CN207906547U - Intelligent energy valve - Google Patents
Intelligent energy valve Download PDFInfo
- Publication number
- CN207906547U CN207906547U CN201820074893.8U CN201820074893U CN207906547U CN 207906547 U CN207906547 U CN 207906547U CN 201820074893 U CN201820074893 U CN 201820074893U CN 207906547 U CN207906547 U CN 207906547U
- Authority
- CN
- China
- Prior art keywords
- valve
- energy
- loose joint
- control
- flow
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Measuring Volume Flow (AREA)
Abstract
The utility model provides a kind of Intelligent Energy valve, belongs to heat control equipment technical field.It solves the problems such as prior art installation effectiveness is low.This Intelligent Energy valve at least a pair of temperature sensor for detecting flowing water temperature in external pipe fitting, at least one flow sensor for detecting flowing water flow in external pipe fitting, it is characterised in that:Further include that tube assembly is installed for the loose joint with external pipe fitting loose joint, flow sensor is set in loose joint installation tube assembly, it is additionally provided with energy control valve in loose joint installation tube assembly and controls the valve control assembly of energy control valve folding, valve control assembly is wiredly and/or wirelessly connect with temperature sensor and flow sensor respectively.The advantages of this Intelligent Energy valve, is:Loose joint installs tube assembly due to pre-setting flow sensor, energy control valve and valve control assembly on it before being connect with external pipe fitting, facilitates installation, shortens the set-up time, improves installation effectiveness.
Description
Technical field
The utility model belongs to heat control equipment technical field, more particularly, to a kind of Intelligent Energy valve.
Background technology
Calorimeter is also known as heat energy meter, thermal energy integrating instrument, is heat metering equipment, is suitable for measuring in heat exchange loop
In, the liquid referred to as thermal liquid absorbs or the instrument of conversion thermal energy, it is by temperature sensor, flow sensor and calculating
The compositions such as device, operation principle are the pipelines of import and outlet that pairing temperature sensor is separately mounted to heat exchange loop
On, flow sensor is mounted on water inlet line or water return pipeline, flow sensor acquires flow signal, and temperature sensor is adopted
Collect the temperature signal of water inlet end and backwater end, calculator is by collected flow signal and temperature signal, after calculation processing
Show the heat that detected fluid is discharged from water inlet end to backwater end.
Currently a popular calorimeter is mainly ultrasonic energy table, measures the operation principle of flow velocity:When ultrasonic wave is flowing
When being propagated in body, sound wave transmission speed information will load the velocity information of upper fluid, because the superposition of both signals, just makes sound
Spread speed of the wave in fair current and adverse current is unequal, therefore by measuring both different velocity informations, can by calculating
The flow velocity for obtaining fluid, is then converted into flow again, to realize the measurement of flow.Existing ultrasonic energy table includes super
Sound wave calorimeter and electric temperature control valve, are all the parts of separate dispersion, are needed when being controlled at the scene independent
Configuration Control Unit, and need after programming engineer to field adjustable.It is susceptible to problems with when installing at the scene simultaneously::
When installing the corollary equipment of ultrasonic energy table, it is also necessary to have some special mounting conditions, as calorimeter is mounted on by design
After electric temperature control valve is mounted on return pipe Temp. measuring ball valve when water inlet pipe or feed pipe, as the lead sealing on calorimeter cannot damage;It is super
Acoustic wave energy table is close instrument, carry out installation be need it is careful, in order to avoid damage;Ultrasonic energy table is at the scene
Also need to debug the valve controlled whether can be closed when installation;Ultrasonic energy table is also noted that temp probe when installing
Length, too small pipe need it is particularly customized;It is possible that installation question when ultrasonic energy table and valve are installed, such as:
Installation is not firm, there is phenomena such as loosening;Sometimes someone will accidentally cause to be arranged by what button for ultrasonic energy table
Parameter change.
Utility model content
The purpose of this utility model is the installation fast, easily intelligent energy in view of the above-mentioned problems, provide a kind of reasonable design
Measure valve.
In order to achieve the above objectives, the utility model uses following technical proposal:The Intelligent Energy valve of the utility model, packet
At least a pair of temperature sensor for detecting flowing water temperature in external pipe fitting is included, it is at least one to be flowed in external pipe fitting for detecting
The flow sensor of water flow, it is characterised in that:Further include that tube assembly is installed for the loose joint with external pipe fitting loose joint, flow passes
Sensor is set in loose joint installation tube assembly, and energy control valve and control energy control valve folding are additionally provided in loose joint installation tube assembly
Valve control assembly, valve control assembly wiredly and/or wirelessly connect with temperature sensor and flow sensor respectively.Loose joint is installed
Tube assembly due to pre-setting flow sensor, energy control valve and valve control on it before being connect with external pipe fitting
Component facilitates installation, shortens the set-up time, improves installation effectiveness.
Preferably, valve control assembly includes the variation of actuator and the temperature measured according to temperature sensor and according to flow
Sensor measures the energy meter measuring device of the value of the supply gross energy of the flowmeter calculating of water, the output end and energy hole of actuator
Valve connection, input terminal and control circuit board connect, and control circuit board is connect with energy meter measuring device, energy meter measuring device respectively with temperature
Sensor and flow sensor wiredly and/or wirelessly connect.It realizes automatically controlling for flow, facilitates operation.
Preferably, control circuit board is wiredly and/or wirelessly connect with remote control computer.It improves to this Intelligent Energy
The remote control ability of valve, while can avoid the case where site operation personnel changes by mistake parameter occur.
Preferably, energy meter measuring device is ultrasonic energy meter.It is good to measure effect.
Preferably, per temperature sensor be set to on a loose joint short tube of external pipe fitting loose joint.Due to pre- on loose joint short tube
It is first equipped with temperature sensor, therefore before the mounting it is only necessary to know that the pipe diameter size of external pipe fitting, then big according to the caliber
It is small select the loose joint short tube that is adapted to it can, without temperature sensor to be individually attached on external pipe fitting, facilitate
Installation.
Preferably, loose joint installation tube assembly includes being equipped with the flow detection pipeline section of flow sensor and communicating therewith
Flow control pipeline section equipped with energy control valve and valve control assembly.Can as needed flow sensor, energy control valve and
The model of valve control assembly is combined, and improves the scope of application, while being convenient for changing and being safeguarded.
Preferably, loose joint installation tube assembly and the connection type of external pipe fitting use appointing in horizontal connection and vertical connection
Meaning is a kind of;Flow detection pipeline section and flow control pipeline section are linked together.It ensure that the detection of flow sensor and valve control assembly
The reliability of data, is wholely set and improves working strength.
Preferably, external pipe fitting includes water return pipeline and water inlet line.
Preferably, loose joint installation tube assembly is set on water return pipeline.More accurate numerical value is measured convenient for flow sensor.
Preferably, temperature sensor needs at least to be respectively provided with one on water return pipeline and water inlet line.Convenient for preferably obtaining
Go out the temperature gap of the flowing water in water return pipeline and water inlet line.
Compared with prior art, the advantages of this Intelligent Energy valve, is:Pre-set flow sensor, energy control valve
Tube assembly is installed before being connect with external pipe fitting with the loose joint of valve control assembly, it is only necessary to know that the caliber of external pipe fitting, then root
According to its choice of diameter suitable loose joint installation tube assembly can, when installation loose joint need to only be installed the both ends of tube assembly with it is outer
Jointed tubular workpieces are tightly connected, and are had the following advantages:When connecting with external pipe fitting, need not go to carry out installation energy meter again
Device also just substantially reduces the possibility that energy meter measuring device has been damaged because of installation;Just adjusting has been done when manufacture
It is good, it no longer needs to adjust energy meter measuring device to scene;Reduce the workload needed for installation, while can be installed to avoid some
Hidden danger.
Description of the drawings
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor
Under, other drawings may also be obtained based on these drawings.
Fig. 1 provides the structural schematic diagram in the utility model embodiment.
Fig. 2 provides the operation principle block diagram in the utility model embodiment.
In figure, temperature sensor 1, flow sensor 2, flow detection pipeline section 31, flow control pipeline section 32, energy control valve
4, valve control assembly 5, actuator 51, energy meter measuring device 52, control circuit board 53, remote control computer 54, loose joint short tube 6.
Specific implementation mode
The utility model is described in further detail below in conjunction with the accompanying drawings and by embodiment, and following embodiment is pair
The explanation of the utility model and the utility model is not limited to following embodiment.
As shown in Fig. 1 to 2, this Intelligent Energy valve, including at least a pair of temperature for detecting flowing water temperature in external pipe fitting
Spend sensor 1, at least one flow sensor 2 for detecting flowing water flow in external pipe fitting, it is characterised in that:Further include using
Tube assembly is installed in the loose joint with external pipe fitting loose joint, flow sensor 2 is set in loose joint installation tube assembly, loose joint installing pipe group
Be additionally provided on part energy control valve 4 and control energy control valve 4 open and close valve control assembly 5, valve control assembly 5 respectively with temperature
Sensor 1 and flow sensor 2 wiredly and/or wirelessly connect, and loose joint installs tube assembly due to before being connect with external pipe fitting
It has pre-set flow sensor 2, energy control valve 4 and valve control assembly 5 on it, has facilitated installation, shortens installation
Time improves installation effectiveness.
Specifically, valve control assembly 5 here includes the variation of actuator 51 and the temperature measured according to temperature sensor 1
The energy meter measuring device 52 of the value of the supply gross energy calculated with the flowmeter for measuring water according to flow sensor 2, actuator 51
Output end is connect with energy control valve 4, input terminal and control circuit board 53 connect, and control circuit board 53 connects with energy meter measuring device 52
It connects, energy meter measuring device 52 is wiredly and/or wirelessly connect with temperature sensor 1 and flow sensor 2 respectively, realizes the automatic of flow
Control, facilitates operation;Here control circuit board 53 is wiredly and/or wirelessly connect with remote control computer 54, is improved
To the remote control ability of this Intelligent Energy valve, while it can avoid the case where site operation personnel changes by mistake parameter occur;Here
Energy meter measuring device 52 is ultrasonic energy meter, and metering effect is good;Here every temperature sensor 1 is set to lives with external pipe fitting
On the loose joint short tube 6 connect, due to being previously provided with temperature sensor 1 on loose joint short tube 6, before the mounting it is only necessary to know that
The pipe diameter size of external pipe fitting, then according to the loose joint short tube 6 that is adapted to it of pipe diameter size selection can, without general
Temperature sensor 1 is individually attached on external pipe fitting, facilitates installation;Here loose joint installation tube assembly includes being equipped with flow to pass
The flow detection pipeline section 31 of sensor 2 and the flow control tube equipped with energy control valve 4 and valve control assembly 5 communicated therewith
Section 32 model of flow sensor 2, energy control valve 4 and valve control assembly 5 can be combined, improve suitable as needed
With range, while being convenient for changing and safeguarding.
Further, loose joint installation tube assembly and the connection type of external pipe fitting here uses horizontal connection and vertical connects
Any one in connecing, flow detection pipeline section 31 and flow control pipeline section 32 are linked together, and ensure that flow sensor 2 and valve control
The reliability of the detection data of component 5 processed, is wholely set and improves working strength;Here external pipe fitting include water return pipeline and
Water inlet line;Here loose joint installation tube assembly is set on water return pipeline, and more accurate numerical value is measured convenient for flow sensor 2;
Here temperature sensor 1 needs at least to be respectively provided with one on water return pipeline and water inlet line, convenient for preferably obtaining return pipe
The temperature gap of flowing water in road and water inlet line.
When installation, the caliber data of external pipe fitting are obtained first, are then selected according to the caliber data matched
The loose joint installation tube assembly of flow sensor 2, energy control valve 4 and valve control assembly 5 has been installed in advance, has then only been needed
Loose joint installation tube assembly is connect with external pipe fitting, is similarly selected according to the caliber data of external pipe fitting matched
The loose joint short tube 6 for being equipped with temperature sensor 1 in advance, then only loose joint short tube 6 need to be connect i.e. with external pipe fitting
Can, finally by temperature sensor 1, flow sensor 2 and remote control computer 54 respectively with valve control assembly 5 it is wired and/or
Wireless connection.Filter screen preferably is installed in outer jointed tubular workpieces, to improve the service life of this Intelligent Energy valve;When external
The caliber of pipe fitting need to be grounded when being more than DN65, to prevent the interference to monitoring result;Tube assembly is installed in loose joint and loose joint is short
The installation site of pipe 6 needs to meet it and all must not at a distance from external pipe fitting delivery outlet with it at a distance from external pipe fitting input port
Less than the requirement of 5 times of length of the outer tube diameter of the external pipe fitting, to ensure that measurement accuracy reaches specification.
When operation, temperature sensor 1 is by the flowing water temperature in the flowing water temperature value and water inlet line in the water return pipeline measured
Angle value, flow sensor 2 will measure flowing water flow value is sent to after energy meter measuring device 52 in valve control assembly 5 to calculate
The variation of the value that institute is calculated according to energy meter measuring device 52 for gross energy, control circuit board 53 manipulates actuator 51, in turn
The switching action of energy control valve 4 is controlled by actuator 51.Preferably valve control assembly 5 is equipped with position control, flow control
The various controls pattern such as system or power control, the moment such as opened in energy control valve 4, since the very low very little of flow leads to temperature
Sensor 1 and flow sensor 2 monitoring less than, or due to one or more of temperature sensor 1 and flow sensor 2 pass
Sensor breaks down, and at this moment valve control assembly 5 is set as position control mode, and flow control mode or power are recalled to again after normal
Control model.
The specific embodiments described herein are merely examples of the spirit of the present invention.The utility model institute
Belonging to those skilled in the art can make various modifications or additions to the described embodiments or using similar
Mode substitute, but without departing from the spirit of the present application or beyond the scope of the appended claims.
Although temperature sensor 1, flow sensor 2, flow detection pipeline section 31, flow control tube is used more herein
Section 32, energy control valve 4, valve control assembly 5, actuator 51, energy meter measuring device 52, control circuit board 53, remote control calculate
The terms such as machine 54, loose joint short tube 6, but it does not preclude the possibility of using other terms.The use of these items is only for more
Easily describe and explain the essence of the utility model;It is new with this practicality to be construed as any one of the additional limitations all
Type spirit is disagreed.
Claims (10)
1. a kind of Intelligent Energy valve, including at least a pair of temperature sensor (1) for detecting flowing water temperature in external pipe fitting, until
A few flow sensor (2) for detecting flowing water flow in external pipe fitting, it is characterised in that:Further include being used for and extension tube attached
Tube assembly is installed in the loose joint of part loose joint, and the flow sensor (2) is set in the loose joint installation tube assembly, the work
It connects and is additionally provided with energy control valve (4) in installation tube assembly and controls the valve control assembly (5) that energy control valve (4) opens and closes, it is described
Valve control assembly (5) wiredly and/or wirelessly connect with temperature sensor (1) and flow sensor (2) respectively.
2. Intelligent Energy valve according to claim 1, which is characterized in that the valve control assembly (5) includes actuator
(51) and according to temperature sensor (1) variation of the temperature measured and the flowmeter that water is measured according to flow sensor (2) calculate
Supply gross energy value energy meter measuring device (52), the output end of the actuator (51) connect with energy control valve (4),
Input terminal is connect with control circuit board (53), and the control circuit board (53) is connect with energy meter measuring device (52), the energy
Gauge measuring device (52) is wiredly and/or wirelessly connect with temperature sensor (1) and flow sensor (2) respectively.
3. Intelligent Energy valve according to claim 2, which is characterized in that the control circuit board (53) and remote control
Computer (54) wiredly and/or wirelessly connects.
4. Intelligent Energy valve according to claim 2, which is characterized in that the energy meter measuring device (52) is ultrasonic wave energy
Gauge measuring device.
5. Intelligent Energy valve according to claim 1, which is characterized in that per the temperature sensor (1) be set to it is outer
On one loose joint short tube (6) of jointed tubular workpieces loose joint.
6. Intelligent Energy valve according to any one of claims 1 to 5, which is characterized in that tube assembly packet is installed in the loose joint
It includes the flow detection pipeline section (31) equipped with flow sensor (2) and what is communicated therewith is equipped with energy control valve (4) and valve control
The flow control pipeline section (32) of component (5).
7. Intelligent Energy valve according to claim 6, which is characterized in that the loose joint installation tube assembly and external pipe fitting
Connection type using any one in horizontal connection and vertical connection;The flow detection pipeline section (31) and flow control
Pipeline section (32) is linked together.
8. Intelligent Energy valve according to claim 1, which is characterized in that the external pipe fitting include water return pipeline and into
Waterpipe.
9. Intelligent Energy valve according to claim 8, which is characterized in that the loose joint installation tube assembly is set to return pipe
On road.
10. Intelligent Energy valve according to claim 8, which is characterized in that the temperature sensor (1) needs at least returning
One is respectively provided on waterpipe and water inlet line.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820074893.8U CN207906547U (en) | 2018-01-17 | 2018-01-17 | Intelligent energy valve |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820074893.8U CN207906547U (en) | 2018-01-17 | 2018-01-17 | Intelligent energy valve |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207906547U true CN207906547U (en) | 2018-09-25 |
Family
ID=63563811
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820074893.8U Expired - Fee Related CN207906547U (en) | 2018-01-17 | 2018-01-17 | Intelligent energy valve |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207906547U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109237116A (en) * | 2018-09-30 | 2019-01-18 | 盐城欧润石化设备制造有限公司 | A kind of time reminding valve |
CN110131458A (en) * | 2019-06-28 | 2019-08-16 | 郑州睿联智能科技有限公司 | A kind of valve controling circuit being adapted to multiple caliber |
-
2018
- 2018-01-17 CN CN201820074893.8U patent/CN207906547U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109237116A (en) * | 2018-09-30 | 2019-01-18 | 盐城欧润石化设备制造有限公司 | A kind of time reminding valve |
CN110131458A (en) * | 2019-06-28 | 2019-08-16 | 郑州睿联智能科技有限公司 | A kind of valve controling circuit being adapted to multiple caliber |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102635894B (en) | Balance controlling method of heating system and diagnosis measuring device | |
CN207906547U (en) | Intelligent energy valve | |
CN105757785A (en) | Heating pipe network operation monitoring device | |
CN110594472A (en) | Intelligent electric actuator of flow monitoring valve | |
CN2935096Y (en) | Integrated differential pressure flowmeter | |
CN102759145B (en) | Heating system flow balance regulating method and flow balance regulating system | |
CN201096268Y (en) | Flux monitoring -type gas pressure regulating apparatus | |
CN104019871B (en) | Household watermeter on-site calibration instrument and calibration method thereof | |
CN2883878Y (en) | Lossrate monitoring system of delivery pipeline | |
CN211175560U (en) | Intelligent electric actuator of flow monitoring valve | |
CN209014066U (en) | One kind being based on TDC-GP30 double-channel gas ultrasonic flowmeter | |
CN201812209U (en) | Intelligent flow balance device | |
CN205560987U (en) | Operation monitoring and controlling device of heating pipe net | |
CN209117090U (en) | A kind of inserting-type flowmeter suitable for different tube diameters | |
CN207161854U (en) | Internet of Things flow self balance valve | |
CN204241051U (en) | Table gauge valve integrated ultrasonic flow sensor and corresponding IC-card flowmeter | |
CN207528302U (en) | It is a kind of to carry out level monitoring device using ultrasonic sensor | |
CN205228682U (en) | Ultrasonic wave calorimeter based on pressure gauge | |
CN202433043U (en) | Wide-range-ratio pore-plate differential-pressure-type flowmeter | |
CN208443499U (en) | A kind of high pressure-temperature calorimeter based on narrowband Internet of Things | |
CN112179429B (en) | Liquid flow detection device | |
CN207718613U (en) | A kind of heat supply network multiparameter measuring device | |
CN210322093U (en) | Real-time supplementary checking device of heat supply unit heat supply network head station heat supply volume | |
CN104655209A (en) | Ultrasonic water meter with flow rate control function | |
CN205785370U (en) | External clamping ultrasonic flow automatic monitoring system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180925 Termination date: 20200117 |