CN207812508U CN201721731692.2U CN201721731692U CN207812508U CN 207812508 U CN207812508 U CN 207812508U CN 201721731692 U CN201721731692 U CN 201721731692U CN 207812508 U CN207812508 U CN 207812508U
Authority
CN
China
Prior art keywords
cast strip
post
screw rod
fixed
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721731692.2U
Other languages
Chinese (zh)
Inventor
***强
温向东
周作良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201721731692.2U priority Critical patent/CN207812508U/en
Application granted granted Critical
Publication of CN207812508U publication Critical patent/CN207812508U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

A formwork supporting device for a basement exterior wall post-cast strip comprises a plurality of L-shaped fixing bolts, oppositely-pulled fixing screws, turnover screws, secondary keels and main keels, wherein one sides of the L-shaped fixing bolts are fixedly arranged in a precast concrete slab fixed on the outer side of the post-cast strip, the other sides of the L-shaped fixing bolts are connected with one ends of the oppositely-pulled fixing screws, one ends of the turnover screws penetrate through the inner side formwork of the post-cast strip and are connected with the other ends of the oppositely-pulled fixing bolts, and the other ends of the turnover screws penetrate through the main keels and are fixed through fixing nuts.

Description

Poured band of outer wall of basement formwork erection device
Technical field
The utility model belongs to architecture construction field, more particularly to a kind of poured band of outer wall of basement formwork erection dress It sets.
Background technology
The basement of megastore's class building is often long, to reduce the crack generated by concrete shrinkage, building Post-cast strip will be arranged in structure.Post-cast strip set aside some time it is longer, for ensure basement on the outside of the earthwork can backfill in advance, need Using building brick fetal membrane by laying bricks or stones or building groove profile piled bricks by laying bricks or stones on the outside of post-cast strip, inner side template is then installed.It such as uses on the outside of post-cast strip and builds The method for building brick fetal membrane, the template on the inside of post-cast strip can not fix, frequent occurrence the problems such as swollen mould, spillage;Such as outside post-cast strip Side builds supporting module after groove profile piled bricks by laying bricks or stones, not only wastes material, but also labor intensive.
Invention content
The purpose of this utility model, which is that, overcomes above-mentioned the deficiencies in the prior art, and provides outside a kind of basement Wall alter-pouring strips mould plate installs device, can easily fix post-cast strip inner side template using the device, avoid the swollen mould of template and spillage The phenomenon that and can save manpower, save material.
As above design, the technical solution of the utility model are:A kind of poured band of outer wall of basement formwork erection device, it is special Sign is:Including multiple " L " fixing bolts, to drawing standing screw, turnover screw rod, secondary joist and main joist;The multiple " L " shape Fixing bolt is packed on one side in the precast slab being fixed on the outside of post-cast strip, another side and one to drawing standing screw End connection;One end of the turnover screw rod passes through post-cast strip inner side template with to drawing the other end of fixing bolt to connect, and has enough to meet the need spiral shell The other end of bar passes through main joist and is fixed by fixing nut.
Secondary joist is set between above-mentioned post-cast strip inner side template and main joist.
It is above-mentioned to drawing seal ring to be installed in the middle part of standing screw.
It is above-mentioned identical as post-cast strip thickness to the length for drawing standing screw.
The junction installed plug of above-mentioned turnover screw rod and post-cast strip inner side template.
The utility model has the following advantages and good effect:
1, " L " shape fixing bolt is fixed in the precast slab on the outside of post-cast strip by the utility model in advance, after making The fixed form with inner side template is poured to simplify.Post-cast strip inner side template is fixed in a manner of to drawing simultaneously, makes side form in post-cast strip Plate is more firm, and gap smaller not only easily solves the problems, such as that post-cast strip inner side template can not fix, and especially post-cast strip is high The position at place, and avoid the hidden danger that swollen mould, spillage occur for template.
2, the utility model can be such that post-cast strip inner side template reinforces in place, to ensure that construction quality, reduce maintenance cost With, save operating expenses.
3, the utility model post-cast strip inner side template is fixed using the turnover screw rod and fixing nut that can be had enough to meet the need, and is eliminated numerous Trivial shores construction material.The precast slab used on the outside of post-cast strip saves unnecessary piled bricks material when template uses.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Specific implementation mode
As shown in the figure:A kind of poured band of outer wall of basement formwork erection device, by multiple " L " shape fixing bolts 1, to drawing admittedly Determine screw rod 3, turnover screw rod 7, secondary joist 9 and main joist 10 to form.The multiple being packed on one side for " L " fixing bolt is fixed on In precast slab 2 on the outside of post-cast strip, another side and one end to drawing standing screw 3 are affixed;The one of the turnover screw rod 7 It holds across post-cast strip inner side template 6 with to drawing the other end of fixing bolt 3 to tighten, the other end of turnover screw rod 7 passes through main joist It 10 and is fixed by fixing nut 8.Secondary joist 9 is set between above-mentioned post-cast strip inner side template 6 and main joist 10.It is above-mentioned solid to drawing The length for determining screw rod 3 is identical as post-cast strip thickness, and seal ring 4 is installed at its middle part.In above-mentioned turnover screw rod 7 and post-cast strip The junction installed plug 5 of side template 6.
The operating process of the utility model is:
1, in precast slab 2, multiple " L " shape fixing bolts 1 are fixed on according to the size sequenced in advance prefabricated In concrete slab 2;
2, it after the molding of precast slab 2 reaches intensity, is fixed on the outside of post-cast strip;
3, selection it is consistent with post-cast strip thickness to drawing fixing bolt 3, to drawing 3 two ends inner band of fixing bolt 7 one end of turnover screw rod is tightened in one end to drawing fixing bolt 3 by silk, then will be to drawing 3 other end of fixing bolt be anchored on On " L " shape fixing bolt 1;
4, it is poured after being then placed within according to the arrangement size jewel hole of " L " shape fixing bolt 1 in post-cast strip inner side template 6 Band inside;
5, mating fixing nut 8 is selected, main joist and secondary joist is processed, post-cast strip inner side template 6 is fixed.

Claims (5)

1. a kind of poured band of outer wall of basement formwork erection device, it is characterised in that:Including multiple " L " fixing bolts, to drawing admittedly Determine screw rod, turnover screw rod, secondary joist and main joist;The multiple being packed on one side for " L " shape fixing bolt is fixed on post-cast strip In the precast slab in outside, another side is connect with one end to drawing standing screw;After one end of the turnover screw rod passes through It pours with inner side template with to drawing the other end of fixing bolt to connect, the other end for having enough to meet the need screw rod passes through main joist and by fixed spiral shell Mother is fixed.
2. poured band of outer wall of basement formwork erection device according to claim 1, it is characterised in that:In above-mentioned post-cast strip Secondary joist is set between side template and main joist.
3. poured band of outer wall of basement formwork erection device according to claim 1, it is characterised in that:It is above-mentioned to be fixed to drawing Seal ring is installed in the middle part of screw rod.
4. poured band of outer wall of basement formwork erection device according to claim 1, it is characterised in that:It is above-mentioned to be fixed to drawing The length of screw rod is identical as post-cast strip thickness.
5. poured band of outer wall of basement formwork erection device according to claim 1, it is characterised in that:Above-mentioned turnover screw rod With the junction installed plug of post-cast strip inner side template.
CN201721731692.2U 2017-12-13 2017-12-13 Basement outer wall post-cast strip template supporting device Active CN207812508U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721731692.2U CN207812508U (en) 2017-12-13 2017-12-13 Basement outer wall post-cast strip template supporting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721731692.2U CN207812508U (en) 2017-12-13 2017-12-13 Basement outer wall post-cast strip template supporting device

Publications (1)

Publication Number Publication Date
CN207812508U true CN207812508U (en) 2018-09-04

Family

ID=63332109

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721731692.2U Active CN207812508U (en) 2017-12-13 2017-12-13 Basement outer wall post-cast strip template supporting device

Country Status (1)

Country Link
CN (1) CN207812508U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080520A (en) * 2019-05-27 2019-08-02 中建四局第三建筑工程有限公司 A kind of post-cast strip is without support shuttering constructing device and method
CN111441467A (en) * 2020-04-10 2020-07-24 中国十七冶集团有限公司 Basement outer wall post-cast strip pouring front-block anti-seepage component and construction method
CN114016412A (en) * 2021-11-03 2022-02-08 中交二航局广西建设工程有限公司 Construction method for integral post-cast cross beam of T-beam expansion joint

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080520A (en) * 2019-05-27 2019-08-02 中建四局第三建筑工程有限公司 A kind of post-cast strip is without support shuttering constructing device and method
CN111441467A (en) * 2020-04-10 2020-07-24 中国十七冶集团有限公司 Basement outer wall post-cast strip pouring front-block anti-seepage component and construction method
CN114016412A (en) * 2021-11-03 2022-02-08 中交二航局广西建设工程有限公司 Construction method for integral post-cast cross beam of T-beam expansion joint

Similar Documents

Publication Publication Date Title
CN207812508U (en) Basement outer wall post-cast strip template supporting device
CN104947719B (en) The rear pouring tape construction method of formwork erecting structure is hung in basement roof post-cast strip
CN103306501B (en) Energy-saving domestic architecture with cast-in-place industrial gypsum bearing wall and manufacturing method thereof
CN209555978U (en) A kind of cast-in-situ steel reinforced concrete manhole shaft shaping combined steel shuttering
CN206616862U (en) Formwork root bracing means
CN204040078U (en) A kind of alter-pouring strips mould plate installs structure
CN205530344U (en) Utility tunnel is pour to split type no mould
CN205201748U (en) Pour mould of cylindrical mortar test piece
CN203768946U (en) Assembled prefabricated comprehensive pipe rack
CN208343121U (en) Prefabricated assembled steel structure concrete wallboard mould
CN205875736U (en) Sectional type shear force wall is to drawing sealing screw
CN207177286U (en) Add region mould after fabricated shear wall is reserved
CN206457938U (en) A kind of complete bolted steel-combined concrete shear wall assembled module
CN106760173B (en) Prefabricated plate at post-pouring zone of basement outer wall
CN219080981U (en) Non-support fixing device for post-pouring strip of superimposed sheet
CN105256923B (en) Light gauge steel partition wall keel fixed connector
CN208055784U (en) construction site assembled hardened ground
CN109025173A (en) A kind of air channel structure and its construction method
CN205100552U (en) Enclosure assembling die that bears down on one
CN213927514U (en) Plug for two end parts of oppositely-pulling screw rod of building template
CN204941567U (en) A kind of structure accelerating construction of tunnel vault pouring concrete speed
CN211173065U (en) Basement outer wall construction joint anti-seepage template structure
CN208586628U (en) A kind of detachable open caisson reserved holes of pipes mouth template structure
CN202148687U (en) Building template forming structure and fastening piece
CN209556285U (en) A kind of air channel structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant