CN208329204U CN201820937106.8U CN201820937106U CN208329204U CN 208329204 U CN208329204 U CN 208329204U CN 201820937106 U CN201820937106 U CN 201820937106U CN 208329204 U CN208329204 U CN 208329204U
Authority
CN
China
Prior art keywords
layer
reinforcement part
waterproof
mortar levelling
inner corner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820937106.8U
Other languages
Chinese (zh)
Inventor
赵晟煜
陈俊华
高珊珊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Yi Bird Technology Co Ltd
Original Assignee
Chengdu Yi Bird Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Yi Bird Technology Co Ltd filed Critical Chengdu Yi Bird Technology Co Ltd
Priority to CN201820937106.8U priority Critical patent/CN208329204U/en
Application granted granted Critical
Publication of CN208329204U publication Critical patent/CN208329204U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a kind of reinforced waterproof leakage-proof structures of toilet base, the base on ground and metope including toilet, coated on the mortar levelling layer in base, the inner corner trim being made of ground and metope, the downpipe being set on ground, the inner corner trim reinforcement part being set at the inner corner trim of mortar levelling layer, the lower deep gouge being opened at overboard pipe outer wall, it fills up in the nozzle reinforcement part fitted closely in lower deep gouge and with downpipe, repair layer coated on mortar levelling layer surface, it fills up in filling out multiple portion in the subtle gap of mortar levelling layer, the waterproof layer being set in repair layer, and it is set to the waterproof bed course on waterproof layer.The utility model integrally enhances the structural stability of waterproof matrix by inner corner trim reinforcement part and nozzle reinforcement part, it effectively overcomes ground layer sedimentation and downpipe expands with heat and contract with cold leakage hidden trouble caused by generating gap, its is low in cost, construction is easy, there is excellent application effect in toilet warterproof base treatment, be suitble to promote and apply.

Description

A kind of reinforced waterproof leakage-proof structure of toilet base
Technical field
It is to be related to a kind of reinforced waterproof leakproof of toilet base the utility model relates to toilet warterproof processing technique Structure.
Background technique
For domestic premises, especially now high-rise or multilayer folk building, wherein the space of common water, as toilet, Kitchen etc., require carry out water-proofing treatment, generated in normal water utilizing process to avoid resident leaching to lower layer resident or its The house of his resident impacts.Building immersion leak is not only to the concrete of the support of building structure itself and wall and metope Structure is impacted and is destroyed, but also causes irreversible damage to indoor furniture, seriously affects the quality of life of resident.Cause This, the big place of water consumption this kind of for toilet, finishing when water-proofing treatment it is most important.To toilet in building trade The guarantee period of waterproof layer is generally 5 years, and according to waterproof investigate mass data show, guarantee both quality and quantity and build use environment compared with Good waterproof layer service life was up to 10 years or more, or even there are waterproof layer feelings between the building hygiene for reaching 20 years service life Condition.Data also show that simultaneously, some because the problems such as construction side or finishing person's sense of responsibility leads to toilet warterproof processing not When leading to occur the case where waterproof layer rupture leakage in advance, partially sedimentation causes caused by also having because of factors such as building geographical locations Waterproof layer fracture distress leakage scenarios.These controllable or uncontrollable factors are how overcome to influence feelings by some technological means Toilet warterproof problem under condition becomes those skilled in the art to improve the waterproof layer service life in building as much as possible The problem of member's urgent need to resolve.
It in the prior art, is that joint filling first is mended by applying mortar to surface to the mode of the base treatment of toilet warterproof layer Gap is next levelling, and then to be dried rear by prescribed requirement brushing water-repellent paint building base's waterproof layer, generally 1-2mm is completed The basic handling of waterproof layer.It has been investigated that this existing base treatment technology there is also some problems.For example, usually After mortar levelling, micro-cracks generation is had in mortar process of setting, in order to avoid these micro-cracks are in water-repellent paint Holiday or damaged to waterproof coating layer generation stress when brushing, traditional approach is before brushing waterproof material first to levelling surface Water is brushed one times, it is expected that some moisture block these gaps and waterproof layer is cooperated to lock moisture, realizes joint filling effect, although by real Joint filling effect can be reached to a certain extent by trampling this mode of verifying, but especially high to technical requirements, firstly because brush water meeting Lead to ground brushing water-repellent paint constructional difficulties, secondly because moisture is easy evaporation, once evaporation will influence joint filling effect very much Fruit.For another example, the contact area very little between screed and toilet downpipe after levelling, the waterproof layer and downpipe of brushing it Between contact area also very little, it is easy to generated around downpipe and wrap up imprecise situation, so as to cause overboard pipe outer wall Gap between screed and waterproof layer along with downpipe has certain state of expanding with heat and contract with cold, and can be further exacerbated by The gap of tube wall and surrounding causes waterproof layer to support at this location out of strength, and then causes breakage of the waterproof layer at this, exists Very big leakage hidden trouble.For another example, the accomodation ground of part building will appear certain nature during long-time service Sedimentation, there is no the corresponding reinforcement measures of progress after accomodation ground is levelling in the prior art, and ground nature once occur Sedimentation, the then screed or waterproof layer that will lead to the intersection of ground and metope occur connection fracture, cause waterproof damaging problem, Equally exist certain leakage hidden trouble.
Utility model content
In view of the above shortcomings of the prior art, the utility model provides a kind of reinforced waterproof leakproof of toilet base Structure, by constructing relatively stable reliable waterproof construction in construction, to avoid these leakage hidden troubles.
To achieve the above object, this technical solution adopted is as follows:
A kind of reinforced waterproof leakage-proof structure of toilet base, the base on ground and metope including toilet, coating In the mortar levelling layer in base, the inner corner trim being made of ground and metope, the downpipe being set on ground passes through high-intensitive sand Slurry fills up the inner corner trim reinforcement part formed at the inner corner trim of mortar levelling layer, the sinking being opened in base at overboard pipe outer wall Slot is filled up in the nozzle reinforcement part fitted closely in lower deep gouge and with downpipe by mortar, is coated by organosilicon moisture repellent In mortar levelling layer surface and be allowed to infiltration formed repair layer, by organosilicon moisture repellent the mortar levelling layer subtle seam What crystallization was formed in gap fills out multiple portion, is coated on the waterproof layer formed in repair layer by water-repellent paint, and be set to waterproof layer On waterproof bed course;Wherein, the nozzle reinforcement part is engaged with mortar levelling layer and upper part is higher than mortar levelling layer, described Inner corner trim reinforcement part, nozzle reinforcement part and mortar levelling layer is completely covered in repair layer.
Specifically, the arc-shaped shape in surface of the inner corner trim reinforcement part, the mortar of the mortar levelling layer and metope that make ground are looked for Leveling forms smooth transition, improves the globality of the mortar levelling layer of different sides, also facilitates construction, and pipe fitting can be used and directly squeeze Pressure smoothes out.
Preferably, the height of the inner corner trim reinforcement part is 2-3cm, to guarantee not cause interference feelings with the construction of other levels Condition.
Specifically, the section of the lower deep gouge is wedge shaped, depth 3-4cm, and corresponding tool can be used in width 2-3cm Shovel into or dig at.
Specifically, the arc-shaped shape of upper face of the nozzle reinforcement part makes outside the mortar levelling layer and downpipe on ground Wall forms smooth transition, facilitates the construction of subsequent level.
Preferably, the top of the nozzle reinforcement part is higher than mortar levelling layer and is no more than 3cm, applies to avoid with other levels Work interferes situation.
Preferably, the nozzle reinforcement part is filled up by high density anticracking grout piles up, with improve nozzle reinforcement part with The fitting ability and crack resistance of overboard pipe outer wall.
Compared with prior art, the utility model has the following beneficial effects:
The utility model improves reinforcement for the weakness of current waterproof matrix constructing structure, passes through inner corner trim reinforcement part Joint Properties of the reinforced mortar screed-coat at the inner corner trim of ground and metope, considerably increase mortar levelling by nozzle reinforcement part The contact area of layer and downpipe integrally enhances the structural stability of waterproof matrix to enhance its Joint Properties, and effective gram It has taken ground layer sedimentation and downpipe expands with heat and contract with cold leakage hidden trouble caused by generating gap, while having been existed by organosilicon moisture repellent Mortar levelling layer surface permeates to form repair layer, fills up the micro-cracks generated on mortar levelling layer by mortar solidification, reaches Reliable joint filling effect, improves the Joint Properties of waterproof layer and base and reduces difficulty of construction, low in cost, and construction is held Easily, there is excellent application effect in toilet warterproof base treatment, be suitble to promote and apply.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the partial enlargement diagram of repair layer in the utility model.
Specific embodiment
Explanation and embodiment be to being originally described further with reference to the accompanying drawing, and the embodiments of the present invention includes but not It is only limitted to following embodiment.
Embodiment
As illustrated in fig. 1 and 2, the reinforced waterproof leakage-proof structure of the toilet base, ground and metope including toilet Base 1, coated on the mortar levelling layer 2 in base, the inner corner trim 3 being made of ground and metope is set to overboard on ground Pipe 4 is filled up the inner corner trim reinforcement part 5 formed at the inner corner trim of mortar levelling layer by high-strength mortar, is opened at overboard pipe outer wall Lower deep gouge 6 in base is filled up in the nozzle reinforcement part 7 fitted closely in lower deep gouge and with downpipe by mortar, is led to Organosilicon moisture repellent is crossed coated on mortar levelling layer surface and is allowed to the repair layer 8 of infiltration formation, by organosilicon moisture repellent in institute That states that crystallization in the subtle gap 12 of mortar levelling layer formed fill out multiple portion 9, is coated on by water-repellent paint and is formed in repair layer Waterproof layer 10, and the waterproof bed course 11 being set on waterproof layer;Wherein, the nozzle reinforcement part is engaged with mortar levelling layer And upper part is higher than mortar levelling layer, inner corner trim reinforcement part, nozzle reinforcement part and mortar levelling layer is completely covered in the repair layer.
Specifically, the arc-shaped shape in surface of the inner corner trim reinforcement part, the mortar of the mortar levelling layer and metope that make ground are looked for Leveling forms smooth transition, improves the globality of the mortar levelling layer of different sides.Preferably, the height of the inner corner trim reinforcement part For 2-3cm, interference situation is caused to guarantee not construct with other levels.
Specifically, the section of the lower deep gouge is wedge shaped, depth 3-4cm, and corresponding tool can be used in width 2-3cm Shovel into or dig at.
Specifically, the arc-shaped shape of upper face of the nozzle reinforcement part makes outside the mortar levelling layer and downpipe on ground Wall forms smooth transition, facilitates the construction of subsequent level.Preferably, the top of the nozzle reinforcement part is higher than mortar levelling layer not More than 3cm, situation is interfered to avoid with the construction of other levels.
Preferably, the nozzle reinforcement part is filled up by high density anticracking grout piles up, with improve nozzle reinforcement part with The fitting ability and crack resistance of overboard pipe outer wall.
For the arc shape of inner corner trim reinforcement part and nozzle reinforcement part top, pipe fitting can be used and squeeze floating, pipe fitting can be used 50 pipes, 75 pipes etc., are easily obtained in construction, facilitate construction.
The utility model need not significantly alter conventional construction process in construction, need to only be added in corresponding construction process The processing of corresponding part, difficulty of construction are low.As it is negative again behind ground and metope applying mortar screed-coat for inner corner trim reinforcement part High-strength mortar is filled at angle and is squeezed with pipe fitting smooth out and can be formed;It such as opens or chisels in applying mortar screed-coat rear shovel and is overboard Lower deep gouge is formed around pipe, mends raising density anticracking grout and the extruding of upper part pipe fitting is smoothed out and can be formed again;Such as repair layer It can be formed by whole brushing organosilicon moisture repellent before brushing waterproof coating and after its drying.Do not increasing substantially so Add and reached reliable and stable waterproof matrix treatment effect on the basis of construction cost, cost performance is high.
Above-described embodiment is only the preferred embodiment of the utility model, is not intended to limit the scope of the present invention, In every case the design principle of the utility model is used, and carries out the non-creative variation worked and made on this basis, it should all Belong within the protection scope of the utility model.

Claims (7)

1. a kind of reinforced waterproof leakage-proof structure of toilet base, the base on ground and metope including toilet are coated on Mortar levelling layer in base, the inner corner trim being made of ground and metope, and the downpipe being set on ground, feature exist In, further include filled up by high-strength mortar at the inner corner trim of mortar levelling layer formed inner corner trim reinforcement part, in overboard pipe outer wall Place is opened in the lower deep gouge in base, is filled up by mortar in the nozzle reinforcement part fitted closely in lower deep gouge and with downpipe, Mortar levelling layer surface is coated on by organosilicon moisture repellent and is allowed to the repair layer that infiltration is formed, by organosilicon moisture repellent in institute That states in the subtle gap of mortar levelling layer that crystallization formed fills out multiple portion, is coated on the waterproof formed in repair layer by water-repellent paint Layer, and the waterproof bed course being set on waterproof layer;Wherein, the nozzle reinforcement part engages and upper part with mortar levelling layer Higher than mortar levelling layer, inner corner trim reinforcement part, nozzle reinforcement part and mortar levelling layer is completely covered in the repair layer.
2. a kind of reinforced waterproof leakage-proof structure of toilet base according to claim 1, which is characterized in that the yin The arc-shaped shape in the surface of angle reinforcement part.
3. a kind of reinforced waterproof leakage-proof structure of toilet base according to claim 2, which is characterized in that the yin The height of angle reinforcement part is 2-3cm.
4. a kind of reinforced waterproof leakage-proof structure of toilet base according to claim 1, which is characterized in that under described The section of deep gouge is wedge shaped, depth 3-4cm, width 2-3cm.
5. a kind of reinforced waterproof leakage-proof structure of toilet base according to claim 1, which is characterized in that the pipe The arc-shaped shape of upper face of mouth reinforcement part.
6. a kind of reinforced waterproof leakage-proof structure of toilet base according to claim 5, which is characterized in that the pipe The top of mouth reinforcement part is higher than mortar levelling layer and is no more than 3cm.
7. a kind of reinforced waterproof leakage-proof structure of toilet base according to claim 5, which is characterized in that the pipe Mouth reinforcement part is filled up by high density anticracking grout to be piled up.
CN201820937106.8U 2018-06-14 2018-06-14 A kind of reinforced waterproof leakage-proof structure of toilet base Active CN208329204U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820937106.8U CN208329204U (en) 2018-06-14 2018-06-14 A kind of reinforced waterproof leakage-proof structure of toilet base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820937106.8U CN208329204U (en) 2018-06-14 2018-06-14 A kind of reinforced waterproof leakage-proof structure of toilet base

Publications (1)

Publication Number Publication Date
CN208329204U true CN208329204U (en) 2019-01-04

Family

ID=64771171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820937106.8U Active CN208329204U (en) 2018-06-14 2018-06-14 A kind of reinforced waterproof leakage-proof structure of toilet base

Country Status (1)

Country Link
CN (1) CN208329204U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109864644A (en) * 2019-01-29 2019-06-11 台州铭星装饰工程股份有限公司 A kind of toilet shower tray and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109864644A (en) * 2019-01-29 2019-06-11 台州铭星装饰工程股份有限公司 A kind of toilet shower tray and its construction method

Similar Documents

Publication Publication Date Title
CN107190844B (en) The waterproof and water drainage system and construction method of a kind of basement bottom board and exterior wall
CN207144170U (en) A kind of prefabricated out-hung panel upper and lower opening waterproof connecting structure of prefabricated concrete structure
CN105220713B (en) The waterproof construction of outer wall of basement subsiding crack
CN108487481A (en) A kind of antiseep assembled water stopping thresholds and its construction method
CN106801517A (en) A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method
CN205857593U (en) A kind of stone material wet combining structure of anti-stone material pathological changes
CN103046513A (en) Method for coating and sealing fracture of bed rock in uncovered heavy consolidation grouting
CN207775948U (en) Pulling-Resistant Anchor Rod root waterproofing node structure
CN208329204U (en) A kind of reinforced waterproof leakage-proof structure of toilet base
CN105178364B (en) Underground building light precipitation well point post-cast strip anti-seepage construction method
CN207959289U (en) Structure is repaired in a kind of leak for basement post-pouring zone position
CN106884436A (en) A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab
CN103206093B (en) Leakage repairing and preventing method for roof settlement joint
CN210767302U (en) Enhanced vertical-filament rock wool board external wall insulation system
CN211735379U (en) Waterproof structure of anti-floating anchor rod penetrating through basement bottom plate
CN106869304A (en) Outer wall of basement waterproof construction and construction method in a kind of confined space
CN107514150A (en) A kind of construction technology of utilization space displacement method reconstruction Durable Water Repellant
CN208380137U (en) A kind of kitchen and toilet percolating water repairerment system
CN208380085U (en) The draining pipe-through floor slab structure of a kind of ground leak
CN208668952U (en) A kind of kitchen drainage standpipe through-flooring structure
CN103590508A (en) Composite thermal insulating wall structure and construction method thereof
CN208039921U (en) A kind of bathroom integrally backfills structure
CN206607675U (en) A kind of basement composite external wall anti-cracking and seepage control structure construction
CN215106892U (en) Non-dismantling brick maintenance structure for sunken toilet
CN214117025U (en) Wear floor riser waterproof construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant