CN208105078U - Bridge triangular hanging basket - Google Patents
Bridge triangular hanging basket Download PDFInfo
- Publication number
- CN208105078U CN208105078U CN201820374046.3U CN201820374046U CN208105078U CN 208105078 U CN208105078 U CN 208105078U CN 201820374046 U CN201820374046 U CN 201820374046U CN 208105078 U CN208105078 U CN 208105078U
- Authority
- CN
- China
- Prior art keywords
- pillar
- hanging basket
- bridge
- fixedly connected
- fixedly installed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses bridge triangular hanging baskets, including bridge column, bottom plate and Hanging Basket, the upper end of the bridge column is fixedly connected with bridge floor, the left and right ends of the bridge floor are fixedly installed with guide rail, the inner surface of the guide rail is connected with Guide rollers, the left and right ends of the bottom base plate are fixedly installed with wheel frame, left and right ends at the top of the bottom plate are fixedly connected to triangle hack lever, it is fixedly installed with the first pillar at the center of the left end triangle hack lever, is fixedly installed with the second pillar at the center of the right end triangle hack lever.The utility model is cooperated by bridge floor, guide rail, wheel frame, rope shaft, cross bar, motor, motor fixed block, bottom plate, Guide rollers, stock, pulley blocks, rope, Hanging Basket, the first pillar, tripod bar and the second pillar, solving existing triangle hanging basket may only generally be moved forward and backward, want to move up and down and just needs to reinstall Hanging Basket, problem very troublesome.
Description
Technical field
The utility model relates to bridge construction technical fields, specially bridge triangular hanging basket.
Background technique
Hanging Basket cantilever pouring construction be also known as Di Weidake construction method, since nineteen sixties by preceding West Germany first
It since use, has been developed so far, it has also become build a kind of extremely efficient construction means of big-and-middle across footpath bridge, Hanging Basket is filled as outstanding
The capital equipment of method construction has developed into numerous kinds, as parallel truss Hanging Basket, triangle combination beam type Hanging Basket, bowstring type are hung
Basket, stayed-cable hanging basket and triangular truss formula Hanging Basket etc., China has achieved huge since the eighties introduce the technique
Achievement, wherein with triangle because its structure is simple and the advantages such as reasonable stress will be widely welcomed, but existing triangle hanging basket
It may only generally be moved forward and backward, it is desirable to it moves up and down and just needs to reinstall Hanging Basket, it is very troublesome, for this purpose, it is proposed that bridge
Triangle hanging basket.
Utility model content
The purpose of this utility model is to provide bridge triangular hanging baskets, have multi-direction mobile advantage, solve existing
Triangle hanging basket may only be generally moved forward and backward, it is desirable to and it moves up and down and just needs to reinstall Hanging Basket, problem very troublesome.
To achieve the above object, the utility model provides the following technical solutions:Bridge triangular hanging basket, including bridge column, bottom plate
And Hanging Basket, the upper end of the bridge column are fixedly connected with bridge floor, the left and right ends of the bridge floor are fixedly installed with guide rail, described to lead
The inner surface of rail is connected with Guide rollers, and the left and right ends of the bottom base plate are fixedly installed with wheel frame, the bottom
Left and right ends at the top of plate are fixedly connected to triangle hack lever, are fixedly installed with first at the center of triangle hack lever left end
Column is fixedly installed with the second pillar at the center of the triangle hack lever right end, is fixedly installed with electricity on the left of first pillar
Machine, is rotatably connected to shaft between first pillar and the second pillar, the output shaft of the motor and the left side of shaft are fixed
The top of connection, first pillar and the second pillar is fixedly connected to cross bar, and the left and right ends of the cross bar front surface are equal
It is fixedly connected with stock, the bottom of the stock front surface is movably installed with pulley blocks.
Preferably, the outer surface of the shaft is arranged with rope, and the material of rope is irony.
Preferably, the bottom of the motor is fixedly connected with motor fixed block, and the motor fixed block is fixedly connected on
The left side of one pillar.
Preferably, the inner surface of the wheel frame is flexibly connected with Guide rollers, and pulley system is equipped on Guide rollers
Dynamic structure.
Compared with prior art, the beneficial effects of the utility model are as follows:
1, the utility model is fixedly installed with guide rail in the left and right ends of bridge floor, and the inner surface of guide rail, which is connected with, leads
Rail pulley, the left and right ends of bottom base plate are fixedly installed with wheel frame, and the inner surface of wheel frame is flexibly connected with Guide rollers,
Hanging Basket can be allowed to be moved forward and backward, the left and right ends at the top of bottom plate are fixedly connected to triangle hack lever, in triangle hack lever left end
It is fixedly installed with the first pillar at center, the second pillar, a left side for the first pillar are fixedly installed at the center of triangle hack lever right end
Side is fixedly installed with motor, and shaft, the output shaft of motor and a left side for shaft are rotatably connected between the first pillar and the second pillar
Side is fixedly connected, and the top of the first pillar and the second pillar is fixedly connected to cross bar, and the left and right ends of cross bar front surface are solid
Surely it is connected with stock, the bottom of stock front surface is movably installed with pulley blocks, Hanging Basket can be made to move up and down, and solves existing
Triangle hanging basket may only be generally moved forward and backward, it is desirable to and it moves up and down and just needs to reinstall Hanging Basket, problem very troublesome.
2, the utility model is fixedly connected with motor fixed block in the bottom of motor, and motor fixed block is fixedly connected on first
The left side of pillar guarantees the stability of motor during the work time, pulley brake structure is equipped on Guide rollers, guarantees to lead
Rail pulley can stop at any time.
Detailed description of the invention
Fig. 1 is the utility model schematic view of the front view;
Fig. 2 is the utility model right side structural representation.
In figure:Bridge 1 column, Bridge 2 face, 3 guide rails, 4 wheel frames, 5 rope shafts, 6 cross bars, 7 motors, 8 motor fixed blocks, 9 bottoms
Plate, 10 Guide rollers, 11 stocks, 12 pulley blocks, 13 ropes, 14 Hanging Baskets, 15 first pillars, 16 tripod bars, 17 second pillars.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Bridge triangular hanging basket referring to FIG. 1-2, including bridge column 1, bottom plate 9 and Hanging Basket 14, the upper end of bridge column 1 are fixedly connected
There is bridge floor 2, the left and right ends of bridge floor 2 are fixedly installed with guide rail 3, and the inner surface of guide rail 3 is connected with Guide rollers 10, bottom
The left and right ends of 9 bottom of plate are fixedly installed with wheel frame 4, and the inner surface of wheel frame 4 is flexibly connected with Guide rollers 10, can be with
It allows Hanging Basket to be moved forward and backward, and pulley brake structure is installed on Guide rollers 10, guarantee that Guide rollers 10 can stop at any time, bottom
The left and right ends at 9 top of plate are fixedly connected to triangle hack lever 16, are fixedly installed with first at the center of 16 left end of triangle hack lever
Pillar 15 is fixedly installed with the second pillar 17 at the center of 16 right end of triangle hack lever, and the left side of the first pillar 15 is fixedly installed with
Motor 7, the bottom of motor 7 are fixedly connected with motor fixed block 8, and motor fixed block 8 is fixedly connected on the left side of the first pillar 15,
Shaft 5 is rotatably connected between first pillar 15 and the second pillar 17, the outer surface of shaft 5 is arranged with rope 13, and rope 13
Material be irony, the output shaft of motor 7 is fixedly connected with the left side of shaft 5, the top of the first pillar 15 and the second pillar 17
It is fixedly connected to cross bar 6, the left and right ends of 6 front surface of cross bar are fixedly connected to stock 11, the bottom of 11 front surface of stock
Pulley blocks 12 are movably installed with, Hanging Basket can be made to move up and down, solving existing triangle hanging basket may only generally be moved forward and backward,
Want to move up and down and just needs to reinstall Hanging Basket, problem very troublesome.
In use, being fixedly installed with guide rail 3 in the left and right ends of bridge floor 2, the inner surface of guide rail 3 is connected with guide rail
Pulley 10, the left and right ends of 9 bottom of bottom plate are fixedly installed with wheel frame 4,10 activity of inner surface and Guide rollers of wheel frame 4
Connection, can allow Hanging Basket to be moved forward and backward, and triangle hack lever 16 is fixedly connected in the left and right ends at 9 top of bottom plate, in tripod
It is fixedly installed with the first pillar 15 at the center of 16 left end of bar, is fixedly installed with the second pillar at the center of 16 right end of triangle hack lever
17, the left side of the first pillar 15 is fixedly installed with motor 7, is fixedly connected with motor fixed block 8 in the bottom of motor 7, motor is solid
Determine the left side that block 8 is fixedly connected on the first pillar 15, guarantees the stability of motor 7 during the work time, the first pillar 15 and the
Shaft 5 is rotatably connected between two pillars 17, the output shaft of motor 7 is fixedly connected with the left side of shaft 5, the first pillar 15 and
The top of two pillars 17 is fixedly connected to cross bar 6, and the left and right ends of 6 front surface of cross bar are fixedly connected to stock 11, stock
The bottom of 11 front surfaces is movably installed with pulley blocks 12, Hanging Basket can be made to move up and down, and it is general to solve existing triangle hanging basket
It may only be moved forward and backward, it is desirable to it moves up and down and just needs to reinstall Hanging Basket, problem very troublesome.
In summary:The bridge triangular hanging basket passes through bridge floor 2, guide rail 3, wheel frame 4, rope shaft 5, cross bar 6, motor
7, motor fixed block 8, bottom plate 9, Guide rollers 10, stock 11, pulley blocks 12, rope 13, Hanging Basket 14, the first pillar 15, three feet
Hack lever 16 and the second pillar 17 cooperate, and solving existing triangle hanging basket may only generally be moved forward and backward, it is desirable to above move down
It is dynamic just to need to reinstall Hanging Basket, problem very troublesome.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (4)
1. bridge triangular hanging basket, including bridge column (1), bottom plate (9) and Hanging Basket (14), it is characterised in that:The upper end of the bridge column (1)
It is fixedly connected with bridge floor (2), the left and right ends of the bridge floor (2) are fixedly installed with guide rail (3), the interior table of the guide rail (3)
Face is connected with Guide rollers (10), and the left and right ends of bottom plate (9) bottom are fixedly installed with wheel frame (4), described
Left and right ends at the top of bottom plate (9) are fixedly connected to triangle hack lever (16), are consolidated at the center of triangle hack lever (16) left end
Dingan County is equipped with the first pillar (15), is fixedly installed with the second pillar (17) at the center of triangle hack lever (16) right end, described
It is fixedly installed on the left of first pillar (15) motor (7), the company of rotation between first pillar (15) and the second pillar (17)
It is connected to shaft (5), is fixedly connected on the left of the output shaft of the motor (7) and shaft (5), first pillar (15) and second
The top of pillar (17) is fixedly connected to cross bar (6), and the left and right ends of cross bar (6) front surface are fixedly connected to stock
(11), the bottom of stock (11) front surface is movably installed with pulley blocks (12).
2. bridge triangular hanging basket according to claim 1, it is characterised in that:The outer surface of the shaft (5) is arranged with rope
Sub (13), and the material of rope (13) is irony.
3. bridge triangular hanging basket according to claim 1, it is characterised in that:The bottom of the motor (7) is fixedly connected with
Motor fixed block (8), the motor fixed block (8) are fixedly connected on the left side of the first pillar (15).
4. bridge triangular hanging basket according to claim 1, it is characterised in that:The inner surface and guide rail of the wheel frame (4)
Pulley (10) is flexibly connected, and is equipped with pulley brake structure on Guide rollers (10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820374046.3U CN208105078U (en) | 2018-03-20 | 2018-03-20 | Bridge triangular hanging basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820374046.3U CN208105078U (en) | 2018-03-20 | 2018-03-20 | Bridge triangular hanging basket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208105078U true CN208105078U (en) | 2018-11-16 |
Family
ID=64127628
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820374046.3U Expired - Fee Related CN208105078U (en) | 2018-03-20 | 2018-03-20 | Bridge triangular hanging basket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208105078U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110820584A (en) * | 2019-11-22 | 2020-02-21 | 安徽信睦信息科技有限公司 | Triangular hanging basket applied to building bridge construction and safe auxiliary positioning structure thereof |
CN111042005A (en) * | 2020-01-16 | 2020-04-21 | 中建七局安装工程有限公司 | Construction method for cantilever casting of corrugated steel web diagonal box girder bridge by hanging basket method |
-
2018
- 2018-03-20 CN CN201820374046.3U patent/CN208105078U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110820584A (en) * | 2019-11-22 | 2020-02-21 | 安徽信睦信息科技有限公司 | Triangular hanging basket applied to building bridge construction and safe auxiliary positioning structure thereof |
CN110820584B (en) * | 2019-11-22 | 2021-04-23 | 安徽启源建筑工程有限公司 | Triangular hanging basket applied to building bridge construction and safe auxiliary positioning structure thereof |
CN111042005A (en) * | 2020-01-16 | 2020-04-21 | 中建七局安装工程有限公司 | Construction method for cantilever casting of corrugated steel web diagonal box girder bridge by hanging basket method |
CN111042005B (en) * | 2020-01-16 | 2022-02-01 | 中建七局安装工程有限公司 | Construction method for cantilever casting of corrugated steel web diagonal box girder bridge by hanging basket method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208105078U (en) | Bridge triangular hanging basket | |
CN109399432B (en) | A kind of hoistway job platform that climbs certainly | |
CN205206304U (en) | Novel creeping formwork support body | |
CN110778120B (en) | Pouring trolley for shear wall | |
CN205802845U (en) | A kind of civil engineering is with hanging a liter machine | |
CN213445861U (en) | Reinforced portal frame for construction of constructional engineering | |
CN204266651U (en) | Novel two-layer lift-sliding formula parking apparatus | |
CN109967547A (en) | A kind of crane end carriage automation pressurizing unit | |
CN105858488A (en) | Indoor and outdoor moving hoisting frame for buildings | |
CN209367631U (en) | A kind of elevator fixes device with Novel counterweight block | |
CN204402000U (en) | Can lateral displacement building external application hanging basket | |
CN209416016U (en) | A kind of dry kiln car automatic loader and unloader structure | |
CN203976331U (en) | Can cross travel building external application hanging basket | |
CN202508782U (en) | Novel automatic gantry crane mechanism | |
CN206997622U (en) | A kind of new reinforcing steel bar apparatus for bending | |
CN111945496A (en) | Rail sleeper replacement equipment with automatic assembly function | |
CN217051474U (en) | Height-adjustable's material hoist for building engineering | |
CN205151529U (en) | A lift dolly for electric plate wire | |
CN206277280U (en) | A kind of Novel double-station integral type electroplates sand-planting machine | |
CN105171892A (en) | House printing device based on balance weight system | |
CN213173367U (en) | Box girder inner top plate die carrier for bridge | |
CN215798318U (en) | Hang whole elevating gear of basket template | |
CN203701558U (en) | Cantilever mechanism of electric hanging basket | |
CN208717883U (en) | The manual portal frame system of approach channel general-purpose type | |
CN214359804U (en) | High-stability beam lifting machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181116 Termination date: 20190320 |
|
CF01 | Termination of patent right due to non-payment of annual fee |