rotation freedom degree relative to slide unit 34;Cutting motor is provided in the slide unit 34;The sliding rail 35 It is horizontally arranged in scraper portion 4, sliding rail 35 and tunneling direction are perpendicular;The slide unit 34 is mounted on sliding rail 35,34 phase of slide unit There is linear movement freedom degree for sliding rail 35.
The scraper portion 4 include scraper-type shovel coal mechanism 36, quarter bend transshipment acitivity 37, scraper-type transporting coal mechanism 38, fortune Coal mechanism driving-motor 39, transporting coal mechanism driving-motor mounting seat 40 and scraper-type transporting coal mechanism mounting seat 41;It is described to scrape The board-like mechanism 36 that shovels coal is connected by working face transverse adjusting oil cylinder 42 with support portion pedestal 6 is tunneled, and scraper-type is shoveled coal mechanism 36 It is connected by quarter bend transshipment acitivity 37 with scraper-type transporting coal mechanism 38, scraper-type transporting coal mechanism 38 is mounted on scraper-type conveyer In structure mounting seat 41;The transporting coal mechanism driving-motor 39 is used to provide power, transporting coal mechanism for scraper-type transporting coal mechanism 38 Driving motor 39 is mounted in transporting coal mechanism driving-motor mounting seat 40;The scraper-type shovel coal 36 both ends horizontal of mechanism peace Equipped with mechanism lateral support oil cylinder 43 of shoveling coal, 43 one end of the mechanism that shovels coal lateral support oil cylinder is packed in scraper-type and shovels coal mechanism 36 On, 43 other end of the mechanism that shovels coal lateral support oil cylinder is equipped with mechanism lateral support seat 44 of shoveling coal.
The steady drop vibration structural member 45 of increasing is added on the driving support portion pedestal 6, the steady drop vibration structural member 45 of increasing wraps Include fixed block 46, briquetting 47 and down pressing oil cylinder 48;The fixed block 46 be packed in driving support portion pedestal 6 on, fixed block 46 with Briquetting 47 is hinged, and described 48 one end of down pressing oil cylinder is hinged on fixed block 46, and 48 other end of down pressing oil cylinder is hinged on briquetting 47 On, briquetting 47 has rotation freedom degree, briquetting 47 and 16 compression fit of anchorage support portion pedestal relative to hinge joint.
The application method of the anchor combined unit of fully mechanized mining formula pick branch, includes the following steps:
Step 1: preparing some steel bands at the scene, these steel bands are used as lateral steel band beam 49;
Step 2: by lateral steel band beam 49 be placed into driving support portion longitudinal roof girder and anchorage support portion longitudinal roof girder it is upper Side;
Step 3: control driving support portion longitudinal roof girder and anchorage support portion longitudinal roof girder rise, and keep driving support portion vertical Pass through lateral steel band beam 49 to top beam and anchorage support portion longitudinal roof girder and holds out against back;
Step 4: control anchorage support portion lateral support oil cylinder 28 and anchorage support portion end support oil cylinder 29 stretch out, and make Anchorage support portion lateral support seat 30 and anchorage support portion end support seat 31 are held out against respectively to tunnel side wall and roadway floor;
Step 5: control down pressing oil cylinder 48 is stretched out, and is pressed to briquetting 47 on anchorage support portion pedestal 16;
Step 6: starting cutting units 3 and scraper portion 4 carry out cutting operation to coal petrography by cutting units 3, while passing through shovel The scraper-type in fortune portion 4 mechanism 36 that shovels coal is collected the coal breakage after cutting, then will be collected by quarter bend transshipment acitivity 37 Coal breakage be transferred in scraper-type transporting coal mechanism 38, coal breakage is transported finally by scraper-type transporting coal mechanism 38, and Starting bore portion 5, which synchronizes, in cutting operation process carries out anchoring operation;
Step 7: lane is individually performed by anchorage support portion longitudinal roof girder at this time in control driving support portion longitudinal roof girder decline Road country rock supports task;
Step 8: control, which is advanced, elapses the stretching of drive cylinder 25, makes driving support portion 1 is whole to move forward a step pitch;
Step 9: control driving support portion longitudinal roof girder rises, and driving support portion longitudinal roof girder is made to pass through lateral steel again Band beam 49 holds out against back;
Step 10: control anchorage support portion longitudinal roof girder decline, while controlling anchorage support portion lateral support oil cylinder 28, anchor Clamped support part end support oil cylinder 29 and down pressing oil cylinder 48 retract, and tunnel is individually performed by driving support portion longitudinal roof girder at this time and encloses Petrous branch supports task;
Step 11: control, which is advanced, elapses the retraction of drive cylinder 25, and anchorage support portion 2 is made integrally to move forward a step Away from;
Step 12: lateral steel band beam 49 is placed into the top of anchorage support portion longitudinal roof girder;
Step 13: control anchorage support portion longitudinal roof girder rises, and anchorage support portion longitudinal roof girder is made to pass through transverse direction again Steel band beam 49 holds out against back, tunnels support portion longitudinal roof girder at this time and longitudinal roof girder recovery in anchorage support portion rises at the same time State;
Step 14: step 4 is repeated to step 13, realizes continuously tunneling forward for the fully mechanized mining formula anchor combined unit of pick branch.
Scheme in embodiment is not the scope of patent protection to limit the utility model, all without departing from the utility model Carried out by equivalence enforcement or change, be both contained in the scope of the patents of this case.

Claims (7)

1. a kind of anchor combined unit of fully mechanized mining formula pick branch, it is characterised in that: including tunneling support portion, anchorage support portion, cutting units, shovel Fortune portion and bore portion;The cutting units is located in front of driving support portion, and cutting units is mounted in scraper portion, passes through cutting units pair Coal petrography is crushed;The scraper portion is mounted on driving support portion, and coal breakage is collected and is transported by scraper portion;It is described Anchorage support portion is symmetrically distributed in the left and right sides of driving support portion, is leapfroged reality by driving support portion and anchorage support portion Existing step type cooperation;The bore portion is mounted in anchorage support portion, and anchor hole is processed on palisades by bore portion.
2. a kind of anchor combined unit of fully mechanized mining formula pick branch according to claim 1, it is characterised in that: the driving support portion packet Include driving support portion pedestal, driving support portion outer support sliding sleeve, driving support portion inner support sliding sleeve, driving support portion shored oil cylinder And driving support portion longitudinal roof girder;The driving support portion longitudinal roof girder uses three stage structure, indulges before being divided into driving support portion Longitudinal roof girder after to top beam, driving support portion centre longitudinal roof girder and driving support portion, tunnels longitudinal roof girder rear end before support portion It is hinged with longitudinal roof girder front end among driving support portion, is indulged after longitudinal roof girder rear end and driving support portion among driving support portion It is hinged to top beam front end;The driving support portion outer support sliding sleeve is packed in vertically on driving support portion pedestal, the driving Support portion inner support sliding sleeve is vertically installed on the inside of driving support portion outer support sliding sleeve, and driving support portion inner support slides over driving There is vertically movable freedom degree in support portion outer support sliding sleeve;The driving support portion shored oil cylinder is vertically installed at driving support On the inside of portion's inner support sliding sleeve, driving support portion shored oil cylinder top is fixedly connected with driving support portion inner support sliding sleeve, driving support Portion shored oil cylinder bottom end is fixedly connected with driving support portion outer support sliding sleeve;Longitudinal roof girder level is fixedly mounted among the driving support portion At the top of driving support portion inner support sliding sleeve;Before the driving support portion longitudinal roof girder and driving support portion outer support sliding sleeve it Between be equipped with driving support portion before diagonal brace oil cylinder, tunnel support portion before diagonal brace oil cylinder one end be hinged on driving support portion before longitudinally push up In the middle part of beam, the diagonal brace oil cylinder other end is hinged in the middle part of driving support portion outer support sliding sleeve before tunneling support portion;In driving branch Diagonal brace oil cylinder after tunneling support portion is installed between longitudinal roof girder and driving support portion outer support sliding sleeve behind support part, tunnels support portion Diagonal brace oil cylinder one end is hinged on longitudinal roof girder middle part after driving support portion afterwards, and the diagonal brace oil cylinder other end is hinged on after tunneling support portion It tunnels in the middle part of support portion outer support sliding sleeve;The driver's cabin of the anchor combined unit of fully mechanized mining formula pick branch is located at driving support portion pedestal On.
3. a kind of anchor combined unit of fully mechanized mining formula pick branch according to claim 2, it is characterised in that: the anchorage support portion packet Include anchorage support portion pedestal, anchorage support portion outer support sliding sleeve, anchorage support portion inner support sliding sleeve, anchorage support portion shored oil cylinder And anchorage support portion longitudinal roof girder;Anchorage support portion longitudinal roof girder uses three stage structure, indulges before being divided into anchorage support portion To top beam, longitudinal roof girder behind longitudinal roof girder and anchorage support portion among anchorage support portion, before anchorage support portion longitudinal roof girder rear end It is hinged with longitudinal roof girder front end among anchorage support portion, is indulged behind longitudinal roof girder rear end and anchorage support portion among anchorage support portion It is hinged to top beam front end;The anchorage support portion outer support sliding sleeve is packed in vertically on anchorage support portion pedestal, the anchoring Support portion inner support sliding sleeve is vertically installed on the inside of anchorage support portion outer support sliding sleeve, and anchorage support portion inner support slides over anchoring There is vertically movable freedom degree in support portion outer support sliding sleeve;Anchorage support portion shored oil cylinder is vertically installed at anchorage support On the inside of portion's inner support sliding sleeve, anchorage support portion shored oil cylinder top is fixedly connected with anchorage support portion inner support sliding sleeve, anchorage support Portion shored oil cylinder bottom end is fixedly connected with anchorage support portion outer support sliding sleeve;Longitudinal roof girder level is fixedly mounted among the anchorage support portion At the top of anchorage support portion inner support sliding sleeve;Before the anchorage support portion longitudinal roof girder and anchorage support portion outer support sliding sleeve it Between diagonal brace oil cylinder before anchorage support portion is installed, diagonal brace oil cylinder one end is longitudinally pushed up before being hinged on anchorage support portion before anchorage support portion In the middle part of beam, the diagonal brace oil cylinder other end is hinged in the middle part of anchorage support portion outer support sliding sleeve before anchorage support portion;In anchoring branch Diagonal brace oil cylinder behind anchorage support portion, anchorage support portion are installed between longitudinal roof girder and anchorage support portion outer support sliding sleeve behind support part Diagonal brace oil cylinder one end is hinged on longitudinal roof girder middle part behind anchorage support portion afterwards, and the diagonal brace oil cylinder other end is hinged on behind anchorage support portion In the middle part of anchorage support portion outer support sliding sleeve;Advance is installed between anchorage support portion pedestal and driving support portion pedestal to push away Drive cylinder is moved, passage drive cylinder of advancing is used to provide onward impulse for the anchor combined unit of fully mechanized mining formula pick branch.
4. a kind of anchor combined unit of fully mechanized mining formula pick branch according to claim 3, it is characterised in that: the bore portion is mounted on On anchorage support portion pedestal, electric cabinet, pumping plant, anchorage support portion lateral support are also respectively provided on anchorage support portion pedestal Oil cylinder and anchorage support portion end support oil cylinder;The anchorage support portion lateral support oil cylinder is horizontally disposed, anchorage support portion side It is hinged on anchorage support portion pedestal to support cylinder one end, the anchorage support portion lateral support oil cylinder other end is equipped with anchoring branch Support part lateral support seat;The anchorage support portion end support oil cylinder tilts down setting, anchorage support portion end support oil cylinder One end is hinged on anchorage support portion pedestal, and the anchorage support portion end support oil cylinder other end is equipped with anchorage support portion tail end branch Support seat.
5. a kind of anchor combined unit of fully mechanized mining formula pick branch according to claim 1, it is characterised in that: the cutting units includes cutting Cut head, cutting arm, slide unit and sliding rail;The cutterhead uses horizontal shaft type structure or vertical axis structure;The cutterhead is mounted on Cutting arm one end, the cutting arm other end are connected on slide unit, and cutting arm has rotation freedom degree relative to slide unit;In the slide unit Inside it is provided with cutting motor;The sliding rail is horizontally arranged in scraper portion, and sliding rail is perpendicular with tunneling direction;The slide unit installation On the slide rail, slide unit has linear movement freedom degree relative to sliding rail.
6. a kind of anchor combined unit of fully mechanized mining formula pick branch according to claim 2, it is characterised in that: the scraper portion includes scraping The board-like mechanism that shovels coal, quarter bend transshipment acitivity, scraper-type transporting coal mechanism, transporting coal mechanism driving-motor, transporting coal mechanism driving-motor Mounting seat and scraper-type transporting coal mechanism mounting seat;The scraper-type shovel coal mechanism by working face transverse adjusting oil cylinder and pick It is connected into support portion pedestal, the scraper-type mechanism that shovels coal is connected by quarter bend transshipment acitivity with scraper-type transporting coal mechanism, scraper-type Transporting coal mechanism is mounted in scraper-type transporting coal mechanism mounting seat;The transporting coal mechanism driving-motor is used to be scraper-type conveyer Structure provides power, and transporting coal mechanism driving-motor is mounted in transporting coal mechanism driving-motor mounting seat;It shovels coal in the scraper-type Mechanism both ends horizontal is equipped with mechanism lateral support oil cylinder of shoveling coal, and the mechanism that shovels coal lateral support oil cylinder one end is packed in scraper-type shovel In coal mechanism, the mechanism that the shovels coal lateral support oil cylinder other end is equipped with mechanism lateral support seat of shoveling coal.
7. a kind of anchor combined unit of fully mechanized mining formula pick branch according to claim 3, it is characterised in that: in the driving support portion The steady drop vibration structural member of increasing is added on pedestal, the steady drop vibration structural member of increasing includes fixed block, briquetting and down pressing oil cylinder;It is described solid To determine block to be packed on driving support portion pedestal, fixed block is hinged with briquetting, and described down pressing oil cylinder one end is hinged on fixed block, The down pressing oil cylinder other end is hinged on briquetting, and briquetting has rotation freedom degree, briquetting and anchorage support portion bottom relative to hinge joint Seat compression fit.
CN201821359316.XU 2018-08-22 2018-08-22 A kind of anchor combined unit of fully mechanized mining formula pick branch Withdrawn - After Issue CN208777996U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821359316.XU CN208777996U (en) 2018-08-22 2018-08-22 A kind of anchor combined unit of fully mechanized mining formula pick branch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821359316.XU CN208777996U (en) 2018-08-22 2018-08-22 A kind of anchor combined unit of fully mechanized mining formula pick branch

Publications (1)

Publication Number Publication Date
CN208777996U true CN208777996U (en) 2019-04-23

Family

ID=66157978

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821359316.XU Withdrawn - After Issue CN208777996U (en) 2018-08-22 2018-08-22 A kind of anchor combined unit of fully mechanized mining formula pick branch

Country Status (1)

Country Link
CN (1) CN208777996U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109026050A (en) * 2018-08-22 2018-12-18 辽宁工程技术大学 A kind of anchor combined unit of fully mechanized mining formula pick branch and its an application method
CN110578519A (en) * 2019-10-16 2019-12-17 周口师范学院 Crawler-type driven walking supporting mechanism suitable for heading machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109026050A (en) * 2018-08-22 2018-12-18 辽宁工程技术大学 A kind of anchor combined unit of fully mechanized mining formula pick branch and its an application method
CN110578519A (en) * 2019-10-16 2019-12-17 周口师范学院 Crawler-type driven walking supporting mechanism suitable for heading machine

Similar Documents

Publication Publication Date Title
CN109026050A (en) A kind of anchor combined unit of fully mechanized mining formula pick branch and its an application method
CN109026049A (en) A kind of anchor combined unit of step type pick branch and its an application method
CN203669865U (en) Constant-support alpine bolter miner
CN104747199B (en) A kind of open type TBM with section of jurisdiction installation function
WO2009043234A1 (en) A track-mounted elevator top and side bolts and cables drilling machine
CN103266904B (en) Anchor bolt support device and heading machine with same
CN105952453B (en) Longwell protrusive working face of coal seam mechanization exploits complete set of equipments without lane
CN103104260B (en) Under complex geological condition, comprehensive-machine is to hand-pulled noodles coal-mining method
CN103277107B (en) Shield type roadway heading machine
CN102704927A (en) Comprehensive mechanization stone drift heading machine set
CN111485900A (en) Rock tunnel boring machine
CN103527228A (en) Self-propelled type temporary support and anchor support machine for coal mine roadway
CN110541705B (en) Crawler type excavating, supporting and anchoring combined unit and application method thereof
CN208777996U (en) A kind of anchor combined unit of fully mechanized mining formula pick branch
CN109538224A (en) A kind of novel coal lane high-speed driving machine
CN203362198U (en) Track walking type immediate support device of fully-mechanized drivage roadway
CN104632233A (en) Mechanical repair technology of distortional roadway and roadway repair machine
CN203499708U (en) Self-propelled coal mine tunnel temporary supporting anchor protecting machine
CN102383793A (en) Dual function machine for drilling and loading in tunnel
CN111255496B (en) Coal pillar auxiliary type mining advanced temporary support device and using method thereof
CN114013935A (en) Self-moving tail for rapid tunneling following type belt conveyor
CN117569829A (en) Hard rock heading machine and cutting mechanism
CN208777997U (en) A kind of anchor combined unit of step type pick branch
CN209494569U (en) A kind of novel coal lane high-speed driving machine
CN111828073A (en) Novel roadway support device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20190423

Effective date of abandoning: 20230704

AV01 Patent right actively abandoned

Granted publication date: 20190423

Effective date of abandoning: 20230704