CN208732432U CN201821245098.7U CN201821245098U CN208732432U CN 208732432 U CN208732432 U CN 208732432U CN 201821245098 U CN201821245098 U CN 201821245098U CN 208732432 U CN208732432 U CN 208732432U
Authority
CN
China
Prior art keywords
equalizer bar
hole
fixed
overboard
board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821245098.7U
Other languages
Chinese (zh)
Inventor
吕烜
吕宛珈
梁辛
杨扬
潘楠
潘一楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHAOXING LANDSCAPE & CONSTRUCTION Co Ltd
Original Assignee
SHAOXING LANDSCAPE & CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHAOXING LANDSCAPE & CONSTRUCTION Co Ltd filed Critical SHAOXING LANDSCAPE & CONSTRUCTION Co Ltd
Priority to CN201821245098.7U priority Critical patent/CN208732432U/en
Application granted granted Critical
Publication of CN208732432U publication Critical patent/CN208732432U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

The utility model discloses a kind of ancient architecture and gardens equalizer bar boards for building to install lifting device, including crane arm, travelling jack is installed on crane arm, it is hung on the suspension hook of the travelling jack and adjusts object band body, object is adjusted to be fixed with promotion equalizer bar with the lower end of body, the right end top surface for promoting equalizer bar is fixed with counterweight water tank, top cover is fixed at the top of counterweight water tank, there is through-hole of pouring water on top cover, overboard through-hole is formed on the bottom plate of counterweight water tank, overboard through-hole is communicated with the transverse holes formed in the middle part of equalizer bar are promoted, the right end inner sidewall of transverse holes forms internal screw thread;It can will promote equalizer bar by the travelling jack of crane arm and be promoted, then, manually rotate and upgrade equalizer bar, so that the board that the end for promoting equalizer bar is fixed is close to wall, to facilitate installation, meanwhile, the aqueous in counterweight water tank can be toppled over during installation, guarantee balance to after unloading in promotion equalizer bar, promote the equalizer bar moment in board.

Description

A kind of ancient architecture and gardens equalizer bar board installation lifting device for building
Technical field:
The utility model relates to gardens to install equipment technical field, and more specifically to a kind of ancient architecture and gardens are for building flat Balance beam board installs lifting device.
Background technique:
In existing gardens construction, the upper portion side wall in ancient building building needs to install board, and existing board is general Weight is bigger, manually lifts very troublesome, can only be lifted by crane with loop wheel machine, and when loop wheel machine lifts by crane, due on the metope of installation board Side has eaves, and the boom of loop wheel machine can not protrude into, and thus cannot achieve lifting installation;
And manually lift and dangerous, general board at 100 jin or more, and it is large-scale then reach very heavy, it is artificial to lift Rise support it is inadequate when, be easy to fall and pound on people, it is very dangerous, have security risk.
Utility model content:
The purpose of the utility model is to overcome the deficiencies in the prior art, provide a kind of ancient architecture and gardens equalizer bar board for building Lifting device is installed, it can will promote equalizer bar by the travelling jack of crane arm and be promoted, and then, manually rotate and upgrade Equalizer bar, so that the fixed board in the end for promoting equalizer bar is close to wall, thus facilitate installation, it is highly-safe, meanwhile, The aqueous in counterweight water tank can be toppled over when installation, thus in board after being unloaded in promotion equalizer bar, when promoting equalizer bar It carves and guarantees balance.
The scheme that the utility model solves the technical problem is:
A kind of ancient architecture and gardens equalizer bar board for building installs lifting device, including crane arm, on crane arm Travelling jack is installed, is hung on the suspension hook of the travelling jack and adjusts object band body, object is adjusted to be fixed with promotion balance with the lower end of body Beam, the right end top surface for promoting equalizer bar are fixed with counterweight water tank, and top cover is fixed at the top of counterweight water tank, has on top cover and pours water Through-hole, forms overboard through-hole on the bottom plate of counterweight water tank, overboard through-hole and promotes the transverse holes formed in the middle part of equalizer bar It communicates, the right end inner sidewall of transverse holes forms internal screw thread, and the right end of transverse holes stretches out the right side wall for promoting equalizer bar, plug spiral shell Connect on internal screw thread, the left part bottom surface for promoting equalizer bar forms down the overboard through-hole that is spirally connected, under overboard through-hole and the transverse holes of being spirally connected Left end bottom surface communicate, lower end cap is screwed onto down overboard be spirally connected in through-hole;
It is promoted and is fixed with holding frame on the left side wall of equalizer bar, holding frame includes two vertical pipes, the bottom of two vertical pipes Face is fixed on the right side top surface of bottom support plate, and the both ends of multiple transverse pipes are weldingly fixed on the inner sidewall of two vertical pipes On, the top and bottom for promoting the left end of equalizer bar are weldingly fixed in corresponding transverse pipe, the top sleeve of two vertical pipes There is telescopic rod, the top of telescopic rod is welded with hook part, and in bottom support plate, board is clamped in perpendicular the bottom abutment of board Between straight tube and hook part.
Further, the upper portion side wall of the vertical pipe is bolted with hold-down bolt, and the screw rod end of hold-down bolt is pressed against On the side wall of telescopic rod.
Further, the left end top surface for promoting equalizer bar is fixed with clump weight.
Further, the overboard through-hole is communicated with the upper through-hole that the right end top surface of transverse holes forms.
Further, the bottom surface of the counterweight water tank forms sealing annular groove, and density circle is nested in sealing annular In groove, overboard through-hole is in density circle, and density circle is pressed against on the top surface for promoting equalizer bar.
Further, irrigation pipe is fixed on the inner sidewall of the through-hole of pouring water, top cover is stretched out in the upper end of irrigation pipe Top surface.
The protrusion effect of the utility model is:
Compared with prior art, it can will promote equalizer bar by the travelling jack of crane arm and be promoted, then, people Work rotates and upgrades equalizer bar, so that the fixed board in the end for promoting equalizer bar is close to wall, to facilitate installation, safety Height, meanwhile, the aqueous in counterweight water tank can be toppled over during installation, thus in board after being unloaded in promotion equalizer bar, Promote equalizer bar moment guarantee balance.
Detailed description of the invention:
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the partial enlarged view of the utility model;
Fig. 3 is the partial structural diagram of the holding frame of the utility model.
Specific embodiment:
Embodiment is shown in a kind of as shown in Figure 1 to Figure 3, ancient architecture and gardens equalizer bar board installation lifting device for building, including Crane arm 10 is equipped with travelling jack 11 on crane arm 10, hangs on the suspension hook of the travelling jack 11 and adjusts object band Body 12 adjusts object to be fixed with the lower end of body 12 and promotes equalizer bar 20, and the right end top surface for promoting equalizer bar 20 is fixed with counterweight water tank 21, the top of counterweight water tank 21 is fixed with top cover 22, has through-hole 23 of pouring water on top cover 22, forms on the bottom plate of counterweight water tank 21 There is overboard through-hole 24, overboard through-hole 24 is communicated with the transverse holes 25 that the middle part for promoting equalizer bar 20 forms, the right side of transverse holes 25 End inner sidewall forms internal screw thread, and the right end of transverse holes 25 stretches out the right side wall for promoting equalizer bar 20, and plug 1 is screwed onto internal screw thread On, the left part bottom surface for promoting equalizer bar 20 forms down the overboard through-hole 26 that is spirally connected, under overboard be spirally connected through-hole 26 and transverse holes 25 Left end bottom surface communicates, and lower end cap 2 is screwed onto down overboard be spirally connected in through-hole 26;
It is promoted and is fixed with holding frame 30 on the left side wall of equalizer bar 20, holding frame 30 includes two vertical pipes 31, and two perpendicular The bottom surface of straight tube 31 is fixed on the right side top surface of bottom support plate 32, and the both ends of multiple transverse pipes 33 are weldingly fixed on two and erect On the inner sidewall of straight tube 31, the top and bottom for promoting the left end of equalizer bar 20 are weldingly fixed in corresponding transverse pipe 33, and two The top of a vertical pipe 31 is inserted with telescopic rod 34, and the top of telescopic rod 34 is welded with hook part 35, the bottom pressure of board 100 It leans against in bottom support plate 32, board 100 is clamped between vertical pipe 31 and hook part 35.
Further, the upper portion side wall of the vertical pipe 31 is bolted with hold-down bolt 36, the screw rod end of hold-down bolt 36 Portion is pressed against on the side wall of telescopic rod 34.
Further, the left end top surface for promoting equalizer bar 20 is fixed with clump weight 27.
Further, the overboard through-hole 24 is communicated with the upper through-hole 251 that the right end top surface of transverse holes 25 forms.
Further, the bottom surface of the counterweight water tank 21 forms sealing annular groove, and density circle 29 is nested in sealing In annular groove, overboard through-hole 24 is in density circle 29, and density circle 29 is pressed against on the top surface for promoting equalizer bar 20.
Further, it is fixed with irrigation pipe 231 on the inner sidewall of the through-hole 23 of pouring water, the upper end of irrigation pipe 231 is stretched The top surface of top cover 22 out.
This implementation when in use, by the bottom abutment of board 100 in bottom support plate 32, then, adjusts telescopic rod 34 High and low position then board 100 is clamped between vertical pipe 31 and hook part 35, then tighten hold-down bolt 36, so Afterwards, object band body 12 will be adjusted to hang on suspension hook, then, promoted at simultaneously close wall to be installed, then, pass through the room near wall The people that stand at the top of eaves rotates equalizer bar 20 is promoted, so that board 100 close to wall, then, unscrews hold-down bolt 36, lower hook part 35 is unloaded, board 100 can be unloaded and be installed, meanwhile, lower end cap 2 is unloaded can will be in counterweight water tank 21 Aqueous bleed off, guarantee that unloading the promotion equalizer bar 20 after board is in horizontality, then, can by travelling jack 11 to It moves right, is removed so that promoting equalizer bar 20, then, decline is placed on the ground, very convenient.
Finally, embodiment of above is merely to illustrate the utility model, and it is not limitation of the utility model, related skill The those of ordinary skill in art field can also make various changes in the case where not departing from the spirit and scope of the utility model Change and modification, therefore all equivalent technical solutions also belong to the scope of the utility model, the patent protection model of the utility model Enclosing should be defined by the claims.

Claims (6)

1. a kind of ancient architecture and gardens equalizer bar board for building installs lifting device, including crane arm (10), crane arm (10) travelling jack (11) are installed on, it is characterised in that: it is hung on the suspension hook of the travelling jack (11) and adjusts object band body (12), It adjusts object to be fixed with the lower end of body (12) and promotes equalizer bar (20), the right end top surface for promoting equalizer bar (20) is fixed with counterweight water tank (21), it is fixed with top cover (22) at the top of counterweight water tank (21), has on top cover (22) and pour water through-hole (23), counterweight water tank (21) Bottom plate on form overboard through-hole (24), overboard through-hole (24) and promote the transverse holes that form in the middle part of equalizer bar (20) (25) it communicates, the right end inner sidewall of transverse holes (25) forms internal screw thread, and the right end of transverse holes (25), which stretches out, promotes equalizer bar (20) right side wall, plug (1) are screwed on internal screw thread, promoted equalizer bar (20) left part bottom surface form down it is overboard be spirally connected it is logical Hole (26), under the overboard through-hole that is spirally connected (26) communicated with the left end bottom surface of transverse holes (25), lower end cap (2) is screwed onto down overboard be spirally connected In through-hole (26);
Promoted equalizer bar (20) left side wall on be fixed with holding frame (30), holding frame (30) include two vertical pipes (31), two The bottom surface of a vertical pipe (31) is fixed on the right side top surface of bottom support plate (32), and the both ends welding of multiple transverse pipes (33) is solid It is scheduled on the inner sidewall of two vertical pipes (31), the top and bottom of the left end of promotion equalizer bar (20) are weldingly fixed on corresponding In transverse pipe (33), it is inserted with telescopic rod (34) at the top of two vertical pipes (31), the top of telescopic rod (34) is welded with Hook part (35), on bottom support plate (32), board (100) is clamped in vertical pipe (31) and hooks the bottom abutment of board (100) Between portion (35).
2. a kind of ancient architecture and gardens equalizer bar board for building according to claim 1 installs lifting device, it is characterised in that: The upper portion side wall of the vertical pipe (31) is bolted with hold-down bolt (36), and the screw rod end of hold-down bolt (36) is pressed against telescopic rod (34) on side wall.
3. a kind of ancient architecture and gardens equalizer bar board for building according to claim 1 installs lifting device, it is characterised in that: The left end top surface for promoting equalizer bar (20) is fixed with clump weight (27).
4. a kind of ancient architecture and gardens equalizer bar board for building according to claim 1 installs lifting device, it is characterised in that: The overboard through-hole (24) communicates with the upper through-hole (251) that the right end top surface of transverse holes (25) forms.
5. a kind of ancient architecture and gardens equalizer bar board for building according to claim 1 installs lifting device, it is characterised in that: The bottom surface of the counterweight water tank (21) forms sealing annular groove, and density circle (29) is nested in sealing annular groove, overboard Through-hole (24) is in density circle (29), and density circle (29) is pressed against on the top surface for promoting equalizer bar (20).
6. a kind of ancient architecture and gardens equalizer bar board for building according to claim 1 installs lifting device, it is characterised in that: It is fixed with irrigation pipe (231) on the inner sidewall of the through-hole of pouring water (23), the top of top cover (22) is stretched out in the upper end of irrigation pipe (231) Face.
CN201821245098.7U 2018-08-03 2018-08-03 A kind of ancient architecture and gardens equalizer bar board installation lifting device for building Active CN208732432U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821245098.7U CN208732432U (en) 2018-08-03 2018-08-03 A kind of ancient architecture and gardens equalizer bar board installation lifting device for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821245098.7U CN208732432U (en) 2018-08-03 2018-08-03 A kind of ancient architecture and gardens equalizer bar board installation lifting device for building

Publications (1)

Publication Number Publication Date
CN208732432U true CN208732432U (en) 2019-04-12

Family

ID=66028147

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821245098.7U Active CN208732432U (en) 2018-08-03 2018-08-03 A kind of ancient architecture and gardens equalizer bar board installation lifting device for building

Country Status (1)

Country Link
CN (1) CN208732432U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111410123A (en) * 2020-04-24 2020-07-14 遂宁福家科技有限公司 Device for directly hoisting object into house by tower crane
CN115520771A (en) * 2022-11-30 2022-12-27 泉州市佩海科技有限公司 Auxiliary frame for installing compressor of air conditioning unit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111410123A (en) * 2020-04-24 2020-07-14 遂宁福家科技有限公司 Device for directly hoisting object into house by tower crane
CN115520771A (en) * 2022-11-30 2022-12-27 泉州市佩海科技有限公司 Auxiliary frame for installing compressor of air conditioning unit

Similar Documents

Publication Publication Date Title
CN208732432U (en) A kind of ancient architecture and gardens equalizer bar board installation lifting device for building
CN201224993Y (en) Elevating rack body for chimney and well path inner wall constructions
CN206341631U (en) One kind suspension vertical greening device
CN206156567U (en) Thin cylinder body hoist
CN202787267U (en) Automatic venting hopper device
CN204752012U (en) Wall -hanging miniature hoist
CN206859630U (en) Moveable cantilevered hanging basket device
CN212609004U (en) Self-adjusting surface contact lifting device
CN206643862U (en) A kind of pendent lamp installation auxiliary device of house ornamentation
CN208576972U (en) The manhole device of tank body
CN207761687U (en) A kind of shield-tunneling construction section of jurisdiction hanging apparatus
CN107720302A (en) A kind of effortless device of convertible bottled water pouring
CN209145257U (en) Hang lift-type pit shaft platform
CN208429796U (en) A kind of bridge installation tool vehicle
CN206955520U (en) The anti-heel brace of collapse type three
CN202379580U (en) Pipeline horizontal lifting appliance with automatic hook
CN207141307U (en) A kind of equipment handling support on ship main deck
CN205687396U (en) A kind of rotary suspension hook of wind-power tower
CN106586822A (en) Lifting tool
CN206244264U (en) A kind of auxiliary lifting appliance for leveling
CN205838328U (en) A kind of reel lifting tool
CN206872274U (en) A kind of spiral case dismounts aid
CN206203723U (en) A kind of ship is hung with petroleum pipeline
CN210236921U (en) Civil engineering construction is with hoist machine
CN206336912U (en) A kind of cylinder head one side clamping lifting device

Legal Events

Date Code Title Description
GR01 Patent grant