CN207576149U CN201721671394.9U CN201721671394U CN207576149U CN 207576149 U CN207576149 U CN 207576149U CN 201721671394 U CN201721671394 U CN 201721671394U CN 207576149 U CN207576149 U CN 207576149U
Authority
CN
China
Prior art keywords
backwash
valve
main pipeline
cleaning
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721671394.9U
Other languages
Chinese (zh)
Inventor
王杰
杨正宏
孙毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Yicheng New Energy Co ltd
Original Assignee
Henan Yicheng New Energy Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Yicheng New Energy Co ltd filed Critical Henan Yicheng New Energy Co ltd
Priority to CN201721671394.9U priority Critical patent/CN207576149U/en
Application granted granted Critical
Publication of CN207576149U publication Critical patent/CN207576149U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Using Semi-Permeable Membranes (AREA)

Abstract

The utility model discloses a kind of reversed cleaning plant of ultrafiltration hydrotreater, the utility model includes Cleaning pipes, the hyperfiltration membrane assembly for treating backwash and backwash main pipeline;Described hyperfiltration membrane assembly one end is connected with the Cleaning pipes, and the other end is connected with the backwash main pipeline;The Cleaning pipes are equipped with cleaning branch pipe, and the first shut-off valve and the second shut-off valve are respectively equipped in the Cleaning pipes and cleaning branch pipe;According to from the connecting pin to the direction of the other end of the backwash main pipeline of the hyperfiltration membrane assembly and the backwash main pipeline, third shut-off valve, the first blow-off pipe, backwash medicament component, the first aeration tube, cleaning agent component, the second aeration tube, the second blow-off pipe and backwash water assembly are sequentially installed on the backwash main pipeline.The silicon carbide micro-powder material that deposited in backwash main pipeline can be cleared up for the utility model and thorough, effective cleaning ultrafiltration hydrotreater, so as to ensure the water quality and water of ultrafiltration hydrotreater water.

Description

The reversed cleaning plant of ultrafiltration hydrotreater
Technical field
The utility model is related to ultrafiltration hydrotreater Removal Technology fields, and in particular to a kind of ultrafiltration hydrotreater is reversely clear Manage device.
Background technology
Ultrafiltration is a kind of technology detached using the film that pressurizes, and in ultra-filtration process, aqueous solution is under the promotion of pressure Ultrafiltration membrane surface is flowed through, screening filtering is carried out to aqueous solution by the micropore that ultrafiltration membrane surface gathers, less than the water of fenestra and small Molecule solute becomes purified water by ultrafiltration membrane, and the impurity such as suspended matter, particle, microorganism and colloid bigger than fenestra in water can It is trapped, is discharged with concentrated water from water outlet, so as to reach the isolation of purified purpose to water, the separation that water is carried out using ultrafiltration is net Change has the characteristics that with short production cycle, easy to operate, system energy consumption is low, of low cost, is widely used at industrial Water warfare Reason field.But ultrafiltration hydrotreater uses the suspended matter, particle, micro- life after a period of time, retained in water body by ultrafiltration membrane The impurity such as object and colloid can be deposited on ultrafiltration membrane surface, and as time increase is cumulative, and cause the product of made water intaking Matter declines, water speed rate processed reduces, work efficiency drop, it is therefore desirable to ultrafiltration membrane be cleared up, the backwash of ultrafiltration refers to close It closes raw water valve pump and water purification is squeezed into the process that hyperfiltration membrane assembly is rinsed from the production mouth of a river, wherein, make water purification by normal mistake The negative direction of filter penetrates ultrafiltration membrane, to wash away the pollutant impurity of film surface retention deposition and it made to be discharged from concentrated water spout, from And complete the backwash of hyperfiltration membrane assembly.In solar battery sheet cuts industry, silicon carbide micro-powder is after hydraulic classiciation, often The secondary water of be carbonized containing micron order colloidal silica and micro powder granule can be generated, usually uses ultrafiltration hydrotreater secondary to this in enterprise Water carries out purified treatment, to filter out carbonization colloidal silica and micro powder granule therein, and periodically hyperfiltration membrane assembly can be carried out anti- It rinses.But because new hyperfiltration reverse-rinsing pipeline is thick, blow-off line is long, and hyperfiltration membrane assembly is large number of, to holding during hyperfiltration membrane assembly backwash Easily silicon carbide micro-powder material is washed out, and silicon carbide density is big, is easy to settle in water so that silicon carbide micro-powder can be deposited on pipeline Interior bottom, normal backwash water outlet be difficult the silicon carbide micro-powder material these depositions by being discharged in pipeline, so as to cause in pipeline Silicon carbide micro-powder material it is cumulative with the backwash increase of number, in the case where aggregation is carbonized silicon material, in ultrafiltration membrane The pollutant impurity for retaining the silicon carbide-containing micro powder granule of deposition also is difficult to be discharged, and forms material stock in ultrafiltration membrane surface, separately Material stock in the outer hyperfiltration membrane assembly will also result in the pressure increase in single membrane module, so as to cause ultrafiltration membrane filaments more easily broken It splits, seriously affects the water quality and water of excess of export drainage processor water, influence being normally carried out for production.
Invention content
The technical problem to be solved by the present invention is to provide a kind of effective, thoroughly carbonizations to being deposited in backwash pipeline The reversed cleaning plant of ultrafiltration hydrotreater that silicon powder material is cleared up.
In order to solve the above technical problems, the utility model adopts the following technical solution:
A kind of reversed cleaning plant of ultrafiltration hydrotreater is designed, including Cleaning pipes, treats the hyperfiltration membrane assembly of backwash and anti- Wash main pipeline;Described hyperfiltration membrane assembly one end is connected with the Cleaning pipes, and the other end is connected with the backwash main pipeline; The Cleaning pipes are equipped with cleaning branch pipe, and the first shut-off valve and second are respectively equipped in the Cleaning pipes and cleaning branch pipe Shut-off valve;According to from the connecting pin of the hyperfiltration membrane assembly and the backwash main pipeline to the other end of the backwash main pipeline Direction is sequentially installed with third shut-off valve, the first blow-off pipe, backwash medicament component, the first aeration on the backwash main pipeline Pipe, cleaning agent component, the second aeration tube, the second blow-off pipe and backwash water assembly;The third shut-off valve is located at close to described super The junction of filter membrane component and backwash main pipeline;First blow-off pipe is installed at the third shut-off valve, described First blowdown valve is installed in the first blow-off pipe;The backwash medicament component includes backwash pharmacy jar and positioned at the backwash medicament Backwash pharmacy jar liquid discharging tube below tank is equipped with backwash medicament bleeder valve, the backwash in the backwash pharmacy jar liquid discharging tube Pharmacy jar is connected by the backwash pharmacy jar liquid discharging tube and the backwash main pipeline;The cleaning agent component includes cleaning agent Tank and the cleaning agent liquid discharging tube below the cleaning agent tank are equipped with cleaning agent bleeder valve in the cleaning agent liquid discharging tube, The cleaning agent tank is connected by the cleaning agent tank liquid discharging tube and the backwash main pipeline;The backwash water assembly includes anti- Wash water tank, backwash water liquid discharging tube and bypass pipe below the backwash water pot, the backwash water pot pass through the backwash water Liquid discharging tube is connected with the backwash main pipeline, and the first backwash water bleeder valve is equipped in the backwash water liquid discharging tube and is located at The second backwash water bleeder valve below the first backwash water bleeder valve, one end of the bypass pipe are communicated in first backwash At the backwash water liquid discharging tube between water bleeder valve and the second backwash water bleeder valve, the other end of the bypass pipe with it is described anti- The end for washing main pipeline is connected, and by-passing valve and pipeline pump are sequentially installed on the bypass pipe;First aeration tube and The first aeration valve and the second aeration valve are respectively equipped in second aeration tube;The second blowdown valve is equipped in second blow-off pipe.
Preferably, first blow-off pipe and the second blow-off pipe are all connected to the bottom of the backwash main pipeline.
Preferably, first aeration tube and the second aeration tube are all connected to the top of the backwash main pipeline.
Compared with prior art, the advantageous effects of the utility model are:
It, can be to being deposited in backwash main pipeline 1. cleaning agent component and backwash water assembly are used cooperatively in the utility model Silicon carbide micro-powder is rinsed cleaning.
2. the first aeration tube and the second aeration tube can generate gas in the utility model, gas enters can in backwash main pipeline Accelerating impurity scatter in water body.
3. the utility model is thoroughly effective to the cleaning of ultrafiltration hydrotreater.
Description of the drawings
Fig. 1 is the structure diagram of the utility model.
Specific embodiment
Illustrate specific embodiment of the present utility model, but following embodiment is only used with reference to the accompanying drawings and examples It is described in detail the utility model, does not limit the scope of the utility model in any way.
Involved parts etc., are then conventional commercial product unless otherwise instructed in following embodiment.
Embodiment 1:A kind of reversed cleaning plant of ultrafiltration hydrotreater referring to Fig. 1, including Cleaning pipes 2, treats the super of backwash Filter membrane component 1 and backwash main pipeline 4;Described 1 one end of hyperfiltration membrane assembly is connected with the Cleaning pipes 2, the other end with it is described Backwash main pipeline 4 is connected;The Cleaning pipes 2 are equipped with cleaning branch pipe 3, divide in the Cleaning pipes 2 and cleaning branch pipe 3 It She You not the first shut-off valve 27 and the second shut-off valve 28;According to the connection from the hyperfiltration membrane assembly 1 and the backwash main pipeline 4 The direction of the other end of the backwash main pipeline 4 is held, third shut-off valve 5, are sequentially installed on the backwash main pipeline 4 One blow-off pipe 6, backwash medicament component(18,19,20), the first aeration tube 21, cleaning agent component(15,16,17), the second aeration tube 23rd, the second blow-off pipe 25 and backwash water assembly(8,9,10,11,12,13,14);The third shut-off valve 5 is located at close to described super The junction of filter membrane component 1 and backwash main pipeline 4;First blow-off pipe 6 is installed on close to the described of the third shut-off valve 5 The bottom of backwash main pipeline 4 is equipped with the first blowdown valve 7 in first blow-off pipe 6;The backwash medicament component(18, 19,20)Backwash pharmacy jar liquid discharging tube 20 including backwash pharmacy jar 18 and positioned at 18 lower section of backwash pharmacy jar, described anti- Pharmacy jar liquid discharging tube top is washed equipped with backwash medicament bleeder valve 19, the backwash pharmacy jar 18 passes through the backwash pharmacy jar tapping Pipe 20 and the backwash main pipeline 4 are connected;The cleaning agent component(15,16,17)Including cleaning agent tank 15 and positioned at described The cleaning agent liquid discharging tube 17 of 15 lower section of cleaning agent tank, cleaning agent bleeder valve 16, institute are equipped on 17 top of cleaning agent liquid discharging tube Cleaning agent tank 15 is stated to be connected by the cleaning agent tank liquid discharging tube 17 and the backwash main pipeline 4;The backwash water assembly(8, 9,10,11,12,13,14)Backwash water liquid discharging tube 9 and bypass pipe including backwash water pot 8, positioned at 8 lower section of backwash water pot 11, the backwash water pot 8 is connected by the backwash water liquid discharging tube 9 with the backwash main pipeline 4, in the backwash water tapping First backwash water bleeder valve 10 and the second backwash water tapping positioned at 10 lower section of the first backwash water bleeder valve are installed in pipe 9 Valve 14, one end of the bypass pipe 11 are communicated between the first backwash water bleeder valve 10 and the second backwash water bleeder valve 14 At the backwash water liquid discharging tube 9, the other end of the bypass pipe 11 is connected with the end of the backwash main pipeline 4, described By-passing valve 12 and pipeline pump 13 are sequentially installed on bypass pipe 11;First aeration tube, 21 and second aeration tube 23 is mounted on The top of the backwash main pipeline 4 is respectively equipped with 22 He of the first aeration valve in first aeration tube, 21 and second aeration tube 23 Second aeration valve 24;Second blow-off pipe 25 is installed on the bottom of the backwash main pipeline 4, is set in second blow-off pipe 25 There is the second blowdown valve 26.
The course of work of the above-mentioned reversed cleaning plant of ultrafiltration hydrotreater is as follows:
During work, in backwash water pot 8 water is pumped into backwash main pipeline 4 by the pipeline pump 13 on bypass pipe 11, to backwash The silicon carbide micro-powder of deposition accumulation is rinsed cleaning in main pipeline 4, opens simultaneously cleaning agent bleeder valve 16, makes cleaning agent tank 15 In cleaning agent slowly flow into backwash main pipeline 4, for cleaning backwash main pipeline 4 in silicon carbide micro-powder, first expose Air valve 22 and second is aerated under the control of valve 24, and the gas with pressure enters backwash by the first aeration tube 21 and the second aeration tube 23 In main pipeline 4, the impact force accelerating impurity for being evoked water body formation using air-flow is scatter in water body, so as to accelerate to backwash master Silicon carbide micro-powder in pipeline 4 is rinsed cleaning, and impure water body is in the first blowdown valve 7 and/or the second blowdown after cleaning It under the action of valve 26, is discharged by the first blow-off pipe 6 and/or the second blow-off pipe 25, so as to avoid the impurity deposited in pipeline to filter Membrane cleaning impacts.When ultrafiltration module backwash needs addition medicament to clean filter membrane, backwash medicament tapping can be opened Valve 19 makes the medicament in backwash pharmacy jar 19 be flowed into backwash main pipeline 4 through backwash medicament liquid discharging tube 20 and realizes to ultrafiltration module Backwash.
The utility model is described in detail above in conjunction with drawings and examples, still, the skill of technical field Art personnel, can also be to each specific in above-described embodiment it is understood that under the premise of the utility model aims are not departed from Parameter changes, and forms multiple specific embodiments, is the common variation range of the utility model, no longer detailed one by one herein It states.

Claims (3)

1. a kind of reversed cleaning plant of ultrafiltration hydrotreater, which is characterized in that including Cleaning pipes, treat the hyperfiltration membrane assembly of backwash With backwash main pipeline;Described hyperfiltration membrane assembly one end is connected with the Cleaning pipes, the other end and the backwash main pipeline phase Connection;The Cleaning pipes are equipped with cleaning branch pipe, and the first shut-off valve is respectively equipped in the Cleaning pipes and cleaning branch pipe With the second shut-off valve;According to from the connecting pin of the hyperfiltration membrane assembly and the backwash main pipeline to the another of the backwash main pipeline The direction of one end is sequentially installed with third shut-off valve, the first blow-off pipe, backwash medicament component, on the backwash main pipeline One aeration tube, cleaning agent component, the second aeration tube, the second blow-off pipe and backwash water assembly;The third shut-off valve is located at close The junction of the hyperfiltration membrane assembly and backwash main pipeline;First blow-off pipe is installed at the third shut-off valve, The first blowdown valve is installed in first blow-off pipe;The backwash medicament component includes backwash pharmacy jar and positioned at described anti- The backwash pharmacy jar liquid discharging tube below pharmacy jar is washed, backwash medicament bleeder valve, institute are equipped in the backwash pharmacy jar liquid discharging tube Backwash pharmacy jar is stated to be connected by the backwash pharmacy jar liquid discharging tube and the backwash main pipeline;The cleaning agent component includes Cleaning agent tank and the cleaning agent liquid discharging tube below the cleaning agent tank, put in the cleaning agent liquid discharging tube equipped with cleaning agent Liquid valve, the cleaning agent tank are connected by the cleaning agent tank liquid discharging tube and the backwash main pipeline;The backwash water assembly Backwash water liquid discharging tube and bypass pipe including backwash water pot, below the backwash water pot, the backwash water pot pass through described Backwash water liquid discharging tube is connected with the backwash main pipeline, and the first backwash water bleeder valve is equipped in the backwash water liquid discharging tube With the second backwash water bleeder valve below the first backwash water bleeder valve, one end of the bypass pipe is communicated in described At the backwash water liquid discharging tube between one backwash water bleeder valve and the second backwash water bleeder valve, the other end of the bypass pipe with The end of the backwash main pipeline is connected, and by-passing valve and pipeline pump are sequentially installed on the bypass pipe;Described first exposes The first aeration valve and the second aeration valve are respectively equipped in tracheae and the second aeration tube;The second blowdown is equipped in second blow-off pipe Valve.
2. the reversed cleaning plant of ultrafiltration hydrotreater according to claim 1, which is characterized in that first blow-off pipe and Second blow-off pipe is all connected to the bottom of the backwash main pipeline.
3. the reversed cleaning plant of ultrafiltration hydrotreater according to claim 1, which is characterized in that first aeration tube and Second aeration tube is all connected to the top of the backwash main pipeline.
CN201721671394.9U 2017-12-05 2017-12-05 The reversed cleaning plant of ultrafiltration hydrotreater Expired - Fee Related CN207576149U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721671394.9U CN207576149U (en) 2017-12-05 2017-12-05 The reversed cleaning plant of ultrafiltration hydrotreater

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721671394.9U CN207576149U (en) 2017-12-05 2017-12-05 The reversed cleaning plant of ultrafiltration hydrotreater

Publications (1)

Publication Number Publication Date
CN207576149U true CN207576149U (en) 2018-07-06

Family

ID=62735760

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721671394.9U Expired - Fee Related CN207576149U (en) 2017-12-05 2017-12-05 The reversed cleaning plant of ultrafiltration hydrotreater

Country Status (1)

Country Link
CN (1) CN207576149U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113842780A (en) * 2021-09-09 2021-12-28 华能嘉祥发电有限公司 Ultra-filtration device for combined frame pipeline

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113842780A (en) * 2021-09-09 2021-12-28 华能嘉祥发电有限公司 Ultra-filtration device for combined frame pipeline
CN113842780B (en) * 2021-09-09 2024-05-14 华能嘉祥发电有限公司 Ultrafiltration filter equipment for combination frame pipeline

Similar Documents

Publication Publication Date Title
CN105478016B (en) A kind of automatic backwash scraping tubular membrane filter device
CN203946982U (en) A kind of textile printing and dyeing wastewater refining plant
CN108191093A (en) A kind of air supporting-Dynamic Membrane integrated separation device and separation method suitable for condensed oil sewage processing
CN108203196A (en) A kind of municipal sewage treatment purifier
CN106006847B (en) A kind of direct filtration reactor of Dynamic Membrane sewage and operation method based on different sewage water quality
CN201541541U (en) 100m3/h centrifugal net type manual backwashing combined type filtering fertilization device
JPH07236818A (en) Backwashing of inner pressure type hollow yarn module
CN207576149U (en) The reversed cleaning plant of ultrafiltration hydrotreater
CN103055543B (en) Large-channel vertical-flow membrane device for recycling superfine solid catalyst and process
CN205099414U (en) Reverse osmosis water treatment equipment
CN103990313B (en) Low permeability oil field recovered water filtration system and backwash process thereof
CN202983322U (en) Scrubbing device for desalted water production
CN206232445U (en) Short fiber acid wastewater treatment system
CN205500954U (en) Domestic reverse osmosis water purifier
CN107224877A (en) A kind of packaging type super-filter purifying device
CN201292297Y (en) Integral water purifier
CN203269626U (en) Membrane treatment device for industrial wastewater treatment
CN115159739A (en) Reverse osmosis seawater desalination system
KR101469634B1 (en) Water treatment system use of tubular filter module
CN203419802U (en) Membrane technology integrated comprehensive water purification device
CN211987254U (en) Rotary multi-medium processor
CN209405838U (en) A kind of solid-liquid separation system for liquid waste processing
CN208394917U (en) A kind of coal mine wastewater processing system
CN207748891U (en) A kind of uniformly water inlet ultrafiltration apparatus
CN206915875U (en) The small-sized integrated water purifier of jetting type automatic backwash

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180706

Termination date: 20191205

CF01 Termination of patent right due to non-payment of annual fee