CN208363103U - A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation - Google Patents

A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation Download PDF

Info

Publication number
CN208363103U
CN208363103U CN201820805548.7U CN201820805548U CN208363103U CN 208363103 U CN208363103 U CN 208363103U CN 201820805548 U CN201820805548 U CN 201820805548U CN 208363103 U CN208363103 U CN 208363103U
Authority
CN
China
Prior art keywords
accumbency plate
abdomen formula
accumbency
formula concrete
concrete pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820805548.7U
Other languages
Chinese (zh)
Inventor
王清斌
万朝中
龙浩畅
弓晓慧
李良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRSC Changsha Railway Traffic Control Technology Co Ltd
Original Assignee
CRSC Changsha Railway Traffic Control Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRSC Changsha Railway Traffic Control Technology Co Ltd filed Critical CRSC Changsha Railway Traffic Control Technology Co Ltd
Priority to CN201820805548.7U priority Critical patent/CN208363103U/en
Application granted granted Critical
Publication of CN208363103U publication Critical patent/CN208363103U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation, including pole anchor ear, pulley blocks, rope, two two shackles linked up with and be symmetrically disposed on accumbency plate being installed on horizontal abdomen formula concrete pillar, two hooks are each passed through two shackles and hook, and are combined and are attached by the pulley blocks and rope between the pole anchor ear and two hooks.By the way that the installation tool is arranged, only need two people that can operate on it, a people carries out handling operation to accumbency plate by pulley blocks, another person is responsible for adjusting the position of accumbency plate, it can be achieved that primary lifting can be installed in place, and saves manpower, it is easy to operate, it is high-efficient;In addition shackle is symmetrically set on accumbency plate, be can ensure that accumbency plate keeps balance during lifting, is facilitated installation, highly-safe.

Description

A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation
Technical field
The utility model relates to railway electrification project equipment technical field more particularly to a kind of horizontal abdomen formula concrete pillars The new tool of accumbency plate installation.
Background technique
In general speed running railway line electrification innovation construction, when carrying out direct-burried concrete pillar accumbency plate installation exercise, What industry generallyd use at present is artificial, it may be assumed that worker first lifts to accumbency plate with big rope near coal-mine, is then tied up using 2 big rope Accumbency plate, 4 people lift by its accumbency plate, are slowly put into hole.There are the following problems for this process installation accumbency plate:
1. working efficiency is low: because accumbency plate is than heavier, needing that first accumbency plate is put into hole, 4 operators carry out two Secondary lifting attaches it to position, wastes labour and time.
2. cheating interior operator during lifting accumbency plate twice and cable being easy to be pounded to injury.
3. friction can be generated between the big rope and crater wall of lifting accumbency plate, need to often replace, it is uneconomical.After big rope abrasion such as It replaces not in time, easily initiation safety accident.
4. lift accumbency plate, the position for tying up accumbency plate is entirely empirically determined with worker, if the positional shift tied up exists Accumbency plate is uneven during lifting, easily hanging belt is caused to skid, and steel column occurs and topples or even slips, causes considerable safety thing Therefore.
Utility model content
Place, the utility model provide a kind of horizontal abdomen formula concrete pillar accumbency in view of the deficiency of the prior art The new tool of plate installation carries out the horizontal abdomen formula concrete pillar accumbency of direct-burried in general fast running railway line electrification innovation construction Plate uses when installing, low efficiency and unsafe when solving the problems, such as that accumbency plate is installed in the prior art.
The utility model provides a kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation, including is installed on cross Pole anchor ear, pulley blocks, rope, two two hooks linked up with and be symmetrically disposed on accumbency plate on abdomen formula concrete pillar Ring, two hooks are each passed through two shackles and hook, pass through between the pole anchor ear and two hooks The pulley blocks and rope combination are attached.
The pulley blocks include a fixed pulley as a further improvement of the utility model, and a movable pulley is described fixed Pulley is installed on the pole anchor ear, and two hooks are connected to the movable pulley bottom.
It is provided with and the free end extension side on the outside of the hook free end as a further improvement of the utility model, To opposite barb, the hook rear end, which is provided with, can engage separable retaining ring with the barb.
It is as a further improvement of the utility model, symmetrical axisymmetric setting with center axis thereof on the accumbency plate There is multiple groups location hole, the shackle is mounted in the location hole.
The shackle is connect by way of screw thread with the location hole as a further improvement of the utility model,.
It as a further improvement of the utility model, further include the whole bar for fixing the horizontal abdomen formula concrete pillar Device, the anchor ear of the whole bar device are installed on the horizontal abdomen formula concrete pillar.
Horizontal abdomen formula concrete pillar: supporting in railway electrification project and hangs contact net equipment, and section is rectangular Concrete pillar.
Accumbency plate: in the construction of railway electrification project direct-burried concrete pillar, it is installed on pillar stress side, section is in length It is rectangular.
Compared with prior art, the utility model has the following beneficial effects: only needing two by the way that the installation tool is arranged People can operate on it, and a people carries out handling operation to accumbency plate by pulley blocks, and another person is responsible for adjusting horizontal , it can be achieved that primary lifting can be installed in place, saving manpower is easy to operate, high-efficient for the position of bodyboard;In addition shackle is symmetrical It is set on accumbency plate, can ensure that accumbency plate keeps balance during lifting, facilitate installation, it is highly-safe.
Detailed description of the invention
Fig. 1 is the structural representation of the new tool of horizontal abdomen formula concrete pillar accumbency plate installation provided by the utility model Figure.
Specific embodiment
Utility model will be further described in detail below with reference to the attached drawings and specific embodiments.
As shown in Figure 1, the utility model discloses a kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation, packet It includes the pole anchor ear 3 being installed on horizontal abdomen formula concrete pillar 1, pulley blocks, 5, two, rope hooks 6 and is symmetrically disposed on accumbency Two shackles 21 on plate 2, two hooks 6 are each passed through two shackles 21 and hook, the pole anchor ear 3 and two It is attached between a hook 6 by the pulley blocks and the combination of rope 5.
By the way that the installation tool is arranged, only need two people that can operate on it, a people is by pulley blocks to cross Bodyboard 2 carries out handling operation, and another person is responsible for adjusting the position of accumbency plate 2, it can be achieved that primary lifting can be installed in place, and saves Human-saving, it is easy to operate, it is high-efficient;In addition shackle 21 is symmetrically set on accumbency plate 2, can ensure that accumbency plate 2 in lifting Balance is kept in the process, facilitates installation, it is highly-safe.
The pulley blocks include a fixed pulley 41, a movable pulley 42, and the fixed pulley 41 is installed on the pole and embraces On hoop 3, two hooks 6 are connected to 42 bottom of movable pulley.
The barb opposite with the free end extending direction is provided on the outside of 6 free ends of the hook, after the hook 6 End, which is provided with, can engage separable retaining ring with the barb.After hooking shackle, retaining ring can be engaged with barb, be kept away Exempt from during lifting that safety accident occurs because shaking and being detached from hook 6 with shackle 21, it, will after installing accumbency plate 2 Retaining ring and Barb portion from, so that it may hook 6 is separated with shackle 21.
It is symmetrically arranged with multiple groups location hole by symmetry axis of center axis thereof on the accumbency plate 2, the shackle 21 can Disassembly is installed in the location hole, and in the present embodiment, the shackle 21 is connect by way of screw thread with the location hole. The symmetrical location hole of multiple groups is set, preferably three groups in the present embodiment, the peace of shackle 21 can be selected according to the actual working conditions Holding position, operation is finer when making to lift more convenient when accumbency plate 2 and installation accumbency plate 2, improves installation quality.
It further include the whole bar device (not shown) for fixing the horizontal abdomen formula concrete pillar 1, the whole bar device Anchor ear is installed on the horizontal abdomen formula concrete pillar 1.Horizontal abdomen formula concrete pillar 1 is fixed on the positioning in whole bar device, prevents When lifting installation accumbency plate 2, because horizontal abdomen formula concrete pillar 1 is made to generate inclination the reason of stress.
It, cannot the above content is specific preferred embodiment further detailed description of the utility model is combined Assert that the specific implementation of the utility model is only limited to these instructions.For the ordinary skill of the utility model technical field For personnel, without departing from the concept of the premise utility, a number of simple deductions or replacements can also be made, should all regard To belong to the protection scope of the utility model.

Claims (6)

1. a kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation, it is characterised in that: mixed including being installed on horizontal abdomen formula Pole anchor ear, pulley blocks, rope, two two shackles linked up with and be symmetrically disposed on accumbency plate on solidifying soil pillar, two The hook is each passed through two shackles and hooks, and passes through the pulley between the pole anchor ear and two hooks Group and rope combination are attached.
2. the new tool of horizontal abdomen formula concrete pillar accumbency plate installation according to claim 1, it is characterised in that: described Pulley blocks include a fixed pulley, a movable pulley, and the fixed pulley is installed on the pole anchor ear, and two hooks connect It is connected to the movable pulley bottom.
3. the new tool of horizontal abdomen formula concrete pillar accumbency plate installation according to claim 1, it is characterised in that: described Hook is provided with the barb opposite with the free end extending direction on the outside of free end, the hook rear end be provided with it is described Barb can engage separable retaining ring.
4. the new tool of horizontal abdomen formula concrete pillar accumbency plate installation according to claim 1, it is characterised in that: described It is symmetrically arranged with multiple groups location hole by symmetry axis of center axis thereof on accumbency plate, the shackle is mounted at described In location hole.
5. the new tool of horizontal abdomen formula concrete pillar accumbency plate installation according to claim 4, it is characterised in that: described Shackle is connect by way of screw thread with the location hole.
6. the new tool of horizontal abdomen formula concrete pillar accumbency plate installation according to claim 1, it is characterised in that: also wrap The whole bar device for fixing the horizontal abdomen formula concrete pillar is included, the anchor ear of the whole bar device is installed on the horizontal abdomen formula concrete On pillar.
CN201820805548.7U 2018-05-28 2018-05-28 A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation Expired - Fee Related CN208363103U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820805548.7U CN208363103U (en) 2018-05-28 2018-05-28 A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820805548.7U CN208363103U (en) 2018-05-28 2018-05-28 A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation

Publications (1)

Publication Number Publication Date
CN208363103U true CN208363103U (en) 2019-01-11

Family

ID=64930310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820805548.7U Expired - Fee Related CN208363103U (en) 2018-05-28 2018-05-28 A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation

Country Status (1)

Country Link
CN (1) CN208363103U (en)

Similar Documents

Publication Publication Date Title
CN103470093B (en) Concrete chimney dismantling method
CN101830388B (en) Installation method of counter-weight frame of elevator
CN209844409U (en) Hoisting frame for power transmission line
US3860092A (en) Portable hoisting and evacuation apparatus
CN104499723A (en) Movable safety net and installation method thereof
KR950007007B1 (en) Dismounting device for heavy load hoisting member
CN208363103U (en) A kind of new tool of horizontal abdomen formula concrete pillar accumbency plate installation
CN202390075U (en) Simple lifting device special for PHC (prestress high-strength concrete) tubular pile
CN109969927B (en) Hanging row and using method thereof
CN106121254B (en) Construction method of heavy component transportation system after disassembly by reverse construction method
CN203750064U (en) Portable safety belt fixing device for power equipment framework
CN113264458A (en) Tower crane system and method for removing attachment rod thereof
JP2015054777A (en) Hoisting accessory for jib
CN210885048U (en) Large-scale equipment hoisting system
JP2003306291A (en) Engagement implement for lifting heavy object such as steel plate
CN210855091U (en) Simple movable heavy object vertical lifting equipment
CN210239195U (en) Safety belt suspension system for subway deep foundation pit
CN211034868U (en) Steel reinforcement cage hoist device
CN110171766B (en) Steel bar transportation lifting appliance
US20180140876A1 (en) Grid mesh anchor
CN207537036U (en) A kind of construction elevator
KR100812130B1 (en) A safety net using lifesaving rope
CN212953822U (en) Concrete pipe pile hoisting device
CN211393557U (en) Wire rod reinforcing bar lifting device
CN203345920U (en) Multifunctional lifting hook

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190111

CF01 Termination of patent right due to non-payment of annual fee