CN207812460U - A kind of pattern foundation pit supporting structure support changing structure for use - Google Patents

A kind of pattern foundation pit supporting structure support changing structure for use Download PDF

Info

Publication number
CN207812460U
CN207812460U CN201820133530.7U CN201820133530U CN207812460U CN 207812460 U CN207812460 U CN 207812460U CN 201820133530 U CN201820133530 U CN 201820133530U CN 207812460 U CN207812460 U CN 207812460U
Authority
CN
China
Prior art keywords
foundation pit
lifting
vertical wall
power
backfill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820133530.7U
Other languages
Chinese (zh)
Inventor
黄晨亮
刘淑清
孟娇娇
李磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820133530.7U priority Critical patent/CN207812460U/en
Application granted granted Critical
Publication of CN207812460U publication Critical patent/CN207812460U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a kind of pattern foundation pit supporting structure support changing structure for use, including foundation pit bottom, unload power backfill, the first waist rail, the second waist rail, bored concrete pile, the vertical wall of lifting and fixed pedestal, the top of the foundation pit bottom is equipped with concrete cushion, the side of the power of the unloading backfill far from concrete cushion is equipped with bored concrete pile, the bored concrete pile is equipped with the first waist rail, the second waist rail and Guan Liang successively from top to bottom close to the side for unloading power backfill, the fixed pedestal is equipped with fixed lifting gear, and the lower end both sides of the vertical wall of lifting are equipped with fastening gag lever post.The utility model forms stress check calculation system by structures such as oblique steel pipe, inner support frame and each waist rails, and cooperation unloads the structures power transmission such as power backfill and load transfering strip and unloads power, stress check calculation system is set more to stablize, and it is safe and reliable, it lifts vertical wall cooperation lifting limit hole and fastening gag lever post carries out fastening limit, construction efficiency is improved, and manufacturing cost is low.

Description

A kind of pattern foundation pit supporting structure support changing structure for use
Technical field
The utility model is related to technical field of building construction, specially a kind of pattern foundation pit supporting structure support changing structure for use.
Background technology
With the increase of present urban population, more and more people start to focus on the exploitation underground space, but underground engineering Complex geologic conditions form new excavated section after especially excavating, destroy the stability of rock mass original structure, hold in construction The safety accidents such as come down, cave in easily occur, above-mentioned safety accident occurs in order to prevent, need to carry out supporting to foundation pit, it is big at present Most support patterns are all to carry out supporting with piled anchor, must be used at a certain distance on the waist rail of bored concrete pile anchor cable or anchor pole into Row supporting, cost is higher, and speed of application is slow, and efficiency is low, and pattern foundation pit supporting structure support changing structure for use also is complex, influences main body knot Structure is continuously constructed, and which increases the costs of construction, while extending the construction period.
Utility model content
The purpose of this utility model is to provide a kind of pattern foundation pit supporting structure support changing structure for use, to solve to propose in above-mentioned background technology The problem of.
To achieve the above object, the utility model provides the following technical solutions:A kind of pattern foundation pit supporting structure support changing structure for use, including base Hole bottom unloads power backfill, the first waist rail, the second waist rail, bored concrete pile, the vertical wall of lifting and fixed pedestal, the foundation pit bottom The top of layer is equipped with concrete cushion, and the top of concrete cushion is equipped with fixed pedestal, and foundation pit bottom is close to concrete cushion Side be equipped with and unload power backfill, the top of the power of the unloading backfill is equipped with load transfering strip, unloads power backfill far from concrete cushion Side be equipped with bored concrete pile, and one end of load transfering strip is connected with bored concrete pile, the close side for unloading power backfill of the bored concrete pile from Under to it is upper successively be equipped with the first waist rail, the second waist rail and Guan Liang, side and oblique steel of first waist rail far from bored concrete pile One end of pipe is fixedly connected, and the other end of oblique steel pipe is fixedly connected with concrete cushion, and the fixed pedestal is equipped with solid The inside determined lifting gear, and fix lifting gear, which is run through, the vertical wall of lifting, the lower end both sides of the vertical wall of lifting It is equipped with fastening gag lever post, side of the upper end far from bored concrete pile for lifting vertical wall is equipped with horizontal equilibrium frame, second waist Between side of the beam far from bored concrete pile is flexibly connected by chimeric end with one end of inner support frame, and the other end of inner support frame passes through Spacing body is flexibly connected with vertical wall is lifted.
Preferably, the lifting limit hole to match with fastening gag lever post is offered on the fixed lifting gear, and is fastened Gag lever post is dismounting helix structure.
Preferably, injected hole is offered on the outside of the upper end of the oblique steel pipe, and the waist of oblique steel pipe and load transfering strip The other end is connected.
Preferably, it is fixedly connected by built-in fitting between the concrete cushion and foundation pit bottom, and built-in fitting uniformly divides It is distributed in the both sides of fixed pedestal.
Preferably, the inner homogeneous of the inner support frame is equipped with horizontal stiffener, and lifts the inner homogeneous of vertical wall Equipped with vertical strengthening ribs.
Compared with prior art, the utility model has the beneficial effects that:The utility model is simple in structure, by oblique steel Reperfusion serosity supports bored concrete pile in pipe, while coordinating the respective outer side edges such as the vertical wall of lifting, inner support frame and each waist rail, Guan Liang It uses, forms stress check calculation system, and cooperation unloads the progress power transmission of the structures such as power backfill and load transfering strip and unloads power etc., utilizes simultaneously The dead weight of slurries makes stress check calculation system more stablize, securely and reliably, it can be ensured that the safety of construction personnel, also lifting are vertical The lifting limit hole and fastening gag lever post opened up on the fixed lifting gear of wall cooperation carries out fastening limit, easy to use, carries High construction efficiency, and manufacturing cost is low, is suitable for large-scale promotion application.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is another structural schematic diagram of the utility model;
In figure:1- foundation pit bottoms;2- built-in fittings;3- concrete cushions;The oblique steel pipes of 4-;5- unloads power backfill;6- power transmissions Band;7- injected holes;The first waist rails of 8-;The second waist rails of 9-;10- bored concrete piles;11- Guan Liangs;The chimeric ends 12-;13- inner support frames;14- Lift vertical wall;15- horizontal equilibrium framves;16- lifts limit hole;17- fixes lifting gear;18- fastens gag lever post;19- is solid Determine pedestal;20- spacers.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
- 2 are please referred to Fig.1, a kind of embodiment provided by the utility model:A kind of pattern foundation pit supporting structure support changing structure for use, including foundation pit Bottom 1 unloads power backfill 5, the first waist rail 8, the second waist rail 9, bored concrete pile 10, the vertical wall 14 of lifting and fixed pedestal 19, base Cheat bottom 1 top be equipped with concrete cushion 3, and the top of concrete cushion 3 be equipped with fixed pedestal 19, concrete cushion 3 with It is fixedly connected by built-in fitting 2 between foundation pit bottom 1, and built-in fitting 2 is uniformly distributed in the both sides of fixed pedestal 19, foundation pit bottom 1 close to the side of concrete cushion 3 be equipped with unload power backfill 5, unload power backfill 5 top be equipped with load transfering strip 6, unload power backfill 5 sides far from concrete cushion 3 are equipped with bored concrete pile 10, and one end of load transfering strip 6 is connected with bored concrete pile 10, and bored concrete pile 10 is close The side for unloading power backfill 5 is equipped with the first waist rail 8, the second waist rail 9 and Guan Liang 11 successively from top to bottom, and the first waist rail 8 is separate The side of bored concrete pile 10 is fixedly connected with one end of oblique steel pipe 4, and the other end of oblique steel pipe 4 is fixed with concrete cushion 3 The upper end outside of connection, oblique steel pipe 4 offers injected hole 7, and the waist of oblique steel pipe 4 is connected with the other end of load transfering strip 6, Fixed pedestal 19, which is equipped with the inside fixed lifting gear 17, and fix lifting gear 17, which to be run through, the vertical wall 14 of lifting, Gu Determine to offer the lifting limit hole 16 to match with fastening gag lever post 18 on lifting gear 17, and fastens gag lever post 18 and torn open for spiral Structure is unloaded, the lower end both sides for lifting vertical wall 14 are equipped with fastening gag lever post 18, lift the upper end of vertical wall 14 far from filling The side for noting stake 10 is equipped with horizontal equilibrium frame 15, and the second side of the waist rail 9 far from bored concrete pile 10 passes through chimeric end 12 and inner support One end of frame 13 is flexibly connected, and the other end of inner support frame 13 is flexibly connected by spacer 20 with vertical wall 14 is lifted, The inner homogeneous of inner support frame 13 is equipped with horizontal stiffener, and the inner homogeneous for lifting vertical wall 14 is equipped with vertical strengthening ribs.
Specifically used mode:When using utility model works, by injected hole 7 to injecting slurries inside oblique steel pipe 4, And then the first waist rail 8 and bored concrete pile 10 are supported, and lift vertical wall 14, interior using the cooperation of its own gravity of slurries The structures such as supporting rack 13 and each waist rail, Guan Liang 11 form stress check calculation system, while utilizing and unloading power backfill 5 and load transfering strip The structures such as 6 carry out power transmission and unload power, and carry out the backfill of soil, at the same time by fixed lifting gear 17 to lifting vertical wall Body 14 is lifted, and carries out fastening limit using fastening gag lever post 18, and certain height is reached when lifting vertical wall 14 When, the spacer 20 on the second waist rail 9 is abutted with vertical wall 14 is lifted, and cooperation horizontal equilibrium frame 15 forms the second stress Converting system avoids the generation for phenomenon of caving in.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this practicality is new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this practicality is new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing in the equivalent requirements of the claims will be fallen All changes in justice and range are embraced therein.Any reference numeral in claim should not be considered as limitation Involved claim.

Claims (5)

1. a kind of pattern foundation pit supporting structure support changing structure for use, including foundation pit bottom (1), unload power backfill (5), the first waist rail (8), the second waist rail (9), bored concrete pile (10), the vertical wall (14) of lifting and fixed pedestal (19), it is characterised in that:The foundation pit bottom (1) it is upper Side is equipped with concrete cushion (3), and the top of concrete cushion (3) is equipped with fixed pedestal (19), and foundation pit bottom (1) is close to coagulation The side of soil padding (3), which is equipped with, unloads power backfill (5), and the top of the power of the unloading backfill (5) is equipped with load transfering strip (6), unloads power and returns The side of (5) far from concrete cushion (3) of banketing is equipped with bored concrete pile (10), and one end of load transfering strip (6) and bored concrete pile (10) phase Even, the bored concrete pile (10) is equipped with the first waist rail (8), the second waist rail successively from top to bottom close to the side for unloading power backfill (5) (9) and company is fixed in Guan Liang (11), side of first waist rail (8) far from bored concrete pile (10) and one end of oblique steel pipe (4) It connects, and the other end of oblique steel pipe (4) is fixedly connected with concrete cushion (3), the fixed pedestal (19) is equipped with fixed rise Falling unit (17), and the inside of fixed lifting gear (17) is through having the vertical wall (14) of lifting, the vertical wall of lifting (14) lower end both sides are equipped with fastening gag lever post (18), lift side of the upper end far from bored concrete pile (10) of vertical wall (14) Equipped with horizontal equilibrium frame (15), side of second waist rail (9) far from bored concrete pile (10) passes through chimeric end (12) and inner support One end of frame (13) is flexibly connected, and the other end of inner support frame (13) is lived by spacer (20) with vertical wall (14) is lifted Dynamic connection.
2. a kind of pattern foundation pit supporting structure support changing structure for use according to claim 1, it is characterised in that:The fixed lifting gear (17) On offer with fastening gag lever post (18) the lifting limit hole (16) that matches, and it is dismounting helix knot to fasten gag lever post (18) Structure.
3. a kind of pattern foundation pit supporting structure support changing structure for use according to claim 1, it is characterised in that:The oblique steel pipe (4) it is upper End outside offers injected hole (7), and the waist of oblique steel pipe (4) is connected with the other end of load transfering strip (6).
4. a kind of pattern foundation pit supporting structure support changing structure for use according to claim 1, it is characterised in that:The concrete cushion (3) with It is fixedly connected by built-in fitting (2) between foundation pit bottom (1), and built-in fitting (2) is uniformly distributed in the both sides of fixed pedestal (19).
5. a kind of pattern foundation pit supporting structure support changing structure for use according to claim 1, it is characterised in that:The inner support frame (13) it is interior Portion is uniformly provided with horizontal stiffener, and the inner homogeneous for lifting vertical wall (14) is equipped with vertical strengthening ribs.
CN201820133530.7U 2018-01-26 2018-01-26 A kind of pattern foundation pit supporting structure support changing structure for use Expired - Fee Related CN207812460U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820133530.7U CN207812460U (en) 2018-01-26 2018-01-26 A kind of pattern foundation pit supporting structure support changing structure for use

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820133530.7U CN207812460U (en) 2018-01-26 2018-01-26 A kind of pattern foundation pit supporting structure support changing structure for use

Publications (1)

Publication Number Publication Date
CN207812460U true CN207812460U (en) 2018-09-04

Family

ID=63325195

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820133530.7U Expired - Fee Related CN207812460U (en) 2018-01-26 2018-01-26 A kind of pattern foundation pit supporting structure support changing structure for use

Country Status (1)

Country Link
CN (1) CN207812460U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109868826A (en) * 2019-03-13 2019-06-11 温州开源建设工程有限公司 A kind of well-set foundation pit and its earthwork digging method
CN112593560A (en) * 2020-11-23 2021-04-02 上海建工二建集团有限公司 Supporting beam replacing structure between supporting pile and basement outer wall and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109868826A (en) * 2019-03-13 2019-06-11 温州开源建设工程有限公司 A kind of well-set foundation pit and its earthwork digging method
CN112593560A (en) * 2020-11-23 2021-04-02 上海建工二建集团有限公司 Supporting beam replacing structure between supporting pile and basement outer wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN101240550A (en) Construction method for lattice type steel column tower crane pedestal
CN203654294U (en) Foundation pit supporting structure used in reverse building method
CN207812460U (en) A kind of pattern foundation pit supporting structure support changing structure for use
CN105155602A (en) Multi-support foundation strengthening comprehensive controlling method
CN104652475A (en) Truss type retaining wall
CN104790412A (en) Large-width foundation pit supporting construction method under confined water condition
CN101851923B (en) Support pillar construction and erection method
CN203977432U (en) Multistage H type soil blocking pile
CN211200437U (en) Oblique vertical bracing combined type foundation structure of arch bridge
CN203821399U (en) Deep foundation pit supporting structure
CN203625911U (en) Soil discharging construction structure with pit-in-pit door opening arranged in deep foundation pit
CN203498863U (en) Three-dimensional continuous-frame-type reinforced concrete structural retaining wall
CN206887980U (en) A kind of integrated bracket basis of antifreeze pile
CN202767281U (en) Assembly type reinforced concrete combination back wall
CN201722700U (en) Infrastructure of tower crane
CN210086193U (en) Rock-fill dam spillway based on concrete pile supports
CN212582702U (en) Lifting type deep foundation pit supporting device
CN203846494U (en) Breast beam soil anchor rod segmented connection structure
CN203603162U (en) Construction elevator load basic system based on foundation pit edge
CN112411618A (en) Grass planting type precast concrete retaining wall
CN104328794B (en) A kind of narrow base tower four lower limb associating well foundation
CN201896319U (en) Conversion platform for connecting tower crane basic section with steel lattice piles
CN206646523U (en) A kind of Sloping equipment
CN204626419U (en) Large width foundation pit supporting construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180904