CN207980672U - Welding fume gas cleaning plant - Google Patents

Welding fume gas cleaning plant Download PDF

Info

Publication number
CN207980672U
CN207980672U CN201721771436.6U CN201721771436U CN207980672U CN 207980672 U CN207980672 U CN 207980672U CN 201721771436 U CN201721771436 U CN 201721771436U CN 207980672 U CN207980672 U CN 207980672U
Authority
CN
China
Prior art keywords
dust accumulation
radiator
cleaning plant
gas cleaning
welding fume
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721771436.6U
Other languages
Chinese (zh)
Inventor
何洪宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Dingyunsheng Technology Co Ltd
Original Assignee
Beijing Dingyunsheng Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Dingyunsheng Technology Co Ltd filed Critical Beijing Dingyunsheng Technology Co Ltd
Priority to CN201721771436.6U priority Critical patent/CN207980672U/en
Application granted granted Critical
Publication of CN207980672U publication Critical patent/CN207980672U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filtering Of Dispersed Particles In Gases (AREA)

Abstract

The utility model provides welding fume gas cleaning plant,Including shell and internal structure,Left and right ends before shell are respectively set there are two starting switch jack,4 external nozzles of hose are provided between the starting switch jack of left and right ends,Internal structure is symmetrical identical structure,Left lower is provided with dust accumulation bucket,Dust accumulation bucket top is provided with radiator,Radiator upper middle position is provided with filter cylinder and fixes butterfly bolt,Filtering material there are one being respectively set at left and right sides of radiator top,Filter cylinder fixes butterfly bolt upper end and connects air-valve,Air-valve is connected with one end of connecting tube,The other end of connecting tube connects exhaust blower,Exhaust blower lower part is provided with exhaust passage,Exhaust passage lower part is provided with gas purifier,The utility model is designed reasonably,It is easy to use,It is energy saving,It can be convenient for carrying,Equipment collection adsorbs,Heat dissipation,Filtering,Purification is integrated,Purification efficiency is high,There is good application prospect.

Description

Welding fume gas cleaning plant
Technical field
The utility model is related to air purification fields, and in particular to welding fume gas cleaning plant.
Background technology
Small enterprise's processing welding fume in China is general at present just uses natural ventilation system and fixed, and investment is less, Principle be by nature and by force air draft in the way of, the fume gases in workshop are transferred in outdoor air, are relatively changed It has been apt to the environment in workshop, while pollution is caused to air.In Some Enterprises, especially in some large, medium-sized enterprises, use Some develop faster cleaner, such as bag filter, filter cylinder wheat rush deduster and electric precipitation.Better dust removal effect, but There is also some problems simultaneously:Huge investment, power consumption is high, and the energy loss in workshop is big.Welding pollution is ground by foreign countries Study carefully and start more early than China, treatment technology is relatively advanced, ripe.Outdoor welding or the welding of open space, generally use nature Draft type, for office operation force ventilation mode, by the axial flow blower on mounted to a wall or ceiling, in workshop Weld fumes discharge is outdoor, or is recycled in workshop after clarifier purifies, and reaching makes the reduction of workshop dust concentration Purpose.It is ventilating system selection principle based on local ventilation, supplemented by general ventilation.Weld pollution treatment device from unicity, It is fixed, enlarged to develop to complete property, associativity, mobility, miniaturization and saving resource direction.
Utility model content
The purpose of this utility model is to solve above-mentioned deficiency, providing welding fume gas cleaning plant.
The purpose of this utility model is achieved through the following technical solutions:
Welding fume gas cleaning plant, including shell and internal structure, the left and right ends before shell are respectively arranged with Two starting switch jacks are provided with 4 external nozzles of hose, internal structure between the starting switch jack of left and right ends For symmetrical identical structure, left lower is provided with dust accumulation bucket, and dust accumulation bucket top is provided with radiator, among radiator top Position is provided with filter cylinder and fixes butterfly bolt, is respectively set at left and right sides of radiator top there are one filtering material, filter cylinder fixes butterfly Butterfly bolt upper end connects air-valve, and air-valve is connected with one end of connecting tube, and the other end of connecting tube connects exhaust blower, exhaust blower lower part It is provided with exhaust passage, exhaust passage lower part is provided with gas purifier.
There are one power supply external interfaces for two starting switch jack lower parts setting of right end.
Both ends on the outside of dust accumulation bucket bottom surface are separately installed with a dust accumulation bucket slideway.
The top of dust accumulation bucket left and right sides edge is provided with cloud and slides plate.
The utility model has following beneficial effect:
The utility model is designed reasonably, it is easy to use, it is energy saving, it can be convenient for carrying, the absorption of equipment collection, heat dissipation, mistake Filter, purification are integrated, and purification efficiency is high, there is good application prospect.
Description of the drawings
Fig. 1 is the external structure schematic diagram of the utility model;
Fig. 2 is the internal structure schematic diagram of the utility model.
Specific implementation mode
The utility model will be further described below with reference to the accompanying drawings:
As depicted in figs. 1 and 2, welding fume gas cleaning plant, including shell 1 and internal structure, a left side for 1 front of shell Right both ends are respectively set there are two starting switch jack 2, and 4 hoses are provided between the starting switch jack of left and right ends External nozzle 3, internal structure are symmetrical identical structure, and left lower is provided with dust accumulation bucket 5, and 5 top of dust accumulation bucket is provided with Radiator 13,13 upper middle position of radiator are provided with filter cylinder and fix butterfly bolt 15, and 13 top of the radiator left and right sides is respectively Setting is there are one filtering material 10, and filter cylinder fixes 15 upper end of butterfly bolt and connects air-valve 9, and air-valve 9 is connected with one end of connecting tube 8 It connects, the other end of connecting tube 8 connects exhaust blower 7, and 7 lower part of exhaust blower is provided with exhaust passage 6, and 6 lower part of exhaust passage is provided with Gas purifier 11.
There are one power supply external interfaces 4 for two 2 lower parts of starting switch jack setting of right end.
Both ends on the outside of 5 bottom surface of dust accumulation bucket are separately installed with a dust accumulation bucket slideway 14.
The top of 5 left and right sides edge of dust accumulation bucket is provided with cloud and slides plate 12.
The course of work:Weld fumes → welding gun sweep-up pipe → solenoid valve drawing valve → radiator heat-dissipation → cartridge filter filtering → Air-valve → vacuum motor exhausting → gas purifier → discharge gas.After powering on, is opened compress by control mechanism first The inflation of air source, air reservoir valve make compressed gas pass through the outside blowback in each position returned and blow antipriming pipe to filtering cavity wall, will Accumulate in filtering cavity wall(Filtering material)On dust accumulation blow off, through air duct, cloud slide plate, into dust hopper, it is ensured that filtering Device is good and works normally.After entering normal and continuous operation state, blowback is primary per hour.
After machine start, under the action of air draft mechanism motor, makes to be arranged the air-valve at exhaust tube and open, at this time It, will by the dust suction facility being connected on the external nozzle of hose of radiator setting under the action of air draft mechanism wind-force Welding fume, gas through air inlet by connecting valve, into radiator, and upward from the bottom of radiator and surrounding, warp The welding fume gas air inlet duct between cavity outer wall and dust-extraction unit cabinet wall is filtered, is entered after being filtered by filter layer Filter chamber enters effect of the flue gas in exhaust fan of filter chamber after filtering
Under, by the way that the pumping for connecting air draft mechanism being connected with filter chamber in dust-extraction unit top of the box is arranged Gas tube orifice enters welding fume gas air inlet duct, and cigarette air duct is passed through downwards gas purifier, is machined on bottom plate from below The gas vent being connected with the external world is discharged.

Claims (4)

1. welding fume gas cleaning plant, including shell and internal structure, it is characterised in that:Left and right ends point before shell 4 external nozzles of hose She Zhi not be provided between the starting switch jack of left and right ends there are two starting switch jack, Internal structure is symmetrical identical structure, and left lower is provided with dust accumulation bucket, and dust accumulation bucket top is provided with radiator, radiator Upper middle position is provided with filter cylinder and fixes butterfly bolt, is respectively set at left and right sides of radiator top there are one filtering material, is filtered Cylinder fixed butterfly bolt upper end connects air-valve, and air-valve is connected with one end of connecting tube, and the other end of connecting tube connects exhaust blower, row Wind turbine lower part is provided with exhaust passage, and exhaust passage lower part is provided with gas purifier.
2. welding fume gas cleaning plant according to claim 1, it is characterised in that:Described two startups of right end are opened Closing the setting of jack lower part, there are one power supply external interfaces.
3. welding fume gas cleaning plant according to claim 1, it is characterised in that:Outside the dust accumulation bucket bottom surface The both ends of side are separately installed with a dust accumulation bucket slideway.
4. welding fume gas cleaning plant according to claim 1, it is characterised in that:At left and right sides of the dust accumulation bucket The top at edge is provided with cloud and slides plate.
CN201721771436.6U 2017-12-18 2017-12-18 Welding fume gas cleaning plant Expired - Fee Related CN207980672U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721771436.6U CN207980672U (en) 2017-12-18 2017-12-18 Welding fume gas cleaning plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721771436.6U CN207980672U (en) 2017-12-18 2017-12-18 Welding fume gas cleaning plant

Publications (1)

Publication Number Publication Date
CN207980672U true CN207980672U (en) 2018-10-19

Family

ID=63817787

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721771436.6U Expired - Fee Related CN207980672U (en) 2017-12-18 2017-12-18 Welding fume gas cleaning plant

Country Status (1)

Country Link
CN (1) CN207980672U (en)

Similar Documents

Publication Publication Date Title
CN201049353Y (en) Weld fume ventilating and purifying installation
CN205495170U (en) Many air inlets industrial dust removal ware
CN209084996U (en) A kind of blowing and drawing type weldering dust collection system being adjustable room temperature and humidity
WO2022022418A1 (en) Integrated factory building air purification device having telescopic air suction and supply structures
CN207980672U (en) Welding fume gas cleaning plant
CN205008091U (en) Powder coating inner loop crocus dust removal cooling system
CN110613988A (en) Dust bag dust remover capable of compressing high-temperature flue gas and purifying back-blowing ash
CN202284907U (en) Three-way chimney at forced air drying section of chain grate machine
CN200948111Y (en) L type multifunctional automatic dust cleaning machine
CN204502632U (en) Spiral negative pressure dust removing device
CN212731552U (en) Portable dust purification device
CN211384201U (en) Dust bag dust remover capable of compressing high-temperature flue gas and purifying back-blowing ash
CN203657503U (en) Exhaust gas processing system of kiln
CN2510147Y (en) Self-cleaning cartridge air filter with forward filtering net
CN109812875B (en) Replacement recirculation ventilation method
CN208372681U (en) A kind of boiler room waste gas recovering device
CN209271031U (en) A kind of energy conservation coal mine negative pressure dust removing device
CN209188471U (en) A kind of out of stock integrated treatment unit of dust-removal and desulfurizing
CN203540238U (en) Dust collector of energy-saving and environment-friendly axial flow fan unit
CN105709550A (en) Combined dust remover
CN201569101U (en) Moveable suction system
CN206507883U (en) A kind of modified dust catcher filter mantle
CN213610315U (en) Bag type high-voltage pulse dust collector with back blowing function
CN209139005U (en) A kind of aeration device for Painting Shop
CN211384223U (en) Automatic control device for leakage detection of fluorescent powder of dust removing equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181019

Termination date: 20181218