CN207813086U - A kind of building band basis integral translation device - Google Patents
A kind of building band basis integral translation device Download PDFInfo
- Publication number
- CN207813086U CN207813086U CN201721743760.7U CN201721743760U CN207813086U CN 207813086 U CN207813086 U CN 207813086U CN 201721743760 U CN201721743760 U CN 201721743760U CN 207813086 U CN207813086 U CN 207813086U
- Authority
- CN
- China
- Prior art keywords
- steel beam
- structural steel
- bail
- translation device
- main body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of building band basis integral translation devices, including bail, winch and main body steelframe at a slow speed, the side of the winch at a slow speed is equipped with power motor, pulley blocks are connected with above support frame as described above, bail is installed on the inside of the pulley blocks, steel wire rope is installed at the center of the bail, it is provided with moving track above the main body steelframe, reaction support is installed above the structural steel beam, and oil pressure top is provided at the center of structural steel beam, the side of the main body steelframe is equipped with final limit device, traveling scale is installed at the center of the roller bearing, it is connected with mobile indicator below the traveling scale.The utility model is provided with final limit dress, can improve safety and reliability, while lowering risk, reduce cost;It is provided with mobile indicator, accurately response measurement can go out mobile track, angle, the data such as distance, and then improve the integrality of building band.
Description
Technical field
The utility model is related to technical field of buildings, specifically a kind of building band basis integral translation device.
Background technology
It is the quite high technology of a technology content to translate building, it is close building structure mechanics and Geotechnical Engineering
Combine, the weight during basic principle and lifting are carried moves horizontally similar, and main technical finesse is:By building
It is cut off in certain level face, so that it is detached with basis and become " weight " that can be moved;It is underpined in the setting of building cut-off part
Beam forms a removable joist;On setting new basis in place's in place;The setting walking track girder between new and old basis;Installation walking
Mechanism applies additionaling power and moves building;Walking mechanism is removed after in place and carries out up-down structure connection, has so far been translated
At.
Traditional building band is difficult to keep complete form in transformation process, thus can cause any property loss, environment
The social concerns such as pollution, it is therefore desirable to which a kind of building band basis integral translation device is for solving the above problems.
Utility model content
The purpose of this utility model is to provide a kind of dust-proof power distributing cabinet of building band basis integral translation device,
To solve the problems such as in the prior art.
To achieve the above object, the utility model provides the following technical solutions:A kind of building band basis integral translation dress
It sets, including bail, at a slow speed winch and main body steelframe, the side of the winch at a slow speed is equipped with power motor, described to twist at a slow speed
Supporting rack is installed above vehicle, pulley blocks are connected with above support frame as described above, traction is installed on the inside of the pulley blocks
Ring is equipped with steel wire rope at the center of the bail, moving track, the moving rail is provided with above the main body steelframe
Structural steel beam is installed above road, reaction support is installed, and set at the center of structural steel beam above the structural steel beam
It is equipped with oil pressure top, the side of the main body steelframe is equipped with final limit device, and the inside of the structural steel beam is equipped with roller bearing,
Traveling scale is installed at the center of the roller bearing, mobile indicator is connected with below the traveling scale.
The roller bearing is symmetrically distributed at left and right sides of the inside of structural steel beam.
Connection is engaged by gear between the pulley blocks and bail.
The upper of the structural steel beam intensive is provided with reaction support.
The mobile indicator uses laser positioning.
Compared with prior art, the utility model has the beneficial effects that:The utility model is scientific and reasonable for structure, safe to use
It is convenient, high-rise panning techniques are made full use of, do not interfere with the live and work order of the common people, and can be to a certain extent
Avoid and eliminate above-mentioned contradiction;By expense caused by translation, only accounting for the one third of reconstruction can save to 1/6th, one years
About tens yuans;It can also the valuable historical building of effective protection and history relic;It is for solving in urban construction
It inherits and provides a new approaches with the contradiction of development, be provided with final limit dress, it can be in building band translation motion, it is ensured that
It will not derail, and then improve safety and reliability, while lower risk, reduce cost;It is provided with mobile indicator, it can
Accurate response measurement goes out mobile track, angle, the data such as distance, and then improves the integrality of building band.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the sectional view of the utility model.
In figure:1- bails, 2- steel wire ropes, 3- pulley blocks, 4- supporting racks, 5- winch, 6- power motors, 7- counter-forces at a slow speed
Bearing, 8- oil pressure top, 9- final limits device, 10- structural steel beams, 11- moving tracks, 12- main bodys steelframe, 13- travelings scale,
14- roller bearings, 15- move indicator.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
The every other embodiment obtained, shall fall within the protection scope of the present invention.
Please refer to Fig.1~2, in the utility model embodiment, a kind of building band basis integral translation device, including traction
Ring 1, at a slow speed winch 5 and main body steelframe 12, at a slow speed the side of winch 5 power motor 6 is installed, at a slow speed winch 5 top installation
There are supporting rack 4, the top of supporting rack 4 to be connected with pulley blocks 3, the inside of pulley blocks 3 is equipped with bail 1, the center of bail 1
Place is equipped with steel wire rope 2, and the top of main body steelframe 12 is provided with moving track 11, and the top of moving track 11 is equipped with structure
The top of girder steel 10, structural steel beam 10 is equipped with reaction support 7, and oil pressure top 8 is provided at the center of structural steel beam 10, main
The side of body steelframe 12 is equipped with final limit device 9, and the inside of structural steel beam 10 is equipped with roller bearing 14, at the center of roller bearing 14
Traveling scale 13 is installed, the lower section of traveling scale 13 is connected with mobile indicator 15.Roller bearing 14 is symmetrically distributed in structural steel beam
At left and right sides of 10 inside.Connection is engaged by gear between pulley blocks 3 and bail 1.The upper intensive of structural steel beam 10 is set
It is equipped with reaction support 7.Mobile indicator 15 uses laser positioning.
The operation principle of the utility model is the building band basis integral translation device, examine first poor draft gear and
The performance and state of power plant, and then ensure that it can safely and efficiently work, reinforcing that original building becomes first can
Moving body, and new basis is set.Moving track 11 and reaction support 7 are installed;Track must be horizontal when building translation, to reduce
Frictional resistance;And it can be with the active force in 7 moving process of reaction support;6 running parameter of power motor is set, and power motor 6 passes through
Bail 1, steel wire rope 2, pulley blocks 3, which form, pulls the dynamical system of building, and traction bearing network oil pressure top 8 provides enough anti-
Power can just enable building to move, and the quantity for drawing bearing needs to determine by calculating;Advance system is referred to by traveling scale 13, movement
Show needle 11 and 9 three parts of final limit device composition.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and
And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this practicality is new in other specific forms
Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this practicality is new
The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing in the equivalent requirements of the claims will be fallen
All changes in justice and range are embraced therein.Any reference numeral in claim should not be considered as limitation
Involved claim.
Claims (5)
1. a kind of building band basis integral translation device, including bail(1), winch at a slow speed(5)With main body steelframe(12), institute
State winch at a slow speed(5)Side power motor is installed(6), the winch at a slow speed(5)Top supporting rack is installed(4), institute
State supporting rack(4)Top be connected with pulley blocks(3), the pulley blocks(3)Inside bail is installed(1), the traction
Ring(1)Center at steel wire rope is installed(2), the main body steelframe(12)Top be provided with moving track(11), the shifting
Dynamic rail road(11)Top structural steel beam is installed(10), the structural steel beam(10)Top reaction support is installed(7), and
Structural steel beam(10)Center at be provided with oil pressure top(8), the main body steelframe(12)Side final limit device is installed
(9), the structural steel beam(10)Inside roller bearing is installed(14), the roller bearing(14)Center at traveling scale is installed
(13), the traveling scale(13)Lower section be connected with mobile indicator(15).
2. a kind of building band basis according to claim 1 integral translation device, it is characterised in that:The roller bearing(14)
It is symmetrically distributed in structural steel beam(10)Inside at left and right sides of.
3. a kind of building band basis according to claim 1 integral translation device, it is characterised in that:The pulley blocks
(3)With bail(1)Between pass through gear engagement connection.
4. a kind of building band basis according to claim 1 integral translation device, it is characterised in that:The structural steel beam
(10)Upper intensive be provided with reaction support(7).
5. a kind of building band basis according to claim 1 integral translation device, it is characterised in that:The mobile instruction
Needle(15)Using laser positioning.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721743760.7U CN207813086U (en) | 2017-12-14 | 2017-12-14 | A kind of building band basis integral translation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721743760.7U CN207813086U (en) | 2017-12-14 | 2017-12-14 | A kind of building band basis integral translation device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207813086U true CN207813086U (en) | 2018-09-04 |
Family
ID=63332989
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721743760.7U Expired - Fee Related CN207813086U (en) | 2017-12-14 | 2017-12-14 | A kind of building band basis integral translation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207813086U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914850A (en) * | 2019-03-27 | 2019-06-21 | 山东建固特种专业工程有限公司 | A kind of transport building instruction device in place and method |
CN112282422A (en) * | 2020-10-15 | 2021-01-29 | 深圳市众安工程技术有限公司 | Integral translation device with foundation for building |
-
2017
- 2017-12-14 CN CN201721743760.7U patent/CN207813086U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914850A (en) * | 2019-03-27 | 2019-06-21 | 山东建固特种专业工程有限公司 | A kind of transport building instruction device in place and method |
CN112282422A (en) * | 2020-10-15 | 2021-01-29 | 深圳市众安工程技术有限公司 | Integral translation device with foundation for building |
CN112282422B (en) * | 2020-10-15 | 2022-03-29 | 深圳市众安工程技术有限公司 | Integral translation device with foundation for building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207813086U (en) | A kind of building band basis integral translation device | |
CN105002831A (en) | Wheel-rail type loading and traveling cable crane | |
CN204510844U (en) | A kind of large-span steel girder high-altitude mounting slip device | |
CN203998646U (en) | Walking tower crane traveling gear | |
CN204608602U (en) | Novel bridge maintenance protection installation work car | |
CN202429889U (en) | Crane travel mechanism for bridge crane | |
CN204873485U (en) | River course is bridge crane usefulness walking portal frame for pier | |
CN207276051U (en) | Gantry crane transverse translation flat car | |
CN204057678U (en) | Hoisting crane hook structure | |
CN203498743U (en) | Railway concrete continuous beam implemented on basis of flat pushing method | |
CN203877728U (en) | Bridge type lifting hanging mechanism for hydropower station | |
CN110777666A (en) | Steel box girder construction platform and use method | |
CN209602035U (en) | A kind of operation platform for waterproof and Drainage Construction of Tunnel | |
CN205998891U (en) | Harbour gantry with cruise beacon | |
CN109555537A (en) | A kind of lining of railway tunnel two construction working rig | |
CN209654054U (en) | A kind of lining of railway tunnel two construction working rig | |
CN205116006U (en) | High -speed railway bridge longmen walking maintenance detection device | |
CN204875543U (en) | Wheel rail formula load walking cable carries loop wheel machine | |
CN203558725U (en) | Moving device for gantry crane | |
CN209853591U (en) | Insulating protective door type hoisting device used in case of insufficient safety clearance under high-voltage line | |
CN208632957U (en) | A kind of novel steel truss bridge inspection device | |
CN104071687B (en) | Power station overhead traveling crane mechanism | |
CN205822024U (en) | A kind of mountainous area highway moves beam device | |
CN203639822U (en) | Vertical truss of principal rafter inspection trolley | |
CN202449760U (en) | Container portal crane with rails |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180904 Termination date: 20201214 |
|
CF01 | Termination of patent right due to non-payment of annual fee |