Prior art keywords
conditioning tank
agitating device
connect
pipe
mining method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820934102.4U
Other languages
Chinese (zh)
Inventor
吕青松
贺维国
曲艺明
段悟哲
金若翃
田峰
毕经东
刘鹏
宋超业
冯霞
朱祝龙
程士好
任靳玉
李东蒙
冯巍
王倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
Original Assignee
China Railway Liuyuan Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Liuyuan Group Co Ltd filed Critical China Railway Liuyuan Group Co Ltd
Priority to CN201820934102.4U priority Critical patent/CN208561977U/en
Application granted granted Critical
Publication of CN208561977U publication Critical patent/CN208561977U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Suspended Particles By Flocculating Agents (AREA)
  • Physical Water Treatments (AREA)

Abstract

A kind of mobile integrated mining method construction wastewater treatment equipment, it is related to underground engineering mining method construction technical field;Water inlet pipe and oil exit pipe are connected in slagging-off oil separator, slagging-off oil separator is connect by the first outlet pipe with coagulating basin, the first dosing agitating device is provided in coagulating basin, coagulating basin is connect by the first water pump and the first drainpipe with centrifuge, centrifuge is connect with the second outlet pipe, sludge pipe, second outlet pipe is connect with ammonia nitrogen conditioning tank, the second dosing agitating device is provided in ammonia nitrogen conditioning tank, the side of second dosing agitating device is provided with weir divider, the side of weir divider is provided with pH conditioning tank, and third dosing agitating device is provided in pH conditioning tank.The utility model can be realized in the hole of construction waste water and be handled, and wastewater treatment capacity is greatly reduced;Load-carrying wheel can be moved forward with the propulsion of work surface;Fundamentally solve the problems, such as that mining method construction waste water is reluctant.

Description

A kind of mobile integrated mining method construction wastewater treatment equipment
Technical field
The utility model relates to underground engineering mining method construction technical fields, and in particular to a kind of mobile integrated mine Method construction wastewater treatment equipment.
Background technique
With the development of economic technology, more and more underground engineerings such as railway tunnel, vcehicular tunnel, subway tunnel, comprehensive Piping lane etc. is closed to be built.Main engineering method one of of the Mining Method as constructing underground building is widely used in underground engineering neck Domain.Certain construction waste water can be generated when Mining Method constructing underground building at work surface.Waste water major pollutants are as follows: suspend Object, petroleum-type, ammonia nitrogen, and pH higher.Past, underground engineering construction draining was provisional row in addition since environmental consciousness is thin Water, pollution are long-term ignored.Sedimentation basin, oil separator, engineering practice hair is typically only arranged in underground engineering in the design process Existing, construction waste water at all can not be up to standard.
Underground engineering construction waste water is concentrated mainly on two linings and does not complete section i.e. operation side between two lining completion sections Region, its waste water of region that two linings have performed is mainly structural percolating water, and water quality is similar with underground water, can be with direct emission.Mesh It is preceding also to there are individual underground engineerings to take treatment measures to construction waste water, but treatment measures are set to ground or underground engineering Construct oral area, due to underground engineering narrow space, two serve as a contrast do not complete section waste water completed with two linings it is shared after segment structures infiltration mixes Ground is discharged in temporary drainage system, and the processing unit actual treatment amount for being set to ground is caused to cover two lining to be treated not Complete section waste water and be not required to two lining to be processed to complete segment structure infiltration, actual treatment amount is very big.Engineering practice shows to be set to There are two types of results mostly for the processing unit on ground: one is because treatment scale is excessive, cost is excessively high and hard to carry on;It is a kind of because It is too small for design treatment ability, and actual treatment scale is excessive and is difficult to up to standard.
It is easily installed in conclusion underground engineering mining method construction field urgent need is a set of at present, is easy to remove, can be directed to Two serve as a contrast the mining method construction wastewater treatment equipment for not completing and handling in section construction waste water progress hole.
Utility model content
The purpose of this utility model is that in view of the drawbacks of the prior art and insufficient, mine can be effectively removed by providing one kind The mobile integrated mining method construction wastewater treatment equipment of the pollutants such as suspended matter, petroleum-type, ammonia nitrogen in method construction waste water.
In order to achieve the above purposes, the technical solution adopted by the utility model is:, and it includes water inlet pipe, slagging-off oil separator, the One outlet pipe, oil exit pipe, coagulating basin, the first dosing agitating device, the first water pump, the first drainpipe, centrifuge, the second water outlet Pipe, sludge pipe, ammonia nitrogen conditioning tank, the second dosing agitating device, weir divider, pH conditioning tank, third dosing agitating device;It is described Slagging-off oil separator on be connected with water inlet pipe and oil exit pipe, slagging-off oil separator is connect by the first outlet pipe with coagulating basin, coagulation The first dosing agitating device is provided in pond, coagulating basin is connect by the first water pump and the first drainpipe with centrifuge, centrifuge It is connect with the second outlet pipe, sludge pipe, the second outlet pipe is connect with ammonia nitrogen conditioning tank, and the second dosing is provided in ammonia nitrogen conditioning tank Agitating device, the side of the second dosing agitating device are provided with weir divider, and the side of weir divider is provided with pH conditioning tank, pH Third dosing agitating device is provided in conditioning tank.
Preferably, the pH conditioning tank is connect by the second water pump and the second drainpipe with transfer pond.
Preferably, the slagging-off oil separator, coagulating basin, centrifuge, ammonia nitrogen conditioning tank and the setting of pH conditioning tank are being dragged On chassis, the bottom of trailer chassis is equipped with load-carrying wheel.
Preferably, the water inlet pipe is connect by submersible sewage pump with catch pit.
When the utility model operates, is adjusted with oil removal precipitating, dosing flocculation, centrifuge separation, ammonia nitrogen and PH adjusts technique Flow processing Tunneling by mining method operation surface construction waste water.Operation side waste water is pooled to the catch pit before work surface, passes through collection Puddle it is first it is heavy after, raw wastewater is promoted to the utility model through submersible sewage pump.Raw wastewater initially enters slagging-off oil removal by water inlet pipe Pond, bulky grain suspended matter are slagged tap by filter screen retention, and petroleum substance contained by waste water is retained by slagging-off oil separator and passes through oil extraction Pipe periodically collects outward transport.Waste water through the first outlet pipe enters coagulating basin after the slagging-off oil removal processing by the oil separator that removes the gred, through the Through the first water pump lifting after one dosing agitating device dosing coagulation, processing is centrifuged through the first drainpipe to centrifuge. Waste water after flocculation is separated into sludge and waste water by centrifuge, and sludge B is through sludge pipe outlet and collects outward transport landfill.Through centrifuge Treated waste water enters ammonia nitrogen conditioning tank through the second outlet pipe, by overflowing after the second dosing agitating device dosing removes ammonia nitrogen Stream partition enters pH conditioning tank, after third dosing agitating device chemicals addition control pH value, handles up to standard.Through second after waste water up to standard Water pump lifting is drained by the second drainpipe to transfer pond, is completed together with segment structure percolating water with two linings through temporary drainage system System is promoted to construction portal emission.
After adopting the above structure, the utility model is the beneficial effects are as follows: a kind of movable type described in the utility model Integrated mining method construction wastewater treatment equipment greatly reduces wastewater treatment capacity, it can be achieved that processing in the hole of construction waste water;It carries Roller can accordingly be moved with the propulsion of work surface, can by work surface wastewater treatment it is up to standard after be discharged into tunnel drainage system and be discharged together Outside hole;Handle it is up to standard after waste water can with two lining complete sections structure seep water share temporary drainage system together with promote discharge, from Fundamentally solve the problems, such as that mining method construction waste water is reluctant.
Detailed description of the invention
Fig. 1 is the structure chart of the utility model.
Specific embodiment
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, before not making the creative labor property It puts, is also possible to obtain other drawings based on these drawings.
Referring to as shown in Figure 1, present embodiment adopts the following technical scheme that it includes water inlet pipe 1, slagging-off oil separator 2, the first outlet pipe 3, oil exit pipe 4, coagulating basin 5, the first dosing agitating device 6, the first water pump 7, the first drainpipe 8, centrifuge 9, the second outlet pipe 10, sludge pipe 11, ammonia nitrogen conditioning tank 12, the second dosing agitating device 13, weir divider 14, pH conditioning tank 15, third dosing agitating device 16;Water inlet pipe 1 and oil exit pipe 4 are connected in the slagging-off oil separator 2, slagging-off oil separator 2 is logical It crosses the first outlet pipe 3 to connect with coagulating basin 5, the first dosing agitating device 6 is provided in coagulating basin 5, coagulating basin 5 passes through the first water Pump 7 and the first drainpipe 8 are connect with centrifuge 9, and centrifuge 9 is connect with the second outlet pipe 10, sludge pipe 11, the second outlet pipe 10 It is connect with ammonia nitrogen conditioning tank 12, the second dosing agitating device 13, the second dosing agitating device 13 is provided in ammonia nitrogen conditioning tank 12 Side be provided with weir divider 14, the side of weir divider 14 is provided with pH conditioning tank 15, and is provided in pH conditioning tank 15 Three dosing agitating devices 16.
Preferably, the pH conditioning tank 15 is connect by the second water pump 17 and the second drainpipe 18 with transfer pond.
Preferably, the slagging-off oil separator 2, coagulating basin 5, centrifuge 9, ammonia nitrogen conditioning tank 12 and pH conditioning tank 15 are set It sets on trailer chassis 19, the bottom of trailer chassis 19 is equipped with load-carrying wheel 20.
Preferably, the water inlet pipe 1 is connect by submersible sewage pump with catch pit.
When present embodiment operates, operation side waste water is pooled to the catch pit before work surface, passes through catch pit It is first it is heavy after, raw wastewater C is promoted to present embodiment through submersible sewage pump.Raw wastewater by water inlet pipe 1 initially enter slagging-off every Oil sump 2, bulky grain suspended matter are slagged tap by filter screen retention, and petroleum substance A contained by waste water is retained and passed through by slagging-off oil separator 2 Oil exit pipe 4 periodically collects outward transport.Enter coagulation through the first outlet pipe 3 after slagging-off oil removal processing of the waste water by the oil separator 2 that removes the gred Pond 5, after 6 dosing coagulation of the first dosing agitating device through the first water pump 7 promoted, through the first drainpipe 8 to centrifuge 9 carry out from Heart separating treatment.Waste water after flocculation is separated into sludge and waste water by centrifuge 9, and sludge B is through 11 outlet of sludge pipe and collects outer Fortune landfill.Enter ammonia nitrogen conditioning tank 12 through the second outlet pipe 10 through treated the waste water of centrifuge 9, through the second dosing agitating device Enter pH conditioning tank 15 by weir divider 14 after 13 dosings removal ammonia nitrogen, through 16 chemicals addition control pH value of third dosing agitating device Afterwards, it handles up to standard.It is promoted after waste water D up to standard through the second water pump 17, is drained by the second drainpipe 18 to transfer pond, with two linings Segment structure percolating water is completed together through temporary drainage system improving to portal emission of constructing.
First dosing agitating device 6, centrifuge 9 described in present embodiment, the second dosing agitating device 13 and Three dosing agitating devices 16 are the prior art, and this will not be repeated here.
After adopting the above structure, present embodiment is the beneficial effects are as follows: one described in present embodiment The mobile integrated mining method construction wastewater treatment equipment of kind greatly reduces waste water, it can be achieved that processing in the hole of construction waste water Treating capacity;Load-carrying wheel can be moved forward with the propulsion of work surface;Handle it is up to standard after waste water can with two lining complete sections structure The shared temporary drainage system that seeps water promotes discharge together, fundamentally solves the problems, such as that mining method construction waste water is reluctant.
The advantages of basic principles and main features and the utility model of the utility model have been shown and described above.This The technical staff of industry is retouched in above embodiments and description it should be appreciated that the present utility model is not limited to the above embodiments That states only illustrates the principles of the present invention, on the premise of not departing from the spirit and scope of the utility model, the utility model It will also have various changes and improvements, these various changes and improvements fall within the scope of the claimed invention.This is practical new Type is claimed range and is defined by the appending claims and its equivalent thereof.

Claims (4)

1. a kind of mobile integrated mining method construction wastewater treatment equipment, it is characterised in that: it includes water inlet pipe, slagging-off oil removal Pond, the first outlet pipe, oil exit pipe, coagulating basin, the first dosing agitating device, the first water pump, the first drainpipe, centrifuge, second Outlet pipe, sludge pipe, ammonia nitrogen conditioning tank, the second dosing agitating device, weir divider, pH conditioning tank, third dosing agitating device; Water inlet pipe and oil exit pipe are connected in the slagging-off oil separator, slagging-off oil separator is connect by the first outlet pipe with coagulating basin, The first dosing agitating device is provided in coagulating basin, coagulating basin is connect by the first water pump and the first drainpipe with centrifuge, from Scheming is connect with the second outlet pipe, sludge pipe, and the second outlet pipe is connect with ammonia nitrogen conditioning tank, is provided with second in ammonia nitrogen conditioning tank Dosing agitating device, the side of the second dosing agitating device are provided with weir divider, and the side of weir divider is provided with pH adjusting Pond is provided with third dosing agitating device in pH conditioning tank.
2. a kind of mobile integrated mining method construction wastewater treatment equipment according to claim 1, it is characterised in that: institute The pH conditioning tank stated is connect by the second water pump and the second drainpipe with transfer pond.
3. a kind of mobile integrated mining method construction wastewater treatment equipment according to claim 1, it is characterised in that: institute Coagulating basin, ammonia nitrogen conditioning tank and the pH conditioning tank stated are arranged on trailer chassis, and the bottom of trailer chassis is equipped with load-carrying wheel.
4. a kind of mobile integrated mining method construction wastewater treatment equipment according to claim 1, it is characterised in that: institute The water inlet pipe stated is connect by submersible sewage pump with catch pit.
CN201820934102.4U 2018-06-15 2018-06-15 A kind of mobile integrated mining method construction wastewater treatment equipment Active CN208561977U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820934102.4U CN208561977U (en) 2018-06-15 2018-06-15 A kind of mobile integrated mining method construction wastewater treatment equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820934102.4U CN208561977U (en) 2018-06-15 2018-06-15 A kind of mobile integrated mining method construction wastewater treatment equipment

Publications (1)

Publication Number Publication Date
CN208561977U true CN208561977U (en) 2019-03-01

Family

ID=65487001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820934102.4U Active CN208561977U (en) 2018-06-15 2018-06-15 A kind of mobile integrated mining method construction wastewater treatment equipment

Country Status (1)

Country Link
CN (1) CN208561977U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108483753A (en) * 2018-06-15 2018-09-04 中铁第六勘察设计院集团有限公司 A kind of mobile integrated mining method construction wastewater treatment equipment

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108483753A (en) * 2018-06-15 2018-09-04 中铁第六勘察设计院集团有限公司 A kind of mobile integrated mining method construction wastewater treatment equipment
CN108483753B (en) * 2018-06-15 2023-10-31 中铁第六勘察设计院集团有限公司 Mobile integrated mine construction wastewater treatment device

Similar Documents

Publication Publication Date Title
CN103232132B (en) Magnetic separation method and apparatus for mine water underground treatment
CN104174191B (en) Integrated grit chamber for treating rainwater and treatment method
CN211676669U (en) Shield muck treatment system
CN105170631B (en) A kind of quick elution complexes of contaminated soil remediation
CN104478193B (en) The dewatering system of a kind of Soil leaching mud and method thereof
CN103570179A (en) Underground mine water treatment system and method
CN208561977U (en) A kind of mobile integrated mining method construction wastewater treatment equipment
CN203425567U (en) Sewage treatment device
CN103981375A (en) Gold extraction method by heap leaching
CN206769017U (en) A kind of hole pumping system with precipitation function
CN206735879U (en) Integrated high-efficiency magnetic-coagulation precipitation equipment
CN202766398U (en) Pull type sludge treatment equipment
CN207016661U (en) A kind of portable mud thickener
CN104963333A (en) Combined treatment method for dehumidification and vacuum preloading of dredger fill and slurry flocculation
CN109956574A (en) A kind of bulk cement carrier carwash waste liquid synthesization utilizes method and system
CN205840846U (en) Drilling mud does not land processing means
CN108483753A (en) A kind of mobile integrated mining method construction wastewater treatment equipment
CN105417660B (en) Method and device for treating production wastewater of water works
CN212609938U (en) TBM construction tunnel sewage treatment system
CN107754395A (en) A kind of sludge discharging method, sludge drainage system and sludge discharging machine
CN207294427U (en) A kind of quick processing system of beneficiation wastewater
CN208055076U (en) A kind of novel integrated mine water pre-treatment means
CN207048708U (en) A kind of mud does not land intelligent environment protection press filtration skid equipment
CN107434330A (en) A kind of manpower rapid-infiltration sewage water treatment method
CN105174591A (en) Equipment for treating water under mine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant