CN208152583U - A kind of high-building construction ancillary equipment - Google Patents

A kind of high-building construction ancillary equipment Download PDF

Info

Publication number
CN208152583U
CN208152583U CN201820249017.4U CN201820249017U CN208152583U CN 208152583 U CN208152583 U CN 208152583U CN 201820249017 U CN201820249017 U CN 201820249017U CN 208152583 U CN208152583 U CN 208152583U
Authority
CN
China
Prior art keywords
ancillary equipment
truss
building construction
building
vertical truss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820249017.4U
Other languages
Chinese (zh)
Inventor
汪鼎华
佟力
李许
张文全
李改华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Excellence Industrialization Intelligent Construction Development Co Ltd
Original Assignee
Shenzhen Excellence Industrialization Intelligent Construction Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Excellence Industrialization Intelligent Construction Development Co Ltd filed Critical Shenzhen Excellence Industrialization Intelligent Construction Development Co Ltd
Priority to CN201820249017.4U priority Critical patent/CN208152583U/en
Application granted granted Critical
Publication of CN208152583U publication Critical patent/CN208152583U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a kind of high-building construction ancillary equipment, including:Multiple vertical truss being distributed on the outside of building, the vertical truss rectangular array are distributed in the periphery of the building, and the lower end of the vertical truss is equipped with lower jacking elevator group;Horizontal truss is fixedly connected with the vertical truss respectively;Top platform, its upper end for being set to the vertical truss, the top platform is equipped with gantry crane and intelligent casting system, and the horizontal truss of the lower part of the top platform is equipped with bridge crane track beam, and the bridge crane track beam is equipped with bridge crane;Operating platform, on the bridge crane track beam being connected to by wirerope.The purpose of this utility model is to provide a kind of modularization assemblings, integrate a variety of hanging devices, the high-building construction ancillary equipment of stable structure safety.

Description

A kind of high-building construction ancillary equipment
Technical field
The utility model is specifically designed a kind of auxiliary applied to high-building construction about a kind of construction equipment Equipment.
Background technique
With the fast development of Chinese economy, construction projects are increasing, the scale and degree-of-difficulty factor of construction are not yet It is disconnected to increase.Under this overall background, the safety accident to take place frequently in work progress becomes a big restriction of limitation Development of Construction Enterprises Factor.During carrying out high-building construction, scaffold is indispensable equipment, and in recent years, scaffold collapsing is fallen thing Therefore it is higher that the frequency occurs.The reason of causing this phenomenon be it is various, including scaffold set up lack of standardization, excess load operation, Arbitrarily remove drawknot or stressed member etc..In addition, building inherently for scaffold has the characteristics that cumbersome and risk is high, usually It causes casualties.
For assembled architecture, prefabricated component is more, and scene needs a large amount of lifting and assembling work.Lifting aspect, at present Using it is more be exactly derrick crane, this equipment only has a set of hoisting system, and every procedure of assembled-type house all needs The comparable activity duration is wanted, serial construction operation can only be carried out, it reduce the efficiency of overall operation.Skyscraper prefabrication and assembly construction After the lifting in place of formula concrete component, according to design specification, generally by back-grouting connection, be bolted or pre- iron slugging The modes such as connection.When the components such as the beam of prefabricated assembled concrete, column and plate are when outer wall displacement connects, it is necessary to by artificial Operation, on the outside of exterior wall when manual operation, it is necessary to exterior wall scaffold, also some use the techniques such as pylon, climbing frame, hanging basket, And existing scaffolding structure is difficult to accomplish disposably to be compatible with the demand at present, and all exists inconvenient for use and inefficiency Problem.
Utility model content
The purpose of this utility model is to provide a kind of modularization assemblings, integrate a variety of hanging devices, stable structure safety High-building construction ancillary equipment.
The high-building construction ancillary equipment of the utility model, including:
Multiple vertical truss being distributed on the outside of building, the vertical truss rectangular array are distributed in the building Periphery, the lower end of the vertical truss is equipped with lower jacking elevator group;
Horizontal truss is fixedly connected with the vertical truss respectively;
Top platform, is set to the upper end of the vertical truss, and the top platform is equipped with gantry crane and intelligence The horizontal truss of energy casting system, the lower part of the top platform is equipped with bridge crane track beam, the bridge crane Track girder is equipped with bridge crane;
Operating platform, on the bridge crane track beam being connected to by wirerope.
High-building construction ancillary equipment as described above, wherein the vertical truss is fixedly connected by multiple lifting columns It forms, the lifting column is hollow type truss structure;
High-building construction ancillary equipment as described above, wherein be equipped with discharging platform in the periphery of the horizontal truss;
High-building construction ancillary equipment as described above, wherein the lower end of the bridge crane is equipped with system for automatic marker making Positioning device and automatic spray curing means;
High-building construction ancillary equipment as described above, wherein be additionally provided with tower crane on the top platform;
High-building construction ancillary equipment as described above, wherein the vertical truss is built by wall-attaching equipment with described Object is built to be fixedly connected;
High-building construction ancillary equipment as described above, wherein the wall-attaching equipment is steel frame construction, and both ends can be divided It is not fixedly connected with the vertical truss;
High-building construction ancillary equipment as described above, wherein the vertical truss is applied equipped with what can be freely lifted Work elevator.
The high-building construction ancillary equipment of the utility model is fixedly connected with vertical truss using horizontal truss, and led to It crosses wall-attaching equipment to connect with building, structure safety and stability;The high-building construction ancillary equipment of the utility model may be implemented Modularization assembling, crane hoisting equipment include gantry crane, bridge crane and tower crane, and a variety of hoisting and hanging modes are consistent Cooperation, lifting operation range is big, high-efficient;The utility model is integrated with intelligent casting system, system for automatic marker making determines device and automatic Spray system, may be implemented the seamless connection operation for pouring, conserving and spraying, and operating efficiency is high.
Detailed description of the invention
Fig. 1 is the first embodiment schematic diagram of the high-building construction ancillary equipment of the utility model;
The first embodiment side view of the high-building construction ancillary equipment of the position Fig. 2 the utility model;
Fig. 3 is second of embodiment schematic diagram of the high-building construction ancillary equipment of the utility model;
Second of embodiment side view of the high-building construction ancillary equipment of the position Fig. 4 the utility model;
Fig. 5 is the third embodiment schematic diagram of the high-building construction ancillary equipment of the utility model;
The third embodiment side view of the high-building construction ancillary equipment of the position Fig. 6 the utility model;
Fig. 7 is the 4th kind of embodiment schematic diagram of the high-building construction ancillary equipment of the utility model;
Fig. 8 is the 4th kind of embodiment side view of the high-building construction ancillary equipment of the utility model.
Drawing reference numeral explanation:1, gantry crane;2, intelligent casting system;3, top platform;4, bridge crane;5, bridge Formula crane runway beam;6, system for automatic marker making positioning device;7, automatic spray curing means;8, personnel's operating platform;9, discharging is flat Platform;10, first level truss;11, attached wall track;12, the second horizontal truss;13, vertical truss;14, construction elevator;15, under Jack elevator group;16, tower crane;17, upper jacking elevator group;18, be connected formula wall-attaching equipment;100, Lou Ti;200, foundation pit.
Specific embodiment
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7 and Fig. 8, the high-building construction auxiliary of the utility model is set It is standby, including:Multiple vertical truss 13 being distributed on the outside of building, the vertical truss rectangular array are distributed in the building The lower end of the periphery of object, the vertical truss is equipped with lower jacking elevator group 15;Horizontal truss, respectively with the vertical truss 13 are fixedly connected;Top platform, is set to the upper end of the vertical truss 13, and the top platform 3 is equipped with gate-type lifting Machine 1 and intelligent casting system 2, the horizontal truss of the lower part of the top platform 3 is equipped with bridge crane track beam 5, described Bridge crane track beam 5 is equipped with bridge crane 4;Operating platform 8, the bridge crane being connected to by wirerope On track girder 5.The utility model energy modularization assembling integrates a variety of hanging devices, stable structure safety, construction efficiency height.
Further, the vertical truss 13 is formed by fixedly connecting by multiple lifting columns, and the lifting column is hollow type purlin Frame structure has high-tensile structural steel welded connecting, and the intensity of structure is high, and stability is good.
Further, it is equipped with discharging platform 9 in the periphery of the horizontal truss, can according to need arranging multiplayer, just In stratified operation, construction efficiency is higher.
Further, the lower end of the bridge crane 4 is equipped with system for automatic marker making positioning device 6 and automatic spray curing means 7, wherein system for automatic marker making positioning device can in construction flooring accurately system for automatic marker making, can only casting system can realize that fixed point is fixed Amount pours, and automatic spray curing means can be to wall beam and flooring automatic spray maintenance at regular time and quantity.
Further, it is additionally provided with tower crane 16 on the top platform, cooperated with gantry crane 1 and bridge crane 4 It uses, lifting mode diversification lifts high-efficient.
Further, the vertical truss 13 is fixedly connected by wall-attaching equipment 18 with the building, strengthens entirety The stability and safety of structure.Wherein, the wall-attaching equipment 18 be steel frame construction, both ends can respectively with the vertical truss It is fixedly connected
Further, the vertical truss 13 is equipped with the construction elevator 14 that can be freely lifted, construction personnel and various objects Material can be transmitted freely between the layers.
Further, building analyte detection system is installed on horizontal truss, the wall of each floor can be carried out outer Appearance quality and internal flaw real-time detection can find the problem and rectify and improve at any time, at any time so that construction quality be made to be protected.
The utility model can also be different according to the size selection of different buildings truss size, to adapt to different build House type is built, accomplishes a tractor serves several purposes, easy to disassemble and transport.
As shown in Fig. 5, Fig. 6 or Fig. 7, Fig. 8, the utility model can use upper jacking elevator group 17, dynamical element For hydraulic pump or motor, application method is similar with upper jack-up method, and details are not described herein.
The application of the utility model includes prefabricated concrete structure, steel construction, cast-type concrete building or Modern Wood Structure, use scope is extensive, adaptable.
The installation method of the high-building construction ancillary equipment of the utility model:
1) when the basement of building is partially completed construction, the modules of the utility model enter building site, utilize vapour Vehicle, which is hung, is mounted on elevator group 15 in the reserved foundation pit of basement, it is ensured that each lower jacking elevator group 15 is located at same level Face is simultaneously stably fixed in foundation pit;
2) a section lifting column 13 will be installed in each elevator group 15 with truck crane, will be installed in the side of multiple lifting columns 13 Construction elevator 14 installs top platform 3 and gantry crane 1 at the top of multiple lifting columns 13;
3) lifting column 13 is increased the height of a lifting column 13 by elevator group 15, and truck crane is again by new lifting column 13 It inserts in elevator group 15, two lifting columns 13 connected in same elevator group 15, elevator group 15 is again by new lifting column 13 promote the height of a lifting column, once analogize, and multiple lifting columns 13 are together in series to form vertical truss one by one, general next It says, after three to four lifting columns are connected, so that it may enter the ground construction stage, at interval of three to four lifting columns 13, One horizontal truss can be installed.
The method for dismounting of the utility model high-building construction construction auxiliary equipment:
After building binds, take up to remove the present apparatus.Before falling, gantry crane 1 and bridge crane 4 Building periphery must be run to and locked, in other implementations, tower crane 16 must also be rotated to architecture enclosing and be locked, After completing the above operation, starts lower jacking elevator group 15 and fall program after rise, all lifting columns start synchronous falling, every to fall one after rise The height of lifting column, elevator group 15 is inner removes out a section lifting column for each lower jacking.During falling, personnel's operating platform 8 Operation plane when can be used as decoration of exterior wall or defect mending and play a role again.First level truss 10, the second horizontal girder Each horizontal truss such as frame 12 is also same, is removed until falling after rise to Near Ground.All lifting equipments also equal quilt when close to ground Truck crane is removed.The component transition being removed reconfigures the building body that can be applied to different house types after transporting to other building sites. To accomplish a tractor serves several purposes, modular operation.
The characteristics of high-building construction ancillary equipment of the utility model and advantage are:
Vertical truss and horizontal truss are connected by wall-attaching equipment and building, and total stability is good, highly-safe;
Crane hoisting equipment includes gantry crane, bridge crane and tower crane, and a variety of hoisting and hanging modes cooperate simultaneously It uses, the high-efficient, various informative of hoisting and hanging operation, range are wide;
Top platform is equipped with intelligent casting system, and the lower end of bridge crane is equipped with automatic spraying device and system for automatic marker making Positioning device, allow scribing line, pour and spray operation and be seamlessly connected completion, operating efficiency and quality are all very high.
Further, the utility model may be equipped with intelligence control system and remote monitoring system, and intelligence may be implemented Early warning, strong operability can preferably ensure the safety of construction personnel;
The high-building construction ancillary equipment of the utility model is fixedly connected with vertical truss using horizontal truss, and led to It crosses wall-attaching equipment to connect with building, structure safety and stability;The high-building construction ancillary equipment of the utility model may be implemented Modularization assembling, crane hoisting equipment include gantry crane, bridge crane and tower crane, and a variety of hoisting and hanging modes are consistent Cooperation, lifting operation range is big, high-efficient;The utility model is integrated with intelligent casting system, system for automatic marker making determines device and automatic Spray system, may be implemented the seamless connection operation for pouring, conserving and spraying, and operating efficiency is high.
The above is only the preferred embodiment of the utility model, not does in any form to the utility model Limitation, although the utility model has been disclosed with preferred embodiment as above, is not intended to limit the utility model, any affiliated Has usually intellectual in technical field, in the range of not departing from technical solutions of the utility model, when using the disclosure above Technology contents make a little change or be modified to the equivalent embodiment of equivalent variations, but it is all without departing from the utility model technology The content of scheme, it is made by the above technical examples according to the technical essence of the present invention it is any it is simple modification, equivalent variations with Modification, is still within the scope of the technical solutions of the present invention.

Claims (8)

1. a kind of high-building construction ancillary equipment, which is characterized in that the high-building construction ancillary equipment includes:
Multiple vertical truss (13) being distributed on the outside of building, the vertical truss rectangular array are distributed in the building Periphery, the lower end of the vertical truss is equipped with lower jacking elevator group (15);
Horizontal truss is fixedly connected with the vertical truss (13) respectively;
Top platform, is set to the upper end of the vertical truss (13), and the top platform (3) is equipped with gantry crane (1) and intelligent casting system (2), the horizontal truss of the lower part of the top platform (3) are equipped with bridge crane track beam (5), the bridge crane track beam (5) is equipped with bridge crane (4);
Operating platform (8), on the bridge crane track beam (5) being connected to by wirerope.
2. high-building construction ancillary equipment as described in claim 1, which is characterized in that the vertical truss is by multiple liftings Column is formed by fixedly connecting, and the lifting column is hollow type truss structure.
3. high-building construction ancillary equipment as described in claim 1, which is characterized in that set in the periphery of the horizontal truss There are discharging platform (9).
4. high-building construction ancillary equipment as described in claim 1, which is characterized in that under the bridge crane (4) End is equipped with system for automatic marker making positioning device (6) and automatic spray curing means (7).
5. high-building construction ancillary equipment as described in claim 1, which is characterized in that be additionally provided with tower on the top platform It hangs.
6. high-building construction ancillary equipment as described in claim 1, which is characterized in that the vertical truss is filled by attached wall It sets and is fixedly connected with the building.
7. high-building construction ancillary equipment as claimed in claim 6, which is characterized in that the wall-attaching equipment is steelframe knot Structure, both ends can be fixedly connected with the vertical truss respectively.
8. high-building construction ancillary equipment as described in claim 1, which is characterized in that the vertical truss is equipped with can be certainly By the construction elevator gone up and down.
CN201820249017.4U 2018-02-11 2018-02-11 A kind of high-building construction ancillary equipment Active CN208152583U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820249017.4U CN208152583U (en) 2018-02-11 2018-02-11 A kind of high-building construction ancillary equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820249017.4U CN208152583U (en) 2018-02-11 2018-02-11 A kind of high-building construction ancillary equipment

Publications (1)

Publication Number Publication Date
CN208152583U true CN208152583U (en) 2018-11-27

Family

ID=64382423

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820249017.4U Active CN208152583U (en) 2018-02-11 2018-02-11 A kind of high-building construction ancillary equipment

Country Status (1)

Country Link
CN (1) CN208152583U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108277985A (en) * 2018-02-11 2018-07-13 深圳市卓越工业化智能建造开发有限公司 A kind of high-building construction ancillary equipment
CN112431397A (en) * 2020-12-07 2021-03-02 中国二十冶集团有限公司 High-rise building construction system and installation and use method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108277985A (en) * 2018-02-11 2018-07-13 深圳市卓越工业化智能建造开发有限公司 A kind of high-building construction ancillary equipment
CN112431397A (en) * 2020-12-07 2021-03-02 中国二十冶集团有限公司 High-rise building construction system and installation and use method thereof
CN112431397B (en) * 2020-12-07 2022-06-28 中国二十冶集团有限公司 High-rise building construction system and installation and use method thereof

Similar Documents

Publication Publication Date Title
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN100587206C (en) Steel pillar supporting type integral self-lifting steel platform scaffold template system
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN106400951B (en) A kind of level and vertical structure method for synchronously constructing of super high-rise building
CN110552507A (en) Well is from automatic cloth system of concrete that climbs
CN105442839A (en) Erecting method of cantilever structure formwork bent
CN101566005B (en) Chimney hydraulic mould lifting device
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN208152583U (en) A kind of high-building construction ancillary equipment
CN103485574B (en) A kind of granulation tower tower top structure of reinforced concrete method
CN102777044B (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN202401769U (en) Detachable concrete cloth machine for self-elevating creeping formwork system
CN111039197B (en) Construction method for reverse-order joint addition of jacking of internal-climbing tower crane
CN210483094U (en) Inverted triangular pipe truss lifting device
CN112267692A (en) Assembly type building component hoisting comprehensive equipment and construction method thereof
CN104499706A (en) Elevator well template platform and construction method thereof
CN108277985A (en) A kind of high-building construction ancillary equipment
CN204850469U (en) Commercial mansion system that builds
CN115680286A (en) Nuclear island reactor factory building construction equipment integration platform and climbing method thereof
CN216840692U (en) Construction device for super high-rise building
CN204754150U (en) Dish -type node formula scaffold
CN211472175U (en) Aerial working platform device suitable for steel bridge construction
CN209651673U (en) A kind of construction elevator attaching structure of lifting platform
CN112854702A (en) Large-span silo roof construction platform and erection method
CN206693239U (en) The cast-in-place device of bridge machine T beams is realized on a kind of high-altitude thin-wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant