CN208309406U - A kind of bridge pier bracing means - Google Patents

A kind of bridge pier bracing means Download PDF

Info

Publication number
CN208309406U
CN208309406U CN201820473156.5U CN201820473156U CN208309406U CN 208309406 U CN208309406 U CN 208309406U CN 201820473156 U CN201820473156 U CN 201820473156U CN 208309406 U CN208309406 U CN 208309406U
Authority
CN
China
Prior art keywords
fixedly installed
bridge pier
runner
bracing means
gauge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820473156.5U
Other languages
Chinese (zh)
Inventor
陈希军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Guangzhiyuan Electronics Technology Co Ltd
Original Assignee
Zhengzhou Guangzhiyuan Electronics Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou Guangzhiyuan Electronics Technology Co Ltd filed Critical Zhengzhou Guangzhiyuan Electronics Technology Co Ltd
Priority to CN201820473156.5U priority Critical patent/CN208309406U/en
Application granted granted Critical
Publication of CN208309406U publication Critical patent/CN208309406U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Coating Apparatus (AREA)

Abstract

Purpose of the utility model is to solve the problems that bridge pier is reinforced in existing inconvenience, disclose a kind of bridge pier bracing means, including cabinet, hairbrush, reclaiming plate, slide bar, guide ring, first connecting rod, helical spring, block, clamping plate, screw rod, snap-gauge, support rod, link block, locating rod, brace, shaft, the first runner, the first rack gear, conveyer belt, support plate, fixed link, connection strap, motor, the second runner, the second rack gear, air pump and conduit.The utility model passes through the cooperation of the first rack gear and the second rack gear, to conveniently hairbrush be made to slide up and down, convenient for carrying out coating to bridge pier, in addition the cooperation of air pump, consequently facilitating cement is uniformly sprayed, instead of manually to the coating of bridge pier, it is more laborsaving, and reasonable design, easy operation, it is worthy to be popularized, meets demand.

Description

A kind of bridge pier bracing means
Technical field
The utility model relates to bridge field more particularly to a kind of bridge pier bracing means.
Background technique
The intermediate support structure of multiple span bridge is known as bridge pier.Bridge pier is divided into solid pier, column pier and framed bent pier etc..By plane Shape can be divided into rectangle pier, tip shape pier, round pier etc..The material for building bridge pier can be mixed with timber, building stones, concrete, reinforcing bar Solidifying soil, steel etc..
For the bridge pier of concrete, it is easy to appear crack, so that the firmness that will will affect bridge pier, needs to bridge Pier is reinforced, existing exactly to be reinforced using reinforcing bar anchor ear to bridge pier, but since the passage of vehicle is easy to make bridge pier Crack increase, while this reinforcing mode is also relatively elaborate, and not easy to operate, also some carries out coating to bridge pier, but is applying During material, general to carry out coating using artificial, manual operation speed is slower, while also relatively elaborate, and being easy will be more With cement splashes, be not easy uniformly to smear bridge pier cement, device also when in use, the inconvenient difference to bridge pier Position carries out consolidation process, and therefore, urgent need designs a kind of bridge pier bracing means to solve the above problems.
Utility model content
Purpose of the utility model is to solve the deficiencies in the prior art, provide a kind of bridge pier bracing means.
The utility model is achieved through the following technical solutions:
A kind of bridge pier bracing means, including snap-gauge, screw rod is uniformly equipped on the snap-gauge, and the screw rod inner end is solid Dingan County is equipped with clamping plate, and left end is fixedly installed with support rod on the upside of the snap-gauge, and the post upper is fixedly installed with link block, It is fixedly installed with first connecting rod on the right side of the link block, the first connecting rod right end is fixedly installed with guide ring, described to lead It is fixedly installed with helical spring on the downside of to ring, slide bar is socketed with inside the helical spring, the lower end of the slider is fixedly installed with Block, the slide bar left-hand face are fixedly installed with the second rack gear, and the slide bar upper end is fixedly installed with air pump, and the air pump is right Side is fixedly installed with conduit, is equipped with cabinet on the right side of the conduit, the cabinet right lateral surface is fixedly installed with reclaiming plate, described Reclaiming plate right lateral surface is uniformly equipped with hairbrush, and locating rod is fixedly installed on the left of the link block, and the locating rod left side is solid Dingan County is equipped with brace, and the locating rod upper end is fixedly installed with connection strap, is equipped with the first runner on the left of the connection strap, described The second runner is installed on the right side of connection strap, first runner and the second runner are equipped with shaft between connection strap respectively, institute It states and is provided with motor on the outside of the second runner, be socketed with conveyer belt between first runner and the second runner, outside the conveyer belt Surface half cycle is fixedly installed with the first rack gear, is fixedly installed with fixed link on the upside of the connection strap, the fixed link upper end is fixed Support plate is installed.
As the optimal technical scheme of the utility model, the screw rod is threadedly engaged with snap-gauge.
As the optimal technical scheme of the utility model, the snap-gauge is c-type structure.
As the optimal technical scheme of the utility model, the slide bar is slidably matched with guide ring.
As the optimal technical scheme of the utility model, the reclaiming plate is hollow structure and connects with cabinet.
As the optimal technical scheme of the utility model, the discharging plate surface is uniformly provided with through-hole.
As the optimal technical scheme of the utility model, the conduit is threadedly engaged with cabinet.
Compared with prior art, the utility model has the beneficial effects that
The utility model passes through the cooperation of screw rod and clamping plate, steps up the device on the bridge pier of different thicknesses to facilitate Carry out using, expand the scope of application of device, increase the stability of device, by being rotatably assorted for support rod and snap-gauge, To which the convenient different location to bridge pier carries out coating processing, is reinforced convenient for the different location to bridge pier, improve bridge pier Robustness, by the cooperation of the first rack gear and the second rack gear, to conveniently hairbrush be made to slide up and down, convenient for being carried out to bridge pier Coating, it is more laborsaving instead of manually to the coating of bridge pier consequently facilitating cement is uniformly sprayed in addition the cooperation of air pump, and Reasonable design, easy operation is worthy to be popularized, and meets demand.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the bottom view of the utility model snap-gauge.
In figure: 1, cabinet, 2, hairbrush, 3, reclaiming plate, 4, slide bar, 5, guide ring, 6, first connecting rod, 7, helical spring, 8, block, 9, clamping plate, 10, screw rod, 11, snap-gauge, 12, support rod, 13, link block, 14, locating rod, 15, brace, 16, shaft, 17, the first runner, the 18, first rack gear, 19, conveyer belt, 20, support plate, 21, fixed link, 22, connection strap, 23, motor, 24, Two runners, the 25, second rack gear, 26, air pump, 27, conduit.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
The utility model provides a kind of technical solution referring to FIG. 1-2:
A kind of bridge pier bracing means, including snap-gauge 11, the snap-gauge 11 are c-type structure, on the snap-gauge 11 uniformly Screw rod 10 is installed, the screw rod 10 is threadedly engaged with snap-gauge 11, and 10 inner end of screw rod is fixedly installed with clamping plate 9, the card 11 upside left end of plate is fixedly installed with support rod 12, and 12 upper end of support rod is fixedly installed with link block 13, the link block 13 right sides are fixedly installed with first connecting rod 6, and 6 right end of first connecting rod is fixedly installed with guide ring 5, the guide ring 5 Downside is fixedly installed with helical spring 7, and slide bar 4 is socketed with inside the helical spring 7, and the slide bar 4 is matched with the sliding of guide ring 5 It closes, 4 lower end of slide bar is fixedly installed with block 8, and 4 left-hand face of slide bar is fixedly installed with the second rack gear 25, the cunning 4 upper end of bar is fixedly installed with air pump 26, and conduit 27 is fixedly installed on the right side of the air pump 26, is equipped with case on the right side of the conduit 27 Body 1, the conduit 27 are threadedly engaged with cabinet 1, and 1 right lateral surface of cabinet is fixedly installed with reclaiming plate 3, the reclaiming plate 3 Surface is uniformly provided with through-hole, and the reclaiming plate 3 is hollow structure and connects with cabinet 1 that 3 right lateral surface of reclaiming plate is uniformly pacified Equipped with hairbrush 2, it is fixedly installed with locating rod 14 on the left of the link block 13, is fixedly installed with brace on the left of the locating rod 14 15,14 upper end of locating rod is fixedly installed with connection strap 22, and the first runner 17, the company are equipped on the left of the connection strap 22 Second runner 24 is installed, first runner 17 and the second runner 24 are equipped between connection strap 22 respectively on the right side of narrow bars 22 Shaft 16 is provided with motor 23 on the outside of second runner 24, is socketed with biography between first runner 17 and the second runner 24 Band 19 is sent, the 19 outer surface half cycle of conveyer belt is fixedly installed with the first rack gear 18, is fixedly installed on the upside of the connection strap 22 Fixed link 21,21 upper end of fixed link are fixedly installed with support plate 20.
Working principle: when being reinforced to bridge pier, cabinet 1 is rotated first, cabinet 1 is backed out, by what is mixed Cement pours into cabinet 1, then screws on cabinet 1, at this point, snap-gauge 11 is stuck on the outside of bridge pier, then to 10 turns of screw rod It is dynamic, step up clamping plate 9 to bridge pier, anti-locking apparatus slides, then motor 23 is connected to neighbouring power supply, air pump with air pump 26 26 will be inflated by conduit 27 into cabinet, to be sprayed cement by reclaiming plate 3, cement is sprayed on bridge pier, then Motor 23 will will drive the first runner 17 and the second runner 24 rotates, it will nibble the first rack gear 18 and the second rack gear 25 It closes, so that 4 slide downward of slide bar is made 3 slide downward of reclaiming plate, be smeared using hairbrush 2 cement, when 19 turns of conveyer belt After dynamic half cycle, it will the first rack gear 18 and the second rack gear 25 are separated, at this time since the elastic force of helical spring 7 rises slide bar 4, To make 2 upward sliding of reclaiming plate 3 and hairbrush, when needing to carry out coating processing to the different surfaces of bridge pier, it is only necessary to right Screw rod 10 is rotated, and clamping plate 9 is loosened, so that it may be rotated to snap-gauge 11, consequently facilitating the different sides to bridge pier carry out Consolidation process.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (7)

1. a kind of bridge pier bracing means, including snap-gauge (11), it is characterised in that: be uniformly equipped with spiral shell on the snap-gauge (11) Bar (10), screw rod (10) inner end are fixedly installed with clamping plate (9), and left end is fixedly installed with support rod on the upside of the snap-gauge (11) (12), support rod (12) upper end is fixedly installed with link block (13), is fixedly installed with first on the right side of the link block (13) Connecting rod (6), first connecting rod (6) right end are fixedly installed with guide ring (5), are fixedly mounted on the downside of the guide ring (5) Have helical spring (7), is socketed with slide bar (4) inside the helical spring (7), slide bar (4) lower end is fixedly installed with block (8), slide bar (4) left-hand face is fixedly installed with the second rack gear (25), and slide bar (4) upper end is fixedly installed with air pump (26), it is fixedly installed with conduit (27) on the right side of the air pump (26), cabinet (1), the case is installed on the right side of the conduit (27) Body (1) right lateral surface is fixedly installed with reclaiming plate (3), and reclaiming plate (3) right lateral surface is uniformly equipped with hairbrush (2), described It is fixedly installed with locating rod (14) on the left of link block (13), is fixedly installed with brace (15) on the left of the locating rod (14), it is described Locating rod (14) upper end is fixedly installed with connection strap (22), is equipped with the first runner (17) on the left of the connection strap (22), described Be equipped with the second runner (24) on the right side of connection strap (22), first runner (17) and the second runner (24) respectively with connection strap (22) be equipped between shaft (16), be provided with motor (23) on the outside of second runner (24), first runner (17) with It is socketed between second runner (24) conveyer belt (19), conveyer belt (19) outer surface half cycle is fixedly installed with the first rack gear (18), it is fixedly installed with fixed link (21) on the upside of the connection strap (22), fixed link (21) upper end is fixedly installed with support Plate (20).
2. a kind of bridge pier bracing means according to claim 1, it is characterised in that: the screw rod (10) and snap-gauge (11) it is threadedly engaged.
3. a kind of bridge pier bracing means according to claim 1, it is characterised in that: the snap-gauge (11) is c-type knot Structure.
4. a kind of bridge pier bracing means according to claim 1, it is characterised in that: the slide bar (4) and guide ring (5) it is slidably matched.
5. a kind of bridge pier bracing means according to claim 1, it is characterised in that: the reclaiming plate (3) is hollow Structure and with cabinet (1) connect.
6. a kind of bridge pier bracing means according to claim 1, it is characterised in that: reclaiming plate (3) surface is equal It is even to be provided with through-hole.
7. a kind of bridge pier bracing means according to claim 1, it is characterised in that: the conduit (27) and cabinet (1) it is threadedly engaged.
CN201820473156.5U 2018-03-30 2018-03-30 A kind of bridge pier bracing means Expired - Fee Related CN208309406U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820473156.5U CN208309406U (en) 2018-03-30 2018-03-30 A kind of bridge pier bracing means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820473156.5U CN208309406U (en) 2018-03-30 2018-03-30 A kind of bridge pier bracing means

Publications (1)

Publication Number Publication Date
CN208309406U true CN208309406U (en) 2019-01-01

Family

ID=64718351

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820473156.5U Expired - Fee Related CN208309406U (en) 2018-03-30 2018-03-30 A kind of bridge pier bracing means

Country Status (1)

Country Link
CN (1) CN208309406U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111893903A (en) * 2020-08-05 2020-11-06 钱昌杰 Bridge concrete pier detection and maintenance method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111893903A (en) * 2020-08-05 2020-11-06 钱昌杰 Bridge concrete pier detection and maintenance method

Similar Documents

Publication Publication Date Title
CN205966241U (en) Fitment is with high -efficient japanning device of iron plate
CN110843138A (en) Make reinforced compounding device of muddy earth ration based on gravity changes
CN208309406U (en) A kind of bridge pier bracing means
CN207508990U (en) It is a kind of to move sand paper machine structure certainly
CN209632705U (en) One kind being used for die surface sanding and polishing device
CN207840040U (en) A kind of hydraulic pressure turnover machine
CN208220229U (en) A kind of bottom concrete pours device
CN214266076U (en) Make things convenient for concrete prefabricated part mould of drawing of patterns
CN214224702U (en) Cement detects curing means
CN111573301A (en) Metallurgical device convenient to fall material
CN209491882U (en) A kind of concrete block moulding machine being conveniently adjusted size
CN207615562U (en) A kind of machine straightening device of spring steel line of spring coiling machine
CN207228613U (en) A kind of building engineering construction formwork for placing device
CN208882786U (en) A kind of quick-replaceable carrying roller portable device
CN207772443U (en) A kind of artificial quartz plate stone equipment recycling function with clout
CN202168398U (en) Material tower
CN204780973U (en) Concrete chamfer construction tool
CN205552285U (en) Novel shaping emery wheel profiling trimmer
CN217480857U (en) Concrete curing is with preventing automatic spray device who splits
CN2796987Y (en) Grinding apparatus shaping scraper
CN205200400U (en) Quick reinforcing bar bending device
CN218149794U (en) Reinforced concrete template convenient to quick form removal
CN217222397U (en) Construction is with high-efficient screening sand device
CN219563565U (en) Side form structure is used in production of adjustable concrete structure component
CN205129546U (en) Be used for coupling corner grinding machanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190101

Termination date: 20190330

CF01 Termination of patent right due to non-payment of annual fee