CN207917857U - A kind of novel track structure - Google Patents

A kind of novel track structure Download PDF

Info

Publication number
CN207917857U
CN207917857U CN201721908749.1U CN201721908749U CN207917857U CN 207917857 U CN207917857 U CN 207917857U CN 201721908749 U CN201721908749 U CN 201721908749U CN 207917857 U CN207917857 U CN 207917857U
Authority
CN
China
Prior art keywords
groove
track
hoisting bracket
guide rail
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721908749.1U
Other languages
Chinese (zh)
Inventor
陶卫军
孙家升
徐俊翊
吴益飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing University of Science and Technology
Original Assignee
Nanjing University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing University of Science and Technology filed Critical Nanjing University of Science and Technology
Priority to CN201721908749.1U priority Critical patent/CN207917857U/en
Application granted granted Critical
Publication of CN207917857U publication Critical patent/CN207917857U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)

Abstract

The utility model provides a kind of novel track structure, including straight rail and bending track, and each track includes guide upper, guide rail middle part and guide rail lower part;Square groove is arranged in guide upper, and through-hole is arranged in the middle part of guide rail, and groove is arranged in guide rail lower part;The first groove bar is fixed in square groove, which is fixed on by track hoisting bracket on ceiling;The second groove bar of same root is set in the through-hole of adjacent rails, and the block extended to groove center direction is arranged in guide rail lower part bottom surface, and the cavity of installation chain is formed between block and groove floor.

Description

A kind of novel track structure
Technical field
The utility model is related to a kind of guide rail technology, especially a kind of novel track structure.
Background technology
In the prior art, in track production and installation process, it is ensured that the technology of track requires and installation is stablized Property.Production installation for simplicity, it is necessary to change the structure of one entirety of track.Traditional track is generally one whole section of vertical bar type, Each section of track is directly connected to, and at turning, vertical bar type is welded with arc-shaped rail or connect with screw.When installation, hang Frame is directly connected to track.When trolley is when track moves, especially turning is easy cornering difficulties and stuck.When in track A certain section when there is unusual condition, maintenance overhaul is comparatively laborious.
Utility model content
The utility model provides a kind of novel track structure, which can be simple assembled.
Realization includes straight rail and bending track, and each track includes guide upper, guide rail middle part and guide rail lower part;Guide upper Square groove is set, through-hole is set in the middle part of guide rail, groove is arranged in guide rail lower part;The first groove bar is fixed in square groove, this first Groove bar is fixed on by track hoisting bracket on ceiling;The second groove bar of same root is set in the through-holes of adjacent rails, under guide rail The block extended to groove center direction is arranged in subordinate bottom surface, and the cavity of installation chain is formed between block and groove floor.
The utility model compared with prior art, has the following advantages:(1) simple in structure, reasonable design is ingenious;(2) add Convenient and simple when work manufactured parts, splicing is easy when package assembly, and technology requires to can reach requirement;(3) when failure repair, Sectional maintenance and inspection, it is convenient that proximate matter is replaced, and improves efficiency.
The utility model is further described with reference to the accompanying drawings of the specification.
Description of the drawings
Fig. 1 is the tomograph of the utility model.
Fig. 2 is the sectional view of the utility model.
Fig. 3 is the utility model guide rail frame schematic diagram.
Fig. 4 is profile structure schematic diagram.
Specific implementation mode
In conjunction with Fig. 1 to Fig. 3, a kind of novel track structure, including straight rail 1 and bending track 3, each track include on guide rail In the middle part of portion, guide rail and guide rail lower part;Square groove A-1 is arranged in guide upper, through-hole A-2 is arranged in the middle part of guide rail, guide rail lower part is set Set groove;The first groove bar 8 is fixed in square groove, which is fixed on by track hoisting bracket 6 on ceiling;Phase The second groove bar of same root is set in the through-hole of adjacent guide rail, the block extended to groove center direction is arranged in guide rail lower part bottom surface, The cavity A-3 of installation chain 12 is formed between block and groove floor.
First groove bar 8 is fixedly connected on by proximate matter 9 in square groove A-1.In conjunction with Fig. 4, used in the utility model Proximate matter 9 is 2060 proximate matters, and groove is arranged in both ends.In order to fix proximate matter 9, square groove both sides inner wall setting protrusion, 9 both ends of proximate matter Setting is fixed in the through-hole of proximate matter 9 on proximate matter 9 with the matched groove of protrusion, the first groove bar 8.Groove bar may be used 2020 Groove bar.
Track hoisting bracket 6 is fixed on by track hoisting bracket lower connecting member 5 in the first groove bar 8;Each track crane 5 bottom surface of dress holder lower connecting member is fixedly connected with the first groove bar 8, the setting of 5 upper bottom surface of track hoisting bracket lower connecting member Groove, track hoisting bracket 6, which is set in groove and connects bolt 4 by hoisting bracket and be fixed below track hoisting bracket, to be connected On fitting 5.
Two through-holes up and down can be set in the middle part of guide rail, the second groove bar 10,11 is all set in each through-hole, it is strong to increase Degree.
Width in the middle part of guide rail is less than the width of rail superior portion and lower part, and idler wheel can be in-orbit during traveling for external trolley Road lower part, which is wider than on the upper bottom surface in the middle part of track, advances.
Second groove bar is fixedly connected by track attachment screw 2 with guide rail.
Embodiment one
Adjacent interorbital shares identical first groove bar 8, proximate matter 9.5 bottom surface of track hoisting bracket lower connecting member with First groove bar 8 is fixedly connected, and groove is arranged in 5 upper bottom surface of track hoisting bracket lower connecting member, and track hoisting bracket 6 is set to recessed In slot and bolt 4 is connected by hoisting bracket to be fixed on track hoisting bracket lower connecting member 5.
Embodiment two
Adjacent interorbital uses the first different groove bars 8, proximate matter 9.Each track hoisting bracket lower connecting member 5 is gone to the bottom Face is fixedly connected with the first groove bar 8 of adjacent guide rail respectively, and groove is arranged in 5 upper bottom surface of track hoisting bracket lower connecting member, Track hoisting bracket 6, which is set in groove and connects bolt 4 by hoisting bracket, is fixed on track hoisting bracket lower connecting member 5 On.

Claims (7)

1. a kind of novel track structure, which is characterized in that including straight rail and bending track, each track includes guide upper, guide rail Middle part and guide rail lower part;Square groove is arranged in guide upper, and through-hole is arranged in the middle part of guide rail, and groove is arranged in guide rail lower part;
The first groove bar (8) is fixed in square groove, which is fixed on by track hoisting bracket (6) on ceiling;
The second groove bar of same root is set in the through-hole of adjacent rails,
The block extended to groove center direction is arranged in guide rail lower part bottom surface, and installation chain is formed between block and groove floor Cavity.
2. structure according to claim 1, which is characterized in that the first groove bar (8) is fixedly connected on rectangular by proximate matter (9) In groove;
Square groove both sides inner wall setting protrusion,
Proximate matter (9) both ends are arranged and the matched groove of protrusion,
First groove bar (8) is fixed on proximate matter (9).
3. structure according to claim 1, which is characterized in that adjacent interorbital shares identical first groove bar (8), type Material (9) uses different the first groove bars (8), proximate matter (9).
4. structure according to claim 3, which is characterized in that track hoisting bracket (6) passes through track hoisting bracket lower section Connector (5) is fixed in the first groove bar (8);
Each track hoisting bracket lower connecting member (5) bottom surface is fixedly connected with the first groove bar of adjacent guide rail (8) respectively,
Groove is arranged in track hoisting bracket lower connecting member (5) upper bottom surface,
Track hoisting bracket (6), which is set in groove and connects bolt (4) by hoisting bracket, to be fixed under track hoisting bracket On square connector (5).
5. structure according to claim 3, which is characterized in that track hoisting bracket (6) passes through track hoisting bracket lower section Connector (5) is fixed in the first groove bar (8);
Track hoisting bracket lower connecting member (5) bottom surface is fixedly connected with the first groove bar (8),
Groove is arranged in track hoisting bracket lower connecting member (5) upper bottom surface,
Track hoisting bracket (6), which is set in groove and connects bolt (4) by hoisting bracket, to be fixed under track hoisting bracket On square connector (5).
6. structure according to claim 1, which is characterized in that setting two through-holes up and down in the middle part of guide rail, in each through-hole Second groove bar is all set.
7. structure according to claim 1 or 6, which is characterized in that the second groove bar is solid by track attachment screw and guide rail Fixed connection.
CN201721908749.1U 2017-12-29 2017-12-29 A kind of novel track structure Expired - Fee Related CN207917857U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721908749.1U CN207917857U (en) 2017-12-29 2017-12-29 A kind of novel track structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721908749.1U CN207917857U (en) 2017-12-29 2017-12-29 A kind of novel track structure

Publications (1)

Publication Number Publication Date
CN207917857U true CN207917857U (en) 2018-09-28

Family

ID=63615842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721908749.1U Expired - Fee Related CN207917857U (en) 2017-12-29 2017-12-29 A kind of novel track structure

Country Status (1)

Country Link
CN (1) CN207917857U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107985948A (en) * 2017-12-29 2018-05-04 南京理工大学 A kind of novel track structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107985948A (en) * 2017-12-29 2018-05-04 南京理工大学 A kind of novel track structure
CN107985948B (en) * 2017-12-29 2024-04-05 南京理工大学 Novel track structure

Similar Documents

Publication Publication Date Title
CN204956498U (en) Rail vehicle chassis boundary beam suspended structure
CN105197031A (en) Rail car and side wall assembly thereof
CN207917857U (en) A kind of novel track structure
CN106672006A (en) Underframe of railway vehicle and railway vehicle
CN109317911A (en) A kind of cross column welding production line
CN104453922A (en) Shield machine trolley
CN102966032B (en) A kind of structural member of aluminum alloy passenger foot-bridge
CN107985948A (en) A kind of novel track structure
CN204455858U (en) A kind of hanger of large sections steel box-girder
CN208857603U (en) A kind of special-shaped transition rail being connect for groove profile rail with I-rail
CN203130707U (en) Connecting structure for mounting rod body
CN106185616A (en) A kind of vehicle mounted portable unloads rail portal frame and construction method thereof
CN201634343U (en) Large tower crane and transition joint used thereby
CN104100002A (en) Connecting structure of floor and column
CN203128036U (en) Rotary table and crane
CN208792063U (en) A kind of single-track turnout tailing axle pedestal assembly tool
CN207375553U (en) Vertical beam component
CN202202872U (en) Railway tunnel lining jacking frame
CN205132970U (en) Removable stock structure of tower machine
CN209426496U (en) A kind of central axle van and its draw bar
CN205254417U (en) Flexibility that is suitable for longeron welding production mechanism that remodels
CN208413715U (en) A kind of bracket of electric hoist free of replacement
CN203477613U (en) Detachable cable bridge rack with adjustable width
CN204823774U (en) Bridge crane end beam convenient to maintenance
CN203410940U (en) Large-size E type bolt

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180928

Termination date: 20201229