CN208202294U - Furred ceiling conversion layer structure - Google Patents

Furred ceiling conversion layer structure Download PDF

Info

Publication number
CN208202294U
CN208202294U CN201820492061.8U CN201820492061U CN208202294U CN 208202294 U CN208202294 U CN 208202294U CN 201820492061 U CN201820492061 U CN 201820492061U CN 208202294 U CN208202294 U CN 208202294U
Authority
CN
China
Prior art keywords
positioning plate
conversion layer
angle steel
plate
furred ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820492061.8U
Other languages
Chinese (zh)
Inventor
乔辉
余洋
陈容
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Yuan Ben Interior Architectural Design Co Ltd
Original Assignee
Shenzhen Yuan Ben Interior Architectural Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Yuan Ben Interior Architectural Design Co Ltd filed Critical Shenzhen Yuan Ben Interior Architectural Design Co Ltd
Priority to CN201820492061.8U priority Critical patent/CN208202294U/en
Application granted granted Critical
Publication of CN208202294U publication Critical patent/CN208202294U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses furred ceiling conversion layer structures, common hang ceiling panel is solved because by external force, or the negative pressure of indoor generation leads to the thrust of panel receiving from the bottom up, lead to the problem that ceiling structure is unbalance, its key points of the technical solution are that, including sunpender and set on the hang ceiling panel of downrod lower end, it further include the conversion layer that sunpender upper end is set, the conversion layer is equipped with the main support connecting with smallpox, the main support two sides are equipped with bearing diagonal, and counter support and structurally stable purpose can be provided by reaching.

Description

Furred ceiling conversion layer structure
Technical field
The utility model relates to building decoration areas, in particular to furred ceiling conversion layer structure.
Background technique
As the multidimensional in current public building space changes, equipment is gradually increased in furred ceiling, the span in furred ceiling engineering space Increasing, height is higher and higher, and the indoor suspended ceiling engineering of big width large space is also more and more, especially the above space of furred ceiling Height in 3m -5m, large space is adapted to often through the length of boom for lengthening furred ceiling, since sunpender be mainly receiving It is hung vertically the gravity of ceiling joist under it, panel and light-duty fixture, is born in vertical direction downward Gravity, but have the following deficiencies: when hang ceiling panel by external force, or the negative pressure of indoor generation because being caused panel to bear from lower past On thrust, since length of boom is too long, stability is not good enough, it is difficult to offset the thrust, will lead in the past for a long time ceiling structure mistake Weighing apparatus.
Utility model content
The purpose of the utility model is to provide furred ceiling conversion layer structure, counter support and structurally stable can be provided by having Advantage.
The above-mentioned technical purpose of the utility model has the technical scheme that furred ceiling conversion layer knot Structure further includes the conversion layer that sunpender upper end is arranged in including sunpender and set on the hang ceiling panel of downrod lower end, on the conversion layer Equipped with the main support connecting with smallpox, the main support two sides are equipped with bearing diagonal.
By using above-mentioned technical proposal, sunpender is directly connected to conversion layer, is shortened the length of sunpender, is avoided because hanging Bar is too long to lead to self structure fragility and unstable, the setting of conversion layer and main support, provides sunpender and hang ceiling panel enough Reversed support, the setting of bearing diagonal, further improve conversion layer installation stability, so as to provide counter support and structure It is firm, it effectively prevent hang ceiling panel to occur because of the situation for being caused hang ceiling panel unstable by external force or suction function.
The further setting of the utility model, the conversion layer include multiple lateral angle steel disposed in parallel, the transverse direction Angle steel both ends are equipped with the connector with wall connecting.
By using above-mentioned technical proposal, multiple transverse direction angle steel provide enough reversed supports to sunpender and hang ceiling panel.
The further setting of the utility model, the connector include by the fixed mounting plate of expansion bolt and wall and It is integrally formed the loading plate carried for lateral angle steel with mounting plate, the loading plate is fixed with lateral angle steel by bolt and nut.
By using above-mentioned technical proposal, mounting plate is mounted on wall by expansion bolt, and lateral angle steel, which is mounted in, to be held On support plate, then by bolt and nut lateral angle steel is fixed, to keep the installation of lateral angle steel relatively stable.
The further setting of the utility model is equipped with deep floor between the mounting plate and loading plate.
By using above-mentioned technical proposal, deep floor improves the stability that mounting plate is connect with loading plate.
The further setting of the utility model, it is described transverse direction angle steel between spacing be 1-2m.
It is relatively reasonable when spacing between lateral angle steel is within the scope of 1-2m by using above-mentioned technical proposal.
The further setting of the utility model, the main support upper end are equipped with the first positioning plate, and the main support lower end is set There is the second positioning plate, first positioning plate is fixed by expansion bolt and smallpox, and second positioning plate passes through bolt and cross It is fixed to angle steel.
By using above-mentioned technical proposal, the first positioning plate is fixed by expansion bolt and smallpox, and the second positioning plate passes through Bolt is fixed with lateral angle steel, so that main support can firmly be connect with lateral angle steel.
The further setting of the utility model, the bearing diagonal lower end are equipped with third positioning plate, and second positioning plate is set There is the first groove for the accommodating of third positioning plate, the bearing diagonal upper end is equipped with the 4th positioning plate, and adjacent bearing diagonal upper end is equipped with 5th positioning plate, the 4th positioning plate are equipped with the second groove, and the 5th positioning plate is equipped with and is connected in the second groove Second protrusive board, second positioning plate and third positioning plate are fixed by bolt and nut and lateral angle steel, the 4th positioning plate And the 5th positioning plate fixed by expansion bolt and smallpox.
By using above-mentioned technical proposal, third positioning plate is connected in the first groove on the second positioning plate, makes third The connection of positioning plate and the second positioning plate is relatively stable, and the second protrusive board of the 5th positioning plate is connected in second on the 4th positioning plate In groove, keep the connection of the 5th positioning plate and the 4th positioning plate relatively stable.
In conclusion the utility model has the following beneficial effects:
1, so as to provide counter support and stabilized structure, it effectively prevent hang ceiling panel because being caused by external force or suction function The unstable situation of hang ceiling panel occurs;
2, third positioning plate is connected in the first groove on the second positioning plate, makes third positioning plate and the second positioning plate Connect relatively stable, the second protrusive board of the 5th positioning plate is connected in the second groove on the 4th positioning plate, makes the 5th positioning plate It is relatively stable with the connection of the 4th positioning plate.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the present embodiment;
Fig. 2 is the structural schematic diagram of connector in the present embodiment;
Fig. 3 is the enlarged drawing in Fig. 3 at A;
Fig. 4 is the connection relationship diagram of main support and smallpox in the present embodiment;
Fig. 5 is the enlarged drawing in Fig. 4 at B.
Appended drawing reference: 1, sunpender;2, hang ceiling panel;3, conversion layer;31, lateral angle steel;4, main support;41, the first positioning Plate;42, the second positioning plate;43, the first groove;5, bearing diagonal;51, third positioning plate;52, the 4th positioning plate;53, the 5th positioning Plate;54, the second groove;55, the second protrusive board;6, connector;61, mounting plate;62, loading plate;63, deep floor;7, main joist; 8, false keel;9, Skeleton hanging part.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment: furred ceiling conversion layer structure further includes that setting exists as shown in Figure 1, including sunpender 1 and hang ceiling panel 2 The conversion layer 3 of 1 upper end of sunpender, conversion layer 3 are equipped with the main support 4 connecting with smallpox, and 4 two sides of main support are equipped with bearing diagonal 5.
1 lower end of sunpender is equipped with Skeleton hanging part 9, and main joist 7 is hung on Skeleton hanging part 9, and 7 lower end of main joist is provided with secondary dragon Bone 8, hang ceiling panel 2 are fixed on 8 lower end of false keel.
Conversion layer 3 includes multiple lateral angle steel 31 disposed in parallel, and lateral 31 both ends of angle steel are equipped with the company with wall connecting Fitting 6, multiple transverse direction angle steel 31 provide enough reversed supports to sunpender 1 and hang ceiling panel 2.
Spacing between lateral angle steel 31 is 1-2m, when the spacing between lateral angle steel 31 is within the scope of 1-2m, is more closed Reason.
As shown in Fig. 2, connector 6 include by the fixed mounting plate 61 of expansion bolt and wall and with 61 one of mounting plate The loading plate 62 carried for lateral angle steel 31 is formed, loading plate 62 is fixed with lateral angle steel 31 by bolt and nut, mounting plate 61 It is mounted on wall by expansion bolt, lateral angle steel 31 is mounted on loading plate 62, then passes through bolt and nut for lateral angle steel 31 is fixed, to keep the installation of lateral angle steel 31 relatively stable.
Deep floor 63 is equipped between mounting plate 61 and loading plate 62, deep floor 63 improves mounting plate 61 and loading plate The stability of 62 connections.
As shown in Figure 3 and Figure 4,4 upper ends of main support are equipped with the first positioning plate 41, and 4 lower ends of main support are equipped with the second positioning plate 42, the first positioning plate 41 is fixed by expansion bolt and smallpox, and the second positioning plate 42 is fixed by bolt and lateral angle steel 31, from And main support 4 can firmly be connect with lateral angle steel 31.
As shown in Figure 3 and Figure 5,5 lower end of bearing diagonal is equipped with third positioning plate 51, and the second positioning plate 42 is equipped with to be positioned for third The first groove 43 that plate 51 accommodates, 5 upper end of bearing diagonal are equipped with the 4th positioning plate 52, and adjacent 5 upper end of bearing diagonal is equipped with the 5th positioning Plate 53, the 4th positioning plate 52 are equipped with the second groove 54, and it is convex that the 5th positioning plate 53 is equipped with second be connected in the second groove 54 Plate 55, the second positioning plate 42 and third positioning plate 51 are fixed by bolt and nut and lateral angle steel 31, the 4th positioning plate 52 and the Five positioning plates 53 are fixed by expansion bolt and smallpox.
Third positioning plate 51 is connected in the first groove 43 on the second positioning plate 42, determines third positioning plate 51 and second The connection of position plate 42 is relatively stable, and the second protrusive board 55 of the 5th positioning plate 53 is connected in the second groove 54 on the 4th positioning plate 52 It is interior, keep the connection of the 5th positioning plate 53 and the 4th positioning plate 52 relatively stable.
Concrete principle illustrates: sunpender 1 is directly connected to conversion layer 3, shortens the length of sunpender 1, is avoided because of 1 mistake of sunpender Long to lead to self structure fragility and unstable, the setting of conversion layer 3 and main support 4 provides enough sunpender 1 and hang ceiling panel 2 Reversed support, the setting of bearing diagonal 5, further improve conversion layer 3 installation stability, so as to provide counter support and knot Structure is firm, and hang ceiling panel 2 is effectively prevent to occur because of the situation for being caused hang ceiling panel 2 unstable by external force or suction function.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (7)

1. furred ceiling conversion layer structure, including sunpender (1) and set on the hang ceiling panel (2) of sunpender (1) lower end, feature exists In further including conversion layer (3) of the setting in sunpender (1) upper end, the conversion layer (3) is equipped with the main support that connect with smallpox (4), main support (4) two sides are equipped with bearing diagonal (5).
2. furred ceiling conversion layer structure according to claim 1, which is characterized in that the conversion layer (3) includes multiple Transverse direction angle steel (31) disposed in parallel, transverse direction angle steel (31) both ends are equipped with the connector (6) with wall connecting.
3. furred ceiling conversion layer structure according to claim 2, which is characterized in that the connector (6) includes passing through The mounting plate (61) and be integrally formed the carrying carried for lateral angle steel (31) with mounting plate (61) that expansion bolt and wall are fixed Plate (62), the loading plate (62) are fixed with lateral angle steel (31) by bolt and nut.
4. furred ceiling conversion layer structure according to claim 3, which is characterized in that the mounting plate (61) and loading plate (62) deep floor (63) are equipped between.
5. furred ceiling conversion layer structure according to claim 2, which is characterized in that between the transverse direction angle steel (31) Spacing is 1-2m.
6. furred ceiling conversion layer structure according to claim 1, which is characterized in that described main support (4) upper end is equipped with First positioning plate (41), main support (4) lower end are equipped with the second positioning plate (42), and first positioning plate (41) passes through expansion Bolt is fixed with smallpox, and second positioning plate (42) is fixed by bolt and lateral angle steel (31).
7. furred ceiling conversion layer structure according to claim 6, which is characterized in that bearing diagonal (5) lower end is equipped with Third positioning plate (51), second positioning plate (42) is equipped with the first groove (43) accommodated for third positioning plate (51), described Bearing diagonal (5) upper end be equipped with the 4th positioning plate (52), adjacent bearing diagonal (5) upper end be equipped with the 5th positioning plate (53), the described 4th Positioning plate (52) is equipped with the second groove (54), and the 5th positioning plate (53) is equipped with second be connected in the second groove (54) Protrusive board (55), second positioning plate (42) and third positioning plate (51) are fixed by bolt and nut and lateral angle steel (31), institute It states the 4th positioning plate (52) and the 5th positioning plate (53) is fixed by expansion bolt and smallpox.
CN201820492061.8U 2018-04-09 2018-04-09 Furred ceiling conversion layer structure Expired - Fee Related CN208202294U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820492061.8U CN208202294U (en) 2018-04-09 2018-04-09 Furred ceiling conversion layer structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820492061.8U CN208202294U (en) 2018-04-09 2018-04-09 Furred ceiling conversion layer structure

Publications (1)

Publication Number Publication Date
CN208202294U true CN208202294U (en) 2018-12-07

Family

ID=64525618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820492061.8U Expired - Fee Related CN208202294U (en) 2018-04-09 2018-04-09 Furred ceiling conversion layer structure

Country Status (1)

Country Link
CN (1) CN208202294U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113027033A (en) * 2021-03-19 2021-06-25 上海二十冶建设有限公司 Suspended ceiling mounting structure of pipeline dense embedded area and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113027033A (en) * 2021-03-19 2021-06-25 上海二十冶建设有限公司 Suspended ceiling mounting structure of pipeline dense embedded area and construction method

Similar Documents

Publication Publication Date Title
CN208202294U (en) Furred ceiling conversion layer structure
CN205557941U (en) Outer wall perforation aluminum curtain wall
CN211200882U (en) Steel construction conversion layer furred ceiling
CN209907705U (en) Prevent furred ceiling structure of gypsum board deformation
CN207846817U (en) A kind of ceiling structure
CN216713553U (en) Fireproof environment-friendly curtain box
CN114592638A (en) Hanging structure of split type assembly type ceiling
CN209874218U (en) Light keel decorative structure
CN201635228U (en) Novel flash rack ceiling system
CN207176988U (en) It is easy to the combined partition body of handling
CN206888312U (en) Assembled open-type builds the general erection support and mounting assembly of bottom plate
CN216195911U (en) Corridor suspended ceiling
CN212984292U (en) Structure platform unit body articulates structure
CN204983510U (en) Seat is hung to convenient to use's stone material
CN205134691U (en) Integrated furred ceiling of suspending free
CN218374901U (en) Novel ceramic tile dry-hanging system
CN218176155U (en) External hanging type wall body and main body connecting device
CN216276627U (en) Fixing structure of decorative board for building
CN217353145U (en) Suspended ceiling convenient to assemble and install
CN201972280U (en) Splicing hanging mechanism for unitized curtain wall
CN218292438U (en) Assembled light indoor suspended ceiling
CN220644821U (en) Stacked modeling assembled suspended ceiling
CN215563761U (en) Hospital is with assembled high steady keel frame furred ceiling
CN213509105U (en) Waterproof and anticorrosive open type stone curtain wall system
CN215594557U (en) Two-foot pendant

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181207

Termination date: 20200409

CF01 Termination of patent right due to non-payment of annual fee