- CN207296567U CN207296567U CN201721007165.7U CN201721007165U CN207296567U CN 207296567 U CN207296567 U CN 207296567U CN 201721007165 U CN201721007165 U CN 201721007165U CN 207296567 U CN207296567 U CN 207296567U
- Authority
- CN
- China
- Prior art keywords
- tower
- bar
- prefabricated section
- tower bar
- secondary pedestal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000004891 communication Methods 0.000 title claims abstract description 43
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical group C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 67
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 4
- 238000012544 monitoring process Methods 0.000 claims description 11
- 239000000523 sample Substances 0.000 claims description 10
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 8
- 229910052742 iron Inorganic materials 0.000 claims description 4
- 238000005266 casting Methods 0.000 claims description 3
- 239000004973 liquid crystal related substance Substances 0.000 claims description 3
- 239000007787 solid Substances 0.000 claims 1
- 238000003466 welding Methods 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 5
- 238000010276 construction Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 238000007493 shaping process Methods 0.000 description 2
- 239000004567 concrete Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000005286 illumination Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000000007 visual effect Effects 0.000 description 1
Landscapes
- Support Of Aerials (AREA)
Abstract
A kind of intelligence communication bar, including tower body and column foot, column foot includes the main basal base, secondary pedestal and connecting seat of reinforced concrete structure, the of length no more than 10m of tower body, tower body includes the first tower bar, the second tower bar, the 3rd tower bar and the 4th tower bar connected by casing from bottom to top, and tower body is equipped with multiple functions component.The utility model has the advantages that tower-base structure, and rationally tower body firm, easy to assembly is integrated with multiple functions.
Description
Technical field
Communication tower field is the utility model is related to, especially a kind of intelligence communication bar.
Background technology
Communication tower is being set up, it is necessary to pour pedestal below tower body, communication tower is being fixed on pedestal.According to communication tower
Size, pedestal can be provided in the foundation pit of pre- digging and be embedded in underground, can also be set directly on ground.Existing communication
The pedestal of tower is typically to use an entirety of concrete cast in situs in the position for building communication tower, when communication tower tower body needs
When replacing position, original place can only be discarded in by pouring integral pedestal, can not be moved to replace position.Also, the function of communication tower
It is single.
Utility model content
To solve the above-mentioned problems, the purpose of this utility model is to provide a kind of reasonable firm, the assembling side of tower-base structure
Just tower body is integrated with the intelligence communication bar of multiple functions.
In order to realize above-mentioned purpose, the utility model employs following technical solution:
A kind of intelligence communication bar, including tower body and column foot, the main basal base of column foot including reinforced concrete structure, secondary pedestal and
Connecting seat, main basal base include the identical main basal base prefabricated section of three sizes, and each main basal base prefabricated section is set up in parallel and by long spiral shell
Bar connects;Crab-bolt that is multiple longitudinally disposed and being distributed in the horizontal plane with circumference array is fixed with connecting seat, connecting seat is set
Positioned at the top of middle prefabricated section, the centre position in the prefabricated section is simultaneously molded with the prefabricated section formed by integrally casting;Secondary base
Seat is placed directly within above main basal base, and secondary pedestal includes the identical secondary pedestal prefabricated section of four structures, and secondary pedestal prefabricated section is in cube
Body, secondary pedestal prefabricated section staggeredly splices to be set around connecting seat, and the long side and short side of adjacent two secondary pedestal prefabricated sections are direct
Adjacent, the communication tower pedestal after the completion of assembly, the outer edge of secondary pedestal aligns with the outer edge of main basal base, and the height of connecting seat is high
In the height of secondary pedestal prefabricated section;The of length no more than 10m of tower body, tower body include the first tower connected by casing from bottom to top
Bar, the second tower bar, the 3rd tower bar and the 4th tower bar, the tower bar for forming tower body is pipe of the caliber in 0.1-0.3m, described
First tower bar, the second tower bar, the length ratio of the 3rd tower bar and the 4th tower bar are 3:3:3:1;The lower end of first tower bar is equipped with method
Blue plate, which, which is equipped with, is used to be fixed on the connecting seat of column foot with the matched flange hole of crab-bolt on column foot, the first tower bar
On;First tower bar is equipped with charging pile, and installing advertisement board and monitoring probe in the second tower bar, billboard and monitoring probe are away from ground
Height is between 3.5m-6m, and the 3rd tower bar is equipped with long-armed street lamp and galianconism street lamp, and long-armed street lamp and galianconism street lamp is set respectively
In the front and rear sides of the 3rd tower bar, galianconism street lamp is located at the lower section of long-armed street lamp, and long-armed street lamp and galianconism street lamp is apart from ground height
For degree between 6.5-9m, the 4th tower bar is equipped with antenna system.
Above-mentioned communication tower pedestal, point two layers of setting, main basal base and secondary pedestal are by various sizes of standardization prefabricated section splicing
Shaping, the volume of single prefabricated section, weight reduce, and pour the time and shorten, are conducive to shorten construction period, especially relatively large
The more aobvious advantage of communication tower.The main basal base prefabricated section of lower floor is connected as a single entity by long bolt, can guarantee that the stability of pedestal, upper strata
Secondary pedestal prefabricated section is placed directly within the stability of increase connecting seat above main basal base, and the dead weight of secondary pedestal prefabricated section is sufficiently large, secondary
The stability for the Base body that other connection structure can ensure after the completion of assembly need not be set between pedestal and main basal base.
For the diameter of tower body between 0.1-0.3m, the height of tower body is no more than 10m, ensures tower body intensity in itself and each functional component
The realizability of function.It is logical using being highly arranged on according to it that tower body is divided into the functional component such as multistage tower bar, charging pile, billboard
Assembled after believing on the different tower bodies of tower, communication tower is easy to assembly.The function part such as combined charging stake, billboard on communication tower
Part, enriches the function of communication tower, improves the practicality of communication tower.
Preferably, be embedded with the first reinforced frame in connecting seat, the second reinforced frame is embedded with main basal base prefabricated section, first
Reinforced frame bottom extends to the prefabricated second reinforced frame lower part in the block of the main basal base being connected with connecting seat.Connecting seat and main basal base
Prefabricated section is set by said structure, is conducive to increase the intensity of connecting seat and the prefabricated block part connection structure of main basal base.
Preferably, the crab-bolt is respectively connected with nut up and down, each crab-bolt coordinates the nut to be connected to two annular anchors
On plate, the anchor slab is welded and fixed with the first reinforced frame.
Preferably, secondary pedestal prefabricated section is equipped with hanging ring.Carried easy to the lifting to secondary pedestal prefabricated section.
Preferably, leave splicing seams between adjacent secondary pedestal prefabricated section and between secondary pedestal prefabricated section and connecting seat
Gap, and rely on the width in gap between 0-0.6m.Splicing is reserved by the size for the longer side and a shorter side for setting secondary base unit
Gap, makes secondary pedestal prefabricated section that certain deviation may be present when mounted and nor affects on the stability after subsequent installation communication tower,
Ease of assembly.
Preferably, being equipped with lightning rod at the top of the 4th tower bar, ground connection band iron is equipped with the first tower bar.
Preferably, billboard is liquid crystal display, billboard is connected with base station by wireless network, is controlled by base station
The advertisement putting of billboard.
Above-mentioned communication tower pedestal, point two layers of setting, main basal base and secondary pedestal are by various sizes of standardization prefabricated section splicing
Shaping, the volume of single prefabricated section, weight reduce, and pour the time and shorten, are conducive to shorten construction period, especially relatively large
The more aobvious advantage of communication tower.And tower body is integrated with multiple functions, the practicality of communication tower is improved.
Brief description of the drawings
Fig. 1 is the side structure schematic diagram of the utility model column foot.
Fig. 2 is the structure diagram of the utility model main basal base and connecting seat.
Fig. 3 is the structure diagram of connecting seat and connected main basal base prefabricated section.
Fig. 4 is the diagrammatic cross-section of Fig. 3.
Fig. 5 is the splicing construction schematic diagram of secondary pedestal.
Fig. 6 is the structure diagram of the utility model tower body.
Fig. 7 is the sectional view of the first tower bar bottom in the utility model.
Wherein:1st, column foot, 11, main basal base, 111, main basal base prefabricated section, the 1111, second reinforced frame, 112, connecting hole, 12,
Secondary pedestal, 121, secondary pedestal prefabricated section, 1211, hanging ring, 13, connecting seat, 131, crab-bolt, the 132, first reinforced frame, 14, long spiral shell
Bar, 2, tower body, the 21, first tower bar, 211, charging pile, 212, feeder hole, 213, ground connection band iron, the 22, second tower bar, 221, advertisement
Board, 222, monitoring probe, the 23, the 3rd tower bar, 231, galianconism street lamp, 232, long-armed street lamp, 233, entrance hole, the 24, the 4th tower bar,
241st, antenna system, 25, flanged plate, 251, support plate, 252, flange hole.
Embodiment
The preferred embodiment of this patent is described in further detail below in conjunction with the accompanying drawings.
A kind of intelligence communication bar, including column foot 1 and tower body 2, column foot as shown in Figs. 1-5, including main basal base 11, secondary pedestal
12 and connecting seat 13, main basal base 11 includes the identical main basal base prefabricated section 111 of three sizes, and main basal base prefabricated section 111 is equipped with
Run through the connecting hole 112 of main basal base prefabricated section from side, multiple main basal base prefabricated sections are set up in parallel and are connected by long bolt 14.
The main basal base prefabricated section upper surface is in elongated rectangular shape, and the length, width and height size of main basal base prefabricated section 111 is in 54m* in the present embodiment
18m*6m, each main basal base prefabricated section have very big dead weight in itself.
The upper surface of connecting seat 13 is equal to or less than the square of 111 short side of main basal base prefabricated section in the length of side.Connecting seat 13
On be fixed with it is multiple longitudinally disposed and in the horizontal plane with circumference array be distributed crab-bolt 131, during connecting seat 13 is arranged in
Between main basal base prefabricated section 111 top, the centre position in the prefabricated section simultaneously with the prefabricated section formed by integrally casting be molded.Main base
Seat 11, secondary pedestal 12 and connecting seat 13 are reinforced concrete structures, and the first reinforced frame 132, main base are embedded with connecting seat 13
The second reinforced frame 1111 is embedded with seat prefabricated section 111,132 bottom of the first reinforced frame extends to the main base being connected with connecting seat
Second reinforced frame, 1111 lower part in seat prefabricated section.First reinforced frame, the 132 lower face periphery and 1111 upper end of the second reinforced frame
Between face, reinforcing angle is welded between 132 lower face periphery of the first reinforced frame and the second reinforced frame 1111.The crab-bolt 131
Nut is respectively connected with up and down, and each crab-bolt 131 coordinates the nut to be connected on two annular anchor slabs, the anchor slab and the first reinforcing bar
Frame 1111 is welded and fixed.
Secondary pedestal 12 includes the identical secondary pedestal prefabricated section 121 of four structures, and secondary pedestal prefabricated section 121 is arranged on main basal base
On 11, secondary pedestal prefabricated section 121 is in cube, and secondary pedestal prefabricated section 121 staggeredly splices to be set around connecting seat, adjacent two
The long side and short side direct neighbor of secondary pedestal prefabricated section, the off(-)center of each pair pedestal prefabricated section, advantageously ensure that logical in installation
Base body uniform force after letter tower.In order to easy to assembly, while ensure the intensity of communication tower pedestal, adjacent secondary pedestal is prefabricated
Splicing gap A between block 121 and between secondary pedestal prefabricated section and connecting seat is between 0-0.6m.After the completion of assembly, secondary base
The outer edge of seat 12 aligns with the outer edge of main basal base 11, and the height of connecting seat 13 is higher than the height of secondary pedestal prefabricated section 121.This
The length, width and height size of secondary pedestal prefabricated section 121 is in 36*17.5*5 in embodiment, and the dead weight of secondary pedestal prefabricated section 121 is larger, secondary base
Between seat prefabricated section 121 and main basal base prefabricated section 111 and connecting seat 13 in addition other link structures need not be set, pass through secondary pedestal
The dead weight of prefabricated section can keep the stability of communication tower pedestal.
Secondary pedestal 12 is directly born against on main basal base 11, other connection structures are not provided between secondary pedestal and main basal base.Due to
The unit volume of main basal base prefabricated section and secondary pedestal prefabricated section is larger, and main basal base prefabricated section and secondary pedestal prefabricated section are at the construction field (site)
Directly pour, also, in order to lift conveniently, hole for hoist is equipped with secondary pedestal prefabricated section, metal hanging ring is embedded with hole for hoist.
And since main basal base prefabricated section is arranged below, smooth after the completion of assembly in order to ensure, main basal base prefabricated section directly passes through rope
Rope etc. coordinates with loop wheel machine to be carried.
Two layers of setting of above-mentioned column foot point, main basal base and secondary pedestal are single by various sizes of standardization prefabricated section spicing forming type
Volume, the weight of a prefabricated section reduce, and transport and lifting are convenient, the more aobvious advantage of especially relatively large communication tower.
Tower body 2 as shown in Figure 6 and Figure 7, its of length no more than 10m, tower body include what is connected by casing from bottom to top
First tower bar 21, the second tower bar 22, the 3rd tower bar 23 and the 4th tower bar 24, the tower bar for forming tower body are caliber in 0.1-0.3m
Pipe, first tower bar 21, the second tower bar 22, the length ratio of the 3rd tower bar 23 and the 4th tower bar 24 are 3:3:3:1.
The lower end of first tower bar 21 is equipped with flanged plate 25, which, which is equipped with, is used for and the matched flange hole of crab-bolt on column foot
252, the first tower bar 21 is fixed on the connecting seat of column foot, and support plate 251 is equipped between 25 and first tower bar 21 of flanged plate.
First tower bar is equipped with charging pile 211, and charging pile 211 is connected with distribution box and base station.Charging pile is installed on the
It is smaller apart from ground location in one tower bar, it is convenient to charge for electrical equipment.Installing advertisement board 221 and monitoring in second tower bar 22
Probe 222, monitoring probe 222 is connected by wireless network with base station, and communication tower is nearby monitored.Preferably billboard 21
For liquid crystal display, billboard 21 is connected by wireless network with base station, and the advertisement putting of billboard is controlled by base station.Advertisement
The height of board generally selects 2m or so, and billboard 21 and monitoring probe 222 are arranged in the second tower bar, exist away from ground level
Between 3.5m-6m, monitoring probe is set to cover sufficiently large monitoring range, and the visual field of billboard is preferable.In 3rd tower bar 23
Equipped with long-armed street lamp 32 and galianconism street lamp 231, the 3rd tower bar 23 is equipped with entrance hole 233, connects with long-armed street lamp and galianconism street lamp
Lead and it is pierced by the electric wire tower body connect from entrance hole 233.Long-armed street lamp 232 and galianconism street lamp 231 are separately positioned on the 3rd tower
The front and rear sides of bar 23, long-armed street lamp 232 and galianconism street lamp 231 apart from ground level between 6.5-9m, and galianconism street lamp 231
Positioned at the lower section of long-armed street lamp 232.Set long-armed street lamp 232 and galianconism street lamp 231 to coordinate, the illumination range of light can be increased,
Illuminating effect is more preferably.4th tower bar 24 is equipped with antenna system 241, and the top of the 4th tower bar 24 is equipped with lightning rod, the first tower bar 21
It is interior to be equipped with ground connection band iron 13.The functional components such as the above-mentioned monitoring probe for needing lead, from tower body interior cabling.
For the diameter of tower body between 0.1-0.3m, the height of tower body is no more than 10m, ensures tower body intensity in itself and each
The realizability of functional component function.Tower body is divided into the functional component such as multistage tower bar, charging pile, billboard and uses height according to it
Assembled after being arranged on the different tower bodies of communication tower, communication tower is easy to assembly.Combined charging stake, billboard etc. on communication tower
Functional component, enriches the function of communication tower, improves the practicality of communication tower.
Claims (7)
1. a kind of intelligence communication bar, including tower body and column foot, it is characterised in that column foot includes the main basal base of reinforced concrete structure
(11), secondary pedestal(12)And connecting seat(13), main basal base(11)Including the identical main basal base prefabricated section of three sizes(111), respectively
Main basal base prefabricated section is set up in parallel and by horizontally disposed long bolt(14)Connection;Connecting seat(13)On be fixed with multiple longitudinal directions
The crab-bolt for setting and being distributed in the horizontal plane with circumference array(131), connecting seat(13)The main basal base for being arranged in centre is pre-
Clamp dog(111)Top, the centre position in the prefabricated section simultaneously with the prefabricated section formed by integrally casting be molded;Secondary pedestal(12)Directly
It is pressed in above main basal base, secondary pedestal includes the identical secondary pedestal prefabricated section of four structures(121), secondary pedestal prefabricated section is in cube
Body, secondary pedestal prefabricated section, which staggeredly splices, surrounds connecting seat(13)Set, the long side and short side of adjacent two secondary pedestal prefabricated sections
Direct neighbor, the communication tower pedestal after the completion of assembly, the outer edge of secondary pedestal align with the outer edge of main basal base, the height of connecting seat
Height of the degree higher than secondary pedestal prefabricated section;The of length no more than 10m of tower body, tower body include first connected by casing from bottom to top
Tower bar(21), the second tower bar(22), the 3rd tower bar(23)With the 4th tower bar(24), the tower bar that forms tower body is caliber in 0.1-
The pipe of 0.3m, first tower bar(21), the second tower bar(22), the 3rd tower bar(23)With the 4th tower bar(24)Length it
Than for 3:3:3:1;The lower end of first tower bar is equipped with flanged plate(25), the flanged plate(25)It is equipped with and is used for and the crab-bolt on column foot
Matched flange hole(252), the first tower bar(21)It is fixed on the connecting seat of column foot;First tower bar is equipped with charging pile(211),
Second tower bar(22)Upper installing advertisement board(221)And monitoring probe(222), billboard(221)And monitoring probe(222)Away from ground
Height is between 3.5m-6m, the 3rd tower bar(23)It is equipped with long-armed street lamp(232)With galianconism street lamp(231), long-armed street lamp
(232)With galianconism street lamp(231)It is separately positioned on the 3rd tower bar(23)Front and rear sides, galianconism street lamp(231)Positioned at long-armed road
Lamp(232)Lower section, long-armed street lamp(232)And galianconism street lamp(231)Apart from ground level between 6.5-9m, the 4th tower bar
(24)It is equipped with antenna system(241).
2. a kind of intelligence communication bar according to claim 1, it is characterised in that the first reinforced frame is embedded with connecting seat
(132), the second reinforced frame is embedded with main basal base prefabricated section(1111), the first reinforced frame(132)Bottom extends to and connects
The main basal base prefabricated section of seat connection(111)In the second reinforced frame(1111)Lower part.
A kind of 3. intelligence communication bar according to claim 2, it is characterised in that the crab-bolt(131)It is respectively connected with up and down
Nut, each crab-bolt coordinate the nut to be connected on two annular anchor slabs, the anchor slab and the first reinforced frame(132)Welding is solid
It is fixed.
A kind of 4. intelligence communication bar according to claim 1, it is characterised in that secondary pedestal prefabricated section(121)It is equipped with and hangs
Ring(1211).
A kind of 5. intelligence communication bar according to claim 1, it is characterised in that adjacent secondary pedestal prefabricated section(121)It
Between and secondary pedestal prefabricated section(121)With connecting seat(13)Between leave splicing gap, and by gap width in 0-0.6m
Between.
A kind of 6. intelligence communication bar according to claim 1, it is characterised in that the 4th tower bar(24)Top is equipped with lightning-arrest
Pin, the first tower bar(21)It is interior to be equipped with ground connection band iron(213).
A kind of 7. intelligence communication bar according to claim 1, it is characterised in that billboard(221)For liquid crystal display, extensively
Accuse board(221)It is connected by wireless network with base station, the advertisement putting of billboard is controlled by base station.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721007165.7U CN207296567U (en) | 2017-08-11 | 2017-08-11 | A kind of intelligence communication bar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721007165.7U CN207296567U (en) | 2017-08-11 | 2017-08-11 | A kind of intelligence communication bar |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207296567U true CN207296567U (en) | 2018-05-01 |
Family
ID=62443739
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721007165.7U Expired - Fee Related CN207296567U (en) | 2017-08-11 | 2017-08-11 | A kind of intelligence communication bar |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207296567U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2019208134A (en) * | 2018-05-29 | 2019-12-05 | 富士通株式会社 | Antenna fixed mount, base station, and base station installation method |
-
2017
- 2017-08-11 CN CN201721007165.7U patent/CN207296567U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2019208134A (en) * | 2018-05-29 | 2019-12-05 | 富士通株式会社 | Antenna fixed mount, base station, and base station installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102359302A (en) | Extra-high voltage large-span iron tower assembling method | |
CN103375033A (en) | Integrated communication base station | |
CN103132766A (en) | Truss for lifting power transmission line tower connecting leg and erection method | |
CN207296567U (en) | A kind of intelligence communication bar | |
CN204418201U (en) | Base station modularization prefabricated foundation | |
CN117537289A (en) | Multifunctional solar intelligent street lamp system | |
CN210483094U (en) | Inverted triangular pipe truss lifting device | |
CN207348585U (en) | Intelligence communication bar | |
CN204609435U (en) | The auxiliary tower that hoists of emergent repairing tower | |
CN207796872U (en) | A kind of solar street lamp structure | |
CN206655065U (en) | Combined type support post and overhead rail system for overhead rail system | |
CN205500636U (en) | Water conservancy project component handling device | |
CN205990820U (en) | A kind of industrial working Assembled enclosing wall | |
CN211312514U (en) | Movable ground anchor device for mounting conical section of steel structure cooling tower | |
CN209686977U (en) | A kind of wisdom communication tower | |
CN209799529U (en) | communication tower prefabricated base convenient for wiring | |
CN203271221U (en) | Self-standing type ground combined derrick with equipment platform | |
CN205894833U (en) | Box -like base of matrix system of communication tower | |
CN205077519U (en) | Protection device of inspection shaft well lid | |
CN205976431U (en) | Tube -shape structures hydraulic pressure slipform promotes construction platform | |
JPH05286694A (en) | Construction method and crane for assembling external type steel tower | |
CN205172123U (en) | Multi -functional camouflage communication tower | |
CN205421021U (en) | Integral hoisting roof beam sand box that falls | |
CN219430838U (en) | Internal supporting type hanging die structure of concrete well ring | |
CN210482296U (en) | Construction equipment of airport parking apron and ground anchor pit mold thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180501 |