CN207959201U - Synchronous grouting pile for prestressed pipe - Google Patents

Synchronous grouting pile for prestressed pipe Download PDF

Info

Publication number
CN207959201U
CN207959201U CN201820231176.1U CN201820231176U CN207959201U CN 207959201 U CN207959201 U CN 207959201U CN 201820231176 U CN201820231176 U CN 201820231176U CN 207959201 U CN207959201 U CN 207959201U
Authority
CN
China
Prior art keywords
pile
pipe
grouting
charge
slip casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820231176.1U
Other languages
Chinese (zh)
Inventor
魏纲
张鑫海
王彬
蔡姝萸
叶星宇
洪文强
董北北
陆世杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201820231176.1U priority Critical patent/CN207959201U/en
Application granted granted Critical
Publication of CN207959201U publication Critical patent/CN207959201U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model is related to a kind of synchronous grouting pile for prestressed pipe, including special shoe device, prefabricated tubular pile, slip casting pipe device and grouting layer;The special shoe device includes main Grouting Pipe, is in charge of connector, is in charge of and slurry outlet;The main Grouting Pipe upper end is connected with slip casting pipe device, and main Grouting Pipe lower end is connected by being in charge of connector with being in charge of;It is described be in charge of be connected with slurry outlet, the slurry outlet equidistantly distributed is on the outside of the pile pile seam at shoe edge;Slip casting pipe device is equipped in the prefabricated tubular pile cavity, the slip casting pipe device includes four paws hook, upper end interface, grouting pipe and lower end interface.The utility model has the beneficial effects that:The synchronous grouting pile for prestressed pipe of the utility model is to increase that special shoe is arranged on using for reference original pile for prestressed pipe, and pass through a kind of novel pile basis made of static pressure method pile sinking;So that injection slurry is lubricated pile pile side wall by synchronous grouting, reduce piling difficulty, reduces place requirement for bearing capacity and pile compacting equipment requirement.

Description

Synchronous grouting pile for prestressed pipe
Technical field
The utility model belongs to field of foundation treatment more particularly to a kind of prestressed pipe pilework.
Background technology
Pile for prestressed pipe has many advantages, such as that speed of application is fast, low cost, high capacity, but it is there are stake diameter is smaller, horizontal Load low bearing capacity is unable to give full play pile body bearing capacity since pile strength and soil strength are at a distance of larger in weak soil The problems such as.Static pressure method pile sinking is low with construction noise, vibration is light, pollution is small, and speed of application is fast, and work efficiency is high, and short time limit, construction is answered The advantages that power is small, and pile quality is relatively reliable, but itself is relatively high to equipment requirement, provides larger pressure of sinking pile and just needs more More ballasts, to more demanding to place foundation bearing capacity, the shortcomings of pile sinking is difficult in hard stratum.
Utility model content
The purpose of the utility model is to overcome deficiencies in the prior art, provide a kind of synchronous grouting pile for prestressed pipe.This The purpose of utility model is achieved through the following technical solutions:
This synchronous grouting pile for prestressed pipe, including special shoe device, prefabricated tubular pile, slip casting pipe device and grouting layer; The special shoe device includes main Grouting Pipe, is in charge of connector, is in charge of and slurry outlet;The main Grouting Pipe upper end is filled with Grouting Pipe Set connected, main Grouting Pipe lower end is connected by being in charge of connector with being in charge of;It is described be in charge of be connected with slurry outlet, between described slurry outlet etc. Away from the pile pile seam outside for being distributed in shoe edge;Slip casting pipe device, the Grouting Pipe dress are equipped in the prefabricated tubular pile cavity It sets including four paws hook, upper end interface, grouting pipe and lower end interface;Four paws hook hanging buckle stake end on prefabricated tubular pile, Four paws hook center is fixed with end interface, and the upper end interface is connected with grouting pipe upper end, and the grouting pipe lower end is logical End interface is crossed down with the main Grouting Pipe of special shoe device to be connected.
As preferred:The four paws hook is bent using iron plate.
As preferred:The grouting pipe uses pvc pipe or steel pipe.
The utility model has the beneficial effects that:
1, the synchronous grouting pile for prestressed pipe of the utility model is to increase setting spy on using for reference original pile for prestressed pipe Different shoe, and pass through a kind of novel pile basis made of static pressure method pile sinking.
2, by synchronous grouting make injection slurry lubricate pile pile side wall, reduce piling difficulty, reduce place requirement for bearing capacity and Pile compacting equipment requirement.
3, transition zone of the injecting cement paste solidified as pile body and the soil body, contact of the enhancing pile body with the soil body, increases stake side and rubs Resistance further plays pile for prestressed pipe pile strength, improves bearing capacity of single pile.It, can thus in the case where bearing capacity meets By shortening, stake is long to reduce cost.
4, protection and reinforcing of the injecting cement paste solidified as pile body.It increases soil around pile frictional force and Pile side soil level is anti- Power strengthens pile body connector, improves the horizontal bearing capacity of pile pile.
5, it is constructed by pile jacking in method, construction noise is low, vibration is light, pollution is small, speed of application is fast, work efficiency is high, the duration It is short.
Description of the drawings
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is the special shoe device diagrammatic cross-section of the utility model;
Fig. 3 is the special shoe device vertical view of the utility model;
Fig. 4 is the single-unit prefabricated tubular pile diagrammatic cross-section of the utility model;
Fig. 5 is stake end vertical view on the prefabricated tubular pile of the utility model;
Reference sign:Special shoe device 1, main Grouting Pipe 11 are in charge of connector 12, are in charge of 13, slurry outlet 14 is prefabricated Pile pile 2, slip casting pipe device 3, four paws hook 31, upper end interface 32, grouting pipe 33, lower end interface 34, grouting layer 4.
Specific implementation mode
The utility model is described further with reference to embodiment.The explanation of following embodiments is only intended to help to manage Solve the utility model.It should be pointed out that for those skilled in the art, not departing from the utility model principle Under the premise of, several improvements and modifications can be made to this utility model, these improvement and modification also fall into the utility model In scope of the claims.
The synchronous grouting pile for prestressed pipe improves pile for prestressed pipe performance, it is made to have synchronous grouting function, Increase reply such as stake diameter is smaller, and horizontal loading low bearing capacity, pile body joint is easily destroyed, weak soil pile intensity and the soil body Intensity is unable to give full play the ability of the engineering problems such as pile body bearing capacity at a distance of larger.The synchronous grouting pile for prestressed pipe Including:Special shoe device 1, main Grouting Pipe 11 are in charge of connector 12, are in charge of 13, slurry outlet 14, prefabricated tubular pile 2, slip casting pipe device 3, four paws hook 31, upper end interface 32, grouting pipe 33, lower end interface 34, grouting layer 4.
As shown in Figure 2 and Figure 3, the special shoe device 1 includes main Grouting Pipe 11, is in charge of connector 12, is in charge of 13, pulp Hole 14;11 upper end of main Grouting Pipe is connected with slip casting pipe device 3, and 11 lower end of main Grouting Pipe is by being in charge of connector 12 and four pieces points Pipe 13 is connected;It is described to be in charge of 13 and be connected with slurry outlet 14, pile pile seam of 14 equidistantly distributed of the slurry outlet at shoe edge Outside.
As shown in Figure 4, Figure 5, setting slip casting pipe device 3 in 2 cavity of the prefabricated tubular pile;The slip casting pipe device 3 includes Four paws hook 31, upper end interface 32, grouting pipe 33, lower end interface 34;The four paws links up with the stake on prefabricated tubular pile 2 of 31 hanging buckles End, four paws link up with 31 centers and are fixed with end interface 32, and the upper end interface 32 is connected with 33 upper end of grouting pipe, the slip casting 33 lower end of pipeline is connected by lower end interface 34 with the main Grouting Pipe 11 of special shoe device 1.The four paws hook 31 uses iron Piece is bent, and hanging buckle can be welding in connector at 2 ends of prefabricated tubular pile, stake end when welding.33 basis of the grouting pipe The preferred pvc pipe of practical grouting pressure, steel pipe etc., it is 12.4m often to save grouting pipe 33, and 33 both ends of grouting pipe have can pressure-bearing Connector.
The course of work of the utility model is with operation principle:Shoe is first set at stake position, and in first segment pile pile After Grouting Pipe is connect with shoe slip casting manifold, piling applies smaller grouting pressure simultaneously, realizes synchronous grouting, and it is difficult to reduce piling Degree.After the completion of piling, the transition zone of the injecting cement paste of solidification as pile body and the soil body, i.e. grouting layer 4 enhance connecing for pile body and the soil body It touches, increases pile side friction, further play pile for prestressed pipe pile strength, improve bearing capacity of single pile.
The construction method of the synchronous grouting pile for prestressed pipe, includes the following steps:
1) special shoe device 1 is set at stake position;
2) slip casting pipe device 3 is installed inside prefabricated tubular pile 2, and the slip casting hose of peripheral hardware is used in combination to be connected with grouting pump;
3) after pile press machine reaches pre- fixed pile, rotatable truss is rotated, pile press machine clamp port center align piles position center is made, It is used in combination steel wire rope to fasten prefabricated tubular pile 2, slip casting pipe device 3 is lifted by crane simultaneously with prefabricated tubular pile 2;
4) after being put into after pile press machine clamp port after lifting by crane and holding pile body and the alignment of stake position center tightly using fixture, by first Slip casting pipe device 3 in section prefabricated tubular pile 2 is connect with the main Grouting Pipe 11 of special shoe device 1, after adjusting pile body verticality Start hydraulic cylinder and carries out piling;
5) piling applies smaller grouting pressure simultaneously, maintains almost nil grouting amount, need to only prevent the soil body from squeezing into out Starch hole 14.It waits for a side pressure underground layer certain depth, formally starts slip casting, this measure is that slurries are emerged ground in order to prevent;(one As maximum grouting pressure be not more than 2MPa;It is required that slurries are surveyed in stake a certain thickness, cleavage fracture and excessive does not occur for Pile side soil body Displacement.)
6) piling uses high pressure again by first using low pressure rapid pressure pile when soft soil layer when reaching hard stratum or sandy gravel stratum Piling at a slow speed, and slip casting is synchronized during piling, injection slurry is mixed using the cement mortar and bentonite slurry centainly matched It closes.Specific proportioning is determined according to practical soil layer situation and execution conditions;(it is required that there is certain mobility, meet injection slurry The requirement of synchronous distribution and stake side;Presetting period is not less than the single pile construction time, and final setting time meets construction speed requirement;Solidification Intensity reaches given requirements afterwards.)
7) so that the Grouting Pipe in next section stake is connected with a upper section Grouting Pipe when pile extension, then weld pile shaft joint, continue Piling repeats above step.

Claims (3)

1. a kind of synchronous grouting pile for prestressed pipe, it is characterised in that:Including special shoe device (1), prefabricated tubular pile (2), slip casting Pipe device (3) and grouting layer (4);The special shoe device (1) includes main Grouting Pipe (11), is in charge of connector (12), is in charge of (13) and slurry outlet (14);Main Grouting Pipe (11) upper end is connected with slip casting pipe device (3), and main Grouting Pipe (11) lower end passes through It is in charge of connector (12) with (13) are in charge of to be connected;Be in charge of (13) are connected with slurry outlet (14), and the slurry outlet (14) is equidistant It is distributed on the outside of the pile pile seam at shoe edge;Slip casting pipe device (3), the slip casting are equipped in prefabricated tubular pile (2) cavity Pipe device (3) includes four paws hook (31), upper end interface (32), grouting pipe (33) and lower end interface (34);The four paws is hung Hook (31) hanging buckle stake end on prefabricated tubular pile (2), four paws hook (31) center are fixed with end interface (32), the upper end interface (32) it is connected with grouting pipe (33) upper end, grouting pipe (33) lower end passes through lower end interface (34) and special shoe device (1) main Grouting Pipe (11) is connected.
2. synchronous grouting pile for prestressed pipe according to claim 1, it is characterised in that:The four paws hook (31) uses iron Piece is bent.
3. synchronous grouting pile for prestressed pipe according to claim 1, it is characterised in that:The grouting pipe (33) uses Pvc pipe or steel pipe.
CN201820231176.1U 2018-02-09 2018-02-09 Synchronous grouting pile for prestressed pipe Active CN207959201U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820231176.1U CN207959201U (en) 2018-02-09 2018-02-09 Synchronous grouting pile for prestressed pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820231176.1U CN207959201U (en) 2018-02-09 2018-02-09 Synchronous grouting pile for prestressed pipe

Publications (1)

Publication Number Publication Date
CN207959201U true CN207959201U (en) 2018-10-12

Family

ID=63738684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820231176.1U Active CN207959201U (en) 2018-02-09 2018-02-09 Synchronous grouting pile for prestressed pipe

Country Status (1)

Country Link
CN (1) CN207959201U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108179743A (en) * 2018-02-09 2018-06-19 浙江大学城市学院 A kind of synchronous grouting pile for prestressed pipe and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108179743A (en) * 2018-02-09 2018-06-19 浙江大学城市学院 A kind of synchronous grouting pile for prestressed pipe and construction method

Similar Documents

Publication Publication Date Title
CN104234055B (en) A kind of prefabricated pile post-grouting device and technique thereof
CN206784372U (en) Injection forming club-footed pile
CN101289855A (en) Uplift pile construction method through grouting at sides of pile
CN106996104A (en) Injection forming club-footed pile and its construction method
CN207597376U (en) Tidal Flat Reclamation blowing-filling sludge burning into sand layer foundation reinforcing structure
CN108179743A (en) A kind of synchronous grouting pile for prestressed pipe and construction method
CN207959201U (en) Synchronous grouting pile for prestressed pipe
CN104213554A (en) Construction method of slip-casting variable-cross section steel pipe pile and expansion and extrusion device of slip-casting variable-cross section steel pipe pile
CN207121896U (en) Precast hollow uplift pile
CN207553135U (en) A kind of pipe gallery
CN113789779A (en) Pile foundation structure applied to soft soil foundation and coral sand foundation and construction method
CN110453673B (en) Pier foundation reinforcement structure and method
CN208472716U (en) Crack geology mortar leakage prevention drill-pouring pilework
CN204080796U (en) Injection forming Variable Section Steel pile tube expands crowded device
CN111101509A (en) Prefabricated root type pile structure and construction method
CN109958460A (en) The multi-functional anchoring waterproof construction of one kind and its anchoring process
CN205475211U (en) A mix soil extrusion solidification precast pile for soft base is handled
CN202124857U (en) Splitting pile
CN205259188U (en) Miniature pressure -bearing stake of bag pocket type of controllable slip casting scope
CN210086215U (en) Grouting pile for reinforcing soft soil foundation
CN211368723U (en) Novel grouting pipe
CN211289237U (en) Mounting structure for construction machinery
CN113882360A (en) Pile connecting structure and method for pouring tubular pile transverse partition plates
CN201062393Y (en) Concrete hollow building block for circular or arc building
CN206428692U (en) A kind of multitube grouting device of two-tube compound club-footed pile machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant