CN207445943U - Waste gas cleaning system - Google Patents

Waste gas cleaning system Download PDF

Info

Publication number
CN207445943U
CN207445943U CN201721445598.0U CN201721445598U CN207445943U CN 207445943 U CN207445943 U CN 207445943U CN 201721445598 U CN201721445598 U CN 201721445598U CN 207445943 U CN207445943 U CN 207445943U
Authority
CN
China
Prior art keywords
waste gas
gas
cleaning system
treatment equipment
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721445598.0U
Other languages
Chinese (zh)
Inventor
张平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Haisile Gas Treatment Equipment Co Ltd
Original Assignee
Jiangsu Haisile Gas Treatment Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Haisile Gas Treatment Equipment Co Ltd filed Critical Jiangsu Haisile Gas Treatment Equipment Co Ltd
Priority to CN201721445598.0U priority Critical patent/CN207445943U/en
Application granted granted Critical
Publication of CN207445943U publication Critical patent/CN207445943U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model is related to waste gas cleaning systems, include gas gathering mask successively along air-flow moving direction, precooling tower, activated carbon adsorber, desulfurizing tower, plasma waste gas treatment equipment and exhaust chimney, the gas gathering mask, precooling tower, activated carbon adsorber, desulfurizing tower, plasma waste gas treatment equipment and exhaust chimney are sequentially connected by discharge duct, the first wind turbine and gas flow control valve are equipped between the gas gathering mask and the precooling tower, the second wind turbine is equipped between the plasma waste gas treatment equipment and exhaust chimney, the waste gas cleaning system, diversified processing can be carried out for the exhaust gas of complicated component, make the discharge meet the requirement of environmental protection of exhaust gas.

Description

Waste gas cleaning system
Technical field
The utility model is related to field of Environment Protection more particularly to waste gas cleaning systems.
Background technology
Waste gas purification is primarily referred to as the industrial waste gas generated for industrial site, such as dust particle, flue gas flue dust, different The work that taste gas, toxic and harmful gas are administered.Common waste gas purification has factory's fume and exhaust gas purifying, workshop dust to give up Gas purification, organic waste-gas purification, acid-base waste gas purifying, purification of chemical waste gas and foul smell deodorization purification etc..Since exhaust gas generates Situation variation, many exhaust gas constituents are complicated, and the exhaust gas constituents that often different time sections generate are all different, to processing when cause compared with Big influence causes exhaust-gas treatment to be unable to reach the effect of needs, is unfavorable for environmental protection.
Utility model content
In order to solve the above technical problems, the purpose of this utility model is to provide waste gas cleaning system, for complicated component Exhaust gas can carry out diversified processing, make the discharge meet the requirement of environmental protection of exhaust gas.
The waste gas cleaning system of the utility model includes gas gathering mask, precooling tower, activated carbon along air-flow moving direction and inhales successively Attached tower, desulfurizing tower, plasma waste gas treatment equipment and exhaust chimney, the gas gathering mask, precooling tower, activated carbon adsorber, desulfurization Tower, plasma waste gas treatment equipment and exhaust chimney are sequentially connected by discharge duct, the gas gathering mask and the precooling tower Between be equipped with the first wind turbine and gas flow control valve, between the plasma waste gas treatment equipment and exhaust chimney be equipped with second Wind turbine.
Further, wind-guiding isocon, the plasma are installed at the air inlet of the plasma waste gas treatment equipment Reducer pipe is installed at the gas outlet of waste gas treatment equipment.
Further, the gas gathering mask is in horn-like that the gas gathering mask is connected with external exhaust gas seal for pipe joints.
Further, first wind turbine is axial flow blower.
Further, second wind turbine is centrifugal blower.
Further, the height of the precooling tower is the half of the height of the desulfurizing tower.
Further, the activated carbon adsorber is identical with the volume of the plasma waste gas treatment equipment.
Further, the top installation rain hat of the exhaust chimney.
According to the above aspect of the present invention, the utility model at least has the following advantages:The waste gas cleaning system of the utility model passes through Gas gathering mask collects exhaust gas, by precooling tower cooler exhaust gas, prevents the gas fuel burning in exhaust gas, passes through activated carbon adsorber profit The organic exhaust gas in exhaust gas is handled with the mode of absorption, desulfurization process is carried out to exhaust gas by desulfurizing tower, passes through plasma exhaust gas Processing equipment carries out diversified processing come the pollutant in exhaust gas of degrading, so as to fulfill for the exhaust gas of complicated component, makes to give up The discharge meet the requirement of environmental protection of gas.
Above description is only the general introduction of technical solutions of the utility model, in order to better understand the skill of the utility model Art means, and being practiced according to the content of specification with the preferred embodiment of the utility model and coordinate attached drawing detailed below It describes in detail bright as after.
Description of the drawings
Fig. 1 is the structure diagram of the utility model.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiment of the present utility model is described in further detail.Below Embodiment is not intended to limit the scope of the present invention for illustrating the utility model.
Referring to Fig. 1 waste gas cleaning systems, include gas gathering mask 1, precooling tower 2, activated carbon adsorption successively along air-flow moving direction Tower 3, desulfurizing tower 4, plasma waste gas treatment equipment 5 and exhaust chimney 6, it is the gas gathering mask, precooling tower, activated carbon adsorber, de- Sulphur tower, plasma waste gas treatment equipment and exhaust chimney are sequentially connected by discharge duct, the gas gathering mask and the precooling The first wind turbine 7 and gas flow control valve 8 are equipped between tower, is equipped between the plasma waste gas treatment equipment and exhaust chimney Second wind turbine 9.
Wind-guiding isocon 10, the plasma exhaust-gas treatment are installed at the air inlet of the plasma waste gas treatment equipment Reducer pipe 11 is installed at the gas outlet of equipment.
The gas gathering mask is in horn-like, and the gas gathering mask is connected with external exhaust gas seal for pipe joints.
First wind turbine is axial flow blower.
Second wind turbine is centrifugal blower.
The height of the precooling tower is the half of the height of the desulfurizing tower.
The activated carbon adsorber is identical with the volume of the plasma waste gas treatment equipment.
The top installation rain hat 12 of the exhaust chimney.
The waste gas cleaning system collects exhaust gas by gas gathering mask, by precooling tower cooler exhaust gas, prevents flammable in exhaust gas Gas burns, and the organic exhaust gas in exhaust gas is handled in a manner that activated carbon adsorber is using absorption, by desulfurizing tower to exhaust gas Desulfurization process is carried out, by plasma waste gas treatment equipment come the pollutant in exhaust gas of degrading, so as to fulfill for complicated component Exhaust gas carry out diversified processing, make the discharge meet the requirement of environmental protection of exhaust gas.
The above is only the preferred embodiment of the utility model, is not intended to limit the utility model, it is noted that For those skilled in the art, on the premise of the utility model technical principle is not departed from, can also do Go out several improvement and modification, these improvements and modifications also should be regarded as the scope of protection of the utility model.

Claims (8)

1. waste gas cleaning system, it is characterised in that:Include gas gathering mask, precooling tower, activated carbon adsorption successively along air-flow moving direction Tower, desulfurizing tower, plasma waste gas treatment equipment and exhaust chimney, the gas gathering mask, precooling tower, activated carbon adsorber, desulfurizing tower, Plasma waste gas treatment equipment and exhaust chimney are sequentially connected by discharge duct, between the gas gathering mask and the precooling tower Equipped with the first wind turbine and gas flow control valve, the second wind is equipped between the plasma waste gas treatment equipment and exhaust chimney Machine.
2. waste gas cleaning system according to claim 1, it is characterised in that:The air inlet of the plasma waste gas treatment equipment Wind-guiding isocon is installed at mouthful, reducer pipe is installed at the gas outlet of the plasma waste gas treatment equipment.
3. waste gas cleaning system according to claim 2, it is characterised in that:The gas gathering mask is in horn-like, the gas collection Cover is connected with external exhaust gas seal for pipe joints.
4. waste gas cleaning system according to claim 3, it is characterised in that:First wind turbine is axial flow blower.
5. waste gas cleaning system according to claim 4, it is characterised in that:Second wind turbine is centrifugal blower.
6. waste gas cleaning system according to claim 5, it is characterised in that:The height of the precooling tower is the desulfurizing tower Height half.
7. waste gas cleaning system according to claim 6, it is characterised in that:The activated carbon adsorber and the plasma The volume of waste gas treatment equipment is identical.
8. waste gas cleaning system according to claim 7, it is characterised in that:The top installation of the exhaust chimney is rainy Cap.
CN201721445598.0U 2017-11-02 2017-11-02 Waste gas cleaning system Expired - Fee Related CN207445943U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721445598.0U CN207445943U (en) 2017-11-02 2017-11-02 Waste gas cleaning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721445598.0U CN207445943U (en) 2017-11-02 2017-11-02 Waste gas cleaning system

Publications (1)

Publication Number Publication Date
CN207445943U true CN207445943U (en) 2018-06-05

Family

ID=62253428

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721445598.0U Expired - Fee Related CN207445943U (en) 2017-11-02 2017-11-02 Waste gas cleaning system

Country Status (1)

Country Link
CN (1) CN207445943U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110833756A (en) * 2018-08-16 2020-02-25 台山市世隆塑料有限公司 Waste gas purification system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110833756A (en) * 2018-08-16 2020-02-25 台山市世隆塑料有限公司 Waste gas purification system

Similar Documents

Publication Publication Date Title
CN107638781A (en) Waste gas cleaning system with self-checking unit
CN101619881B (en) Dedusting system of whole factory building
CN207445920U (en) Waste gas cleaning system with self-checking unit
CN208959603U (en) A kind of new waste gas purification treatment device
CN205586754U (en) Industry organic waste gas purification device
CN207445943U (en) Waste gas cleaning system
CN107596888A (en) Waste gas cleaning system
CN205392088U (en) Burn burning furnace exhaust treatment device
CN201140014Y (en) Waste gas treating device
CN107413148A (en) A kind of cleaning system
CN106943838A (en) Alternative waste gas cleaning system
CN207562614U (en) A kind of waste gas treatment equipment stovepipe rain-proof structure
CN202427317U (en) Flue gas purifying device
CN205627481U (en) Dual thorough tail gas dust processor
CN205127743U (en) Be used for flue gas denitration system
CN207169317U (en) A kind of vcehicular tunnel dedusting and purifying device based on soil sanitation method
CN204220057U (en) The pulping device of a kind of automatic water supplement and lime
CN207600185U (en) A kind of integrated dedusting device that overturning is servo-actuated for intermediate frequency furnace
CN205948674U (en) Ultralow discharging equipment of coal fired boiler smoke pollutants
CN201543337U (en) Air purifier
CN106984135A (en) A kind of cleaning system for paint spray booth exhaust-gas treatment
CN203099870U (en) Cremation machine smoke and dust decontamination device
CN212167047U (en) Acid gas innocent treatment device of production place
CN207838665U (en) Plasma photooxidation catalytic waste gas processing equipment
CN109954393A (en) Workshop smoke and dust purifier and its control system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180605