CN208346763U - A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank - Google Patents

A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank Download PDF

Info

Publication number
CN208346763U
CN208346763U CN201820806708.XU CN201820806708U CN208346763U CN 208346763 U CN208346763 U CN 208346763U CN 201820806708 U CN201820806708 U CN 201820806708U CN 208346763 U CN208346763 U CN 208346763U
Authority
CN
China
Prior art keywords
rivers
canals
tank
reinforced concrete
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820806708.XU
Other languages
Chinese (zh)
Inventor
赵宗凡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820806708.XU priority Critical patent/CN208346763U/en
Application granted granted Critical
Publication of CN208346763U publication Critical patent/CN208346763U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

A kind of assembled steel reinforced multi-functional rivers and canals of cementing tank provided by the utility model, including cover board and rivers and canals unit, cover board are fixedly connected with rivers and canals unit top;Rivers and canals unit includes the rivers and canals bottom positioned at the rivers and canals wall of two sides and positioned at bottom, rivers and canals wall arranges the first reinforced concrete tank including at least one, each adjacent two the first reinforced concrete tank is seamless to be fixedly connected, and each first reinforced concrete tank includes the first tank body, drainage layer, cavity layer and physical layer;The 2nd reinforced concrete tank is arranged including at least one in rivers and canals bottom, and each adjacent two the second reinforced concrete tank is seamless to be fixedly connected, and each second reinforced concrete tank includes the second tank body, cavity and opening;The height of first reinforced concrete tank is higher than the height of the second reinforced concrete tank;Cover board is fixedly connected with the top of the first reinforced concrete tank.The utility model solves a series of problems that existing rivers and canals construction duration is long, input cost is big, construction section is impassable, land seizure rate height is low with practicability.

Description

A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank
Technical field
The utility model belongs to hydraulic engineering technical field, and in particular to a kind of assembled steel reinforced multi-functional river of cementing tank Canal.
Background technique
Rivers and canals are that China applies a kind of very wide hydraulic engineering at this stage, are mainly used in field irrigation, and plumbing is prevented Flood, flood discharge and to remote mountain areas domestic water etc..
Under the new period, China's rivers and canals engineering development trend is technological innovation, constantly changes, and rivers and canals are built in construction skill at present Completely new change is brought in terms of art, rivers and canals construction technology develops towards fairly perfect direction, generally applies to China Rivers and canals construction, currently in order to breakthrough traditional construction technology obstruction status will development innovation type technology, to improve rivers and canals Construction quality.
Existing rivers and canals are primarily present following problems:
(1) traditional rivers and canals are formed by the water channel manually dug on the ground, and transport and work progress need consumption big The manpower of amount, material resources and financial resources, construction duration is long, and input cost is big.
(2) traditional rivers and canals construction location pedestrian and vehicle are impassable, cause trip inconvenient.
(3) traditional rivers and canals do not have drought resisting function, and dry season rivers and canals are dry.
Utility model content
For above-mentioned deficiency in the prior art, a kind of construction duration provided by the utility model is short, input cost is small, native Ground occupancy is low, practicability is high, the multi-functional rivers and canals of the assembled steel reinforced cementing tank with drought resisting and water storage function, solves existing Rivers and canals construction duration is long, input cost is big, construction impassable a series of problems low with practicability in section.
In order to achieve the above object of the invention, the technical solution adopted in the utility model are as follows:
A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank, including cover board and rivers and canals unit, cover board and rivers and canals unit top It is fixedly connected;
Rivers and canals unit includes the rivers and canals bottom positioned at the rivers and canals wall of two sides and positioned at bottom, and rivers and canals wall arranges the first including at least one Reinforced concrete tank, each adjacent two the first reinforced concrete tank is seamless to be fixedly connected, and each first reinforced concrete tank includes the first tank Body and the drainage layer set gradually from top to bottom positioned at the first tank interior, cavity layer and physical layer are located at one inside rivers and canals Side is provided with discharge orifice diagonally downward, and the bottom of cavity layer is provided with first drinking-water pipe of the top with aperture, the first drinking-water pipe It is connected to the first reinforced concrete tank two sides, and is fixedly connected with adjacent first pipe port that draws water, the bottom end of the first tank body and ground are solid Fixed connection;
Rivers and canals bottom is at least one to arrange the 2nd reinforced concrete tank, and each adjacent two the second reinforced concrete tank is seamless to be fixedly connected, Each second reinforced concrete tank include the second tank body, positioned at the second tank interior cavity and be set to opening for the second tank body top Mouthful, the bottom of cavity is provided with second drinking-water pipe of the top with aperture, and the second drinking-water pipe is connected to the second reinforced concrete tank two sides, and Be fixedly connected with adjacent second pipe port that draws water, the second tank body with the first tank body is seamless is fixedly connected, and its bottom end and ground are solid Fixed connection, the height of the first reinforced concrete tank are higher than the height of the second reinforced concrete tank;
Cover board is fixedly connected with the top of the first reinforced concrete tank.
This programme has the beneficial effect that
Reinforced concrete tank as prefabricated component component in assemble in site at rivers and canals unit, improve the efficiency of rivers and canals construction, Construction duration is shortened, input cost is reduced, the first reinforced concrete tank and the second reinforced concrete tank form groove and realize flowing water Function, cavity layer and inner cavity realize that water storage function, the first drinking-water pipe and the second drinking-water pipe extract the water of savings, realize drought resisting function Can, the drainage layer of the first reinforced concrete tank is filtered river water, improves the practicability of rivers and canals, cover board realizes pedestrian and Che Passage, reduce land seizure rate, further improve the practicability of rivers and canals.
It further, further include the filter screen that rivers and canals unit side is set, filter screen and the first tank body and the second tank body It is fixedly connected.
Above-mentioned further scheme has the beneficial effect that
River garbage on water is intercepted, the practicability of rivers and canals is improved.
Further, the voidage of drainage layer is 10% to 30%.
Above-mentioned further scheme has the beneficial effect that
Different degrees of filtering is carried out to river water, improves the practicability of rivers and canals.
Further, the first drinking-water pipe connects to form the arch pumping channel that middle height is higher than height on both sides, draws water logical The outlet end in road is fixedly connected with city planting ductwork arrival end.
Above-mentioned further scheme has the beneficial effect that
River water in first drinking-water pipe improves the practicability of rivers and canals since gravity flows to two sides.
Further, the outlet end of the first drinking-water pipe of adjacent rivers and canals unit coupling part is managed by T-type blind pipe and municipal administration Web portal end is fixedly connected.
Above-mentioned further scheme has the beneficial effect that
River water after the filtering of collection flows directly into city planting ductwork, improves the practicability of rivers and canals.
Further, one end that the second drinking-water pipe is located at outside rivers and canals is connect with suction pump.
Above-mentioned further scheme has the beneficial effect that
Drought resisting function is enhanced, the practicability of rivers and canals is improved.
Further, the first reinforced concrete tank and the second reinforced concrete tank are made of self waterproofing armored concrete material.
Above-mentioned further scheme has the beneficial effect that
Self waterproofing strength of reinforced concrete is high, has water-proof function, improves the practicability of rivers and canals.
Further, the two sides that cover board is contacted with riverbank are provided with connecting plate, and the top of connecting plate and the top of cover board are protected It holds consistent.
Above-mentioned further scheme has the beneficial effect that
Connecting plate connect cover board with riverbank, reduces the land seizure area of rivers and canals, also facilitates pedestrian and vehicle pass-through, mention The high practicability of rivers and canals.
Further, cover board and connecting plate are made of permeable armored concrete material.
Above-mentioned further scheme has the beneficial effect that
High-intensitive armored concrete material improves safety and practicability, and permeable realization collects rainwater, strengthens river The water storage and drought resisting function of canal.
Detailed description of the invention
Fig. 1 is multi-functional one structural schematic diagram of rivers and canals embodiment of assembled steel reinforced cementing tank;
Fig. 2 is the first reinforced concrete jar structure schematic diagram;
Fig. 3 is the second reinforced concrete jar structure schematic diagram;
Fig. 4 is multi-functional two structural schematic diagram of rivers and canals embodiment of assembled steel reinforced cementing tank;
Fig. 5 is multi-functional three structural schematic diagram of rivers and canals embodiment of assembled steel reinforced cementing tank.
Wherein: 1, cover board;2, the first reinforced concrete tank;21, the first tank body;22, drainage layer;23, cavity layer;24, entity Layer;25, discharge orifice;26, the first drinking-water pipe;3, the second reinforced concrete tank;31, the second tank body;32, cavity;33, it is open;34, Two drinking-water pipes;4, filter screen;5, connecting plate.
Specific embodiment
The utility model is further described With reference to embodiment.Wherein, being given for example only property of attached drawing Illustrate, expression is only schematic diagram, rather than pictorial diagram, should not be understood as the limitation to this patent;In order to which this reality is better described With novel embodiment, the certain components of attached drawing have omission, zoom in or out, and do not represent the size of actual product;To ability For field technique personnel, the omitting of some known structures and their instructions in the attached drawings are understandable.
The same or similar label correspond to the same or similar components in the attached drawing of the utility model embodiment;It is practical at this In novel description, it is to be understood that if the orientation or positional relationship for having the instructions such as term " on ", "lower", "left", "right" is It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of describing the present invention and simplifying the description, rather than indicate Or imply that signified unit or element must have a particular orientation, be constructed and operated in a specific orientation, therefore retouch in attached drawing The term for stating positional relationship only for illustration, should not be understood as the limitation to this patent, for the common skill of this field For art personnel, the concrete meaning of above-mentioned term can be understood as the case may be.
Embodiment one:
As shown in Figure 1, a kind of multi-functional rivers and canals of assembled steel reinforced cementing tank, including one piece of cover board 1 and a rivers and canals unit, Cover board 1 be 120cm*330cm*20cm cube armoured concrete slab, be fixedly connected with rivers and canals unit top, facilitate pedestrian and Vehicle pass-through;
Rivers and canals unit includes the rivers and canals bottom positioned at the rivers and canals wall of two sides and positioned at bottom, and rivers and canals wall includes a row such as Fig. 2 institute The the first reinforced concrete tank 2 shown, quantity are 11, and the first reinforced concrete of each adjacent two tank 2 is seamless to be fixedly connected, each first Reinforced concrete tank 2 be diameter 30cm, height 100cm cylindrical body tank, including the first tank body 21 and be located at the first tank body 21 inside Drainage layer 22, cavity layer 23 and the physical layer 24 set gradually from top to bottom, the voidage of drainage layer 22 are 30%, are located at river Canal interior side is provided with discharge orifice 25 diagonally downward, empty flowing into after the filtering of filtered water level 22 for collecting river water Cavity layer 23, the bottom of cavity layer 23 are provided with first drinking-water pipe 26 of the top with aperture, carry out extraction use to river water, first takes out Water pipe 26 is connected to 2 two sides of the first reinforced concrete tank, and is fixedly connected with adjacent first drinking-water pipe, 26 port, the bottom of the first tank body 21 End is fixedly connected with ground;
Rivers and canals bottom is two rows of second reinforced concrete tanks 3 as shown in Figure 3, and every number of rows amount is 11, each adjacent two second Reinforced concrete tank 3 by gap portion joints cement realize it is seamless be fixedly connected, each second reinforced concrete tank 3 be diameter The cylindrical body tank of 30cm, height 30cm including the second tank body 31, the cavity 32 inside the second tank body 31 and are set to second The opening 33 on 31 top of tank body, river water flow into cavity 32 by opening 33 and carry out water storage, and the bottom of cavity 32 is provided with top band Second drinking-water pipe 34 of aperture carries out extraction use to river water, and the second drinking-water pipe 34 is connected to 3 two sides of the second reinforced concrete tank, and It is fixedly connected with adjacent second drinking-water pipe, 34 port, the second tank body 31 and the first tank body 21 pass through in gap portion joints cement reality It is now seamless to be fixedly connected, and its bottom end is fixedly connected with ground, the height of the first reinforced concrete tank 2 is higher than the second reinforced concrete tank The concave rivers and canals of 3 height, formation realize flowing water function;Cover board 1 is fixedly connected with the top of the first reinforced concrete tank 2.
Further include the filter screen 4 that rivers and canals unit side is set in the present embodiment, stops river rubbish, filter screen 4 and the One tank body 21 is fixedly connected with the second tank body 31.
In the present embodiment, the connection of the first drinking-water pipe 26 forms the arch pumping channel that middle height is higher than height on both sides, takes out Because gravity flows to two sides, the outlet end of pumping channel is fixedly connected with city planting ductwork arrival end for water in aquaporin.
In the present embodiment, one end that the second drinking-water pipe 34 is located at outside rivers and canals is connect with suction pump, to the second reinforced concrete Water in the cavity 32 of tank 3 is extracted, and realizes drought resisting function.
In the present embodiment, the first reinforced concrete tank 2 and the second reinforced concrete tank 3 are self waterproofing armored concrete material system At.
In the present embodiment, the two sides that cover board 1 is contacted with riverbank are provided with connecting plate 5, top and the cover board 1 of connecting plate 5 Top is consistent.
In the present embodiment, cover board 1 and connecting plate 5 are made of permeable armored concrete material.
Construction phase, by the first reinforced concrete tank 2, the second reinforcing bar made of prefabricated self waterproofing armored concrete material Cementing tank 3 and permeable armored concrete material are made cover board 1 and are assembled in rivers and canals construction site, by pouring in gap portion Cement realization is seamless to be fixedly connected, and the two sides of 1 riverbank of cover board contact are provided with connecting plate 5, top and the cover board 1 of connecting plate 5 Top is consistent, and facilitates pedestrian and vehicle pass-through, the wet season, and river is from the first reinforced concrete tank 2 and the second reinforced concrete tank 3 It being flowed through in the concave rivers and canals of formation, realizes flood control-discharge dyke function, river water enters the filter layer 22 of the first tank body by discharge orifice 25, Cavity layer 23 is flowed by filtering, realizes that water storage function, the first drinking-water pipe 26 carry out overflow, rivers and canals to the river water in cavity layer 23 The first drinking-water pipe 26 connection of unit forms the arch pumping channel that middle height is higher than height on both sides, and pumping channel and municipal administration are managed Web portal end is fixedly connected, and the water in pumping channel flows to the city planting ductwork of two sides because of gravity, and river water flows into the by opening 33 Cavity 32 in two tank bodies 31 realizes water storage function, while filter screen 4 thwarts river rubbish;Dry spell, suction pump are logical It crosses the second drinking-water pipe 34 and the water in cavity 32 is subjected to extraction use, realize drought resisting function.
Embodiment two:
As shown in figure 4, a kind of multi-functional rivers and canals of assembled steel reinforced cementing tank, including two cover plates 1 and two rivers and canals units, Cover board 1 be 120cm*330cm*20cm cube armoured concrete slab, be fixedly connected with rivers and canals unit top, facilitate pedestrian and Vehicle pass-through;
Rivers and canals unit includes the rivers and canals bottom positioned at the rivers and canals wall of two sides and positioned at bottom, and rivers and canals wall includes a row such as Fig. 2 institute The the first reinforced concrete tank 2 shown, quantity are 11, and the first reinforced concrete of each adjacent two tank 2 is by pouring water in gap portion Mud realize it is seamless is fixedly connected, each first reinforced concrete tank 2 is the cylindrical body tank of diameter 30cm, height 100cm, including first Tank body 21 and the drainage layer 22 set gradually from top to bottom inside the first tank body 21, cavity layer 23 and physical layer 24, drainage The voidage of layer 22 is 30%, is located at rivers and canals interior side and is provided with discharge orifice 25 diagonally downward, for collecting river water, Cavity layer 23 is flowed into after the filtering of filtered water level 22, the bottom of cavity layer 23 is provided with first drinking-water pipe of the top with aperture 26, extraction use carried out to river water, the first drinking-water pipe 26 is connected to 2 two sides of the first reinforced concrete tank, and with adjacent first drinking-water pipe 26 ports are fixedly connected, and the bottom end of the first tank body 21 is fixedly connected with ground;
Rivers and canals bottom is two rows of second reinforced concrete tanks 3 as shown in Figure 3, and every number of rows amount is 11, each adjacent two second Reinforced concrete tank 3 is seamless to be fixedly connected, and each second reinforced concrete tank 3 is the cylindrical body tank of diameter 30cm, height 30cm, including Second tank body 31, the cavity 32 inside the second tank body 31 and the opening 33 for being set to 31 top of the second tank body, river water passes through Opening 33 flows into cavitys 32 and carries out water storages, and the bottom of cavity 32 is provided with second drinking-water pipe 34 of the top with aperture, to river water into Row, which extracts, to be used, and the second drinking-water pipe 34 is connected to 3 two sides of the second reinforced concrete tank, and fixes and connect with adjacent second drinking-water pipe, 34 port Connect, the second tank body 31 and the first tank body 21 by gap portion joints cement realize it is seamless be fixedly connected, and its bottom end and ground Base is fixedly connected, and the height of the first reinforced concrete tank 2 is higher than the height of the second reinforced concrete tank 3, and the concave rivers and canals of formation are realized Flowing water function;Cover board 1 is fixedly connected with the top of the first reinforced concrete tank 2.
Further include the filter screen 4 that rivers and canals unit side is set in the present embodiment, stops river rubbish, filter screen 4 and the One tank body 21 is fixedly connected with the second tank body 31.
In the present embodiment, the connection of the first drinking-water pipe 26 forms the arch pumping channel that middle height is higher than height on both sides, takes out Because gravity flows to two sides, the outlet end of pumping channel is fixedly connected with city planting ductwork arrival end for water in aquaporin.
In the present embodiment, the outlet end of the first drinking-water pipe 26 of the coupling part between two rivers and canals units is blind by T-type Pipe is fixedly connected with city planting ductwork arrival end.
In the present embodiment, the connection of the first drinking-water pipe 26 forms the arch pumping channel that middle height is higher than height on both sides, takes out Water in aquaporin flows to two sides because of gravity.
In the present embodiment, one end that the second drinking-water pipe 34 is located at outside rivers and canals is connect with suction pump, to the second reinforced concrete Water in the cavity 32 of tank 3 is extracted, and realizes drought resisting function.
In the present embodiment, the first reinforced concrete tank 2 and the second reinforced concrete tank 3 are self waterproofing armored concrete material system At.
In the present embodiment, the two sides that cover board 1 is contacted with riverbank are provided with connecting plate 5, top and the cover board 1 of connecting plate 5 Top is consistent.
In the present embodiment, cover board 1 and connecting plate 5 are made of permeable armored concrete material.
Construction phase, by the first reinforced concrete tank 2, the second reinforcing bar made of prefabricated self waterproofing armored concrete material Cementing tank 3 and permeable armored concrete material are made cover board 1 and are assembled in rivers and canals construction site, and the two of the contact of 1 riverbank of cover board Side is provided with connecting plate 5, and the top of connecting plate 5 and the top of cover board 1 are consistent, and facilitates pedestrian and vehicle pass-through, the wet season, River is flowed through from the concave rivers and canals that the first reinforced concrete tank 2 and the second reinforced concrete tank 3 are formed, and realizes flood control-discharge dyke function, River water enters the filter layer 22 of the first tank body by discharge orifice 25, flows into cavity layer 23 by filtering, realization water storage function, and first Drinking-water pipe 26 carries out overflow to the river water in cavity layer 23, and the first drinking-water pipe 26 connection of rivers and canals unit forms middle height and is higher than The arch pumping channel of height on both sides, pumping channel are fixedly connected with city planting ductwork arrival end, and the water in pumping channel is because of gravity Two sides are flowed to, the outlet end of the first drinking-water pipe 26 of the coupling part between two rivers and canals units is managed by T-type blind pipe and municipal administration Web portal end is fixedly connected, and river water flows into the cavity 32 in the second tank body 31 by opening 33, is realized water storage function, is filtered simultaneously Net 4 thwarts river rubbish;Dry spell, the water in cavity 32 extract by suction pump by the second drinking-water pipe 34 to be made With realization drought resisting function.
Embodiment three:
As shown in figure 5, a kind of multi-functional rivers and canals of assembled steel reinforced cementing tank, including one piece of cover board 1 and a rivers and canals unit, Cover board 1 be 120cm*300cm*20cm cube armoured concrete slab, be fixedly connected with rivers and canals unit top, facilitate pedestrian and Vehicle pass-through;
Rivers and canals unit includes the rivers and canals bottom positioned at the rivers and canals wall of two sides and positioned at bottom, and rivers and canals wall arranges the first reinforcing bar including one Cementing tank 2, quantity are 10, and the first reinforced concrete of each adjacent two tank 2 is seamless to be fixedly connected, each first reinforced concrete tank 2 For the cube of 30cm*30cm*100cm, including the first tank body 21 and set gradually from top to bottom inside the first tank body 21 Drainage layer 22, cavity layer 23 and physical layer 24, the voidage of drainage layer 22 is 30%, is located at rivers and canals interior side and is provided with Discharge orifice 25 diagonally downward is flowing into cavity layer 23 for collecting river water after the filtering of filtered water level 22, cavity layer 23 Bottom is provided with first drinking-water pipe 26 of the top with aperture, carries out extraction use to river water, the first drinking-water pipe 26 is connected to the first steel 2 two sides of muscle cementing tank, and be fixedly connected with adjacent first drinking-water pipe, 26 port, the bottom end of the first tank body 21 and the fixed company of ground It connects;
Rivers and canals bottom ranked second reinforced concrete tank 3 for two, and the second reinforced concrete of each adjacent two tank 3 is seamless to be fixedly connected, often A second reinforced concrete tank 3 is the cube of 30cm*30cm*30cm, including the second tank body 31, inside the second tank body 31 Cavity 32 and the opening 33 for being set to 31 top of the second tank body, river water flow into cavity 32 by opening 33 and carry out water storage, cavity 32 Bottom be provided with second drinking-water pipe 34 of the top with aperture, extraction use carried out to river water, the second drinking-water pipe 34 connection second 3 two sides of reinforced concrete tank, and be fixedly connected with adjacent second drinking-water pipe, 34 port, the second tank body 31 and the first tank body 21 are seamless solid Fixed connection, and its bottom end is fixedly connected with ground, the height of the first reinforced concrete tank 2 is higher than the height of the second reinforced concrete tank 3, The concave rivers and canals of formation realize flowing water function;Cover board 1 is fixedly connected with the top of the first reinforced concrete tank 2.
Further include the filter screen 4 that rivers and canals unit side is set in the present embodiment, stops river rubbish, filter screen 4 and the One tank body 21 is fixedly connected with the second tank body 31.
In the present embodiment, the connection of the first drinking-water pipe 26 forms the arch pumping channel that middle height is higher than height on both sides, takes out Because gravity flows to two sides, the outlet end of pumping channel is fixedly connected with city planting ductwork arrival end for water in aquaporin.
In the present embodiment, one end that the second drinking-water pipe 34 is located at outside rivers and canals is connect with suction pump, to the second reinforced concrete Water in the cavity 32 of tank 3 is extracted, and realizes drought resisting function.
In the present embodiment, the first reinforced concrete tank 2 and the second reinforced concrete tank 3 are self waterproofing armored concrete material system At.
In the present embodiment, the two sides that cover board 1 is contacted with riverbank are provided with connecting plate 5, top and the cover board 1 of connecting plate 5 Top is consistent.
In the present embodiment, cover board 1 and connecting plate 5 are made of permeable armored concrete material.
Construction phase, by the first reinforced concrete tank 2, the second reinforcing bar made of prefabricated self waterproofing armored concrete material Cementing tank 3 and permeable armored concrete material are made cover board 1 and are assembled in rivers and canals construction site, and the two of the contact of 1 riverbank of cover board Side is provided with connecting plate 5, and the top of connecting plate 5 and the top of cover board 1 are consistent, and facilitates pedestrian and vehicle pass-through, the wet season, River is flowed through from the concave rivers and canals that the first reinforced concrete tank 2 and the second reinforced concrete tank 3 are formed, and realizes flood control-discharge dyke function, River water enters the filter layer 22 of the first tank body by discharge orifice 25, flows into cavity layer 23 by filtering, realization water storage function, and first Drinking-water pipe 26 carries out overflow to the river water in cavity layer 23, and the first drinking-water pipe 26 connection of rivers and canals unit forms middle height and is higher than The arch pumping channel of height on both sides, pumping channel are fixedly connected with city planting ductwork arrival end, and the water in pumping channel is because of gravity The city planting ductwork of two sides is flowed to, river water flows into the cavity 32 in the second tank body 31 by opening 33, realizes water storage function, while mistake Strainer 4 thwarts river rubbish;Dry spell, the water in cavity 32 extract by suction pump by the second drinking-water pipe 34 to be made With realization drought resisting function.
A kind of construction duration provided by the utility model is short, input cost is small, land seizure rate is low, practicability is high, has The multi-functional rivers and canals of the assembled steel reinforced cementing tank of drought resisting and water storage function solve existing rivers and canals construction duration length, input cost Greatly, a series of problems that construction section is impassable, land seizure rate height is low with practicability.
The above description is only the embodiments of the present invention, and embodiment is used to understand the structure, function and effect of utility model Fruit, the protection scope being not intended to limit the utility model.Various modifications and changes may be made to the present invention, all practical at this Within novel spirit and principle, any modification, equivalent replacement, improvement and so on should be included in the guarantor of the utility model Within the scope of shield.

Claims (9)

1. a kind of multi-functional rivers and canals of assembled steel reinforced cementing tank, which is characterized in that including cover board (1) and rivers and canals unit, the lid Plate (1) is fixedly connected with rivers and canals unit top;
The rivers and canals unit includes the rivers and canals bottom positioned at the rivers and canals wall of two sides and positioned at bottom, and the rivers and canals wall includes an at least row First reinforced concrete tank (2), the first reinforced concrete tank (2) is seamless described in each adjacent two is fixedly connected, each first steel Muscle cementing tank (2) is including the first tank body (21) and is located at the drainage layer set gradually from top to bottom inside the first tank body (21) (22), cavity layer (23) and physical layer (24) are located at rivers and canals interior side and are provided with discharge orifice (25) diagonally downward, described The bottom of cavity layer (23) is provided with first drinking-water pipe (26) of the top with aperture, and first drinking-water pipe (26) is connected to the first steel Muscle cementing tank (2) two sides, and be fixedly connected with adjacent first drinking-water pipe (26) port, the bottom end and ground of first tank body (21) Base is fixedly connected;
The rivers and canals bottom is at least one to arrange the 2nd reinforced concrete tank (3), and the second reinforced concrete tank (3) described in each adjacent two is seamless It is fixedly connected, each second reinforced concrete tank (3) includes the second tank body (31), is located at the second tank body (31) internal cavity (32) and it is set to the opening (33) on the second tank body (31) top, the bottom of the cavity (32) is provided with of top with aperture Two drinking-water pipes (34), second drinking-water pipe (34) are connected to second reinforced concrete tank (3) two sides, and with adjacent second drinking-water pipe (34) port is fixedly connected, second tank body (31) with the first tank body (21) is seamless is fixedly connected, and its bottom end and ground are solid Fixed connection, the height of the first reinforced concrete tank (2) are higher than the height of the second reinforced concrete tank (3);
The cover board (1) is fixedly connected with the top of the first reinforced concrete tank (2).
2. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 1, which is characterized in that further include being arranged in river The filter screen (4) of canal unit side, the filter screen (4) are fixedly connected with the first tank body (21) and the second tank body (31).
3. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 1, which is characterized in that the drainage layer (22) Voidage be 10% to 30%.
4. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 1, which is characterized in that first drinking-water pipe (26) connection forms the arch pumping channel that middle height is higher than height on both sides, the outlet end of the pumping channel and city planting ductwork Arrival end is fixedly connected.
5. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 1, which is characterized in that the adjacent rivers and canals list The outlet end of the first drinking-water pipe (26) of first coupling part is fixedly connected by T-type blind pipe with city planting ductwork arrival end.
6. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 1, which is characterized in that second drinking-water pipe (34) it is located at one end outside rivers and canals to connect with suction pump.
7. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 1, which is characterized in that the first reinforcing bar water Mud tank (2) and the second reinforced concrete tank (3) are made of self waterproofing armored concrete material.
8. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 1, which is characterized in that the cover board (1) with The two sides of riverbank contact are provided with connecting plate (5), and the top of the connecting plate (5) and the top of cover board (1) are consistent.
9. the multi-functional rivers and canals of assembled steel reinforced cementing tank according to claim 8, which is characterized in that the cover board (1) and Connecting plate (5) is made of permeable armored concrete material.
CN201820806708.XU 2018-05-29 2018-05-29 A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank Expired - Fee Related CN208346763U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820806708.XU CN208346763U (en) 2018-05-29 2018-05-29 A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820806708.XU CN208346763U (en) 2018-05-29 2018-05-29 A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank

Publications (1)

Publication Number Publication Date
CN208346763U true CN208346763U (en) 2019-01-08

Family

ID=64891321

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820806708.XU Expired - Fee Related CN208346763U (en) 2018-05-29 2018-05-29 A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank

Country Status (1)

Country Link
CN (1) CN208346763U (en)

Similar Documents

Publication Publication Date Title
CN202017223U (en) Rain collection and permeation recharging device
CN104692588B (en) For processing the ecological multidimensional gaseous-waste holdup system of bank, river course rain-water drainage
CN206298944U (en) A kind of sponge urban ecology grass planting ditch
CN108218120A (en) A kind of river and lake shore bank band compound intercepting system of Runoff contaminants
CN105297645B (en) A kind of stagnant storage of sponge urban rainwater oozes uses heat-extraction system pipe fitting and its construction method only
CN101785417A (en) Method for constructing five-in-one farmlands
CN203361233U (en) Solar greenhouse surface rainwater collection, filtration and storage facility
CN208346763U (en) A kind of multi-functional rivers and canals of assembled steel reinforced cementing tank
CN209652959U (en) Connected vessels type foundation pit drop and drainage structure
CN209669977U (en) A kind of waterpower mixing Storm Sewer Network
CN209368782U (en) A kind of ecological dam body with filtering water purification function
CN207828737U (en) A kind of greenbelt
CN206752629U (en) A kind of municipal works rainwater inspection well
CN101886424A (en) Water retention system of infiltration well
CN205475662U (en) Well and sump pit
CN209703550U (en) A kind of pervious concrete barrier wall structure
CN210238709U (en) Reduce drainage structure of utility tunnel sump pit quantity
CN204126002U (en) Urban rainwater reuse irrigation system
CN205954806U (en) Box collection retrieval and utilization cistern
CN206800231U (en) A kind of draining roadbed that catchments for preventing surface gathered water
CN207727713U (en) A kind of intelligent multi-directional drainage system of Roads in Residential Area
CN207846600U (en) One kind oozing gully
CN206599732U (en) A kind of bridge drainage system
CN202202269U (en) Drainage system of drainage box structure
CN110924381A (en) Seepage-proofing structure of geotechnical engineering side slope

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190108

Termination date: 20190529