Prior art keywords
mini pile
bank
vertical
retainer structure
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820009180.3U
Other languages
Chinese (zh)
Inventor
罗光财
谭可
瞿永
刘维正
傅鹤林
石志国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCFEB Civil Engineering Co Ltd
Original Assignee
CCFEB Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCFEB Civil Engineering Co Ltd filed Critical CCFEB Civil Engineering Co Ltd
Priority to CN201820009180.3U priority Critical patent/CN207878200U/en
Application granted granted Critical
Publication of CN207878200U publication Critical patent/CN207878200U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides one kind and facing bank subgrade support retainer structure, is related to the technical field of road construction engineering.Bank subgrade support retainer structure provided by the utility model of facing includes:Vertical mini pile tilts mini pile and barricade;The offshore side that mini pile is set to roadbed is tilted, and tilts and extends to roadbed offshore edge down from ground;Vertical mini pile, which is set to, tilts side of the mini pile far from bank, and is vertically extended downwardly from ground;Barricade is fixedly connected on vertical mini pile and tilts at the top of mini pile.Bank subgrade support retainer structure provided by the utility model of facing is by combining vertical mini pile and tilting mini pile, improve the overall stability of road structure, and work progress does not need heavy mechanical equipment, to weak, the big technical problem of difficulty of construction that alleviates in the prior art foundation bearing capacity present in side line road widening project near water.

Description

Face bank subgrade support retainer structure
Technical field
The utility model is related to road construction field of engineering technology, facing bank subgrade support retainer structure more particularly, to one kind.
Background technology
With the development of tourist industry and the growth of the volume of traffic, the planning of the origin road and road conditions cannot be satisfied demand;In order to Carrying capacity is improved, the project of upgrading and rebuilding of Huan He, ring river and the road that circles the lake are increasing, and general modification scheme is near water Road is widened in side.But side is due to river degradation and deposition near water, stratum is mostly muck soil, loose Plain fill or fine sand press from both sides boulder bed, and the bearing capacity of ground is weaker;In addition, side landform is more complicated near water, place is narrow, Construction space is limited, and increasing road construction dike to the side near water increases difficulty.
When the region of equal grounds weakness near water carries out widening of subgrade, to reduce occupancy river width to the greatest extent, frequently with gear Wall protects embankment engineering;Barricade in the prior art includes gravity type, buttress type and cantilevered, barricade mainly according to It fills and is banketed to keep the stabilization of barrier wall structure in the dead weight of wall body or bottom plate.But building barricade wants the bearing capacity of ground Ask higher;For the region of the foundation bearing capacities such as side near water weakness, need to pile foundation be set under barricade.On the one hand pile foundation can enhance Foundation bearing capacity improves the stability of barricade;On the other hand can also play the role of reinforcing side slope near water.
Pile foundation commonly used in the prior art includes cast-in-situ bored pile, powder-spray pile and deal pile.But cast-in-situ bored pile due to Need large scale equipment in the work progress such as pile foundation pore-forming and reinforcing bar cage hoisting, thus the regions constructional difficulties such as road near water compared with Greatly;In addition, the work progress of cast-in-situ bored pile easily causes to disturb to stratum, lead to the additional deformation of roadbed generation near water even unstability It destroys.Powder-spray pile and deal pile are poor in the Domain Stabilities such as near water, and easily being washed away by river water is influenced with factors such as fluctuation in stages, is led Cause pile foundation is impaired to destroy, bearing capacity is lost.
In conclusion side line road widening project there are foundation bearing capacities weak, the big skill of difficulty of construction near water in the prior art Art problem.
Utility model content
The purpose of this utility model is to provide one kind facing bank subgrade support retainer structure, to alleviate in the prior art side line near water Foundation bearing capacity present in the widening project of road is weak, the big technical problem of difficulty of construction.
Bank subgrade support retainer structure provided by the utility model of facing includes:Vertical mini pile tilts mini pile and barricade;It tilts Mini pile is set to the offshore side of roadbed, and tilts and extend to roadbed offshore edge down from ground;Vertical mini pile setting In side of the inclination mini pile far from bank, and vertically extended downwardly from ground;Barricade is fixedly connected on vertical micro- At the top of type stake and inclination mini pile.
Further, ranging from 15 ° -20 ° of angle between the axis of mini pile and plumb line are tilted.
Further, the first steel pipe is provided in vertical mini pile, the first steel pipe prolongs along the length direction of vertical mini pile It stretches, the first slurry outlet is provided on the tube wall of the first steel pipe;It tilts and is provided with the second steel pipe in mini pile, the second steel pipe is along inclination The length direction of mini pile extends, and the second slurry outlet is provided on the tube wall of the second steel pipe.
Further, it includes more inclination mini piles to face bank subgrade support retainer structure, and more tilt length of the mini pile along bank Spend the setting of direction interval;It includes multiple rows of vertical mini pile group to face bank subgrade support retainer structure, and it includes more often to arrange vertical mini pile group The spaced vertical mini pile of length direction along bank, multiple rows of vertical mini pile group is along from facing direction of the bank side to remote bank side Interval setting.
Further, the distance between adjacent upright mini pile is 0.8m-1m.
Further, the side on the separate bank of barricade is provided with weight platform, and weight platform is for carrying backfilled roadbed supported material.
Further, it is to be directed toward bank from bottom to top to tilt that barricade, which is located at the side above weight platform, is located under weight platform The side of side is to be directed toward bank from top to down to tilt.
Further, it further includes cushion cap to face bank subgrade support retainer structure, and cushion cap is fixedly connected on vertical mini pile and tilts micro- The top of type stake, barricade are fixed on the top of cushion cap.
Further, first is both provided in vertical mini pile to put more energy into muscle, the first muscle of putting more energy into extends out of vertical mini pile To cushion cap;It tilts and is both provided with second in mini pile and puts more energy into muscle, the second muscle of putting more energy into extends in cushion cap from tilting in mini pile.
Further, more first muscle of putting more energy into are provided in every vertical mini pile, more first muscle of putting more energy into are along vertical micro- The periphery of type stake is spaced apart, and the part bending outward that every first muscle of putting more energy into is located in cushion cap;Every inclination is miniature It is provided with more second muscle of putting more energy into stake, more second muscle of putting more energy into are spaced apart along the periphery for tilting mini piles, and every the Part bending outward that muscle is located in cushion cap that two put more energy into.
It is provided by the utility model to face bank subgrade support retainer structure, it is related to the technical field of road construction engineering.This practicality is new Type provide bank subgrade support retainer structure of facing include:Vertical mini pile tilts mini pile and barricade;It tilts mini pile and is set to roadbed Offshore side, and from ground down to roadbed offshore edge tilt extend;It is separate that vertical mini pile is set to inclination mini pile The side on bank, and vertically extended downwardly from ground;Barricade is fixedly connected on vertical mini pile and tilts mini pile Top.The barricade provided by the utility model faced in bank subgrade support retainer structure can make the whole center of gravity of road structure to offshore sidesway It is dynamic, to resist soil body lateral pressure, improve the stability of Steep Slope Embankment.On the one hand vertical mini pile and inclination mini pile can reinforce ground Layer, prevention river water wash away erosion, the vertical bearing capacity of ground on the other hand can be improved;In addition, being set to inclining for roadbed offshore side Oblique mini pile can also improve the standard bearing capacity, reduce shearing and damage of the moment of flexure to road structure caused by horizontal loading.It is perpendicular Down-the-hole drill or jumbolter construction can be used in straight mini pile and inclination mini pile, removes the use of heavy mechanical equipment from, makees Industry space requirement is small, smaller to ground disturbance, eco-friendly.
Bank subgrade support retainer structure provided by the utility model of facing is improved by combining vertical mini pile and tilting mini pile The overall stability of road structure, and work progress does not need heavy mechanical equipment, to alleviate in the prior art near water Foundation bearing capacity present in the widening project of side line road is weak, the big technical problem of difficulty of construction.
To enable the above objects, features, and advantages of the utility model to be clearer and more comprehensible, the utility model cited below particularly compared with Good embodiment, and coordinate appended attached drawing, it is described below in detail.
Description of the drawings
It, below will be right in order to illustrate more clearly of specific embodiment of the present invention or technical solution in the prior art Specific implementation mode or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, it is described below In attached drawing be that some embodiments of the utility model are not paying creativeness for those of ordinary skill in the art Under the premise of labour, other drawings may also be obtained based on these drawings.
Fig. 1 is the structural schematic diagram at the first visual angle for facing bank subgrade support retainer structure that the utility model embodiment provides;
Fig. 2 is the local perspective view for facing bank subgrade support retainer structure that the utility model embodiment provides;
Fig. 3 be the utility model embodiment provide face vertical mini pile in bank subgrade support retainer structure, inclination mini pile and The vertical view of cushion cap;
Fig. 4 is the structural schematic diagram for facing the first steel pipe in bank subgrade support retainer structure that the utility model embodiment provides.
Icon:The vertical mini piles of 01-;The first steel pipes of 011-;The first slurry outlets of 0111-;012- first puts more energy into muscle;02- inclines Oblique mini pile;The second steel pipes of 021-;022- second puts more energy into muscle;03- barricades;031- weight platforms;04- cushion caps.
Specific implementation mode
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described Embodiment is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, originally The every other embodiment that field those of ordinary skill is obtained without making creative work, belongs to this practicality Novel protected range.
It is in the description of the present invention, it should be noted that term "center", "upper", "lower", "left", "right", " perpendicular Directly ", the orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only The utility model and simplifying describes for ease of description, do not indicate or imply the indicated device or element must have it is specific Orientation, with specific azimuth configuration and operation, therefore should not be understood as limiting the present invention.In addition, term " the One ", " second ", " third " are used for description purposes only, and are not understood to indicate or imply relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally Connection;It can be mechanical connection, can also be electrical connection;Can be directly connected, can also indirectly connected through an intermediary, It can be the connection inside two elements.For the ordinary skill in the art, it can understand above-mentioned art with concrete condition The concrete meaning of language in the present invention.
Fig. 1 is please referred to, the bank subgrade support retainer structure of facing that the utility model embodiment provides includes:Vertical mini pile 01 inclines Oblique mini pile 02 and barricade 03;The offshore side that mini pile 02 is set to roadbed is tilted, and from ground down to roadbed offshore side Extend along tilting;Vertical mini pile 01, which is set to, tilts side of the mini pile 02 far from bank, and vertically from ground It extends downwardly;Barricade 03 is fixedly connected on vertical mini pile 01 and tilts 02 top of mini pile.
Specifically, the barricade 03 faced in bank subgrade support retainer structure that the utility model embodiment provides can make road structure Whole center of gravity is moved to offshore side, to resist soil body lateral pressure, improves the stability of Steep Slope Embankment.Vertical mini pile 01 and inclination Mini pile 02 on the one hand can strengthening stratum, prevent river water from washing away erosion, the vertical bearing capacity of ground on the other hand can be improved.Separately Outside, being set to the inclination mini pile 02 of roadbed offshore side can also improve the standard bearing capacity, reduce shearing caused by horizontal loading Damage with moment of flexure to road structure.Down-the-hole drill or jumbolter can be used to apply for vertical mini pile 01 and inclination mini pile 02 Work, removes the use of heavy mechanical equipment from, and working space requires small, eco-friendly smaller to ground disturbance.
In some embodiments, it for vertical mini pile 01, is drilled using the dry pore-forming mode of down-the-hole drill;Aperture is 20cm, depth of pore forming 4m-12m.Drilling is to projected depth, using air compressor machine high wind aperture blowing, sediment in cleaning hole.
For mini pile 02 is tilted, drilled using jumbolter.When construction, after being positioned to stake position, jumbolter is adjusted Position and angle, check the gradient of stake in time in drilling process.
In some embodiments, after the hole position of vertical mini pile 01 and inclination mini pile 02 is drilled, slurry processes are returned using bottom hole Slip casing by pressure.Injecting paste material is M30 mortars, is prepared using P.O42.5 class g cements and Machine-made Sand, design mixture proportion is water:Cement: Sand:Waterglass=0.42:1:1:0.008, it is sufficiently stirred using mortar mixer after each ingredient mixing.The good coagulation of mixing Soil sand slurry is put into ash-pit made of steel plate welding, then by slip casting machine slip casting, 0.5~1MPa of grouting pressure;After the slurry that overflows, envelope After several minutes of closed pore mouth voltage stabilizing, stop noting after overflowing again.
In some embodiments, barricade 03 uses C30 concretings.Barricade template is set up, using punching block slab supporting, steel Pipe makees rib, mating Screw arbor with nut at both-ends, and fixes to be scheduled in double steel pipe by " 3 " type butterfly and reinforce, and fore shaft is fixed using steel pipe, to carry The stability of high template support system.Barricade 03 sets one of subsiding crack every 10m~15m, slit width 2cm~3cm, is adopted in subsiding crack It is clogged along wall side with pitch hemp cut.Barricade 03 is located at ground above section, is staggered drain hole every 2m~3m, drain hole A diameter of 100mm-110mm;The water inlet end of drain hole is higher than water outlet, and water inlet end is wrapped up using anti-filter geotextiles in order to avoid letting out Silt up in water hole.
Further, ranging from 15 ° -20 ° of angle are tilted between the axis and plumb line of mini pile 02.
Specifically, it according to the size of roadbed and road overall structure feature and the horizontal load of required carrying, tilts miniature Angle may be provided with 15 °, 18 ° or 20 ° etc. between the axis and plumb line of stake 02;Horizontal load is bigger, and the angle is bigger.Root According to engineering construction experience, the angle between the axis and plumb line that tilt mini pile 02 is arranged within the scope of 15 ° -20 °, can be made Tilting mini pile 02 has larger vertical load carrying capacity, and meets road structure and wanted to horizontal load bearing capacity It asks.
Further, Fig. 2 and Fig. 4 are please referred to, the first steel pipe 011,011 edge of the first steel pipe are provided in vertical mini pile 01 The length direction of vertical mini pile 01 extends, and the first slurry outlet 0111 is provided on the tube wall of the first steel pipe 011;Tilt mini pile The second steel pipe 021 is provided in 02, the second steel pipe 021 extends along the length direction for tilting mini pile 02, the pipe of the second steel pipe 021 The second slurry outlet is provided on wall.
Specifically, it when construction, after the hole of vertical mini pile 01 position is drilled, by 011 load hole of the first steel pipe, then carries out Slip casting;Mortar inside and outside first steel pipe 011 is connected as an entirety by the first slurry outlet 0111.First steel pipe 011 can enhance The intensity of vertical mini pile 01 and vertical load carrying capacity.
When construction, tilt mini pile 02 hole position be drilled after, by 021 load hole of the second steel pipe, then carry out slip casting;The Mortar inside and outside two steel pipes 021 is connected as an entirety by the second slurry outlet.Second steel pipe 021, which can enhance, tilts mini pile 02 Intensity, vertical load carrying capacity and horizontal load bearing capacity.
In some embodiments, the first steel pipe 011 and the second steel pipe 021 are made of galvanizing seamless steel pipe.Seamless steel Bore 146mm, thick 6.5mm.When the length of single seamless steel pipe is inadequate, more nothings of sleeve connection can be used by design length Stitch steel pipe.Length sleeve 400mm, wall thickness 6.5mm;The junction of sleeve and seamless steel pipe is welded, and welding is answered full.
In some embodiments, the first slurry outlet 0111 is set to the first section of the steel pipe 011 away from top surface 140cm to bottom It is interior, the diameter 10mm of the first slurry outlet 0111.
Fig. 4 is please referred to, in some embodiments, multiple first slurry outlets 0111 are provided on first steel pipe 011, it is more A first slurry outlet, 0111 arranged for interval, the spacing 15cm between adjacent first slurry outlet 0111.
In some embodiments, multiple second slurry outlets are provided on second steel pipe 021, multiple second slurry outlets are set Be placed in the second section of the steel pipe 021 away from top surface 140cm to bottom, and arranged for interval, between adjacent second slurry outlet between Away from 15cm.The diameter 10mm of second slurry outlet.
Further, it includes more inclination mini piles 02 that the utility model embodiment provided, which faces bank subgrade support retainer structure, More tilt mini pile 02 and are arranged along the length direction interval on bank;What the utility model embodiment provided faces bank subgrade support retainer knot Structure includes multiple rows of vertical mini pile group, and it includes that the more length directions along bank are spaced vertical often to arrange vertical mini pile group Mini pile 01, multiple rows of vertical mini pile group is along from bank side is faced to the setting of the direction interval of remote bank side.
Specifically, Fig. 1 and Fig. 3 are please referred to, more tilt mini pile 02 and are located on the same line, and adjacent inclined is micro- The distance between type stake 02 is equal, and every can be made to tilt the load relative equilibrium that mini pile 02 is born in this way, be conducive to road The overall stability of structure.The quantity of vertical mini pile group is 3 groups, more vertical mini piles 01 in single vertical mini pile group It is located on the same line.
It in some embodiments, can be according to road structure from facing size of the bank side to remote bank side direction, and to road The requirement of road bearing capacity, to adjust the quantity and density of setting of vertical mini pile group.
In some embodiments, can be according to the extending direction on bank, the line of more inclination mini piles 02 is matched Curve, the distance between adjacent inclined mini pile 02 are configured according to the difference of each segment structure of road.
In some embodiments, more tilt mini piles 02 and may be configured as along being set to the direction interval of remote bank side from facing bank side That sets is multiple rows of.
Further, the distance between adjacent upright mini pile 01 is 0.8m-1m.
Specifically, for ease of constructing and the harmony of whole road structure stress, between adjacent upright mini pile 01 away from From being equal, which can be 0.8m, 0.9m or 1m etc..It is right according to the difference required the vertical load carrying capacity of road The density of setting of vertical mini pile 01 is adjusted;Vertical load is bigger, then the distance between adjacent upright mini pile 01 is smaller.
Further, the side on the separate bank of barricade 03 is provided with weight platform 031, and weight platform 031 is backfilled for carrying Roadbed material.
Specifically, Fig. 1 is please referred to, the lower part of barricade 03 is provided with the protrusion extended to offshore side, the top shape of the protrusion At weight platform 031.The top surface of the protrusion is plane, can in the top filling soil or the backfilled roadbed supported material such as sandstone of protrusion, Pavement structure is also disposed on the top of the protrusion.Backfilled roadbed supported material effects can make this reality in the downward active force of the protrusion Face the stress point of the resultant force of vertical direction active force suffered by bank subgrade support retainer structure to offshore sidesway with what new embodiment provided It is dynamic, reduce vertical mini pile 01 and tilts the size of 02 bending moment of mini pile.
Further, the side that barricade 03 is located at 031 top of weight platform is to be directed toward bank from bottom to top to tilt, and is located at weight The side of 031 lower section of platform is to be directed toward bank from top to down to tilt.
Specifically, Fig. 1 is please referred to.The side of barricade 03 by above-mentioned shape tilt, can in a limited space in increase weight The area of 031 top surface of platform, so as to increase the bearing capacity of backfilled roadbed supported material.In addition, the barricade 03 of the shape can be such that center of gravity leans on To offshore side, be conducive to the stability for improving structure.
Further, it further includes cushion cap 04 that the utility model embodiment provided, which faces bank subgrade support retainer structure, and cushion cap 04 is solid Surely it is connected to vertical mini pile 01 and tilts the top of mini pile 02, barricade 03 is fixed on the top of cushion cap 04.
Specifically, Fig. 1 is please referred to, cushion cap 04 is set to vertical mini pile 01 and tilts between mini pile 02 and barricade 03. Cushion cap 04 can spread vertical pressure, keep the stress of vertical mini pile 01 and inclination mini pile 02 more balanced.Cushion cap 04 is by barricade 03 Base foundation be linked to be entirety, can prevent part settle lead to crack.
In vertical mini pile 01 and after tilting the mortar solidification of mini pile 02, cushion cap 04 is formed by branch module and cast-in-situ.Construction When, concrete is poured using automotive pump, and C30 commerical ready-mixed concretes are used in casting process.Concrete carries out placement layer by layer, per 10m If one of expansion joint.
In some embodiments, distributing bar is disposed with inside cushion cap 04, distributing bar is horizontally disposed and vertical by more The bar splicing of setting forms, and the joint of reinforcing bar is connected using overlap welding.
Further, first is both provided in vertical mini pile 01 to put more energy into muscle 012, first puts more energy into muscle 012 from vertical miniature It is extended in cushion cap 04 in stake 01;It tilts and is both provided with second in mini pile 02 and puts more energy into muscle 022, second puts more energy into muscle 022 from inclination It is extended in mini pile 02 in cushion cap 04.
Specifically, the first both ends for putting more energy into muscle 012 are respectively embedded into vertical mini pile 01 and cushion cap 04, can enhance vertical miniature Firmness of the connection between stake 01 and cushion cap 04.Second both ends for putting more energy into muscle 022, which are respectively embedded into, tilts mini pile 02 and cushion cap 04, The firmness of the connection tilted between mini pile 02 and cushion cap 04 can be enhanced.
Further, more first muscle 012 of putting more energy into, more first muscle 012 of putting more energy into are provided in every vertical mini pile 01 It is spaced apart along the periphery of vertical mini pile 01, and every first part that muscle 012 is located in cushion cap 04 of putting more energy into is rolled over outward It is curved;More second muscle 022 of putting more energy into are provided in every inclination mini pile 02, more second muscle 022 of putting more energy into are along inclination mini pile 02 Periphery be spaced apart, and the part bending outward that every second muscle 022 of putting more energy into is located in cushion cap 04.
Specifically, more first connections that muscle 012 further enhances between vertical mini pile 01 and cushion cap 04 of putting more energy into are strong Degree, first puts more energy into the bending outward of muscle 012, and the carrying energy of vertical mini pile 01 and 04 junction horizontal load of cushion cap can be improved Power, to improve the horizontal load bearing capacity for facing bank subgrade support retainer structure of the utility model embodiment offer.More second Muscle 022 of putting more energy into further enhances the bonding strength tilted between mini pile 02 and cushion cap 04, and the second muscle 022 of putting more energy into is rolled over outward It is curved, the bearing capacity for tilting mini pile 02 and 04 junction horizontal load of cushion cap can be improved, implement to improve the utility model The horizontal load bearing capacity for facing bank subgrade support retainer structure that example provides.
Finally it should be noted that:Each embodiment in this specification is described in a progressive manner, each embodiment What is stressed is all the difference with other embodiments, and identical similar part cross-reference is between each embodiment It can;The above various embodiments is only to illustrate the technical solution of the utility model, rather than its limitations;Although with reference to aforementioned each implementation The utility model is described in detail in example, it will be understood by those of ordinary skill in the art that:It still can be to aforementioned Technical solution recorded in each embodiment is modified, and either carries out equivalent replacement to which part or all technical features; And these modifications or replacements, the model for various embodiments of the utility model technical solution that it does not separate the essence of the corresponding technical solution It encloses.

Claims (10)

1. one kind facing bank subgrade support retainer structure, which is characterized in that including:Vertical mini pile tilts mini pile and barricade;It is described to incline Oblique mini pile is set to the offshore side of roadbed, and tilts and extend to roadbed offshore edge down from ground;The vertical mini pile It is set to the inclination side of the mini pile far from bank, and is vertically extended downwardly from ground;
The barricade is fixedly connected at the top of the vertical mini pile and the inclination mini pile.
2. according to claim 1 face bank subgrade support retainer structure, which is characterized in that the axis and lead for tilting mini pile Ranging from 15 ° -20 ° of angle between vertical line.
3. according to claim 1 face bank subgrade support retainer structure, which is characterized in that be provided in the vertical mini pile One steel pipe, first steel pipe extend along the length direction of the vertical mini pile, and the tube wall of first steel pipe is equipped with the One slurry outlet;
The second steel pipe is provided in the inclination mini pile, second steel pipe prolongs along the length direction for tilting mini pile It stretches, the tube wall of second steel pipe is equipped with the second slurry outlet.
4. according to claim 3 face bank subgrade support retainer structure, which is characterized in that the bank subgrade support retainer structure of facing includes The more inclination mini piles, the more mini piles that tilt are arranged along the length direction interval on bank;
The bank subgrade support retainer structure of facing includes multiple rows of vertical mini pile group, and it includes more banks often to arrange the vertical mini pile group The spaced vertical mini pile of length direction on side, multiple rows of vertical mini pile group is along from facing direction of the bank side to remote bank side Interval setting.
5. according to claim 4 face bank subgrade support retainer structure, which is characterized in that between the adjacent vertical mini pile Distance is 0.8m-1m.
6. facing bank subgrade support retainer structure according to claim 1-5 any one of them, which is characterized in that the separate bank of the barricade The side on side is provided with weight platform, and the weight platform is for carrying backfilled roadbed supported material.
7. according to claim 6 face bank subgrade support retainer structure, which is characterized in that the barricade is located on the weight platform Bank inclination is directed toward in the side of side from bottom to top, and bank inclination is directed toward in the side below weight platform from top to down.
8. facing bank subgrade support retainer structure according to claim 1-5 any one, which is characterized in that described to face bank subgrade support It further includes cushion cap to keep off structure, and the cushion cap is fixedly connected on the vertical mini pile and tilts the top of mini pile, the barricade It is fixed on the top of the cushion cap.
9. according to claim 8 face bank subgrade support retainer structure, which is characterized in that be both provided in the vertical mini pile First puts more energy into muscle, and the described first muscle of putting more energy into is extended to from the vertical mini pile in the cushion cap;
It is both provided with second in the inclination mini pile to put more energy into muscle, the described second muscle of putting more energy into is extended to from the inclination mini pile In the cushion cap.
10. according to claim 9 face bank subgrade support retainer structure, which is characterized in that in the every vertical mini pile Equipped with more described first muscle of putting more energy into, more described first muscle of putting more energy into are spaced apart along the periphery of the vertical mini pile, and The part bending outward that every described first muscle of putting more energy into is located in the cushion cap;
More described second muscle of putting more energy into are provided in the every inclination mini pile, more described second are put more energy into muscle along the inclination The periphery of mini pile is spaced apart, and the part bending outward that every described second muscle of putting more energy into is located in the cushion cap.
CN201820009180.3U 2018-01-03 2018-01-03 Face bank subgrade support retainer structure Expired - Fee Related CN207878200U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820009180.3U CN207878200U (en) 2018-01-03 2018-01-03 Face bank subgrade support retainer structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820009180.3U CN207878200U (en) 2018-01-03 2018-01-03 Face bank subgrade support retainer structure

Publications (1)

Publication Number Publication Date
CN207878200U true CN207878200U (en) 2018-09-18

Family

ID=63506547

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820009180.3U Expired - Fee Related CN207878200U (en) 2018-01-03 2018-01-03 Face bank subgrade support retainer structure

Country Status (1)

Country Link
CN (1) CN207878200U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109252542A (en) * 2018-11-14 2019-01-22 山东大学 A kind of root pile lightweight barricade and its construction method for road widening
CN115288170A (en) * 2022-09-16 2022-11-04 南昌航空大学 Construction method of integral repairing structure of landslide of riverside road

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109252542A (en) * 2018-11-14 2019-01-22 山东大学 A kind of root pile lightweight barricade and its construction method for road widening
CN115288170A (en) * 2022-09-16 2022-11-04 南昌航空大学 Construction method of integral repairing structure of landslide of riverside road

Similar Documents

Publication Publication Date Title
CN102966119B (en) Geogrid reinforced wall and construction method thereof
CN102635120B (en) Circular deep foundation ditch is without Construction of Supporting structure and construction method
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN103485363A (en) Three-dimensional continuous frame type reinforced concrete structure retaining wall
CN109440778A (en) Active inclined in two-way method for supporting and protecting row pile pit
CN109252542B (en) Tree root pile light retaining wall for road widening and construction method thereof
CN211200426U (en) Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall
CN207878200U (en) Face bank subgrade support retainer structure
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN107059592A (en) Pier construction method after a kind of first beam in cable-stayed bridge auxiliary pier pier top section
CN108978742A (en) One kind cutting stake forced-landing tilt correcting structure, method
CN218346137U (en) Foundation with strong bearing capacity
CN209066518U (en) A kind of constructing structure of section of stake forced-landing tilt correcting structure and miniature steel pipe pile
JP4029191B2 (en) Subsidence suppression structure, construction method of settlement suppression structure
CN208981337U (en) Tunnel immediately adjacent to bridge section deep foundation pit supporting structure
CN110924401A (en) Construction foundation pit supporting mode for combined arching and bearing of mixing piles and cast-in-place piles
CN109440781A (en) Active inclination foundation pit supporting method with double rows of piles
CN108487226A (en) Multisection type composite bushing punching press sandy pile construction engineering method
CN210507517U (en) Combined member suitable for retaining wall heightening
CN209538212U (en) A kind of anti-horizontal displacement radical combination soil-baffling structure
JP2022098713A (en) Foundation structure of structure, foundation construction method, and support pipe material used for foundation
CN207685842U (en) Foundation construction water proof cistern device
CN205171540U (en) A stock combination rock foundation builds in for transmission tower
CN212656215U (en) Assembled pipe support of cross prefabricated steel concrete pile and steel-pipe column combination
CN217811172U (en) Box culvert soft soil foundation structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180918