CN208056596U - A kind of Novel engineering exterior wall scaffold - Google Patents

A kind of Novel engineering exterior wall scaffold Download PDF

Info

Publication number
CN208056596U
CN208056596U CN201820291024.0U CN201820291024U CN208056596U CN 208056596 U CN208056596 U CN 208056596U CN 201820291024 U CN201820291024 U CN 201820291024U CN 208056596 U CN208056596 U CN 208056596U
Authority
CN
China
Prior art keywords
linking arm
horizontal outrigger
support posts
interior support
locking device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820291024.0U
Other languages
Chinese (zh)
Inventor
张仙荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820291024.0U priority Critical patent/CN208056596U/en
Application granted granted Critical
Publication of CN208056596U publication Critical patent/CN208056596U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of Novel engineering exterior wall scaffolds,Include mainly interior support posts,Horizontal outrigger,Pylon,Upper locking device,Lower locking device,First linking arm and the second linking arm,Interior support posts are arranged in the inside of external wall,Lower locking device is arranged in the lower part at interior support posts through-flooring hole,Upper locking device is arranged in the top at interior support posts through-flooring hole,Horizontal outrigger one end is fixed at the top of interior support posts,The horizontal outrigger other end chooses outside of the building,Uniform gap is set at the top of horizontal outrigger,And bolt hole is arranged in bottom in groove,Horizontal outrigger both sides outer wall is both provided with sliding slot,The first linking arm of fixed setting and the second linking arm at the top of pylon,And first linking arm and the second linking arm relative dislocation setting,It is even at the top of first linking arm and the second linking arm to be connect with horizontal outrigger,The utility model is simple in structure,Without in exterior wall box out mouth,And it can quickly be adjusted according to the distance between required operation.

Description

A kind of Novel engineering exterior wall scaffold
Technical field
The utility model is related to engineering construction technical field, specially a kind of Novel engineering exterior wall scaffold.
Background technology
Scaffold is construction site for operation and solves vertically and horizontally to transport the various holders set up.Scaffold It is the generic term of architecture field, exterior wall, interior decoration or the higher ground that can not directly construct of floor height is generally used on construction site Side, in order to which construction personnel up and down go along with sb. to guard him and high-altitude installation component etc. by operation or perimeter security net.External wall construction foot Hand cradle, national standard《Construction fastener type steel pipe scaffold technical specification of security》JGJ130-2011 such as uses console mode foot Hand cradle maximum height is 50 meters, the height of four floors is generally set up using overhanging scaffold, this scaffold sets up expense Take material when expenses of labour, construction cost is high and is susceptible to safety accident.
Application No. is 200610118946.3 Chinese patent literatures, disclose a kind of tool-type hanging integral falsework system The construction method of system, the tool-type hanging integral falsework include scaffold unit, it is characterised in that scaffold unit includes foot Hand cradle over sling, hanger under the scaffold being connect with scaffold over sling are equipped with top walkway board, in foot in scaffold over sling Hanger is equipped with lower part walkway board under hand cradle, and the bottom of hanger is equipped with bottom plate under scaffold.Scaffold unit after assembling passes through spiral shell Bolt is connect with steel platform, and scaffold realizes Synchronous lifting in steel platform lifting process.All scaffold units are to the end of engineering It is reused after dismountable finishing, realizes the tool of scaffold.This scaffold is suitable only for concrete shear force wall Core Walls Structure and applies Work, and both sides, without floor, there are the building of floor in a large amount of insides and are not suitable in constructing for reality, and external scaffolding Highly larger, material utilization amount is big, is not particularly suitable for the construction of assembled architecture.
Application No. is 201620406622.9 Chinese patent literatures, disclose a kind of special external hanging type operation horizontal of building Platform, including overlap joint hook, outer framework, protection wire netting, overlap joint link, pedal, inner frame, pillar, support end, overlap railing, Building corner, retractable holder, sleeve, helical axis, telescopic rod, groove and support slot;The overlap joint hook setting is outside Frame right centre position;The outer framework is in matrix pattern, is welded by hollow steel pipe;The protection wire netting is placed in outer On the inside of frame;The overlap joint link is welded on centre position on the left of outer framework, with same horizontal line at overlap joint hook;The inside casing Frame is rectangle, perpendicular to outer framework, is welded by hollow steel pipe;The pedal is laid on inner frame;The support end weldering It is connected on posts bottom, is in cylindrical shape;The retractable holder, including sleeve, helical axis, telescopic rod and groove.It is therein Retractable holder, including sleeve, helical axis and telescopic rod are required to through walls or window, then necessary in the case of no window Want through walls, the later stage can not handle wall-through hole, be only suitable for the maintenance construction for the building for there are enough windows that can pass through, and be not suitable for newly-built The construction usage of engineering.
Existing new construction exterior wall scaffold, either overhanging type or external hanging type, are required for through walls or window, are not having Can only be through walls in the case of window, cause hole on wall, post-processing get up it is pretty troublesome, especially for the outer of assembled architecture Wall is even more difficult to handle, and therefore, it is necessary to a kind of new technical solutions to solve the problems, such as this, to meet the needs of construction.
Utility model content
The purpose of this utility model is to provide a kind of Novel engineering exterior wall scaffolds, to solve to carry in above-mentioned background technology The problem of going out.
To achieve the above object, the utility model provides the following technical solutions:A kind of Novel engineering exterior wall scaffold, including Interior support posts, horizontal outrigger, pylon, upper locking device, lower locking device, the first linking arm and the second linking arm, it is described interior Portion's support column is arranged in the inside of external wall, and the lower locking device is arranged in the lower part at interior support posts through-flooring hole, The upper locking device is arranged in the top at interior support posts through-flooring hole, and described horizontal outrigger one end is fixed at internal branch At the top of dagger, and the horizontal outrigger other end chooses outside of the building, uniform gap is arranged at the top of the horizontal outrigger, and bottom is set in groove Set bolt hole, the horizontal outrigger both sides outer wall is both provided with sliding slot, the first linking arm of fixed setting and the at the top of the pylon Two linking arms, and the first linking arm and the setting of the second linking arm relative dislocation, first linking arm and the second linking arm top It is even to be connect with horizontal outrigger, it is additionally provided with bracing piece at the top of the horizontal outrigger, and bracing piece one end is fixedly connected with horizontal outrigger one end, The bracing piece other end is fixedly connected with the horizontal outrigger other end, and gap is provided at the top of the bracing piece bottom and horizontal outrigger, And clearance height is slightly larger than the first linking arm and the second linking arm overhead height;
First linking arm and the second connection arm configuration are completely the same, including connecting rod, pulley and motion bar, and connect Bar is 7 fonts, is provided with pulley on the inside of the connecting rod, and pulley is engaged with sliding slot, and protrusion is provided at the top of the connecting rod Portion, and lug boss and engagement, the lug boss are internally provided with elastic groove, and the elastic groove is internally provided with elastic component, And be fixedly connected with elastic groove inner top at the top of elastic component, motion bar is provided on the lug boss, the motion bar top is high At the top of lug boss, and it is provided with draw ring at the top of motion bar, the motion bar bottom end interts elastic groove, and motion bar and bullet Property part bottom is fixedly connected, and the motion bar bottom is engaged with bolt hole.
Preferably, bottom is provided with non-slip mat in the pylon, and raised points are uniformly arranged on protective pad.
Preferably, the pylon is additionally provided with protection network, and it is 1.2m-1.5m to protect net height.
Compared with prior art, the utility model has the beneficial effects that:
(1)The utility model structural principle is simple, easy to install and use, is not necessarily in exterior wall box out mouth, while not touching and building It builds the interior outside of exterior wall, and can quickly be adjusted according to the distance between the thickness of wall and required operation, it is ensured that is practical Property.
(2)In the utility model, uses and pylon and horizontal outrigger are connected by the connecting rod of 7 fonts, and in horizontal outrigger Bracing piece is equipped between connecting rod, be to be able to ensure pylon it is ambulant simultaneously, it is ensured that the intensity of horizontal outrigger, Improve safety.
(3)In the utility model, using by motion bar and groove engage and the cooperation of pulley and sliding slot, be in order to Enough ensure mobile and solid timing stability, while easy to use.
Description of the drawings
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model the first linking arm structural schematic diagram;
Fig. 3 is the horizontal outrigger structural schematic diagram of the utility model.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
It please refers to Fig.1 to 3 figures, the utility model provides a kind of technical solution:A kind of Novel engineering exterior wall scaffold, including Interior support posts 1, horizontal outrigger 2, pylon 3, upper locking device 4, lower locking device 5, the first linking arm 6 and the second linking arm 7, The interior support posts 1 are arranged in the inside of external wall, and the lower locking device 5 is arranged in 1 through-flooring hole of interior support posts The lower part of mouth, the upper locking device 4 are arranged in the top at 1 through-flooring hole of interior support posts, and described 2 one end of horizontal outrigger is fixed Setting is at 1 top of interior support posts, and 2 other end of horizontal outrigger chooses outside of the building, and uniform gap is arranged in 2 top of the horizontal outrigger 8, and bolt hole is arranged in bottom in groove 8,2 both sides outer wall of the horizontal outrigger is both provided with sliding slot 9, and 3 top of the pylon is solid First linking arm 6 and the second linking arm 7, and the first linking arm 6 and the setting of 7 relative dislocation of the second linking arm are set surely;Pylon 3 Interior bottom is provided with non-slip mat, and raised points are uniformly arranged on protective pad;It can effectively ensure that construction personnel makees using protective pad Skid resistance when industry;Pylon 3 is additionally provided with protection network 18, and 18 height of protection network is 1.2m-1.5m;It can using protection network With the safety for effectively ensuring personnel;First linking arm, 6 and second linking arm, 7 top is even to be connect with horizontal outrigger 2, the cross 2 top of outrigger is additionally provided with bracing piece 10, and 10 one end of bracing piece is fixedly connected with 2 one end of horizontal outrigger, and the bracing piece 10 is another One end is fixedly connected with 2 other end of horizontal outrigger, and 10 bottom of the bracing piece is provided with gap with 2 top of horizontal outrigger, and gap is high Degree is slightly larger than 7 overhead height of the first linking arm 6 and the second linking arm;It is equipped with bracing piece between horizontal outrigger and connecting rod, is In order to ensure pylon it is ambulant simultaneously, it is ensured that the intensity of horizontal outrigger improves safety, and the utility model structure is former Reason is simple, easy to install and use, is not necessarily in exterior wall box out mouth, while not touching the interior outside of external wall, and can be according to wall The distance between the thickness of body and required operation are quickly adjusted, it is ensured that practicability.
In the utility model, the first linking arm 6 and 7 structure of the second linking arm are completely the same, including connecting rod 11, pulley 12 With motion bar 13, and connecting rod 11 is 7 fonts, and the inside of the connecting rod 11 is provided with pulley 12, and pulley 12 is nibbled with sliding slot 9 It closes, 11 top of the connecting rod is provided with lug boss 14, and lug boss 14 is engaged with groove 8,14 inside setting of the lug boss Flexible slot 15, the elastic groove 15 is internally provided with elastic component 16, and 16 top of elastic component is fixed with 15 inner top of elastic groove It connects, motion bar 13 is provided on the lug boss 14,13 top of the motion bar is higher than 14 top of lug boss, and motion bar 13 Top is provided with draw ring 17, and 13 bottom end of the motion bar interts elastic groove 15, and motion bar 13 and 16 bottom of elastic component are solid Fixed connection, 13 bottom of the motion bar is engaged with bolt hole;Using by motion bar and groove engage and pulley and sliding slot Cooperation is to be able to ensure mobile and solid timing stability, while easy to use.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is appreciated that can these embodiments be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (3)

1. a kind of Novel engineering exterior wall scaffold, including interior support posts(1), horizontal outrigger(2), pylon(3), upper locking device (4), lower locking device(5), the first linking arm(6)With the second linking arm(7), it is characterised in that:The interior support posts(1)If It sets in the inside of external wall, the lower locking device(5)It is arranged in interior support posts(1)The lower part at through-flooring hole, it is described Upper locking device(4)It is arranged in interior support posts(1)The top at through-flooring hole, the horizontal outrigger(2)One end is fixed at Interior support posts(1)Top, and horizontal outrigger(2)The other end chooses outside of the building, the horizontal outrigger(2)Uniform gap is arranged in top (8), and groove(8)Bolt hole, the horizontal outrigger is arranged in interior bottom(2)Both sides outer wall is both provided with sliding slot(9), the pylon (3)The first linking arm is fixedly installed in top(6)With the second linking arm(7), and the first linking arm(6)With the second linking arm(7)Phase To shifting to install, first linking arm(6)With the second linking arm(7)Top is even with horizontal outrigger(2)Connection, the horizontal outrigger (2)Top is additionally provided with bracing piece(10), and bracing piece(10)One end and horizontal outrigger(2)One end is fixedly connected, the bracing piece (10)The other end and horizontal outrigger(2)The other end is fixedly connected, the bracing piece(10)Bottom and horizontal outrigger(2)Between top is provided with Gap, and clearance height is slightly larger than the first linking arm(6)With the second linking arm(7)Overhead height;
First linking arm(6)With the second linking arm(7)Structure is completely the same, including connecting rod(11), pulley(12)And work Lever(13), and connecting rod(11)For 7 fonts, the connecting rod(11)Inside is provided with pulley(12), and pulley(12)With cunning Slot(9)Engagement, the connecting rod(11)Top is provided with lug boss(14), and lug boss(14)With groove(8)Engagement, it is described convex The portion of rising(14)It is internally provided with elastic groove(15), the elastic groove(15)It is internally provided with elastic component(16), and elastic component(16) Top and elastic groove(15)Inner top is fixedly connected, the lug boss(14)On be provided with motion bar(13), the motion bar (13)Top is higher than lug boss(14)Top, and motion bar(13)Top is provided with draw ring(17), the motion bar(13)Bottom Intert elastic groove in one end(15), and motion bar(13)With elastic component(16)Bottom is fixedly connected, the motion bar(13)Bottom with Bolt hole engages.
2. a kind of Novel engineering exterior wall scaffold according to claim 1, it is characterised in that:The pylon(3)Interior bottom Portion is provided with non-slip mat, and raised points are uniformly arranged on protective pad.
3. a kind of Novel engineering exterior wall scaffold according to claim 1, it is characterised in that:The pylon(3)Also set It is equipped with protection network(18), and protection network(18)Height is 1.2m-1.5m.
CN201820291024.0U 2018-03-02 2018-03-02 A kind of Novel engineering exterior wall scaffold Expired - Fee Related CN208056596U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820291024.0U CN208056596U (en) 2018-03-02 2018-03-02 A kind of Novel engineering exterior wall scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820291024.0U CN208056596U (en) 2018-03-02 2018-03-02 A kind of Novel engineering exterior wall scaffold

Publications (1)

Publication Number Publication Date
CN208056596U true CN208056596U (en) 2018-11-06

Family

ID=63991520

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820291024.0U Expired - Fee Related CN208056596U (en) 2018-03-02 2018-03-02 A kind of Novel engineering exterior wall scaffold

Country Status (1)

Country Link
CN (1) CN208056596U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403850A (en) * 2018-12-16 2019-03-01 盐城市塔克科技发展有限公司 Lifting and translation construction hanging ladder outside floor window
CN109594913A (en) * 2018-12-29 2019-04-09 盐城市塔克科技发展有限公司 Lifting and translation construction hanging ladder outside floor window
CN111962854A (en) * 2020-08-12 2020-11-20 鹏程建设集团有限公司 Scaffold with safety protection mechanism and building method
CN113250458A (en) * 2021-06-29 2021-08-13 张会娟 Construction template is with appearance of making level based on intelligent computer

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109403850A (en) * 2018-12-16 2019-03-01 盐城市塔克科技发展有限公司 Lifting and translation construction hanging ladder outside floor window
CN109594913A (en) * 2018-12-29 2019-04-09 盐城市塔克科技发展有限公司 Lifting and translation construction hanging ladder outside floor window
CN111962854A (en) * 2020-08-12 2020-11-20 鹏程建设集团有限公司 Scaffold with safety protection mechanism and building method
CN111962854B (en) * 2020-08-12 2021-12-10 鹏程建设集团有限公司 Scaffold with safety protection mechanism and building method
CN113250458A (en) * 2021-06-29 2021-08-13 张会娟 Construction template is with appearance of making level based on intelligent computer
CN113250458B (en) * 2021-06-29 2022-07-01 张会娟 Construction template is with appearance of making level based on intelligent computer

Similar Documents

Publication Publication Date Title
CN208056596U (en) A kind of Novel engineering exterior wall scaffold
CN106400951B (en) A kind of level and vertical structure method for synchronously constructing of super high-rise building
CN103206074B (en) Elevator shaft template construction method, platform and support
CN101824910A (en) Quick template supporting construction method of elevator shaft
CN106400691A (en) Integrated construction process for anti-collision wall formwork
CN205822747U (en) Architectural engineering scaffold
CN205188839U (en) Movably -assembled anti -collision bridge wall construction hanging basket
CN106522541B (en) A kind of template suspension centre spandrel girder of steel platform and the hanging method of template system
CN109653484B (en) Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering
CN208310154U (en) A kind of construction scaffold
CN208363666U (en) It is a kind of for build face side construction safety protection frame
CN216196742U (en) A wallboard installation device for position is striden to height
CN204038917U (en) Dismountable external hanging service platform
CN209874468U (en) Construction hydraulic pressure template climbing device
CN207003989U (en) External hanging type scaffold is climbed in one kind
CN206328110U (en) One kind customization hanging basket apparatus
CN201401000Y (en) Special hanging basket for installing noise barrier roof boards
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform
CN212052563U (en) Scaffold for water conservancy construction
CN208456085U (en) Build builder's jack structure
CN2216104Y (en) Hanging lift scaffold
CN208685448U (en) A kind of safety scaffold of bridge construction
CN220036073U (en) Assembled stairwell construction is with operation steel platform
CN218843687U (en) Portable handling frame for dismantling overhanging I-shaped steel
CN213654180U (en) Scaffold structure convenient to slope building wall construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181106

Termination date: 20190302