CN208272515U - A kind of power scheduling building communications equipment room light current prewiring structure - Google Patents

A kind of power scheduling building communications equipment room light current prewiring structure Download PDF

Info

Publication number
CN208272515U
CN208272515U CN201820730764.XU CN201820730764U CN208272515U CN 208272515 U CN208272515 U CN 208272515U CN 201820730764 U CN201820730764 U CN 201820730764U CN 208272515 U CN208272515 U CN 208272515U
Authority
CN
China
Prior art keywords
area
block
cable
business
device area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820730764.XU
Other languages
Chinese (zh)
Inventor
王晓东
张顼
张慧鑫
刘洁
尤天晴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Original Assignee
Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeast Electric Power Design Institute of China Power Engineering Consulting Group filed Critical Northeast Electric Power Design Institute of China Power Engineering Consulting Group
Priority to CN201820730764.XU priority Critical patent/CN208272515U/en
Application granted granted Critical
Publication of CN208272515U publication Critical patent/CN208272515U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Optical Communication System (AREA)

Abstract

A kind of power scheduling building communications equipment room light current prewiring structure, including block and prewiring cable, the block is separately positioned on the transmission device area, business device area and distribution area of power scheduling building communications equipment room, is respectively interconnected transmission device area and the block of distribution area, business device area and distribution area by the prewiring cable;Service fulfillment and business reorganization are only trivial interior by wire jumper completion in the transmission device area, the business device area and the wiring, are not necessarily to transregional wiring.Communications equipment room transmission device area and distribution area, business device area and distribution area are realized interconnection by configuring the preparation cable of all kinds of blocks and corresponding types by the utility model in advance.In service fulfillment or business reorganization, it is only necessary between the transmission device and block in transmission device area, can be completed between the business device and block in business device area and between the block of distribution area by wire jumper in area.Reduce the operating pressure of computer room O&M and personnel, reduce equipment operational safety hidden danger.

Description

A kind of power scheduling building communications equipment room light current prewiring structure
Technical field
This application involves power industry communications equipment room construction field, in particular to a kind of power scheduling building communications equipment room light current Prewiring structure.
Background technique
With the intelligent development of operation of power networks, each system increasingly increases the business demand of power communication in power scheduling building It is more.The reasonability of power scheduling building communications equipment room comprehensive wiring to the opening of business, adjust and the operation of equipment, maintenance are brought Influence be also more and more obvious.Cable in communications equipment room is divided into strong, weak two class by the voltage carried on cable, wherein is machine The power cable that communication equipment is powered in room is forceful electric power cable, and the communications patching of communication equipment is weak cable.
Currently, power scheduling building communications equipment room strong, weak electricity cable has divided slot to lay more, but a large amount of weak electric wire in computer room Cable needs information communication operation maintenance personnel to need to lay in communications equipment room light current wire casing with business reorganization according to business at any time.
In conventional wire laying mode, each service fulfillment and business reorganization require to lay or adjust in light current wire casing Light current cable, heavy workload.And repeatedly lay and light current wire casing interior lines cable easily caused to lay confusion, cable break core the problems such as, give day Often maintenance brings operating pressure and security risk.Therefore, the task of top priority is to research and develop one kind to be suitable for power scheduling building, and energy The communications equipment room light current prewiring structure for enough avoiding cable from repeatedly laying, to meet the communications equipment room comprehensive wiring of power scheduling building Requirement of reasonableness.
Utility model content
Technical problem to be solved in the utility model is the light current prewiring knot suitable for power scheduling building communications equipment room Structure, the technology to solve the multiple cable laying bring operating pressure of communications equipment room conventional wires structure and security risk are asked Topic.
In order to solve the above technical problems, the utility model provides a kind of power scheduling building communications equipment room light current prewiring knot Structure, including block and cable of precoating, it is characterised in that: the block is separately positioned on the power scheduling building communication Transmission device area, business device area and the distribution area of computer room, the block and the one of wiring in distribution area in transmission device area Unit is interconnected by cable of precoating, and the block in another block of distribution area and business device area is also by cable of precoating Interconnection, the cable of precoating are pre-set in light current wire casing, and service fulfillment and business reorganization are only in the transmission device area, institute It states in business device area and the distribution area and is completed by wire jumper.
The block includes optical fiber distributing unit, digital wiring unit, network wiring unit and voice frequency distributing list Member;The cable of precoating includes boundling stern fast, coaxial cable, twisted pair and audio cable;Optical port business corresponds to optical fiber distributing Unit and boundling stern fast, 2M digital service correspond to digital wiring unit and coaxial cable, ether power port business corresponding network wiring Unit and twisted pair, analog service correspond to audio block and audio cable.
The transmission device area includes: SDH equipment, wave-division device.
The business device area includes data network battery limits, dispatching exchange battery limits, administrative switching equipment area.
The distribution area includes optical fiber distribution cabinet, digital wiring cabinet, network wiring cabinet and voice frequency distributing cabinet.
The utility model is set communications equipment room transmission by configuring the preparation cable of all kinds of blocks and corresponding types Interconnection is realized in preparation area and distribution area, business device area and distribution area in advance.In service fulfillment or business reorganization, it is only necessary to transmit Between the transmission device and block of battery limits, between the business device and block in business device area and distribution area is matched It can be completed between line unit by wire jumper in area.Transregional laying is both needed to without each service fulfillment or business reorganization and is adjusted weak Electric wire cable, avoid because caused by repeatedly laying light current wire casing interior lines cable lay chaotic and maloperation cause cable break core the problems such as, subtract Small room O&M and the operating pressure of personnel reduce equipment operational safety hidden danger.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is specific embodiment of the present invention architecture diagram.
Specific embodiment
With reference to Fig. 1, specific embodiment of the present invention includes:
It is separately positioned on the block 101 in the transmission device area 1 of power scheduling building communications equipment room, is arranged in wiring Block 201, the block 202 in area 2, and the block 301 in business device area 3 is set;By transmission device area 1 Block 101 and distribution area 2 blocks 202 interconnect cable 401 of precoating, by the block 202 of distribution area 2 with The cable 402 of precoating that the block 301 in business device area 3 interconnects.The preparatory cloth of cable of precoating is placed on weak electric wire slot 4.
The block includes optical fiber distributing unit, digital wiring unit, network wiring unit and voice frequency distributing list Member etc..
The prewiring cable includes boundling stern fast, coaxial cable, twisted pair and audio cable etc..
Referring to Fig. 2, the type of the block and the prewiring cable is corresponding with type of service, it may be assumed that optical port business Corresponding optical fiber distributing unit 111 and boundling stern fast 411,2M digital service correspond to digital wiring unit 112 and coaxial cable 412, Ether power port business corresponding network block 113 and twisted pair 413, analog service correspond to audio block 311 and audio Cable 414.
The transmission device area includes: SDH equipment, wave-division device etc.;
The business device area includes data network battery limits, dispatching exchange battery limits, administrative switching equipment area etc.;
It should be noted that the business device area need to be laid by device type subregion.Between different business battery limits It can be pooled to the distribution area by block and cable of precoating, be needed according to business in above-mentioned business device area and distribution area The services interconnection between different business battery limits is completed by wire jumper;Computer room External cable, which also needs to draw, is connected to the distribution area, root It needs to pass through the complete pairwise communications of wire jumper in above-mentioned transmission device area and distribution area or above-mentioned business device area and distribution area according to business Services interconnection outside computer room.
The distribution area includes optical fiber distribution cabinet, digital wiring cabinet, network wiring cabinet and voice frequency distributing cabinet etc..
Different type distribution cabinet needs subregion to lay, and particularly may be divided into optical fiber distributing area 211, digital wiring area 212, network are matched Line area 213 and voice frequency distributing area 214.
After the block and the cable of precoating realize interconnection, service fulfillment or business reorganization without transregional laying and Adjust light current cable, it is only necessary between the transmission device and block in transmission device area, the business device in business device area with It can be completed between block and by wire jumper in area between the block of distribution area, realize the purpose of this utility model.

Claims (5)

1. a kind of power scheduling building communications equipment room light current prewiring structure, including block and cable of precoating, it is characterised in that: The block is separately positioned on the transmission device area, business device area and distribution area of power scheduling building communications equipment room, The block and the one of block in distribution area in transmission device area pass through cable interconnection of precoating, another wiring of distribution area Also by cable interconnection of precoating, the cable of precoating is pre-set at light current wire casing for unit and the block in business device area In, service fulfillment and business reorganization only the transmission device area, the business device area and the wiring it is trivial in pass through Wire jumper is completed.
2. communications equipment room light current prewiring structure in power scheduling building according to claim 1, it is characterised in that: the wiring Unit includes optical fiber distributing unit, digital wiring unit, network wiring unit and voice frequency distributing unit;The cable packet of precoating Include boundling stern fast, coaxial cable, twisted pair and audio cable;Optical port business corresponds to optical fiber distributing unit and boundling stern fast, 2M Digital service corresponds to digital wiring unit and coaxial cable, ether power port business corresponding network block and twisted pair, simulation Business corresponds to audio block and audio cable.
3. communications equipment room light current prewiring structure in power scheduling building according to claim 1, it is characterised in that: the transmission Battery limits include SDH equipment, wave-division device.
4. communications equipment room light current prewiring structure in power scheduling building according to claim 1, it is characterised in that: the business Battery limits include data network battery limits, dispatching exchange battery limits, administrative switching equipment area.
5. communications equipment room light current prewiring structure in power scheduling building according to claim 1, it is characterised in that: the wiring Area includes optical fiber distribution cabinet, digital wiring cabinet, network wiring cabinet and voice frequency distributing cabinet.
CN201820730764.XU 2018-05-17 2018-05-17 A kind of power scheduling building communications equipment room light current prewiring structure Active CN208272515U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820730764.XU CN208272515U (en) 2018-05-17 2018-05-17 A kind of power scheduling building communications equipment room light current prewiring structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820730764.XU CN208272515U (en) 2018-05-17 2018-05-17 A kind of power scheduling building communications equipment room light current prewiring structure

Publications (1)

Publication Number Publication Date
CN208272515U true CN208272515U (en) 2018-12-21

Family

ID=64682956

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820730764.XU Active CN208272515U (en) 2018-05-17 2018-05-17 A kind of power scheduling building communications equipment room light current prewiring structure

Country Status (1)

Country Link
CN (1) CN208272515U (en)

Similar Documents

Publication Publication Date Title
CN202602694U (en) Physical-isolation Ethernet switch
CN104041001B (en) A kind of numeral subscriber line local side device, terminal installation and reverse electric power system
CN111682950B (en) Photoelectric adapter and power distribution system
CN208272515U (en) A kind of power scheduling building communications equipment room light current prewiring structure
US9217995B2 (en) Entertainment, lighting and climate control system
CN205123869U (en) PON interface internet video camera
CN209088970U (en) A kind of novel Optical Channel Protection system based on OASS
CN203233419U (en) Power optical communication experiment device
CN110472867A (en) Power distribution network Network adaptation assessment processing method and device
CN104954065A (en) Passive optical network system and communication method
CN204302547U (en) A kind of optimization FTTH system architecture
CN206506542U (en) Home broadband group network system
CN204167757U (en) box-type substation
CN203365754U (en) Wall-mounted co-built and shared optical cable distribution case
CN207638662U (en) Service operation condition monitoring system
CN202103669U (en) Automatic management system for power distribution network
CN204203513U (en) Novel photoelectric integrated box
CN204652385U (en) Universal audio service tester
CN205038503U (en) Wade vouching position operation and maintenance management system
CN203883554U (en) Wind power converter fault remote diagnostic system
CN205027857U (en) Ground connection route selection device suitable for intelligent substation
CN218772302U (en) Elevator management machine of talkbacking
CN205754387U (en) Intelligence community common access platform
CN112736900B (en) Distribution network distributed self-healing system and device based on split layered architecture
CN210780798U (en) Optical cable core aligning device for converter station

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant