CN207348085U - Composite foundation reinforcement gabion baffling structure - Google Patents

Composite foundation reinforcement gabion baffling structure Download PDF

Info

Publication number
CN207348085U
CN207348085U CN201721250581.XU CN201721250581U CN207348085U CN 207348085 U CN207348085 U CN 207348085U CN 201721250581 U CN201721250581 U CN 201721250581U CN 207348085 U CN207348085 U CN 207348085U
Authority
CN
China
Prior art keywords
gabion
composite foundation
filling body
reinforced
tgxg
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721250581.XU
Other languages
Chinese (zh)
Inventor
刘波
牛运华
石志超
陈培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changjiang Institute of Survey Planning Design and Research Co Ltd
Original Assignee
Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changjiang Institute of Survey Planning Design and Research Co Ltd filed Critical Changjiang Institute of Survey Planning Design and Research Co Ltd
Priority to CN201721250581.XU priority Critical patent/CN207348085U/en
Application granted granted Critical
Publication of CN207348085U publication Critical patent/CN207348085U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses composite foundation reinforcement gabion baffling structure, it includes composite foundation (1), reinforced gabion (2), TGXG (3), loaded filter (4) and filling body (5) composition;The composite foundation (1) locates below ground level and is made of more vibro-replacement stone columns (1.1), multiple reinforced gabions (2) are piled up in the top of the composite foundation (1), filling body (5) is provided with the inside of the reinforced gabion (2), the lower part of the filling body (5) is provided with TGXG (3), loaded filter (4) is provided between the reinforced gabion (2) and the filling body (5);The shortcomings that it is overcome in the prior art since foundation bearing capacity is relatively low, and the filling body after barricade and its wall is by larger deformation or even unstable failure is occurred, has the advantages that easy construction, speed of application be fast, wall body low cost.

Description

Composite foundation reinforcement gabion baffling structure
Technical field
The technical fields such as water conservancy, highway and water and soil conservation are the utility model is related to, are more specifically composite foundations Reinforcement gabion baffling structure.
Background technology
During the filling of the engineerings such as shore protection levee body, highway subgrade, Dumping Sites, generally use barricade resists pressure of banketing Power.When above-mentioned engineering construction is located at coastal region, river and lake seashore, mollisol area, deep covering layer area, earth formation is more It is made of Extra-fine sand, silt, silty clay, muck soil, traditional barrier wall structure can not meet filling body after itself and its wall Stability requirement, must be combined using other modes with barricade, the pressure of banketing after sharing lood wall.
Traditional barricade material is concrete or stone masonry, and concrete guard wall is related to concrete production, transports, pours, applies Construction equipment is more, complex procedures;Stone masonry barricade needs manually to build by laying bricks or stones, expends substantial amounts of manpower, speed of application is slow.Chinese patent CN104674841B puts block stone using machinery and quickly forms retaining wall, although improving the degree of barricade mechanized construction, adds The fast speed of application of barricade, but it faces same problem with concrete guard wall, stone masonry barricade:When running into above-mentioned geology bar During the poor situation of part, since foundation bearing capacity is relatively low, the filling body after barricade and its wall will occur larger deformation or even Unstable failure, therefore should not directly be used on mollisol, deep covering layer ground.Chinese patent CN205116214U, Although CN104389320B, CN103321243B are using bored concrete pile, micro-steel pile, screw rod pile, rotary churning pile, mixing pile to barricade Ground has carried out consolidation process, but above-mentioned pile body is plain concrete or reinforced concrete structure, complicated construction technique, work of constructing Phase is grown, and project cost is high.
When filling body height is higher after barricade, pressure of banketing only is resisted in itself by barricade, can cause bricklaying constructed object Product is huge while higher to the requirement for bearing capacity of ground, and construction cost is also higher.
The content of the invention
The purpose of the utility model is to overcome the shortcoming of above-mentioned background technology, and propose composite foundation reinforcement gabion Barrier wall structure.
The purpose of this utility model is implemented by following technical solution:Composite foundation reinforcement gabion baffling structure, It includes composite foundation, reinforced gabion, TGXG, loaded filter and filling body composition;The composite foundation be located at ground with Lower and be made of more vibro-replacement stone columns, multiple reinforced gabions are piled up in the top of the composite foundation, described Reinforced gabion on the inside of be provided with filling body, the lower part of the filling body is provided with TGXG, in the reinforcing bar stone Loaded filter is provided between cage and the filling body.
In the above-mentioned technical solutions:The outer ledge of the vibro-replacement stone column along the reinforced gabion expands arrangement 2- 3 campsheds.
In the above-mentioned technical solutions:The reinforced gabion is formed using site welding and piles up into triangle;It is and adjacent The reinforced gabion between the fissure of displacement pile up and use it is U-shaped nail be linked to be an entirety.
In the above-mentioned technical solutions:The reinforced gabion includes keel reinforcing bar and fabricated bar, the fabricated bar Between using galvanized wire bind;The keel reinforcing bar be located at the outside of the fabricated bar and be welded to each other into one it is whole Body.
In the above-mentioned technical solutions:The TGXG layered arrangement is and described in the inside of the filling body Filling body is stacked from bottom to top along the bottom of the TGXG;The TGXG lateral length is more than twice of institute The height for the reinforced gabion stated.
In the above-mentioned technical solutions:The loaded filter is in tilted layout along on the inside of the reinforced gabion, and described is anti- The upper end of filtering layer is flushed with the upper end of the reinforced gabion.
The utility model has the following advantages that:1st, steel bar stone cage retaining wall can adapt to certain deformation, especially soft It is more more notable than the advantage of rigid structure barricade in the case of soil base or deep covering layer ground.
2nd, steel bar stone cage retaining wall can be process using reinforcing bar and block building stones at the construction field (site), easy for construction, speed of application It hurry up.
3rd, consolidation process is carried out to barricade ground using vibro-replacement stone column, live metaling can be made full use of, with concrete Stake or reinforced concrete pile are compared, and without purchasing reinforcing bar, cement, construction technology is easy, quick.When stake footpath is 60cm, stake is a length of During 8m, concrete-pile comprehensive unit price is 66 yuan/m, and vibro-replacement stone column comprehensive unit price is 45 yuan/m, and pile body cost can reduce by 30% More than.
The 4th, TGXG is set in the filling body after barricade, it is possible to increase the globality and non-deformability of filling body, energy Enough reduce the soil pressure suffered by wall, so as to reduce barricade bricklaying volume and its requirement for bearing capacity to ground, save engineering Investment.
Brief description of the drawings
Fig. 1 is the structural plan of the utility model.
Fig. 2 is the structural plan of reinforced gabion in the utility model.
Fig. 3 is the floor plan of the vibro-replacement stone column in the utility model.
In figure:Composite foundation 1, vibro-replacement stone column 1.1, reinforced gabion 2, keel reinforcing bar 2.1, fabricated bar 2.2, Tu Gongge Grid 3, loaded filter 4, filling body 5.
Embodiment
Describe the performance of the utility model in detail below in conjunction with the accompanying drawings, but they are not formed to the utility model Limit, it is only for example;The advantages of the utility model, will become clearer and be readily appreciated that by explanation at the same time.
The composite foundation 1 be using vibroreplacement to original soft foundation or deep covering layer ground at Vibro-replacement stone pile composite foundation after reason, its bearing capacity should meet the requirement of barricade resistant slide and antidumping.Through vibro-replacement stone Bearing Capacity of Composite Foundation R after 1.1 consolidation process of stakesp=[1+m (n-1)] × Rs;RsFor the bearing capacity of original ground;M is to shake Rush the replacement rate of broken stone pile 1.1, m=AP/As, APFor the sectional area of broken stone pile, AsFor the area of composite foundation;N is vibro-replacement stone The load intensity share ratio of 1.1 pile bodies of stake and inter-pile soil, n=Rp/Rs;RpFor the bearing capacity of vibro-replacement stone column 1.1.Vibro-replacement stone Stake 1.1 arranges that retaining wall foundation outer rim expands 2-3 campsheds, and stake footpath D, stake spacing L are counted according to above-mentioned formula using equilateral triangle Point counting analysis determines.
The reinforced gabion 2 is welded at the construction field (site), and single size is 2m × 1m × 1m (length × width × height).Dragon Bone reinforcing bar 2.1 is located at the outside of fabricated bar 2.2, and is welded with fabricated bar 2.2, and galvanized wire is used between fabricated bar 2.2 Binding.Reinforced gabion 2 is located on composite foundation, and 2 fissure of displacement of adjacent two layers reinforced gabion is piled up, and all reinforced gabions 2 are adopted each other It is linked to be entirety with U-shaped nail.Block stone grain footpath in reinforced gabion 2 is 25-40cm, and is fresh dysgeogenous rock.
The layering of TGXG 3 is arranged at the inside of filling body 5 after reinforced gabion 2, the lift height of the TGXG 3 50 centimetres.Laying length of the TGXG 3 in filling body can be determined according to actual conditions, be typically no less than twice of reinforced gabion 2 stacking height.
The loaded filter 4 is between reinforced gabion 2 and filling body 5,1 meter of 4 thickness of loaded filter, to prevent Thin particulate matter after barricade in filling body 5 is pulled away.Loaded filter 4 fills material and uses fresh building stones, and particle diameter should meet relevant Grading requirement.
With reference to shown in Fig. 1-3:Composite foundation reinforcement gabion baffling structure, it includes composite foundation 1, reinforced gabion 2, geotechnique Grid 3, loaded filter 4 and filling body 5 form;The composite foundation 1 locates below ground level and by more 1.1 groups of vibro-replacement stone column Into multiple reinforced gabions 2 are piled up in the top of the composite foundation 1, are set in the side of the reinforced gabion 2 There is filling body 5, the lower part of the filling body 5 is provided with TGXG 3, in the reinforced gabion 2 and the geotechnological lattice Loaded filter 4 is provided between grid 3.
The outer ledge of the vibro-replacement stone column 1.1 along the reinforced gabion 2 expands arrangement 2-3 campsheds.
The reinforced gabion 2 is formed using site welding and is piled up into triangle;And the adjacent reinforced gabion 2 Between the fissure of displacement pile up and use it is U-shaped nail be linked to be an entirety.
The reinforced gabion 2 includes keel reinforcing bar 2.1 and fabricated bar 2.2, is used between the fabricated bar 2.2 Galvanized wire is bound;The keel reinforcing bar 2.1 be located at the outside of the fabricated bar 2.2 and be welded to each other into one it is whole Body.
3 layered arrangement of TGXG is in the inside of the filling body 5, and the filling body 5 is along described The bottom of TGXG 3 stack from bottom to top;3 lateral length of TGXG is more than twice of the reinforced gabion 2 height.
The loaded filter 4 is in tilted layout along the inner side of the reinforced gabion 2, the upper end of the loaded filter 4 and institute The upper end for the reinforced gabion 2 stated flushes.
The utility model further includes the construction method of composite foundation reinforcement gabion baffling structure, it includes the following steps;
1., preparation of construction:Needed to carry out levelling of the land, construction cushion coat laying, stake position unwrapping wire and construction equipment according to construction Arrangement in place, adjustment vibrating impacter water spray center are less than 5 centimetres with design stake position centre deviation;
2., vibrating and impacting construction of ballast pile:Determined according to the stake footpath size of foundation soil situation and the vibro-replacement stone column 1.1 needed Vibrating impacter model, the sequence of construction of more vibro-replacement stone columns 1.1 are:In vibrating impacter centering in place → vibroflotation pore-forming, plasma discharge → hole Filler, vibratory compaction → carry out next stage vibroflotation, until forming vibro-replacement stone column 1.1 in the foundation soil of composite foundation 1;When one After vibro-replacement stone column 1.1, the position of mobile vibrating impacter to next vibro-replacement stone column 1.1 carries out stake processed;
3., steel bar stone cage retaining wall construction:Single steel reinforcement cage is transported to Retaining wall field in the prefabricated completion of reinforcement yard Ground, after piling up steel reinforcement cage according to design requirement, then fills building stones into single steel reinforcement cage.Keel reinforcing bar 2.1 is located at fabricated bar 2.2 outside, and welded with fabricated bar 2.2, bound between fabricated bar 2.2 with galvanized wire.2.1 trade mark of keel reinforcing bar is HRB400, diameter 20mm.2.2 trade mark of fabricated bar is HPB235, and diameter 10mm, size of mesh opening is 20cm × 20cm.Reinforcing bar stone Cage 2 is located on composite foundation, and 2 fissure of displacement of adjacent two layers reinforced gabion is piled up, and all reinforced gabions 2 are linked to be using U-shaped nail each other It is overall.
4., embankment construction after barricade;Filling body 5 is provided with after the reinforced gabion 2, the filling body 5 is adopted With placement in layers, grinding compacting;TGXG 3, which is layered, to be arranged in the filling body 5, and the TGXG 3 is layered thickness Spend 50cm;Height of laying length of the TGXG 3 in the filling body 5 not less than twice of reinforced gabion 2; Loaded filter 4, the thickness 1m of the loaded filter 4 are set between the side of the reinforced gabion 2 and the filling body 5;It is described Loaded filter 4 fill material and use fresh building stones, particle diameter should meet the requirement of relevant grading.
The filling body 5, reinforced gabion 2,4 three of loaded filter using concordant construction and synchronous rise.
The loaded filter 4 is in tilted layout along the inner side of the reinforced gabion 2, the upper end of the loaded filter 4 and institute The upper end for the reinforced gabion 2 stated flushes.
Above-mentioned unspecified part is the prior art.

Claims (6)

1. composite foundation reinforcement gabion baffling structure, it is characterised in that:It includes composite foundation (1), reinforced gabion (2), geotechnique Grid (3), loaded filter (4) and filling body (5) composition;The composite foundation (1) locates below ground level and broken by more vibroflotations Stone mar (1.1) forms, and multiple reinforced gabions (2) are piled up in the top of the composite foundation (1), in the reinforcing bar Filling body (5) is provided with the inside of gabion (2), the lower part of the filling body (5) is provided with TGXG (3), described Loaded filter (4) is provided between reinforced gabion (2) and the filling body (5).
2. composite foundation reinforcement gabion baffling structure according to claim 1, it is characterised in that:The vibro-replacement stone column (1.1) arrangement 2-3 campsheds are expanded along the outer ledge of the reinforced gabion (2).
3. composite foundation reinforcement gabion baffling structure according to claim 1 or 2, it is characterised in that:The reinforcing bar stone Cage (2) is formed using site welding and piles up into triangle;And the fissure of displacement is piled up and adopted between the adjacent reinforced gabion (2) It is linked to be an entirety with U-shaped nail.
4. composite foundation reinforcement gabion baffling structure according to claim 3, it is characterised in that:The reinforced gabion (2) include keel reinforcing bar (2.1) and fabricated bar (2.2), bound between the fabricated bar (2.2) using galvanized wire; The keel reinforcing bar (2.1) is located at the outside of the fabricated bar (2.2) and is welded to each other into an entirety.
5. composite foundation reinforcement gabion baffling structure according to claim 4, it is characterised in that:The TGXG (3) layered arrangement is in the inside of the filling body (5), and bottom of the filling body (5) along the TGXG (3) Stack from bottom to top in portion;The height of the reinforced gabion (2) of described TGXG (3) lateral length more than twice.
6. composite foundation reinforcement gabion baffling structure according to claim 5, it is characterised in that:The loaded filter (4) It is in tilted layout along on the inside of the reinforced gabion (2), the upper end of the loaded filter (4) and the reinforced gabion (2) Upper end flushes.
CN201721250581.XU 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure Active CN207348085U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721250581.XU CN207348085U (en) 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721250581.XU CN207348085U (en) 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure

Publications (1)

Publication Number Publication Date
CN207348085U true CN207348085U (en) 2018-05-11

Family

ID=62357315

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721250581.XU Active CN207348085U (en) 2017-09-27 2017-09-27 Composite foundation reinforcement gabion baffling structure

Country Status (1)

Country Link
CN (1) CN207348085U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107842036A (en) * 2017-09-27 2018-03-27 长江勘测规划设计研究有限责任公司 Composite foundation reinforcement gabion baffling structure and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107842036A (en) * 2017-09-27 2018-03-27 长江勘测规划设计研究有限责任公司 Composite foundation reinforcement gabion baffling structure and construction method

Similar Documents

Publication Publication Date Title
CN107419630A (en) A kind of the soft soil foundation high-filled embankment and construction method of effectively control settlement after construction
CN106988178A (en) A kind of subgrade in soft soil zone widened structure and its construction method
CN107842036A (en) Composite foundation reinforcement gabion baffling structure and construction method
CN206902488U (en) A kind of soft soil foundation high-filled embankment of effectively control settlement after construction
CN108560542A (en) A kind of waste tire cladding builds the two-directed reinforcement and its construction method of slag
CN106836244A (en) Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall
CN103510504B (en) High saturated uneven reclaimed ground processing method
CN109680671A (en) A kind of liquefaction foundation treatment method based on building waste
CN112195910A (en) Soft foundation treatment structure and construction method for earth-rock dam reinforced by vibroflotation gravel pile and rockfill
CN215976664U (en) Rigid pile composite foundation treatment structure of lower horizontal pipe gallery structure
CN108824412B (en) Soft foundation treatment method based on gabion wall reinforced soil and dynamic compaction combination
CN206902734U (en) A kind of earth construction of soft foundation zone
CN213390201U (en) Earth-rock dam soft foundation treatment structure with reinforced vibro-replacement gravel pile and rockfill
CN207348085U (en) Composite foundation reinforcement gabion baffling structure
CN107514008A (en) Composite foundation reinforced cantilever retaining wall structure and construction method
CN201339186Y (en) Soft rock concrete replacement pile composite foundation
CN108643172A (en) Silt geology vibro-replacement stone compacting pile construction method
CN210238543U (en) Inclined slope surface layered backfill dynamic compaction leveling structure
CN107558490A (en) Composite foundation reinforcement rockfill barrier wall structure and construction method
CN207452938U (en) Composite foundation reinforced cantilever retaining wall structure
CN108677999B (en) Silt bagged soil retaining wall structure and construction method
CN207419517U (en) Composite foundation reinforcement rockfill barrier wall structure
CN110172988A (en) A kind of piling formula composite concrete placement ground and its construction method
CN215977211U (en) Structure is handled to compound foundation of tubular pile combination cement mixing pile
CN109653241A (en) Composite foundation reinforcement counterfort wall structure and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant