CN207512746U CN201721448894.6U CN201721448894U CN207512746U CN 207512746 U CN207512746 U CN 207512746U CN 201721448894 U CN201721448894 U CN 201721448894U CN 207512746 U CN207512746 U CN 207512746U
Authority
CN
China
Prior art keywords
parcel shelf
rope
crossbeam
ropes
earthwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721448894.6U
Other languages
Chinese (zh)
Inventor
刘小慧
陈乐乐
吴昊
潘鹏飞
徐丽鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou City Construction Foundation Engineering Co Ltd
Original Assignee
Hangzhou City Construction Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou City Construction Foundation Engineering Co Ltd filed Critical Hangzhou City Construction Foundation Engineering Co Ltd
Priority to CN201721448894.6U priority Critical patent/CN207512746U/en
Application granted granted Critical
Publication of CN207512746U publication Critical patent/CN207512746U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

The utility model discloses a kind of earth excavation conversion platform, its key points of the technical solution are that, the crossbeam including the column being vertically arranged and on column, crossbeam has two and is arranged in parallel, and crossbeam uses reinforced concrete structure;The parcel shelf for loading the earthwork is shelved on crossbeam, the both ends of parcel shelf are connected separately with ropes with tilting rope, ropes are connected separately with first hoist and second hoist with tilting one end far from parcel shelf on rope, and ropes by first hoist and second hoist rope closing or put rope respectively with tilting rope under the guiding of the fixed pulley at the top of column, have achieved the effect that facilitate earthwork transportation.

Description

A kind of earth excavation conversion platform
Technical field
The utility model is related to earth excavation equipment, more particularly to a kind of earth excavation conversion platform.
Background technology
With the development of urban construction, the construction quality of municipal works is also increasingly improving.General municipal works are applied Work scene is located at urban inner, in order to reduce the influence to periphery traffic, can reduce the size of excavation of foundation pit in the construction process, For the transport of the earthwork with regard to relatively difficult so during earth excavation.Conventional earthwork transportation is generally using gantry crane, cunning The progress such as arm excavator, but the transport of these machineries is often used for the big engineering of vertical transport, the scope of application is relatively small.
The Chinese patent that Authorization Notice No. is CN202718126U, authorized announcement date is on February 06th, 2013 discloses one Kind deep foundation pit earthwork digging conversion platform, including two parallel support girders, support girder and vertical building enclosure rigidity Connection;Secondary beam vertical rack is supported to be set between two support girders, steel construction plate passes through steel plate and branch pre-buried on support girder Support girder is fixed, and is set on support secondary beam.
The deep foundation pit earthwork digging conversion platform is still needed by artificial or mechanically operated mode, by conversion platform On the earthwork carry out vertical transport, then the earthwork for being transported out foundation pit is transported to again be transferred on transport vehicle stack the earthwork field Ground, such operation extend the construction time, are unfavorable for the development of construction.
Utility model content
The purpose of this utility model is to provide a kind of earth excavation conversion platform, has achieved the effect that facilitate earthwork transportation.
The above-mentioned technical purpose of the utility model technical scheme is that:
A kind of earth excavation conversion platform, the crossbeam including the column being vertically arranged and on column, crossbeam have two It root and is arranged in parallel, crossbeam uses reinforced concrete structure;The parcel shelf for loading the earthwork is shelved on crossbeam, parcel shelf Both ends are connected separately with ropes and are connect respectively with tilting rope, ropes with tilting one end far from parcel shelf on rope There are first hoist and second hoist, and ropes are divided with tilting rope under the guiding of the fixed pulley at the top of column Not by first hoist and second hoist rope closing or put rope.
Using above-mentioned technical proposal, after the earth-moving equipment in foundation pit pushes to the earthwork on parcel shelf, while start the One hoist engine and second hoist so that ropes are with tilting rope by the synchronouss rising of the guiding of fixed pulley, by parcel shelf Outside vertical-lift to foundation pit.It is then shut off first hoist so that tilt rope under the winding of second hoist, pulling is put Object plate tilts, and the earthwork on parcel shelf is poured onto in transporting equipment, then is transported to the earthwork by transporting equipment and stacks place.Its In, crossbeam can preferably support parcel shelf using reinforced concrete structure, strengthen the intensity of total.
Further preferably:The lower rotation of parcel shelf is connected with the telescopic supporting rod being vertically arranged, and supporting rod One end of ropes is equipped with positioned at parcel shelf.
Using above-mentioned technical proposal, after first hoist is closed, parcel shelf is tilting rope using supporting rod as fulcrum It is tilted under pulling force effect, the earthwork on parcel shelf is poured on transporting equipment, improve parcel shelf in the case where tilting rope pull Stability during run-off the straight reduces the feelings for the earthwork being caused to be trickled down due to parcel shelf shaking etc. in cubic metre of earth dropping process Condition.
Further preferably:The guide plate that parcel shelf is defined equipped with two pieces for position when falling to the earthwork, Two pieces of guide plates are symmetrically disposed on parcel shelf close to one end of ropes.
Using above-mentioned technical proposal, when parcel shelf run-off the straight under the pulling force effect for tilting rope, on parcel shelf The earthwork slides under the effect of gravity along parcel shelf, and under the limitation of guide plate, the range that the earthwork is fallen is limited in two pieces of guiding Between plate, reduce the earthwork and situation outside transporting equipment is trickled down in dropping process.
Further preferably:One end of guide plate is rotationally connected on parcel shelf, is equipped on guide plate and is turned for locking The fixing bolt of the position of guide plate after dynamic, when the position of guide plate is locked, one end of fixing bolt is pushed against in glove On plate.
Using above-mentioned technical proposal, fixing bolt is inverted, releases the locking between guide plate and parcel shelf, then rotation is led To plate, change the angle between two pieces of guide plates, to control the range when earthwork is fallen, to adapt to different transporting equipment pan feedings The size of mouth.
Further preferably:The groove that section is V-arrangement is offered on parcel shelf, groove is along parcel shelf from equipped with hoisting rope One end of rope is equipped with the direction setting of the one end for tilting rope to parcel shelf.
Using above-mentioned technical proposal, when earth-moving equipment pushes to the earthwork on parcel shelf, the earthwork is due to the effect of gravity It is piled up in the groove of V-arrangement.Then parcel shelf rises in the pulling force of ropes and inclination rope, the soil in the groove of V-arrangement Side can be more steadily on parcel shelf under the effect of gravity, reduce the feelings that the earthwork is fallen during parcel shelf rises Condition.Then, parcel shelf run-off the straight under the pulling force for tilting rope, the earthwork on parcel shelf along the groove of V-arrangement length side It is fallen on transporting equipment to steadily, further reduces the situation that the earthwork is fallen, improve earthwork transportation efficiency.
Further preferably:One end that parcel shelf is equipped with ropes is provided with baffle.
Using above-mentioned technical proposal, when parcel shelf rises under pulling force effect of the ropes with tilting rope, it is set on Close to ropes one end baffle and be provided close to tilt the guide plate of rope one end and coordinate, reduce the earthwork and two made a clean sweep of from this Situation about falling improves the efficiency of earthwork transportation.
Further preferably:Crossbeam is equipped with secondary beam, and secondary beam is set perpendicular to crossbeam.
Using above-mentioned technical proposal, the structural stability of crossbeam and column is strengthened, reducing causes since the earthwork is overweight The situation that crossbeam destroys.
Further preferably:Crossbeam is equipped with that the earthwork is facilitated to transport the guiding slope onto parcel shelf from foundation pit.
Using above-mentioned technical proposal, when earth-moving equipment pushes to the earthwork in foundation pit on parcel shelf, the earthwork is being oriented to tiltedly Reduce resistance during earthwork push under the guiding role on slope, improve the efficiency of earthwork push.Meanwhile it is oriented to the setting on slope Reduce the situation that the earthwork during the earthwork pushes is piled up in crossbeam side.
To sum up, the utility model has the advantages that:By setting ropes and tilting rope, parcel shelf is carried Rise rear-inclined so that the earthwork on parcel shelf is fallen, and has achieved the effect that facilitate earthwork transportation.
Description of the drawings
Fig. 1 is the overall structure diagram of embodiment;
Fig. 2 is the A-A sectional views of Fig. 1;
Fig. 3 is the overall structure diagram after parcel shelf is elevated;
Fig. 4 is the B-B sectional views of Fig. 1.
In figure, 1, crossbeam;11st, it is oriented to slope;12nd, secondary beam;2nd, building enclosure;3rd, column;31st, fixed pulley;4th, parcel shelf; 41st, end is promoted;411st, ropes;42nd, beveled end;421st, rope is tilted;43rd, supporting rod;5th, first hoist;6th, volume Two Raise machine;7th, guide plate;71st, fixing bolt;8th, groove;9th, baffle.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:A kind of earth excavation conversion platform, as shown in Figure 1, including two crossbeams being arranged in parallel 1, crossbeam 1 hangs down It is directly set in the building enclosure of foundation pit 2, achieve the effect that braced cuts structure 2 and improves its stability.As shown in Fig. 2, crossbeam 1 On be connected with the secondary beam 12 of perpendicular setting, the quantity of secondary beam 12 is configured according to site operation demand.And crossbeam 1 with time Beam 12 is reinforced concrete cast-in-situ structure, and the wherein strength grade of concrete of armored concrete and arrangement of reinforcement is by site operation demand It determines.The both ends of crossbeam 1 are both provided with vertical column 3, and the rectangular parcel shelf for placing the earthwork is shelved on crossbeam 1 4.It is provided on crossbeam 1 and is oriented to slope 11.Earth-moving equipment is pushed to the earthwork on parcel shelf 4 by being oriented to slope 11.
As shown in figure 3, end 41 and beveled end 42 are respectively promoted close to the both ends of building enclosure 2 on parcel shelf 4.Wherein, It is promoted and is fixed with ropes 411 on end 41, be fixed on beveled end 42 and tilt rope 421.Ropes 411 are with tilting rope 421 are connected to by the guiding for the fixed pulley 31 for being fixed on 3 top of column in first hoist 5 and second hoist 6.When When starting first hoist 5 simultaneously with second hoist 6, ropes 411 are with tilting rope 421 under the guiding of fixed pulley 31 It is wound respectively in first hoist 5 and second hoist 6, parcel shelf 4 is in ropes 411 and the pulling force for tilting rope 421 It is elevated under effect.
As shown in figure 3,4 lower surface of parcel shelf is hinged with two telescopic supporting rods 43 close to the one end for promoting end 41, The other end of supporting rod 43 is fixed on the bottom of foundation pit, and two supporting rods 43 are symmetrical arranged.Supporting rod 43 selects what is be arranged step by step Socket type supporting rod, the supporting rod 43 are the prior art, are chiefly used in the structures such as fishing rod, this will not be repeated here.When parcel shelf 4 exists When being promoted to suitable height under ropes 411 and the pulling force effect of inclination rope 421, two supporting rods 43 are stretched, so First hoist 5 is closed afterwards, and second hoist 6 continues winding and tilts rope 421, and parcel shelf 4 is made in the pulling force for tilting rope 421 It is rotated for fulcrum with supporting rod 43 under, is finished until the earthwork on parcel shelf 4 is all toppled over.
As shown in figure 4, falling to situation outside transporting equipment to reduce the earthwork, the recessed of V-arrangement is offered on parcel shelf 4 Slot 8.Groove 8 is opened up along the length direction of parcel shelf 4, and the length of groove 8 is consistent with the length of parcel shelf 4, the width of groove 8 With the equivalent width of parcel shelf 4.One end on parcel shelf 4 close to ropes 411 has additional two pieces of guide plates 7, and two pieces are led It is symmetrical arranged to plate 7.Be rotationally connected on parcel shelf 4 far from one end of ropes 411 on guide plate 7, guide plate 7 it is another End is fixed on by the fixing bolt 71 being arranged on guide plate 7 on parcel shelf 4.When reversion fixing bolt 71 so that fixed spiral shell Bolt 71, so as to unlock guide plate 7, then rotates guide plate 7 and adjusts the angle between two pieces of guide plates 7 to control far from parcel shelf 4 The range when earthwork is fallen when subject-oriented plate 7 turns to suitable position, rotates forward fixing bolt 71 so that guide plate 7 is solid Due on parcel shelf 4.The baffle 9 with 4 same widths of parcel shelf is fixed with far from the one end for setting guide plate 7 on parcel shelf 4, to It reduces the earthwork and situation about falling is made a clean sweep of from this.
The use process of the utility model is as follows, and construction personnel is pushed to the earthwork on parcel shelf 4 by pushing equipment, so Start first hoist 5 and second hoist 6 simultaneously afterwards so that parcel shelf 4 is in the drawing of ropes 411 and inclination rope 421 It is elevated under power effect, meanwhile, the supporting rod 43 set on 4 lower section of parcel shelf is stretched.When parcel shelf 4 is thus lifted to suitable height When spending, first hoist 5 is closed.Parcel shelf 4 is fulcrum with supporting rod 43, occurs to turn under the pulling force effect for tilting rope 421 It is dynamic so that the earthwork on parcel shelf 4 is fallen to along guide plate 7 on conveying equipment under the effect of gravity.Soil on parcel shelf 4 After side falls, reversion second hoist 6 is so that parcel shelf 4 moves to horizontal position.In the feelings for not closing second hoist 6 Under condition, start first hoist 5 and put rope, first hoist 5 and second hoist 6 are closed when parcel shelf 4 drops on crossbeam 1, Next it is to repeat the transport that above-mentioned step carries out the earthwork.
This specific embodiment is only explanation to the utility model, is not the limitation to the utility model, ability Field technique personnel can as needed make the present embodiment the modification of no creative contribution after this specification is read, but As long as within the protection scope of the present utility model all protected by Patent Law.

Claims (8)

1. a kind of earth excavation conversion platform, which is characterized in that including the column being vertically arranged(3)And set on the column (3)On crossbeam(1), the crossbeam(1)There are two and be arranged in parallel, the crossbeam(1)Using reinforced concrete structure;It is described Crossbeam(1)On be shelved with parcel shelf for loading the earthwork(4), the parcel shelf(4)Both ends be connected separately with ropes (411)With tilting rope(421), the ropes(411)With tilting rope(421)Upper separate parcel shelf(4)One end point First hoist is not connected with it(5)And second hoist(6), and the ropes(411)With tilting rope(421)Set on Column(3)The fixed pulley at top(31)Guiding under respectively by first hoist(5)And second hoist(6)Rope closing is put Rope.
A kind of 2. earth excavation conversion platform according to claim 1, which is characterized in that the parcel shelf(4)Bottom It is rotatably connected to the telescopic supporting rod being vertically arranged(43), and the supporting rod(43)Positioned at parcel shelf(4)Equipped with promotion Rope(411)One end.
A kind of 3. earth excavation conversion platform according to claim 2, which is characterized in that the parcel shelf(4)It is equipped with Two pieces of guide plates being defined for position when falling to the earthwork(7), two pieces of guide plates(7)It is symmetrically disposed on glove Plate(4)Upper close ropes(411)One end.
A kind of 4. earth excavation conversion platform according to claim 3, which is characterized in that the guide plate(7)One end It is rotationally connected with the parcel shelf(4)On, the guide plate(7)On be equipped with for lock rotate after guide plate(7)Position The fixing bolt put(71), work as guide plate(7)Position it is locked when, the fixing bolt(71)One end push against put in described Object plate(4)On.
A kind of 5. earth excavation conversion platform according to claim 1, which is characterized in that the parcel shelf(4)On open up There is the groove that section is V-arrangement(8), the groove(8)Along parcel shelf(4)It is upper to be equipped with ropes certainly(411)One end to glove Plate(4)It is equipped with and tilts rope(421)One end direction setting.
A kind of 6. earth excavation conversion platform according to claim 5, which is characterized in that the parcel shelf(4)It is equipped with Ropes(411)One end be provided with baffle(9).
A kind of 7. earth excavation conversion platform according to claim 1, which is characterized in that the crossbeam(1)It is equipped with secondary Beam(12), the secondary beam(12)Perpendicular to crossbeam(1)Setting.
A kind of 8. earth excavation conversion platform according to claim 1, which is characterized in that the crossbeam(1)It is equipped with and uses It is transported in facilitating the earthwork from foundation pit to parcel shelf(4)On guiding slope(11).
CN201721448894.6U 2017-11-02 2017-11-02 A kind of earth excavation conversion platform Expired - Fee Related CN207512746U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721448894.6U CN207512746U (en) 2017-11-02 2017-11-02 A kind of earth excavation conversion platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721448894.6U CN207512746U (en) 2017-11-02 2017-11-02 A kind of earth excavation conversion platform

Publications (1)

Publication Number Publication Date
CN207512746U true CN207512746U (en) 2018-06-19

Family

ID=62536813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721448894.6U Expired - Fee Related CN207512746U (en) 2017-11-02 2017-11-02 A kind of earth excavation conversion platform

Country Status (1)

Country Link
CN (1) CN207512746U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112479049A (en) * 2020-12-09 2021-03-12 武汉市明煌建筑劳务有限公司 Cement building prefab turning device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112479049A (en) * 2020-12-09 2021-03-12 武汉市明煌建筑劳务有限公司 Cement building prefab turning device
CN112479049B (en) * 2020-12-09 2022-08-23 维漫科技(中山)有限公司 Cement building prefab turning device

Similar Documents

Publication Publication Date Title
TW201130713A (en) Deck-elevation-type operation platform-like vehicle and construction method for marine wind power generation facility
CN207512746U (en) A kind of earth excavation conversion platform
CN210737607U (en) A hang braced system for reverse construction method beam slab construction
CN211006749U (en) Easily build formula tower crane foundation structure with prevent falling
CN108104108B (en) Construction equipment and method for shallow in-situ solidification of waste sludge
CN201419898Y (en) Horizontal type storage tank for mortar to be mixed
CN109083442A (en) The construction method of dynamic load bearing structure when existing building is docked with newly-built basis
CN214495489U (en) Rigid landfill operation system
CN209740548U (en) Gantry crane system suitable for deep foundation pit load-carrying vehicle vertical transportation
JP2006071323A (en) Reactor pressure vessel carrying-out method and reactor pressure vessel carrying-in method
CN110980504A (en) A turn over sediment soil collecting box for super deep shaft construction vertical transport system
CN204875664U (en) A retaining wall structure for interim pier in bay
CN113023562A (en) Soil body taking and transporting device and method for existing building underground space development
JP5557667B2 (en) Equipment capacity determination method and equipment in pneumatic caisson method
CN210340170U (en) Detachable multipurpose movable support integrating transportation and hoisting
JP5508488B2 (en) Skater crane
EP4103785A1 (en) Method for introducing a soil penetrating tool into a soil and underground construction device
CN215476699U (en) TRD replacement soil storage device
CN202228859U (en) Mudflat construction equipment and barrel-shaped foundation thereof
CN105390173A (en) Disposal site of radioactive solid waste in nuclear power station
JP3308958B2 (en) Construction method and form carrier for landfill structures
CN212315450U (en) Manual hole digging pile lifting and unearthing device
CN219730423U (en) Lifting machine for building engineering
JPH06257142A (en) Reinforcement cage installing device and reinforcement cage assembling and installing method using this device
CN220334633U (en) Frame type artificial hole digging pile lifting frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180619

Termination date: 20211102

CF01 Termination of patent right due to non-payment of annual fee