CN208603948U - A kind of buried sewage treatment equipment - Google Patents

A kind of buried sewage treatment equipment Download PDF

Info

Publication number
CN208603948U
CN208603948U CN201820592767.1U CN201820592767U CN208603948U CN 208603948 U CN208603948 U CN 208603948U CN 201820592767 U CN201820592767 U CN 201820592767U CN 208603948 U CN208603948 U CN 208603948U
Authority
CN
China
Prior art keywords
sedimentation basin
sludge
bottom wall
sewage treatment
treatment equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820592767.1U
Other languages
Chinese (zh)
Inventor
许铁强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820592767.1U priority Critical patent/CN208603948U/en
Application granted granted Critical
Publication of CN208603948U publication Critical patent/CN208603948U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Aeration Devices For Treatment Of Activated Polluted Sludge (AREA)

Abstract

The utility model relates to technical field of sewage, disclose a kind of buried sewage treatment equipment, including being sequentially connected the grid connect, conditioning tank, anaerobic pond, aerobic tank, sedimentation basin, filtering ponds and clear water reserviors, the sludge pipe communicated with sedimentation basin bottom wall is provided on sedimentation basin, it is provided with sludge pump on sludge pipe, is provided between sedimentation basin and clear water reserviors for the sludge on sedimentation basin bottom wall to be rushed to the overflow cascade washers at sludge pipe;The drainpipe with drain valve is provided on filtering ponds, the bottom wall of sedimentation basin is extended obliquely downward towards the side close to sludge pipe.When precipitating more sludge in sedimentation basin, the drainpipe first passed through on sedimentation basin empties the water in sedimentation basin;Then sludge pump is opened, the sludge for precipitating bottom of pond portion is discharged by sludge pipe;At the same time, spray cleaning is carried out to sedimentation basin bottom wall by spray equipment, so that convenient clear up the sludge of sedimentation basin bottom wall.

Description

A kind of buried sewage treatment equipment
Technical field
The utility model relates to technical field of sewage, in particular to a kind of buried sewage treatment equipment.
Background technique
With the development of increase and the industrial and agricultural production of urban population, production and generated sewage in life process also day Increase is gone through, in order to mitigate harm of the sewage to water body and environment, needs to purify it when by sewage discharge into environment Processing.Buried sewage treatment equipment is a kind of modular high-efficiency sewage biological treating equipment, be one kind with biomembrane is net Change the sewage biological treatment system of main body.
Currently, application publication number is CN103663852A, data of publication of application is that the Chinese patent on March 26th, 2014 discloses A kind of buried sewage treatment equipment, including grille well, conditioning tank, anaerobic pond, aerobic tank, the sedimentation basin, mistake set gradually Filter tank, clear water reserviors.
A large amount of sludge can be generated in sewage disposal process, sludge precipitates in sedimentation basin, and sewage is then from sedimentation basin top Overflow enters filtering ponds, to realize separation of solid and liquid.Turbidity of sewage to guarantee overflow is up to standard, needs frequent spoil disposal.Spoil disposal Flow automatically by sludge, partial sludge cannot flow automatically discharge, will affect turbidity of sewage after sludge accumulation is more, need artificial periodically progress Cleaning, causes to be more troublesome when clearing up sludge.
Utility model content
The purpose of the utility model is to provide a kind of buried sewage treatment equipments, with the dirt in easy cleaning sedimentation basin The effect of mud.
The above-mentioned technical purpose of the utility model has the technical scheme that at a kind of buried sewage Equipment is managed, it is described heavy including being sequentially connected the grid connect, conditioning tank, anaerobic pond, aerobic tank, sedimentation basin, filtering ponds and clear water reserviors It is provided with the sludge pipe communicated with the sedimentation basin bottom wall on the pond of shallow lake, sludge pump, the sedimentation basin are provided on the sludge pipe It is provided between the clear water reserviors for the sludge on sedimentation basin bottom wall to be rushed to the overflow cascade washers at sludge pipe;The filtering The drainpipe with drain valve is provided on pond, the side of the close sludge pipe of bottom wall direction of the sedimentation basin is diagonally downward Extend.
The utility model is further arranged to: the sedimentation basin bottom wall is provided with opening close to the side of the sludge pipe The afflux groove set up offers bore on the bottom wall of the afflux groove and reduces and communicate along vertical direction with sludge pipe Sewage draining exit.
The utility model is further arranged to: the cover board for covering afflux groove is provided on the sedimentation basin.
The utility model is further arranged to: the side of the cover board is hinged on close to sedimentation basin bottom wall lower end side Sedimentation basin side wall on, be fixedly connected on the cover board for drive cover board rotate drawstring, the sedimentation basin top hinge It is connected to inspection window;The drawstring is bundled in the top for checking window far from one end of cover board.
The utility model is further arranged to: the overflow cascade washers includes that mounting rack at the top of sedimentation basin is arranged in, sets Set on mounting rack spray tube, spray head arranged on the spray pipe, the water inlet pipe being arranged between spray tube and clear water reserviors, Water pump on water inlet pipe is set.
The utility model is further arranged to: the mounting rack includes being fixedly connected on pedestal at the top of sedimentation basin, cunning It moves connection on the base and the sliding rack for installing for spray tube, setting is between pedestal and sliding rack and for driving sliding The mobile actuator of frame;It is connected between the spray tube and water inlet pipe by hose.
The utility model is further arranged to: the bottom wall of the sedimentation basin is directed away from the side of filtering ponds diagonally downward Extend, is provided with ceramic tile layer on the bottom wall of the sedimentation basin.
In conclusion the utility model has the following beneficial effects:
1, when precipitating more sludge in sedimentation basin, the running of first arrestment then passes through the draining on sedimentation basin Pipe empties the water in sedimentation basin;Then sludge pump is opened, the sludge for precipitating bottom of pond portion is discharged by sludge pipe;It is same with this When, spray cleaning is carried out to sedimentation basin bottom wall by spray equipment, so that the sludge on sedimentation basin bottom wall can be along precipitating The tilt angle of bottom of pond wall flows to sludge pipe, so that convenient clear up the sludge of sedimentation basin bottom wall;
2, one end of sludge pipe is communicated with the sewage draining exit in afflux groove, covers afflux groove by cover board, so that heavy In the use process of shallow lake pond, sludge is not easy to block sewage draining exit because building up;And in sludge pipe and sludge pump discharge sludge, because Spray equipment forms mud after rinsing to sludge, is not easy to plug sewage draining exit at this time;
3, when actuator driving sliding rack is mobile, sliding rack drives spray tube mobile, thus the spray head on spray tube Uniformly the bottom wall of sedimentation basin can be sprayed;
4, ceramic tile layer is set on the bottom wall of sedimentation basin, the coefficient of friction of the bottom wall of sedimentation basin can be reduced, so that sludge It is more convenient when being flowed on bottom wall, thus convenient so that sludge flows to sludge pipe.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Appended drawing reference: 1, grid;2, conditioning tank;3, anaerobic pond;4, aerobic tank;5, sedimentation basin;51, drainpipe;52, it drains Valve;53, afflux groove;54, sewage draining exit;55, cover board;56, drawstring;57, ceramic tile layer;6, filtering ponds;7, clear water reserviors;81, sludge pipe; 82, sludge pump;9, overflow cascade washers;91, mounting rack;911, pedestal;912, sliding rack;913, actuator;92, spray tube;93, it sprays Drench head;94, water inlet pipe;95, water pump;96, hose.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment 1: a kind of buried sewage treatment equipment, as shown in Figure 1, including being sequentially connected grid 1, the conditioning tank connect 2, anaerobic pond 3, aerobic tank 4, sedimentation basin 5, filtering ponds 6 and clear water reserviors 7.
As shown in Figure 1, the side that the bottom wall of sedimentation basin 5 is directed away from filtering ponds 6 is arranged diagonally downward, and sedimentation basin 5 Ceramic tile layer 57 is formed with after being bonded ceramic tile on bottom wall;And the afflux groove of opening upwards is offered in the lower end of 5 bottom wall of sedimentation basin 53, while bore diminishing sewage draining exit 54 along vertical direction is offered on the bottom wall of afflux groove 53.And in sedimentation basin 5 On be connected with drainpipe 51, drain valve 52 is installed on drainpipe 51.It is provided on sedimentation basin 5 for covering afflux simultaneously The cover board 55 of slot 53, the side of cover board 55 are hinged on 5 side wall of sedimentation basin of 5 bottom wall lower end side of sedimentation basin, cover board The drawstring 56 for driving cover board 55 to rotate is fixedly connected on 55, the top of sedimentation basin 5, which is hinged with, checks window 58;Drawstring 56 is remote One end from cover board 55 is bundled in the top for checking window 58.
As shown in Figure 1, being connected with the sludge pipe 81 communicated with sewage draining exit 54 on sedimentation basin 5, it is equipped on sewage pipe Sludge pump 82.
As shown in Figure 1, being provided between sedimentation basin 5 and clear water reserviors 7 simultaneously for rushing the sludge on 5 bottom wall of sedimentation basin Overflow cascade washers at sludge pipe 81.Spray equipment includes mounting rack 91, spray tube 92, spray head 93, water inlet pipe 94 and water pump 95.Mounting rack 91 include the pedestal 911 for being fixedly connected on the top of sedimentation basin 5, sliding be connected on pedestal 911 sliding rack 912, The actuator 913 being mounted between pedestal 911 and sliding rack 912, actuator 913 are to be fixedly connected on pedestal 911 and piston Bar is connected to the cylinder in sliding rack 912;Spray tube 92 is fixedly connected in sliding rack 912, and spray head 93 has multiple and more A spray head 93 along spray tube 92 length direction arranged distribution;Water pump 95 is communicated with clear water reserviors 7, water inlet pipe 94 is connected to water Between pump 95 and sedimentation basin 5, water inlet pipe 94 is connected by hose 96 with spray tube 92 close to one end of sedimentation basin 5.
Implementation principle: when precipitating more sludge in sedimentation basin 5, the running of first arrestment then passes through sedimentation basin 5 On drainpipe 51 by sedimentation basin 5 water empty;Then cover board 55 is opened by drawstring 56, sludge is enabled to flow to afflux groove In 53;Then sludge pump 82 is opened, the sludge of 5 bottom of sedimentation basin is discharged by sludge pipe 81;At the same time, in spray equipment In, the water in clear water reserviors 7 is transported at spray tube 92 by water pump 95, and from spray head 93 spray, realize to 5 bottom wall of sedimentation basin into Row spray cleaning, so that the sludge on 5 bottom wall of sedimentation basin can flow to sludge pipe along the tilt angle of 5 bottom wall of sedimentation basin 81, so that convenient clear up the sludge of 5 bottom wall of sedimentation basin.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (7)

1. a kind of buried sewage treatment equipment, including being sequentially connected the grid connect (1), conditioning tank (2), anaerobic pond (3), aerobic Pond (4), sedimentation basin (5), filtering ponds (6) and clear water reserviors (7), it is characterised in that: be provided on the sedimentation basin (5) and sink with described The sludge pipe (81) that shallow lake pond (5) bottom wall communicates is provided with sludge pump (82) on the sludge pipe (81), the sedimentation basin (5) with It is provided between the clear water reserviors (7) for the sludge on sedimentation basin (5) bottom wall to be rushed to the overflow cascade washers at sludge pipe (81); The drainpipe (51) with drain valve (52) is provided on the filtering ponds (6), the bottom wall of the sedimentation basin (5) is towards close to institute The side for stating sludge pipe (81) extends obliquely downward.
2. a kind of buried sewage treatment equipment according to claim 1, it is characterised in that: sedimentation basin (5) bottom wall The afflux groove (53) of opening upwards setting is provided with close to the side of the sludge pipe (81), on the bottom wall of the afflux groove (53) Offer the sewage draining exit (54) that bore is reduced along vertical direction and communicated with sludge pipe (81).
3. a kind of buried sewage treatment equipment according to claim 2, it is characterised in that: set on the sedimentation basin (5) It is equipped with the cover board (55) for covering afflux groove (53).
4. a kind of buried sewage treatment equipment according to claim 3, it is characterised in that: the side of the cover board (55) It is hinged on sedimentation basin (5) side wall of sedimentation basin (5) bottom wall lower end side, is fixedly connected on the cover board (55) useful It is hinged at the top of the drawstring (56) for driving cover board (55) to rotate, the sedimentation basin (5) and checks window (58);The drawstring (56) One end far from cover board (55) is bundled in the top for checking window (58).
5. a kind of buried sewage treatment equipment according to claim 1, it is characterised in that: the overflow cascade washers includes setting It sets the mounting rack (91) at the top of sedimentation basin (5), the spray tube (92) being arranged on mounting rack (91), be arranged in spray tube (92) On spray head (93), water inlet pipe (94) between spray tube (92) and clear water reserviors (7), setting are set on water inlet pipe (94) Water pump (95).
6. a kind of buried sewage treatment equipment according to claim 5, it is characterised in that: the mounting rack (91) includes It is fixedly connected on the pedestal (911) at the top of sedimentation basin (5), sliding is connected on pedestal (911) and is used to pacify for spray tube (92) The sliding rack (912) of dress, the drive for being arranged between pedestal (911) and sliding rack (912) and being used to drive sliding rack (912) mobile Moving part (913);It is connected between the spray tube (92) and water inlet pipe (94) by hose (96).
7. a kind of buried sewage treatment equipment according to claim 1, it is characterised in that: the bottom of the sedimentation basin (5) The side that wall is directed away from filtering ponds (6) extends obliquely downward, and is provided with ceramic tile layer (57) on the bottom wall of the sedimentation basin (5).
CN201820592767.1U 2018-04-24 2018-04-24 A kind of buried sewage treatment equipment Expired - Fee Related CN208603948U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820592767.1U CN208603948U (en) 2018-04-24 2018-04-24 A kind of buried sewage treatment equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820592767.1U CN208603948U (en) 2018-04-24 2018-04-24 A kind of buried sewage treatment equipment

Publications (1)

Publication Number Publication Date
CN208603948U true CN208603948U (en) 2019-03-15

Family

ID=65660817

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820592767.1U Expired - Fee Related CN208603948U (en) 2018-04-24 2018-04-24 A kind of buried sewage treatment equipment

Country Status (1)

Country Link
CN (1) CN208603948U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110655270A (en) * 2019-08-30 2020-01-07 杭州广业环保有限公司 Bury formula domestic sewage treatment system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110655270A (en) * 2019-08-30 2020-01-07 杭州广业环保有限公司 Bury formula domestic sewage treatment system

Similar Documents

Publication Publication Date Title
CN105155615B (en) A kind of first rain collection processing system implementing with self-cleaning function
CN108840460B (en) Conveying type sewage stage treatment environment-friendly device
KR101637562B1 (en) Apparatus for treating rain water
CN105879464A (en) Municipal sewage sand removing device and method
CN105569163B (en) Region burst rain processing system based on mixed flow tubulation net
CN207137521U (en) A kind of sewage disposal device of precipitation and filtering integral
CN210384954U (en) Sewage treatment device
CN208603948U (en) A kind of buried sewage treatment equipment
CN201325891Y (en) Device for separating floater, suspended substance and precipitate from sewage
CN205475588U (en) Regional burst rainwater processing system based on reposition of redundant personnel tubulation net
CN103215985B (en) Community rainwater utilization system based on secondary split-flow of rainwater and sewage
CN205867668U (en) Swash plate washing unit
CN209234690U (en) A kind of concealed circulating filtration fish jar
CN208152137U (en) Biological delaying basin
CN207761000U (en) Online Processing System with precipitation and filtering function
CN214763500U (en) Plain concrete grit chamber
CN207582617U (en) A kind of drainage system with first rain storage pond and online processing storage pond
CN207761021U (en) Online device for treating rain water with bottom-open type structure flusher
CN206783489U (en) Transformer station's sewage treatment unit
CN207307277U (en) A kind of inclined tube detention tank with cleaning device
CN2448822Y (en) Composite sewage treatment equipment
CN206279050U (en) A kind of rainwater utilization pre-treatment unmanned plane
CN206607652U (en) The first unconspicuous separate system of rain feature handles exhaust system online
CN220747083U (en) Outdoor drainage equipment of house
CN213771620U (en) Sewage treatment device for green building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190315

Termination date: 20190424