CN207868714U - One kind sending power transformation line construction driving - Google Patents
One kind sending power transformation line construction driving Download PDFInfo
- Publication number
- CN207868714U CN207868714U CN201820160231.2U CN201820160231U CN207868714U CN 207868714 U CN207868714 U CN 207868714U CN 201820160231 U CN201820160231 U CN 201820160231U CN 207868714 U CN207868714 U CN 207868714U
- Authority
- CN
- China
- Prior art keywords
- link
- pulley yoke
- bar
- power transformation
- pulley
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Electric Cable Installation (AREA)
Abstract
One kind sending power transformation line construction driving, is related to sending Substation construction technical field of tools, for solving the problems, such as that insulation gap stick installation existing in the prior art is inconvenient.One kind sending power transformation line construction driving, including lifting seat and link, the link is connected to the top of the front side for lifting seat, the upper end of the link is connected with pulley yoke, pulley is rotatably connected on pulley yoke, the link includes two perforation, spacer bar is equipped between two perforation, the leg of construction personnel can be passed through from the perforation.Advantageous effect is can to facilitate the installment work of insulation gap stick.
Description
Technical field
The utility model is related to send Substation construction technical field of tools, specifically one kind to send power transformation line construction to use and fly
Vehicle.
Background technology
Split conductor is a kind of technological means in extra high voltage network, and split conductor refers to extra high voltage network and is
Inhibit corona discharge and reduces a kind of wire erection mode that line reactance is taken.Split conductor includes multiply according between certain
Conducting wire away from branch.In order to ensure that keeping parallelism between different stock conducting wires, split conductor need to connect between different stock conducting wires
Insulation gap stick.
Existing form of construction work is that construction personnel straddles in horizontal two-wire line, or with a 1t coaster and safety
People is hung on conducting wire by band cooperation, and ground construction personnel are pulled with rope, reaches construction point high-altitude personnel and carries out conductor spacer
Installation, whole process with safety belt carries out two pipe protections.Construction efficiency is relatively low, and safety accident is easily caused when belt wear is serious,
Construction personnel is hung in aerial for a long time, be easy to cause that blood circulation is unsmooth, tired, and severe one is dizzy, and comfort level is bad, there is construction
Security risk.
So the prior art this there is a problem of that insulation gap stick installation is inconvenient.
Utility model content
The purpose of this utility model is to provide one kind sending power transformation line construction driving, is deposited in the prior art for solving
The inconvenient problem of insulation gap stick installation.
The technical solution adopted by the utility model to solve its technical problems is that:
One kind sending power transformation line construction driving, including lifts seat and link, and the link is connected to described lift
The top of the front side of seat, the upper end of the link is connected with pulley yoke, pulley, the link is rotatably connected on pulley yoke
It perforates including two, spacer bar is equipped between two perforation, the leg of construction personnel can be passed through from the perforation.
Further, the seat of lifting includes chassis and seat board, and seat board is connected to the upside of chassis, and the chassis is in frame
Structure.
Further, the lower end solid welding of the link is on the chassis.
Further, it is connected with bearing diagonal between the chassis and link.
Further, the pulley yoke is equipped with notch, and conducting wire can be placed into the bottom of the pulley from the position of notch
Portion, pulley yoke are removably connected with jam plate at the position positioned at notch, and jam plate can close notch.
Further, the upper end of the link is equipped with a bar, and the length direction of bar is along left and right directions
The centre position of setting, the bar is equipped with hanging ring, and hook, the pulley yoke and connection are rotatably connected on the pulley yoke
Frame is by linking up with the mating connection with hanging ring.
Further, the link is being respectively provided with a bar, each bar difference positioned at the top each perforated
In the low arc-shaped bend in intermediate high both sides, the link is equipped with hanging ring, institute at the position between two bars
It states and is rotatably connected to hook on pulley yoke, the pulley yoke and link are by linking up with the mating connection with hanging ring.
The utility model has the beneficial effects that:
One kind provided by the utility model send power transformation line construction driving, is carrying out sending power transformation with novel using this practicality
When the construction operation of circuit high-altitude, pulley is coordinated with high aerial conducting wire is erected at, to keep the utility model outstanding
It hangs on the conducting wire in high-altitude.Then construction personnel climbs the eminence to where the utility model for example, by transmission tower.Then
Left leg is placed through towards link in the perforation in left side by construction personnel, right leg is placed through in the perforation on right side.Then
Construction personnel, which is sitting in, to lift on seat.Construction personnel can slide in high-altitude along conducting wire and move ahead in this way, to convenient high aerial
The installment work for carrying out conductor spacer, to solve the problems, such as that insulation gap stick installation existing in the prior art is inconvenient.
Description of the drawings
Fig. 1 is the schematic diagram of the embodiment one of the utility model;
Fig. 2 is the A direction views of Fig. 1;
Fig. 3 is the schematic diagram of the embodiment two of the utility model;
Fig. 4 is the schematic diagram of the embodiment two of the utility model;
In figure:1 bearer carrier, 11 chassis, 12 seat boards, 2 links, 21 perforation, 22 spacer bars, 3 pulley yokes, 31 pulleys, 32
Hook, 33 jam plates, 4 bearing diagonals, 5 bars, 51 hanging rings.
Specific implementation mode
It is new below in conjunction with this practicality to keep the purpose, technical scheme and advantage of the utility model embodiment clearer
Attached drawing in type embodiment, the technical scheme in the utility model embodiment is clearly and completely described, it is clear that is retouched
The embodiment stated is a part of the embodiment of the utility model, instead of all the embodiments.Based on the reality in the utility model
Apply example, the every other embodiment that those of ordinary skill in the art are obtained without making creative work, all
Belong to the range of the utility model protection.
During to the description of the utility model, term "upper", "lower", " left side " and " right side " refer at the utility model
It is sitting in towards link when lifting on seat in working condition and technical staff, the side of the coordinate system at technical staff
Position relationship.Term "upper", "lower", " left side " and " right side ", are merely for convenience of describing the present invention and simplifying the description, without referring to
Show or imply that signified device or element must have a particular orientation, with specific azimuth configuration and operation, therefore cannot manage
Solution is limitations of the present invention.
Embodiment one:
As depicted in figs. 1 and 2, the utility model includes lifting seat 1 and link 2, and link 2, which is connected to, lifts seat 1
The upper end of the top of front side, link 2 is connected with pulley yoke 3.Pulley 31 is rotatably connected on pulley yoke 3, link 2 includes two
A perforation 21, is equipped with spacer bar 22 between two perforation 21, the leg of construction personnel can be passed through from perforation 21.
Using this practicality with it is novel send become electric line high-altitude construction operation when, by pulley 31 and be erected at height
Aerial conducting wire is coordinated, to make the utility model be hanging on the conducting wire in high-altitude.Then construction personnel passes through example
The eminence to where the utility model is climbed such as transmission tower.Then left leg is placed through left side by construction personnel towards link 2
In perforation 21, right leg is placed through in the perforation on right side.Then construction personnel, which is sitting in, lifts on seat 1.Construction personnel is just in this way
It can slide and move ahead in high-altitude along conducting wire, to convenient in the high aerial installment work for carrying out conductor spacer, to solve existing skill
The inconvenient problem of the installation of insulation gap stick present in art.This practicality newly lifts seat 1 by setting, improves construction personnel and exists
Comfort level during working at height.The utility model advantageously reduces the utility model high aerial by the way that link 2 is arranged
Shaking, ensure body steadiness degree of construction personnel when carrying out working at height, the easypro of construction personnel can also be improved
Suitable degree.
As depicted in figs. 1 and 2, it includes chassis 11 and seat board 12 to lift seat 1, and seat board 12 is connected to the upside of chassis 11, example
If seat board 12 is connected to by welding on chassis 11, for another example being arranged for across the hole of iron wire, seat on seat board 12
Plate 12 is bundled in by iron wire on chassis 11.Chassis 11 is in frame structure.The lower end solid welding of link 2 is on chassis 11.Chassis
Bearing diagonal 4 is connected between 11 and link.The utility model improves the intensity for lifting seat 1 by setting chassis 11, passes through
Level of comfort when seat board 12 ensure that construction personnel's seating is set.On chassis 11, this can be into for the lower end solid welding of link 2
The firmness for improving to one step the utility model, to further improve the safety coefficient of the utility model.Pass through setting
Bearing diagonal 4 further increases the firmness of the utility model.
As shown in Figure 1, pulley yoke 3 is equipped with notch, conducting wire can be placed into the bottom of pulley 31 from the position of notch,
Pulley yoke 3 is removably connected with jam plate 33 at the position positioned at notch, and jam plate 33 can close notch.Pulley yoke 3 passes through
Notch is set, and when the both ends of conducting wire are in stationary state, conducting wire can be still in place by notch in pulley
At position between frame 3 and pulley 31, to enable pulley 31 to coordinate with conducting wire;To facilitate the use of the utility model.Even
The upper end for connecing frame 2 is equipped with a bar 5, and the length direction of bar 5 is arranged along left and right directions, and the utility model is by setting
Bar 5 is set, construction personnel is facilitated to help, this can not only improve the level of comfort of work progress but also can also ensure that construction
The safety of personnel.The left and right ends of bar 5 are respectively provided with hanging ring 51, respectively connect on each hanging ring 51 there are one pulley yoke 3, each
Respectively there are one hooks 32 for rotation connection on pulley yoke 3, and respectively there are one pulley 31, pulley yoke 3 and connections for connection on each pulley yoke 3
The mating connection that frame 2 passes through hook 32 and hanging ring 51.Present embodiment by the way that two pulley yokes 3 and two pulleys 31 are arranged, from
And so that the left side at 2 top of this link can connect on a conducting wire, is connectable to another on the right side of the top of link 2
On bar conducting wire, to facilitate the utility model to be connected on be mutually parallel two conducting wires, be conducive to improve the utility model
Balance and safety.
Embodiment two:
Embodiment two is compared with embodiment one, the difference is that the installation position of hanging ring.
As shown in figure 3, the upper end of link 2 is equipped with a bar 5, the length direction of bar 5 is along left and right directions
The centre position of setting, the bar 5 is equipped with hanging ring 51, and hook 32, pulley yoke 3 and connection are rotatably connected on pulley yoke 3
The mating connection that frame 2 passes through hook 32 and hanging ring 51.
Present embodiment facilitates staff and is held hand steered at this when working at height by the way that bar 5 is arranged
In utility model.When construction personnel it is high be sitting in the air lift on seat 1 when, since present embodiment exists the setting of hanging ring 51
The middle position of bar 51, so under the effect of gravity, the utility model is located at conducting wire in lifting seat in the air high
The state of underface.Due to being only connected on a conducting wire there are one pulley at this time, so the sliding of pulley is smoothly at this time.
So present embodiment also ensures the smooth cunning of pulley in the case where ensureing the balance of the utility model in a state of use
It is dynamic.
Embodiment three:
Embodiment three is with embodiment one and embodiment two the difference is that the installation position of hanging ring and helping
The structure and quantity of hand lever.
As shown in figure 4, link 2 is being respectively provided with a bar 5 positioned at the top of each perforation 21, each bar 5 divides
It Cheng not the low arc-shaped bend in intermediate high both sides.Link 2 is equipped with hanging ring 51 at the position between two bars 5,
The mating connection of hook 32, pulley yoke 3 and link 2 by hook 32 and hanging ring 51 is rotatably connected on pulley yoke 3.
The position of hanging ring in present embodiment is conducive to ensureing the equilibrium state of the utility model when in use
Under the premise of improve pulley sliding smooth degree.The shape of bar 5 in present embodiment is conducive to further carry
The level of comfort of height work the utility model when in use.
Claims (8)
1. one kind sending power transformation line construction driving, characterized in that including lifting seat and link, the link is connected to institute
The top for the front side for lifting seat is stated, the upper end of the link is connected with pulley yoke, pulley is rotatably connected on pulley yoke, described
Link includes two perforation, spacer bar is equipped between two perforation, the leg of construction personnel can be worn from the perforation
It crosses.
2. one kind according to claim 1 send power transformation line construction driving, characterized in that the seat of lifting includes chassis
And seat board, seat board are connected to the upside of chassis, the chassis is in frame structure.
3. one kind according to claim 2 send power transformation line construction driving, characterized in that weld the lower end of the link
Gu on the chassis.
4. one kind according to claim 3 send power transformation line construction driving, characterized in that the chassis and link it
Between be connected with bearing diagonal.
5. one kind according to claim 1 send power transformation line construction driving, characterized in that the pulley yoke, which is equipped with, to be lacked
Mouthful, conducting wire can be placed into the bottom of the pulley from the position of notch, and pulley yoke is dismountable at the position positioned at notch
It is connected with jam plate, jam plate can close notch.
6. one kind according to claim 1 to 5 any one send power transformation line construction driving, characterized in that the company
The upper end for connecing frame is equipped with a bar, and the length direction of bar is arranged along left and right directions, the interposition of the bar
Hanging ring has been installed, hook, the pulley yoke and link are rotatably connected on the pulley yoke by linking up with the cooperation with hanging ring
Connection.
7. one kind according to claim 1 to 5 any one send power transformation line construction driving, characterized in that the company
The upper end for connecing frame is equipped with a bar, and the length direction of bar is arranged along left and right directions, the left and right two of the bar
End is respectively provided with hanging ring, respectively connects on each hanging ring there are one the pulley yoke, on each pulley yoke respectively rotation connection there are one hook,
Respectively there are one the pulley, pulley yoke and links by linking up with the mating connection with hanging ring for connection on each pulley yoke.
8. one kind according to claim 1 to 5 any one send power transformation line construction driving, characterized in that the company
It connects frame and is being respectively provided with a bar positioned at the top each perforated, each bar is in that the low arc-shaped in intermediate high both sides is curved respectively
Song, the link are equipped with hanging ring at the position between two bars, hook are rotatably connected on the pulley yoke,
The pulley yoke and link are by linking up with the mating connection with hanging ring.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820160231.2U CN207868714U (en) | 2018-01-30 | 2018-01-30 | One kind sending power transformation line construction driving |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820160231.2U CN207868714U (en) | 2018-01-30 | 2018-01-30 | One kind sending power transformation line construction driving |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207868714U true CN207868714U (en) | 2018-09-14 |
Family
ID=63459447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820160231.2U Active CN207868714U (en) | 2018-01-30 | 2018-01-30 | One kind sending power transformation line construction driving |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207868714U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110535064A (en) * | 2019-08-28 | 2019-12-03 | 南京驭逡通信科技有限公司 | A kind of electrician's high-voltage line running gear |
-
2018
- 2018-01-30 CN CN201820160231.2U patent/CN207868714U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110535064A (en) * | 2019-08-28 | 2019-12-03 | 南京驭逡通信科技有限公司 | A kind of electrician's high-voltage line running gear |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203924874U (en) | Attaching pole is from lifting appliance | |
CN102359303A (en) | Extra-high voltage common circuit iron tower assembling method | |
CN207868714U (en) | One kind sending power transformation line construction driving | |
CN203486730U (en) | Tool special for mobile box-type substation | |
CN104577870A (en) | Automatic obstacle-crossing type overhead earth wire pay-off tool for maintenance | |
CN206060035U (en) | A kind of releasing pulley hanger | |
CN206571133U (en) | A kind of Novel rod top workbench | |
CN209896574U (en) | High-altitude line sliding operation platform | |
CN203722136U (en) | Insulation rope net apparatus for railway crossing tension stringing construction | |
CN204243623U (en) | A kind of active obstacle type maintenance property-line driving | |
CN110329895A (en) | Large scale prefabricated piece of dedicated boom hoisting | |
CN204737645U (en) | Hoisting accessory | |
CN110159051A (en) | Substation framework | |
CN206117005U (en) | Get into used folding ladder of compact transmission line equipotential in -process | |
CN208883437U (en) | Cable channel cover plate device for opening | |
CN210156820U (en) | Aerial work platform for power transmission line maintenance | |
CN203922528U (en) | A kind of new type auto adjustment pole arm | |
CN203699783U (en) | Hanging bracket fixed with wire pole | |
CN209488740U (en) | A kind of chute with multiple mounting means | |
CN209338064U (en) | A kind of aerial lift device with insulated arm hydraulic lift | |
CN208753832U (en) | Transmitting coaster for extra high voltage network operation | |
CN205882554U (en) | Work platform on power line pole | |
CN208862471U (en) | Anchor support insulator chain overhauls mobile pedal | |
CN207218127U (en) | A kind of high intensity packway bar | |
CN207657178U (en) | A kind of TGXG tensioner |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |