CN208517992U - Triangle notcher - Google Patents

Triangle notcher Download PDF

Info

Publication number
CN208517992U
CN208517992U CN201820647573.7U CN201820647573U CN208517992U CN 208517992 U CN208517992 U CN 208517992U CN 201820647573 U CN201820647573 U CN 201820647573U CN 208517992 U CN208517992 U CN 208517992U
Authority
CN
China
Prior art keywords
fluting
bucket
triangle
working plate
excavator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820647573.7U
Other languages
Chinese (zh)
Inventor
刘剑锋
何金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Provincial Transportation Engineering Group Co Ltd
Original Assignee
Jiangsu Provincial Transportation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Provincial Transportation Engineering Group Co Ltd filed Critical Jiangsu Provincial Transportation Engineering Group Co Ltd
Priority to CN201820647573.7U priority Critical patent/CN208517992U/en
Application granted granted Critical
Publication of CN208517992U publication Critical patent/CN208517992U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Shovels (AREA)

Abstract

The utility model relates to road construction apparatus fields, in particular to a kind of triangle notcher, including excavator, it further include fluting bucket, fluting bucket is connect with excavator, fluting bucket includes working plate identical with institute open channels sidewall shape, the connecting plate connecting with excavator and perpendicular to two transition platess on ground, and the both ends of two transition platess are connect with working plate and connecting plate respectively.When work, excavator excavates at groove needed for driving to, and the fluting bucket insertion of excavator driving at this time operating point, subsequent excavator starts along the required length direction traveling for excavating groove, and working plate starts grooving;Entire mining process is mechanical execution, reduces the labor intensity of worker, while required groove passes through fluting bucket one-pass molding, therefore improves the efficiency for excavating groove.

Description

Triangle notcher
Technical field
The utility model relates to road construction apparatus field, in particular to a kind of triangle notcher.
Background technique
Triangular side ditch usually builds the side in airport expressway, is mainly used for draining.In construction, according to measurement The corresponding contour line of setting-out, puts gutter, bottom of trench and bank sideline well, is then trimmed to design size using hand excavation's groove. Although the method for hand excavation can excavate gutter, entire process of construction heavy workload is time-consuming and laborious, efficiency compared with Slowly.
Utility model content
The purpose of this utility model is to provide a kind of triangle notchers, have and improve triangular side ditch digging efficiency Advantage.
The above-mentioned technical purpose of the utility model has the technical scheme that a kind of triangle fluting Device, including excavator further include fluting bucket, and the fluting bucket is connect with excavator, and the fluting bucket includes cutting with institute's open channels The identical working plate of face shape, the connecting plate being connect with excavator and two transition platess perpendicular to ground, two transition The both ends of plate are connect with working plate and connecting plate respectively.
Implement above-mentioned technical proposal, when work, excavator excavates at groove needed for driving to, the fluting of excavator driving at this time Bucket insertion operating point, subsequent excavator start along the required length direction traveling for excavating groove, and working plate starts grooving;It is whole A mining process is mechanical execution, reduces the labor intensity of worker, while required groove passes through fluting bucket one-pass molding, therefore Improve the efficiency for excavating groove.
Further, the fluting bucket further includes the backboard that fluting bucket is left for reducing soil.
Implement above-mentioned technical proposal, when fluting bucket work, the soil taken be accommodated in backboard and working plate and connecting plate it Between in the cavity that is formed, after the soil in cavity is filled, soil down to designated position, is reduced later period work by fluting bucket People's cross-notching bucket digs out the cleaning of soil, improves the efficiency of groove construction.
Further, the first reinforcing rib is connected between the connecting plate and working plate and backboard.
Implement above-mentioned technical proposal, the setting of the first reinforcing rib reduces fluting so that the structure of fluting bucket is more firm The phenomenon that bucket deforms at work.
Further, the section that the fluting bucket is parallel to the fluting bucket direction of motion is trapezoidal, and closely face is set compared with big end It sets.
Implement above-mentioned technical proposal, so that the spatial volume that backboard, working plate, connecting plate and side sheet room are formed is larger, side Just more soil is accommodated, reduces because soil fills the number that excavator travels to and fro between designated place in fluting bucket, reduces excavation The time required to groove, the working efficiency of the triangle notcher is improved.
Further, the connecting plate is provided with otic placode far from the side on ground, and through-hole is offered on the otic placode, described logical The connector for connecting with excavator is equipped in hole.
Implement above-mentioned technical proposal, the connection between fluting bucket and excavator is detachable, so that operator can be according to construction It is required that the fluting bucket of replacement different size, so that the application range of the triangle notcher is wider.
Further, the working plate is provided with inclined working face, the working face close to one end of required mining clay Inclination lower end is arranged at excavation.
Implement above-mentioned technical proposal, the setting of inclined working face increases on the soil excavated needed for working plate is applied to Pressure improve the excavation speed of fluting bucket, improve the triangle notcher so that working plate is easier to be inserted into soil Working efficiency.
Further, the working plate is provided with the tooth of triangular pyramid type at tap point, and one of the tooth The motion profile of seamed edge and fluting bucket is arranged in parallel, and is arranged close to the soil of required excavation, the bottom surface of the tooth and work Make plate close to the end face on ground in same level.
Implement above-mentioned technical proposal, the connection between soil is destroyed in back work face, so that fluting bucket is easier to excavate soil, digs Pick tooth be set as triangular pyramid type tooth is initially applied to the pressure on soil is larger, and subsequent soil is cut by triangular pyramid seamed edge It opens, moves, eventually entered into cavity along triangular pyramid side wall.
Further, the second reinforcement is connected between the side wall and working plate of soil of the tooth far from required excavation Muscle.
Implement above-mentioned technical proposal, the setting of the second reinforcing rib so that is connected between tooth and working plate is stronger, Reduce the phenomenon that tooth is separated with working plate.
Further, the working plate close to the end face on ground be provided with cross section be arc-shaped protrusion, it is described protrusion with The trenched side-wall contact dug.
Implement above-mentioned technical proposal, raised setting reduces the contact area between the groove and working plate dug, reduces Friction between working plate and ground, while there is the effect of compression to the side wall of the groove that has dug in protrusion, so that the ditch that digging is good The side wall of slot is more smooth, improves the construction quality of the triangle notcher.
In conclusion the utility model having the beneficial effect that in contrast to the prior art
One, entire mining process has mechanical execution, reduces the labor intensity of worker, while required groove passes through fluting bucket One-pass molding improves the efficiency for excavating groove;
Two, so that working plate is easier to be inserted into soil, the excavation speed of raising fluting bucket is improved for the setting of working face The working efficiency of the triangle notcher.
Detailed description of the invention
Fig. 1 is the whole structural schematic diagram of the utility model embodiment;
Fig. 2 is the structural schematic diagram of the fluting bucket of the utility model embodiment.
Appended drawing reference: 1, excavator;2, fluting bucket;21, working plate;211, working face;212, tooth;213, second adds Strengthening tendons;214, raised;22, transition plates;23, connecting plate;231, otic placode;232, through-hole;24, backboard;25, the first reinforcing rib.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.
Embodiment:
As shown in Figure 1, 2, a kind of triangle notcher, including excavator 1 further include bucket 2 of slotting, fluting bucket 2 and excavation Machine 1 connects, fluting bucket 2 includes working plate 21 identical with institute open channels cross sectional shape, the connecting plate 23 that is connect with excavator 1, The backboard 24 of fluting bucket 2 is left and perpendicular to two transition platess 22 on ground, the both ends of two transition platess 22 for reducing soil It is connect respectively with working plate 21 and connecting plate 23.The section that fluting bucket 2 is parallel to fluting 2 directions of motion of bucket is trapezoidal and larger It holds and is arranged close to ground.The first reinforcing rib 25 is connected between connecting plate 23 and working plate 21 and backboard 24.
As shown in Fig. 2, working plate 21 is provided with inclined working face 211, working face close to one end of required mining clay 211 inclination lower ends are arranged at excavation.Working plate 21 is provided with the tooth 212 of triangular pyramid type at tap point, digs The motion profile for digging the seamed edge and fluting bucket 2 of tooth 212 is arranged in parallel, and is arranged close to the soil of required excavation, tooth 212 bottom surface and working plate 21 close to ground end face in same level.The side of soil of the tooth 212 far from required excavation The second reinforcing rib 213 is connected between wall and working plate 21.
As shown in Fig. 2, it is arc-shaped protrusion 214, protrusion 214 that working plate 21, which is provided with cross section close to the end face on ground, It is contacted with the trenched side-wall dug, the cross section of the present embodiment protrusions 214 is set as minor arc.
The course of work of the triangle notcher: excavator 1 excavates at groove needed for driving to, and excavator 1 drives at this time 2 insertion operating point of fluting bucket, even if subsequent excavator 1 starts along required excavation in the sharp parts insertion soil of tooth 212 The length direction of groove travels, and tooth 212 moves in soil at this time, and soil is cut by triangular pyramid seamed edge, along triangular pyramid side Wall is mobile, and the insertion of working face 211 at this time has been mined in the soil that tooth 212 is tentatively cut, and final soil enters along working face 211 In the cavity that backboard 24, working plate 21, connecting plate 23 and side sheet room are formed.When fluting bucket 2 is worked, protrusion 214 is squeezed The side wall of the groove dug, so that the side wall for digging good groove is more smooth.
After the soil in cavity is filled, soil down to designated position, it is split to be reduced later period worker by fluting bucket 2 Slot bucket 2 digs out the cleaning of soil, improves the efficiency of groove construction.
The setting of first reinforcing rib 25 reduces fluting bucket 2 and deforms at work so that the structure of fluting bucket 2 is more firm The phenomenon that occur.The setting of second reinforcing rib 213 reduces so that is connected between tooth 212 and working plate 21 is stronger The phenomenon that tooth 212 is separated with working plate 21.
Tooth 212 is set as triangular pyramid type larger, the backman that makes tooth 212 be initially applied to the pressure on soil Make the connection that face 211 is destroyed between soil, so that fluting bucket 2 is easier to excavate soil.
The setting of inclined working face 211 increases the pressure on the soil excavated needed for working plate 21 is applied to, so that Working plate 21 is easier to be inserted into soil, improves the excavation speed of fluting bucket 2, improves the work effect of the triangle notcher Rate.
Protrusion 214 setting reduce the contact area between the groove dug and working plate 21, reduce working plate 21 and Friction between ground, while there is the effect compressed in the side wall of 214 pairs of grooves dug of protrusion, so that the side wall of groove is more flat It is whole, improve the construction quality of the triangle notcher.
Entire mining process is mechanical execution, reduces the labor intensity of worker, while required groove passes through fluting bucket 2 one Secondary molding, therefore improve the efficiency for excavating groove.
As shown in Fig. 2, connecting plate 23 is provided with otic placode 231 far from the side on ground, through-hole 232 is offered on otic placode 231, The connector for connecting with excavator 1 is equipped in through-hole 232.Connector is set as screw bolt and nut in the present embodiment.
Connection between fluting bucket 2 and excavator 1 is detachable, so that operator can replace different size according to construction requirement Fluting bucket 2 so that the application range of the triangle notcher is wider.
The above is only the exemplary embodiment of the utility model, the protection model rather than limited the present invention It encloses, the protection scope of the utility model is determined by the attached claims.

Claims (9)

1. a kind of triangle notcher, including excavator (1), which is characterized in that further include fluting bucket (2), the fluting struggles against (2) It is connect with excavator (1), the fluting bucket (2) includes working plate (21) identical with institute's open channels cross sectional shape and excavator (1) connecting plate (23) connected and two transition platess (22) perpendicular to ground, the both ends difference of two transition platess (22) It is connect with working plate (21) and connecting plate (23).
2. triangle notcher according to claim 1, which is characterized in that the fluting bucket (2) further includes for reducing Soil leaves the backboard (24) of fluting bucket (2).
3. triangle notcher according to claim 2, which is characterized in that the connecting plate (23) and working plate (21) and The first reinforcing rib (25) are connected between backboard (24).
4. triangle notcher according to claim 2, which is characterized in that the fluting bucket (2) is parallel to fluting bucket (2) The section of the direction of motion is trapezoidal and closely face is arranged compared with big end.
5. triangle notcher according to claim 1, which is characterized in that side of the connecting plate (23) far from ground Be provided with otic placode (231), offered through-hole (232) on the otic placode (231), be equipped in the through-hole (232) for digging The connector of pick machine (1) connection.
6. triangle notcher according to claim 1, which is characterized in that the working plate (21) is close to required excavation mud One end of soil is provided with inclined working face (211), and working face (211) the inclination lower end is arranged at excavation.
7. triangle notcher according to claim 1, which is characterized in that the working plate (21) sets at tap point It is equipped with the tooth (212) of triangular pyramid type, a seamed edge of the tooth (212) is parallel with the fluting bucket motion profile of (2) Setting, and be arranged close to the soil of required excavation, the end face on the close ground in the bottom surface and working plate (21) of the tooth (212) In same level.
8. triangle notcher according to claim 7, which is characterized in that the tooth (212) is far from required excavation Soil side wall and working plate (21) between be connected with the second reinforcing rib (213).
9. triangle notcher according to claim 1, which is characterized in that end face of the working plate (21) close to ground Being provided with cross section is arc-shaped protrusion (214), and the protrusion (214) contacts with the trenched side-wall dug.
CN201820647573.7U 2018-05-02 2018-05-02 Triangle notcher Expired - Fee Related CN208517992U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820647573.7U CN208517992U (en) 2018-05-02 2018-05-02 Triangle notcher

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820647573.7U CN208517992U (en) 2018-05-02 2018-05-02 Triangle notcher

Publications (1)

Publication Number Publication Date
CN208517992U true CN208517992U (en) 2019-02-19

Family

ID=65342354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820647573.7U Expired - Fee Related CN208517992U (en) 2018-05-02 2018-05-02 Triangle notcher

Country Status (1)

Country Link
CN (1) CN208517992U (en)

Similar Documents

Publication Publication Date Title
CN106522298B (en) A kind of buried cable automatic mining laying backfill flattening device
US4476641A (en) Strata rock bucket
CN104164898B (en) A kind of U-shaped irrigation canals and ditches earthwork development machine
USRE33198E (en) Strata rock bucket
CN110241875A (en) A kind of excavator hydraulic quick-change device
CN208517992U (en) Triangle notcher
CN109339032A (en) The method for carrying out construction of diaphragm wall using twisting sucker head
CN209603214U (en) A kind of one-pass molding embankment gutter excavating device
CN210766942U (en) Shaping and excavating device for drainage ditch
CN106812157A (en) A kind of assembled hypogee and its construction method
CN211257122U (en) Quick excavation device of escape canal slot
CN211421211U (en) Excavator for rapidly digging groove and soil cutting plate thereof
CN210946353U (en) Mounting structure of ditch cover plate
CN207727613U (en) A kind of assembled hypogee
CN215594183U (en) Drainage ditch excavation forming structure
CN212427294U (en) Power-assisted shovel of farming machinery
CN217734164U (en) Trapezoidal intercepting ditch bucket
CN220768213U (en) Novel embankment side ditch excavation device
CN218204542U (en) Sinking construction device for cast-in-place underground building
CN212388638U (en) Bituminous paving grooving colludes
CN113605475B (en) Construction equipment is seted up to building escape canal
CN221001211U (en) Bucket of excavator
CN215715638U (en) Energy-saving integrated pipeline landfill equipment
CN210712996U (en) Bull-dozer for municipal construction
CN216765975U (en) Sinking construction device for cast-in-place underground building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190219