CN208109596U - PCCP pipeline pressure test tool pipe - Google Patents

PCCP pipeline pressure test tool pipe Download PDF

Info

Publication number
CN208109596U
CN208109596U CN201820426973.5U CN201820426973U CN208109596U CN 208109596 U CN208109596 U CN 208109596U CN 201820426973 U CN201820426973 U CN 201820426973U CN 208109596 U CN208109596 U CN 208109596U
Authority
CN
China
Prior art keywords
sealing
pipe
pccp
fixed cylinder
cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820426973.5U
Other languages
Chinese (zh)
Inventor
吴悦人
陶哲峰
朱磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
WUXI HUAYI PIPELINE CO Ltd
Original Assignee
WUXI HUAYI PIPELINE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by WUXI HUAYI PIPELINE CO Ltd filed Critical WUXI HUAYI PIPELINE CO Ltd
Priority to CN201820426973.5U priority Critical patent/CN208109596U/en
Application granted granted Critical
Publication of CN208109596U publication Critical patent/CN208109596U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

The utility model relates to a kind of pressure test tools, especially PCCP pipeline pressure test tool pipe, including sealing drum, fixed cylinder, movable cylinder and sealing water filling device;The activity cylinder activity is inserted in sealing drum, sealing drum activity is inserted in fixed cylinder, sealing drum sealed connection activity cylinder and fixed cylinder, the sealing water filling device is separately fixed at one end of one end and fixed cylinder of movable cylinder, sealing water filling device is connect with the bellmouth of PCCP pipe or socket, sealing water filling device is filled the water into PCCP pipeline, and sealing water filling device is communicated with fixed cylinder, and the fixed cylinder is equipped with moisturizing pressurization mouth.Structure provided by the utility model is simple, can reuse, is easy for installation, safety is good, using simple, test is accurate, and test water can be recycled, high financial profit.

Description

PCCP pipeline pressure test tool pipe
Technical field
The utility model relates to a kind of pressure test tools, especially PCCP pipeline pressure test tool pipe.
Background technique
Prestressed concrete cylinder pipe, abbreviation PCCP pipe are a kind of answering with high intensity, high permeability resistant and high leakproofness It is former auxiliary to have gathered sheet metal, high-strength concrete, high-strength prestressed steel wire, high-strength mortar and rubber seal etc. for mould assembly tubing Material is fabricated.The pipeline is particularly suitable for heavy caliber, senior engineer's pressure and high earthing water supply project.PCCP pipe uses bell and spigot formula Connection is sealed by installing rubber seal at socket recess.According to code requirement, after pressure pipeline is installed, The carry out water pressure test should be segmented just allows grid-connected water flowing to come into operation after the water pressure test is qualified (drawdown and water percolating capacity method). The length of pipe section of the pressure pipeline water pressure test is required not to be preferably greater than 1.0km in specification, therefore Pressure Piping Engineering need to carry out repeatedly The water pressure test.The plugging device of the water pressure test counts for much.The especially safety of plugging device, economy and invention convenience It is all influenced on the water pressure test, even on entire pipeline installation engineering great.
Current water pressure test plugging device is:Steel suppresses accessory tube.Steel, which suppresses accessory tube, to be welded by roll of steel plate It forms, general a length of 5000mm, both ends setting bell and spigot is connect with PCCP pipe.The welding of accessory tube bosom is suppressed in steel Steel is suppressed and is blocked inside accessory tube by steel plate, as the closure plate of the water pressure test, is produced using PCCP pipe and the soil body of front and back installation Raw frictional force prevents sliding as backrest, and a certain section of PCCP pipeline for suppressing accessory tube middle position to two section steels carries out Bath and the water pressure test.After the completion of the water pressure test, need to be manually entered closure plate be cut into fritter inside pipeline, closure plate fritter from After hanging out pipeline into manhole, then pipeline inside closure plate position is handled using mortar lining cutting.Therefore, steel suppresses accessory tube cost Higher, generally thickness 20mm~30mm roll of steel plate weldering is made, and inner circular closure plate thickness 30mm~40mm is suppressed with steel and matched The welding of part pipe, steel plate welding quality require high.It, be manually from into cutting in manhole pipe after the completion of the water pressure test, expense of taking a lot of work When, worker carries out cutting operation inside the pipeline that air hardly circulates, and is absolutely unsafe, and endangers health.And it manually cuts Accessory tube may also be suppressed to steel by, which cutting, the adverse effect such as is deformed.Plugging plate is welded on steel and suppresses inside accessory tube, water Displacement or the deformation that the PCCP pipeline as rear backrest can not be observed during pressure test, cause the water pressure test to allow to seep The test of water method is inaccurate.In addition it after the completion of the water pressure test, needs to be manually entered inside pipeline closure plate is cut into fritter, cause Closure plate can only first use, cannot recycle, economic efficacy is low.
Utility model content
To solve the above problems, the utility model provides, a kind of structure is simple, can reuse, easy for installation, safety Well, using simple, test is accurate, and test water can be recycled, the PCCP pipeline pressure test tool pipe of high financial profit, tool Body technique scheme is:
PCCP pipeline pressure test tool pipe, including sealing drum, fixed cylinder, movable cylinder and sealing water filling device;The activity cylinder Activity is inserted in sealing drum, and sealing drum activity is inserted in fixed cylinder, sealing drum sealed connection activity cylinder and fixed cylinder, the sealing Water filling device is separately fixed at one end of movable cylinder and one end of fixed cylinder, seals the bellmouth or socket of water filling device and PCCP pipe Connection, sealing water filling device are filled the water into PCCP pipeline, and sealing water filling device is communicated with fixed cylinder, and the fixed cylinder, which is equipped with, mends Water pressurization mouth.
By using above-mentioned technical proposal, beats behind a section and the water pump in this section is transferred to next section, tried Testing can be recycled with water, and the detachable Reusability of tool pipe, the space after tool pipe is dismantled is closed with gathering pipe.
Preferably, the sealing water filling device includes sealing plate, connecting plate, water injection pipe, bypass pipe, Water filling valve and bypass Valve;The sealing plate and connecting plate are plectane, and sealing plate is connected with connecting plate by stiffening plate, and sealing plate is equipped with water filling Hole, connecting plate are equipped with connecting hole;One end of the Water filling valve and water injection pipe connection, water injection pipe be mounted on two sealing plates it Between, the other end sealing welding of water injection pipe is on the water injection hole of sealing plate;One end of the bypath valve passes through connecting tube and note One end of water pipe connection, the other end and bypass pipe connects, and the other end sealing welding of bypass pipe is on the connecting hole of connecting plate;Institute The end that sealing plate is pressed in PCCP pipe is stated, the connecting plate is connect with one end of fixed cylinder and movable cylinder respectively.
By using above-mentioned technical proposal, the on-off of Water filling valve and bypath valve realization trial zone and tool pipe is convenient Water filling and pressurization.
Preferably, the diameter of the sealing drum and the diameter of fixed cylinder are consistent, are equipped on the periphery of the fixed cylinder other end Positioning tube, sealing drum are inserted in positioning tube, and sealing ring is equipped between sealing drum and fixed cylinder, and sealing ring is also located at movable cylinder and determines Between the cylinder of position.
By using above-mentioned technical proposal, sealing structure is simple, reliable, is not easy to reveal, while can bear biggish pressure.
Preferably, positioning column is housed, positioning column is no less than three, and positioning column is around positioning tube on the periphery of the positioning tube Axis spaced set;Sealing column is housed, sealing column quantity is consistent with positioning column, sealing column on the periphery of the sealing drum Around the axis spaced set of sealing drum;Long bolt is housed, long bolt passes through sealing column, and one end of long bolt is installed on positioning column On connecting plate, the two sides of positioning column and sealing column are equipped with nut, and nut is screwed on long bolt.
By using above-mentioned technical proposal, the position of screw rod realization activity cylinder is adjusted, so that implementation tool pipe and PCCP are managed The sealing of line makes to dismount abundant use that is very convenient, and realizing tool pipe.
Preferably, gasket is housed, gasket is between sealing plate and PCCP pipe on the sealing plate.
By using above-mentioned technical proposal, gasket further increases the leakproofness between tool pipe and PCCP pipe, makes to try The enough primary successes of pressure energy, improve efficiency.
Preferably, the sealing plate is equipped with socket steel ring or bellmouth steel loop, and socket steel ring or bellmouth steel loop and PCCP are managed Bellmouth or socket connection.
Preferably, liftout bolt is housed, liftout bolt is no less than three, and liftout bolt is around fixed cylinder on the sealing plate Axis spaced set, liftout bolt face the end face of PCCP pipe.
By using above-mentioned technical proposal, liftout bolt facilitates separation.
Preferably, the fixed cylinder is equipped with manhole.
Preferably, the sealing ring is no less than two.
Hydraulic test pressure 1.1MPa, longitudinal thrust 5456kN, PCCP pipeline longitudinal direction thrust is by downstream pipeline and soil The frictional force of earth, thrust length are calculated according to soil and PCCP pipe friction coefficient and are determined, the power transmitted between Guan Yuguan is by only outer It encloses concrete to bear, average compressive stress 4.4MPa, grout filler between interface tube is it is ensured that could be into after reaching this intensity requirement The row water pressure test.
For convenience of description, the Water filling valve on the PCCP pipeline pressure test tool pipe left side is set to Water filling valve one, bypath valve It is set to bypath valve one, the Water filling valve on the right is set to Water filling valve two, and bypath valve is set to bypath valve two.
When the pipeline in pressure testing left side section, Water filling valve one, Water filling valve two and bypath valve two are closed, opens bypass Valve one waits tool pipes full of after water, water can be filled from bypass pipe through bypath valve one from the moisturizing pressurization mouth water-filling on tool pipe Enter duct test section, can be full of when 1 kilometer long of DN2400 pipe 48 is small in the case that water source, water can guarantee, trial zone Between be kept open full of bypath valve one after water, from tool pipe moisturizing pressurization mouth pressurization, according to the water pressure test journey of regulation Sequence carries out bulge test.
After the bulge test of left side section, when needing test water to be transferred to the right section from left section, filling the water One 4 cun of self priming pump is installed between valve one and Water filling valve two, opens Water filling valve one and Water filling valve two, closes by-passing valve Door one and bypath valve two, switch on the pump and draw water.When left side section water shortage is to be full of the right section or the right section When having been filled with water and needing to boost, Water filling valve one, Water filling valve two and bypath valve one are closed, bypath valve two is opened, from benefit Water pressurization mouth carries out moisturizing, pressurization.
Nut and nut and sealing column are first passed through when dismantling pressure test tool pipe sealing drum toward moving to left, and loosen sealing ring, Then entire tool length of tube is shortened by nut and nut 5 and long bolt, inserting for pressure test tool pipe is pulled out from PCCP pipe Mouth or bellmouth, while so that the socket steel ring of entire pressure test tool pipe or bellmouth steel loop is detached from PCCP pipe by liftout bolt 5 Socket or bellmouth carefully hang out pressure test tool pipe.
It is carried out when installation tool pipe using with this reverse procedure.
The space that PCCP pipeline pressure test tool pipe leaves after hanging away can be filled up with PCCP gathering pipe, can also be added with bridgeware Cast pipe union is filled up.
Due to using unilateral pressure testing when pressure testing, conducts pressure to the PCCP pipeline of tool pipe two sides, can guarantee that PCCP is managed Frictional force between line and soil meets test needs.
The utility model has the advantages that compared with prior art:
Structure provided by the utility model is simple, can reuse, is easy for installation, safety is good, using simple, test essence Really, and test water can be recycled, high financial profit.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural schematic diagram for sealing water filling device.
Specific embodiment
Now in conjunction with attached drawing, the utility model is described in further detail.
As depicted in figs. 1 and 2, PCCP pipeline pressure test tool pipe, including sealing drum 2, fixed cylinder 1, movable cylinder 3 and sealing note Water installations;Movable 3 activity of cylinder is inserted in sealing drum 2, and 2 activity of sealing drum is inserted in fixed cylinder 1,2 sealed connection activity of sealing drum Cylinder 3 and fixed cylinder 1, sealing water filling device are separately fixed at one end of movable cylinder 3 and one end of fixed cylinder 1, seal water filling device It is connect with the bellmouth of PCCP pipe 10 or socket, sealing water filling device is filled the water into PCCP pipeline, sealing water filling device and fixed cylinder 1 It communicates, fixed cylinder 1 is equipped with moisturizing pressurization mouth 11.
Sealing water filling device includes sealing plate 52, connecting plate 51, water injection pipe 61, bypass pipe 62, Water filling valve and by-passing valve Door;Sealing plate 52 and connecting plate 51 are plectane, and sealing plate 52 and connecting plate 51 are coaxially set, and with 1 coaxial line of fixed cylinder, Sealing plate 52 and connecting plate 51 are connected by stiffening plate 53, and sealing plate 52 is equipped with water injection hole, and connecting plate 51 is equipped with connecting hole; Water filling valve is connect with one end of water injection pipe 61, and water injection pipe 61 is mounted between two sealing plates 52, the other end of water injection pipe 61 Sealing welding is on the water injection hole of sealing plate 52;One end of bypath valve is connect by connecting tube 63 with water injection pipe 61, the other end It is connect with one end of bypass pipe 62, the other end sealing welding of bypass pipe 62 is on the connecting hole of connecting plate 51;Sealing plate 52 is pressed In the end of PCCP pipe 10, connecting plate 51 is connect with one end of fixed cylinder 1 and movable cylinder 3 respectively.
The diameter of sealing drum 2 is consistent with the diameter of fixed cylinder 1, and positioning tube 13 is housed on the periphery of 1 other end of fixed cylinder, Sealing drum 2 is inserted in positioning tube 13, is equipped with sealing ring 4 between sealing drum 2 and fixed cylinder 1, sealing ring 4 be also located at movable cylinder 3 with Between positioning tube 13.There are three sealing ring 4 is set, and cover on movable cylinder 3 side by side.
Positioning column 81 is housed, positioning column 81 is no less than three, and positioning column 81 is around positioning tube 13 on the periphery of positioning tube 13 Axis spaced set;
Sealing column 82 is housed, 82 quantity of sealing column and positioning column 81 are consistent, and sealing column 82 is around close on the periphery of sealing drum 2 The axis spaced set of sealed tube 2;
Long bolt 83 is housed, long bolt 83 passes through sealing column 82, and one end of long bolt 83 is mounted on connection on positioning column 81 On plate 51, the two sides of positioning column 81 are equipped with nut 84 and the two sides of nut 85, sealing column 82 are equipped with nut 86 and nut 87, nut 84, it 85,86 and 87 is screwed on long bolt 83.
Gasket 54 is housed, gasket 54 is between sealing plate 52 and PCCP pipe 10 on sealing plate 52.
Sealing plate 52 is equipped with socket steel ring or bellmouth steel loop, the bellmouth of socket steel ring or bellmouth steel loop and PCCP pipe 10 or Socket connection.
Liftout bolt 54 is housed, liftout bolt 54 is no less than three, axis of the liftout bolt 54 around fixed cylinder 1 on sealing plate 52 Line spaced set, liftout bolt face the end face of PCCP pipe 10.
Fixed cylinder 1 is equipped with manhole 12.
Hydraulic test pressure 1.1MPa, longitudinal thrust 5456kN, PCCP pipeline longitudinal direction thrust is by downstream pipeline and soil The frictional force of earth, thrust length are calculated according to soil and 10 coefficient of friction of PCCP pipe and are determined, the power transmitted between Guan Yuguan is by only leaning on Outer ring concrete is born, average compressive stress 4.4MPa, and grout filler is it is ensured that reach ability after this intensity requirement between interface tube Carry out the water pressure test.
For convenience of description, the Water filling valve on the PCCP pipeline pressure test tool pipe left side is set to Water filling valve 1, by-passing valve Door is set to bypath valve 1, and the Water filling valve on the right is set to Water filling valve 2 72, and bypath valve is set to bypath valve 2 74.
When the pipeline in pressure testing left side section, Water filling valve 1, Water filling valve 2 72 and bypath valve 2 74 are closed, is beaten Bypath valve 1 is opened, from moisturizing pressurization 11 water-filling of mouth on tool pipe, waits tool pipes full of after water, water can be passed through from bypass pipe 62 Bypath valve 1 is filled with duct test section, when 1 kilometer long of DN2400 pipe 48 is small in the case that water source, water can guarantee It can be full of, test section is kept open full of bypath valve 1 after water, it pressurizes from tool pipe moisturizing pressurization mouth 11, according to Defined water pressure test program carries out bulge test.
After the bulge test of left side section, when needing test water to be transferred to the right section from left section, filling the water One 4 cun of self priming pump is installed between valve 1 and Water filling valve 2 72, opens Water filling valve 1 and Water filling valve 2 72, is closed Bypath valve 1 and bypath valve 2 74 are closed, switches on the pump and draws water.When left side section water shortage is to be full of the right area Between or the right section when having been filled with water and needing to boost, close Water filling valve 1, Water filling valve 2 72 and bypath valve 1, beat Bypath valve 2 74 is opened, carries out moisturizing, pressurization from moisturizing pressurization mouth 11.
Nut 86 and nut 87 and sealing column 82 are first passed through when dismantling pressure test tool pipe sealing drum 2 toward moving to left, and make to seal Circle 4 loosens, and then entire tool length of tube is shortened by nut 84 and nut 85 and long bolt 83, is pulled out from PCCP pipe 10 The socket or bellmouth of pressure test tool pipe, while the socket steel ring or bellmouth steel loop of entire pressure test tool pipe are made by liftout bolt 54 It is detached from the socket or bellmouth of PCCP pipe 10, carefully hangs out pressure test tool pipe.
It is carried out when installation tool pipe using with this reverse procedure.
The space that PCCP pipeline pressure test tool pipe leaves after hanging away can be filled up with PCCP gathering pipe, can also be added with bridgeware Cast pipe union is filled up.

Claims (9)

1.PCCP pipeline pressure test tool pipe, which is characterized in that including sealing drum (2), fixed cylinder (1), movable cylinder (3) and sealing note Water installations;Described activity cylinder (3) activity is inserted in sealing drum (2), and sealing drum (2) activity is inserted in fixed cylinder (1), sealing drum (2) sealed connection activity cylinder (3) and fixed cylinder (1), the sealing water filling device are separately fixed at one end of movable cylinder (3) and consolidate One end of safety barrel (1), sealing water filling device are connect with the bellmouth of PCCP pipe (10) or socket, seal water filling device to PCCP pipeline Interior water filling, sealing water filling device are communicated with fixed cylinder (1), and the fixed cylinder (1) is equipped with moisturizing pressurization mouth (11).
2. PCCP pipeline pressure test tool pipe according to claim 1, which is characterized in that the sealing water filling device includes close Sealing plate (52), connecting plate (51), water injection pipe (61), bypass pipe (62), Water filling valve and bypath valve;The sealing plate (52) and Connecting plate (51) is that plectane, sealing plate (52) and connecting plate (51) are connected by stiffening plate (53), and sealing plate (52) is equipped with Water injection hole, connecting plate (51) are equipped with connecting hole;The Water filling valve is connect with the one end of water injection pipe (61), water injection pipe (61) peace Between two sealing plates (52), the other end sealing welding of water injection pipe (61) is on the water injection hole of sealing plate (52);It is described One end of bypath valve is connect by connecting tube (63) with water injection pipe (61), and the other end is connect with the one end of bypass pipe (62), other The other end sealing welding of siphunculus (62) is on the connecting hole of connecting plate (51);The sealing plate (52) is pressed in PCCP pipe (10) End, the connecting plate (51) connect with one end of fixed cylinder (1) and movable cylinder (3) respectively.
3. PCCP pipeline pressure test tool pipe according to claim 2, which is characterized in that the diameter of the sealing drum (2) with The diameter of fixed cylinder (1) is consistent, and positioning tube (13) are housed on the periphery of fixed cylinder (1) other end, and sealing drum (2) is inserted in positioning In cylinder (13), sealing ring (4) are equipped between sealing drum (2) and fixed cylinder (1), sealing ring (4) is also located at movable cylinder (3) and positioning Between cylinder (13).
4. PCCP pipeline pressure test tool pipe according to claim 3, which is characterized in that the periphery of the positioning tube (13) Upper that positioning column (81) are housed, positioning column (81) is no less than three, axis spaced set of the positioning column (81) around positioning tube (13); Sealing column (82) are housed on the periphery of the sealing drum (2), sealing column (82) quantity and positioning column (81) unanimously, sealing column (82) around the axis spaced set of sealing drum (2);Long bolt (83) are housed on positioning column (81), long bolt (83) passes through sealing Column (82), one end of long bolt (83) are mounted on connecting plate (51), and the two sides of positioning column (81) and sealing column (82) are equipped with Nut, nut are screwed on long bolt (83).
5. PCCP pipeline pressure test tool pipe according to claim 2, which is characterized in that equipped with close on the sealing plate (52) Packing (54), gasket (54) are located between sealing plate (52) and PCCP pipe (10).
6. PCCP pipeline pressure test tool pipe according to claim 2, which is characterized in that the sealing plate (52), which is equipped with, inserts Mouth steel loop or bellmouth steel loop, socket steel ring or bellmouth steel loop are connect with the bellmouth of PCCP pipe (10) or socket.
7. PCCP pipeline pressure test tool pipe according to claim 6, which is characterized in that equipped with top on the sealing plate (52) Bolt (55) out, liftout bolt (55) are no less than three, and liftout bolt (55) is pushed up around the axis spaced set of fixed cylinder (1) Bolt faces the end face of PCCP pipe (10) out.
8. PCCP pipeline pressure test tool pipe according to claim 1, which is characterized in that the fixed cylinder (1) is equipped with people Hole (12).
9. PCCP pipeline pressure test tool pipe according to claim 3, which is characterized in that the sealing ring (4) is no less than two It is a.
CN201820426973.5U 2018-03-27 2018-03-27 PCCP pipeline pressure test tool pipe Active CN208109596U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820426973.5U CN208109596U (en) 2018-03-27 2018-03-27 PCCP pipeline pressure test tool pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820426973.5U CN208109596U (en) 2018-03-27 2018-03-27 PCCP pipeline pressure test tool pipe

Publications (1)

Publication Number Publication Date
CN208109596U true CN208109596U (en) 2018-11-16

Family

ID=64121742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820426973.5U Active CN208109596U (en) 2018-03-27 2018-03-27 PCCP pipeline pressure test tool pipe

Country Status (1)

Country Link
CN (1) CN208109596U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112696554A (en) * 2020-12-17 2021-04-23 中国二十冶集团有限公司 Large-diameter pipeline pressure test plugging blind plate and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112696554A (en) * 2020-12-17 2021-04-23 中国二十冶集团有限公司 Large-diameter pipeline pressure test plugging blind plate and construction method thereof

Similar Documents

Publication Publication Date Title
CN107762532B (en) Tunnel vault band mould grouting construction method
CN206346209U (en) A kind of quick solution dewatering well piping plugging structure
CN106015824B (en) Prestressed concrete cylinder pipe road water pressure test plugging device and method
CN208109596U (en) PCCP pipeline pressure test tool pipe
CN210105808U (en) Packing sealing blowout preventer
CN105156117A (en) Tunnel-rescue pipe jacking machine and construction method thereof
CN104564105B (en) A kind of apparatus and method of two grades of sleeve pipes of seat earth grouting and reinforcing
CN103161171B (en) The band pump shut-in well method of Dewatering by pressure reduction well
CN208058113U (en) A kind of amendment construction system of construction push pipe
CN109707417B (en) Supercharging device and method suitable for individual hydraulic prop of underground coal mine
CN102434168B (en) Pipe connecting device
CN208534487U (en) Small-bore mire water equilibrium tube equipment slip casting tail sleeve device
CN102080379A (en) V-shaped steel plate pulling device for ultra-deep ground wall construction
CN206034446U (en) Right structure for institute when ground pile pipe is driven underground
CN211081878U (en) Hydraulic engineering construction is with excavating anti-collapse device
CN210858736U (en) Device for preventing shield spiral conveyor from gushing
CN204386616U (en) A kind of device of seat earth grouting and reinforcing secondary sleeve pipe
CN108086982A (en) A kind of pipe jacking tool and its jacking method
CN210422560U (en) Mining slip casting hole packer
CN103883348B (en) The welding method of a kind of minery gas pumping well ground pipeline
CN207499873U (en) A kind of pipe jacking tool
CN202545384U (en) Siphon outlet device
CN202992424U (en) Reinforced concrete pipe with sealing rod for jacking construction method
CN107061865B (en) A kind of new old pipeline of sewage treatment plant's heavy caliber does not stop production the method for meeting and discussing
CN205475538U (en) Stifled PVC sewer pipe is prevented to high efficiency

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant