CN207622331U CN201721641908.6U CN201721641908U CN207622331U CN 207622331 U CN207622331 U CN 207622331U CN 201721641908 U CN201721641908 U CN 201721641908U CN 207622331 U CN207622331 U CN 207622331U
Authority
CN
China
Prior art keywords
gas
chamber
cooling chamber
gas cooling
suction pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721641908.6U
Other languages
Chinese (zh)
Inventor
张凡飞
魏纲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Peace Power Machinery Co Ltd
Original Assignee
Jiangsu Peace Power Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Peace Power Machinery Co Ltd filed Critical Jiangsu Peace Power Machinery Co Ltd
Priority to CN201721641908.6U priority Critical patent/CN207622331U/en
Application granted granted Critical
Publication of CN207622331U publication Critical patent/CN207622331U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Air Humidification (AREA)

Abstract

The utility model discloses a kind of generator coolers, including body, water storage room, atomizer and gas cooling chamber, the bottom end of the internal body is equipped with reservoir chamber, the middle position of internal body above the reservoir chamber is equipped with gas cooling chamber, all uniformly there are three atomizers for installation in the two side walls of gas cooling chamber interior, uniformly there are three fans for installation on the outer wall of the gas cooling chamber side, and inner wall of the gas cooling chamber close to fan side is equipped with air inlet.The utility model uniformly installs three fans in gas cooling chamber side, three atomizers are uniformly installed on the two side of gas cooling chamber interior, gas cooling chamber interior installs gas coil pipe, atomized water is ejected into gaseous disk pipe outer wall by atomizer, fan dries to gas coil pipe, convenient for the atomized water rapid evaporation on gas coil pipe to take away the heat on gas coil pipe, cools down hydrogen.

Description

A kind of generator cooler
Technical field
The utility model is related to cooling equipment technical field, specially a kind of generator coolers.
Background technology
With the development of generator techniques, generator capacity is increasing, and generator will produce largely at work Heat, therefore in electrical power generators, the cooling device for needing to configure and answering is used for cooling down valve motor, prevents from sending out Motor breaks down, and extends the service life of generator, and existing generator cooler carries out generator using cold air Cooling, cold air heat transfer efficiency is low, while containing moisture in cold air, when being cooled down to generator, cold air heat meeting Water is generated to be damaged to the circuit in generator.
Utility model content
The purpose of this utility model is to provide a kind of generator coolers, to solve mentioned above in the background art ask Topic.
To achieve the above object, the utility model provides the following technical solutions:A kind of generator cooler, including body, The bottom end of water storage room, atomizer and gas cooling chamber, the internal body is equipped with reservoir chamber, the body above the reservoir chamber Internal middle position is equipped with gas cooling chamber, and all uniformly there are three atomizations for installation in the two side walls of gas cooling chamber interior Nozzle, uniformly there are three fans for installation on the outer wall of the gas cooling chamber side, and gas cooling chamber is close to fan side Inner wall is equipped with air inlet, and the inside of the gas cooling chamber is equipped with gas coil pipe, and one end of gas coil pipe and air inlet The internal body of connection, the gas cooling chamber both sides is all equipped with water storage room, and pump chamber is equipped with above water storage room, in the pump chamber The side in portion is equipped with the first suction pump, and the input terminal of the first suction pump is equipped with the first water pipe, and the first water pipe is far from first One end of suction pump extends to the bottom inside water storage room, and the output end of first suction pump is sprayed by the first water pipe and atomization Head connection, the other side of the pump chamber are equipped with the second suction pump, and the input terminal of the second suction pump is equipped with the second water pipe, And second the one end of water pipe far from the second suction pump through pump chamber and extending to inside reservoir chamber, the output of second suction pump End is equipped with the second water pipe at the top of water storage room, and the top of the body is equipped with gas treatment chamber, gas treatment chamber interior Side air compressor is installed, and the input terminal of air compressor passes through tracheae and the one end of gas coil pipe far from air inlet Connection, the side of the gas treatment chamber interior far from air compressor are equipped with moisture trap, the moisture trap Input terminal is connected to by tracheae with the output end of air compressor, and the gas treatment chamber is equipped with close to the side of moisture trap Gas outlet, and the output end of air compressor is connected to by tracheae with gas outlet.
Preferably, the middle position at the top of the reservoir chamber and strainer is installed between gas cooling chamber.
Preferably, plane where the fan is mutually perpendicular to plane where atomizer.
Preferably, the gas-cooled bottom is in inverted prism-frustum-shaped.
Preferably, it is equipped with observation port at the top of the body above the moisture trap.
Compared with prior art, the utility model has the beneficial effects that:By in the uniformly installation three of gas cooling chamber side A fan, three atomizers are uniformly installed on the two side of gas cooling chamber interior, and gas cooling chamber interior installs gaseous disk Atomized water is ejected into gaseous disk pipe outer wall by pipe, atomizer, and fan dries to gas coil pipe, and being convenient for will be on gas coil pipe Atomized water rapid evaporation cools down hydrogen to take away the heat on gas coil pipe, passes through the body in cooling chamber both sides Inside setting water storage room, convenient for cooling down to gas cooling chamber, by installing air compression in gas treatment chamber interior one end Device installs moisture trap in the gas treatment chamber interior other end, convenient for carrying out compression cooling to hydrogen and by the water in hydrogen Divide and removes.
Description of the drawings
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the back view of the utility model.
In figure:1- bodies;2- water storage rooms;3- fans;4- gas coil pipes;The second suction pumps of 5-;The first suction pumps of 6-;7- goes out Gas port;8- moisture traps;9- tracheaes;10- gas treatment chambers;11- atomizers;12- air compressors;13- pump chambers;14- First water pipe;The second water pipes of 15-;16- reservoir chambers;17- gas cooling chambers;18- strainers;19- air inlets.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
- 2 are please referred to Fig.1, a kind of embodiment provided by the utility model:A kind of generator cooler, including body 1, storage Hydroecium 2, atomizer 11 and gas cooling chamber 17, the bottom end inside body 1 are equipped with reservoir chamber 16, the body of 16 top of reservoir chamber Middle position inside 1 is equipped with gas cooling chamber 17, between the middle position and gas cooling chamber 17 at 16 top of reservoir chamber Strainer 18 is installed, all uniformly there are three atomizer 11, gas coolings for installation in the two side walls inside gas cooling chamber 17 Uniformly there are three fans 3,3 place plane of fan mutually to hang down with 11 place plane of atomizer for installation on the outer wall of 17 side of room Directly, and inner wall of the gas cooling chamber 17 close to 3 side of fan is equipped with air inlet 19, and the inside of gas cooling chamber 17 is equipped with gas Body disc pipe 4, and one end of gas coil pipe 4 is connect with air inlet 19, the bottom of gas cooling 17 is in inverted prism-frustum-shaped, and gas is cold But water storage room 2 is all equipped with inside the body 1 of 17 both sides of room, and 2 top of water storage room is equipped with pump chamber 13, the side peace inside pump chamber 13 Equipped with the first suction pump 6, the model of first suction pump 6 can be 150QJ10-50/7, and the input terminal of the first suction pump 6 is equipped with First water pipe 14, and the one end of the first water pipe 14 far from the first suction pump 6 extends to the bottom inside water storage room 2, first draws water The output end of pump 6 is connect by the first water pipe 14 with atomizer 11, and the other side inside pump chamber 13 is equipped with the second suction pump 5, the model of second suction pump 5 can be 150QJ10-100/14, and the input terminal of the second suction pump 5 is equipped with the second water pipe 15, And second the one end of water pipe 15 far from the second suction pump 5 through pump chamber 13 and extending to inside reservoir chamber 16, the second suction pump 5 Output end is equipped with the second water pipe 15 through 2 top of water storage room, and the top of body 1 is equipped with gas treatment chamber 10, gas treatment Side inside room 10 is equipped with air compressor 12, and the input terminal of air compressor 12 is remote by tracheae 9 and gas coil pipe 4 One end connection from air inlet 19,10 side of the inside far from air compressor 12 of gas treatment chamber are equipped with moisture trap 8, The input terminal of moisture trap 8 is connected to by tracheae 9 with the output end of air compressor 12, and gas treatment chamber 10 is close to air water point Side from device 8 is equipped with gas outlet 7, and the output end of air compressor 12 is connected to by tracheae 9 with gas outlet 7, gas-water separation 1 top of body of 8 top of device is equipped with observation port.
Operation principle:Hot hydrogen enters from air inlet 19 in the gas coil pipe 4 inside gas cooling chamber 17, the first suction pump 6 extract the water inside water storage room 2 out, and from atomizer 11, jet atomization water, atomized water encounter the gas of heat on gas coil pipe 4 The evaporation of coil pipe 4 siphons away heat, and fan 3 dries to gas coil pipe 4, and increase air circulation is cooled to improve evaporation efficiency Hydrogen, which is entered by tracheae 9 inside air compressor 12, to be compressed, and reduces temperature again, compressed hydrogen passes through tracheae 9 Moisture content in the hydrogen of cooling compression is removed inside into air-water separation chamber 8, is removed the dry and cold hydrogen of moisture content from 7 row of gas outlet Go out.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this practicality is new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this practicality is new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing in the equivalent requirements of the claims will be fallen All changes in justice and range are embraced therein.Any reference numeral in claim should not be considered as limitation Involved claim.

Claims (5)

1. a kind of generator cooler, including body (1), water storage room (2), atomizer (11) and gas cooling chamber (17), It is characterized in that:The internal bottom end of the body (1) is equipped with reservoir chamber (16), and the body (1) above the reservoir chamber (16) is internal Middle position be equipped with gas cooling chamber (17), in the internal two side walls of gas cooling chamber (17) all uniformly there are three installations Atomizer (11), uniformly installation is there are three fan (3) on the outer wall of gas cooling chamber (17) side, and gas cooling chamber (17) it is equipped with air inlet (19) close to the inner wall of fan (3) side, the inside of the gas cooling chamber (17) is equipped with gas Coil pipe (4), and one end of gas coil pipe (4) is connect with air inlet (19), in the body (1) of gas cooling chamber (17) both sides Portion is all equipped with water storage room (2), and pump chamber (13) is equipped with above water storage room (2), and the internal side of the pump chamber (13) is equipped with the The input terminal of one suction pump (6), the first suction pump (6) is equipped with the first water pipe (14), and the first water pipe (14) is taken out far from first One end of water pump (6) extends to the internal bottom of water storage room (2), and the output end of first suction pump (6) passes through the first water pipe (14) it is connect with atomizer (11), the internal other side of the pump chamber (13) is equipped with the second suction pump (5), the second suction pump (5) input terminal is equipped with the second water pipe (15), and pump chamber is run through in the one end of the second water pipe (15) far from the second suction pump (5) (13) and reservoir chamber (16) inside is extended to, the output end of second suction pump (5) is equipped at the top of water storage room (2) The top of second water pipe (15), the body (1) is equipped with gas treatment chamber (10), the internal side installation of gas treatment chamber (10) There is air compressor (12), and the input terminal of air compressor (12) passes through tracheae (9) and the separate air inlet of gas coil pipe (4) (19) one end connection, the internal side far from air compressor (12) of the gas treatment chamber (10) are equipped with moisture trap (8), the input terminal of the moisture trap (8) is connected to by tracheae (9) with the output end of air compressor (12), the gas Process chamber (10) is equipped with gas outlet (7) close to the side of moisture trap (8), and the output end of air compressor (12) passes through gas Pipe (9) is connected to gas outlet (7).
2. a kind of generator cooler according to claim 1, it is characterised in that:Centre at the top of the reservoir chamber (16) Strainer (18) is installed at position between gas cooling chamber (17).
3. a kind of generator cooler according to claim 1, it is characterised in that:Plane and mist where the fan (3) Plane where changing nozzle (11) is mutually perpendicular to.
4. a kind of generator cooler according to claim 1, it is characterised in that:The bottom of the gas cooling chamber (17) In inverted prism-frustum-shaped.
5. a kind of generator cooler according to claim 1, it is characterised in that:Above the moisture trap (8) Observation port is equipped at the top of body (1).
CN201721641908.6U 2017-11-30 2017-11-30 A kind of generator cooler Expired - Fee Related CN207622331U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721641908.6U CN207622331U (en) 2017-11-30 2017-11-30 A kind of generator cooler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721641908.6U CN207622331U (en) 2017-11-30 2017-11-30 A kind of generator cooler

Publications (1)

Publication Number Publication Date
CN207622331U true CN207622331U (en) 2018-07-17

Family

ID=62824973

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721641908.6U Expired - Fee Related CN207622331U (en) 2017-11-30 2017-11-30 A kind of generator cooler

Country Status (1)

Country Link
CN (1) CN207622331U (en)

Similar Documents

Publication Publication Date Title
CN202254037U (en) Evaporative cooling type air conditioner unit with air cooling type direct expansion unit
CN204214069U (en) A kind of air-cooler of multilayer refrigeration
CN204301389U (en) In conjunction with evaporative cooling and mechanically refrigerated power generating plant cooling tower water-saving system
CN206864960U (en) A kind of heat sink for high-tension switch cabinet
CN103604180B (en) The evaporative cooling of integration Winter-summer dual purpose combines air-conditioner set with mechanical refrigeration
CN207624505U (en) A kind of cooling device for transformer easy to clean
CN207183421U (en) A kind of aerial cooler and its fuel battery air gas handling system of application
CN102767878A (en) Dew-point evaporative cooling water chilling unit
CN210130051U (en) High-efficient heat abstractor is used to mechatronic equipment
CN207622331U (en) A kind of generator cooler
CN105737418A (en) Refrigerating unit
CN109855361A (en) A kind of generator cooler
CN202675933U (en) Efficient cooling tower
CN213278876U (en) Heat exchange dehumidification type transformer substation
CN107387461A (en) Magnetic suspension cfentrifugal blower cooling system
CN208222900U (en) A kind of electrical cabinet to be cooled using vortex tube
CN108061402B (en) Vacuum atomization phase-change refrigeration equipment
CN209386524U (en) A kind of cooling device of idle call
CN209763377U (en) Air conditioning unit based on plate fin-dew point two-stage indirect evaporative cooling
CN205037786U (en) Chemical industry gas cooling device
CN210075761U (en) Electromechanical device protection device
CN208186750U (en) A kind of diffuser design
CN206601655U (en) Possesses the big data processing server of cooling device
CN206370637U (en) Combined heat radiating high-voltage board during a kind of high temperature ashes production zinc oxide
CN211204951U (en) Steam cooler

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180717

Termination date: 20191130

CF01 Termination of patent right due to non-payment of annual fee