Wind-power tower with energy saving climbing mechanism Download PDFInfo
- Publication number
- CN207275957U CN207275957U CN201721380099.8U CN201721380099U CN207275957U CN 207275957 U CN207275957 U CN 207275957U CN 201721380099 U CN201721380099 U CN 201721380099U CN 207275957 U CN207275957 U CN 207275957U
- Authority
- CN
- China
- Prior art keywords
- tower
- pipeline section
- elevator
- wind
- leading screw
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Wind Motors (AREA)
Abstract
The utility model discloses a kind of wind-power tower of the energy saving climbing mechanism of band, including tower pipeline section, the lower end for often saving tower pipeline section is both provided with half space, often saves in tower pipeline section and is both provided with elevator;Elevator includes guide rod and screw, retarder and the servomotor being connected with retarder, fluted roller shaft and clump weight etc..The wind-power tower of the energy saving climbing mechanism of the utility model band, it uses motor driving leading screw to rotate to lift manned platform, and the cooperation between leading screw and thread bush uses self-locking thread engagement, safe.And due to being provided with clump weight, the weight of clump weight sets suitable with the gross weight of manned platform, L-shaped backplate and service personnel three, the weight that such servomotor is actually needed driving lifting just greatly reduces, the energy consumption of solution lifting that can be very big.At the same time using tower above and below elevator so that upper and lower tower is faster, avoids and climbs the problem of time-consuming and laborious existing for tower up and down using cat ladder.
Description
Technical field
Technical field of wind power generation is the utility model is related to, more particularly to a kind of wind-power tower.
Background technology
Wind-power tower is exactly the tower bar of wind-power electricity generation, is mainly played a supportive role in wind power generating set, while absorbs machine
Group vibrations.
Wind-power tower is made of some section tower pipeline sections, and wind-power tower whole height is generally in 60-90m, and height is big, tower
Inside it is usually provided with cat ladder and half space;Staff can reach different tower pipeline sections by cat ladder, to carry out equipment dimension
Shield.
But by manpower climbing up and down tower, there are it is time-consuming and laborious the problem of, be easy to cause staff fatigue, reduce dimension
Protect work efficiency.And the existing elevator being arranged in tower, and there are the low technical problem of high energy consumption, security.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of wind-power tower of the energy saving climbing mechanism of band, to solve to lean on
Manpower climbing tower up and down, there are time-consuming and laborious, be easy to cause staff's fatigue, there are high energy consumption, peace for existing tower elevator
The low technical problem of full property.
The wind-power tower of the energy saving climbing mechanism of the utility model band, including some sections pass through the tower pipeline section of flanged joint,
The lower end for often saving tower pipeline section is both provided with half space, often saves in tower pipeline section and is both provided with elevator;
The elevator includes the guide rod and screw axially in parallel with tower, and the lower end of guide rod and screw is vertically fixed
On half space, the upper end of guide rod and screw is extend into a section tower pipeline section, and the tube wall of upper section tower pipeline section
On set the top plate of left and right fixed guide pole and leading screw, the retarder being connected with leading screw is provided with the top plate and is connected with retarder
The servomotor connect;
The elevator further includes manned platform and the L-shaped backplate being fixedly connected in manned platform edge, the L-shaped shield
Handrail is provided with plate;Be provided with the back side of the L-shaped backplate with guide rod slide up and down cooperation guide sleeve and with silk
The thread bush that thick stick coordinates, and the matching thread between leading screw and thread bush is self-locking thread;
The bottom of the top plate is provided with fluted roller shaft, and the sheave being rotatably assorted with it, the groove are set on the fluted roller shaft
Steel cable is provided with wheel, one end of the steel cable is connected with L-shaped backplate, and the other end of the steel cable is provided with clump weight.
Further, often save in tower pipeline section and be additionally provided with cat ladder, the cat ladder is arranged on the side of manned platform.
The beneficial effects of the utility model:
The wind-power tower of the energy saving climbing mechanism of the utility model band, it is manned flat to lift that it uses motor driving leading screw to rotate
Platform, the cooperation between leading screw and thread bush use self-locking thread engagement so that when elevator breaks down, manned platform can pacify
Stop at entirely on leading screw, manned platform will not freely fall at a high speed so that elevator it is safe.And match somebody with somebody due to being provided with
Pouring weight, the weight of clump weight sets suitable with the gross weight of manned platform, L-shaped backplate and service personnel three, such servo
The weight that motor is actually needed driving lifting just greatly reduces, the energy consumption of solution lifting that can be very big.At the same time using on elevator
Lower tower so that upper and lower tower is faster, avoids and climbs the problem of time-consuming and laborious existing for tower up and down using cat ladder.
Brief description of the drawings
Fig. 1 is the structure diagram of single tower drum pipeline section;
Fig. 2 is the assembly structure diagram of two section tower pipeline sections;
Fig. 3 is the dimensional structure diagram of elevator upper end;
Fig. 4 is the dimensional structure diagram of elevator bottom.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples.
As shown in the figure, the wind-power tower of the energy saving climbing mechanism of the present embodiment band, including the tower that some sections pass through flanged joint
Spool piece 1, the lower end for often saving tower pipeline section are both provided with half space 2, often save in tower pipeline section and are both provided with elevator.
The elevator includes the guide rod 3 and screw 4 axially in parallel with tower, and the lower end of guide rod and screw is vertically solid
It is scheduled on half space, the upper end of guide rod and screw is extend into a section tower pipeline section, and the pipe of upper section tower pipeline section
The top plate 5 of left and right fixed guide pole and leading screw is set on wall, be provided with the top plate retarder 6 that is connected with leading screw and with deceleration
The servomotor 7 of device connection.
The elevator further includes manned platform 8 and the L-shaped backplate 9 being fixedly connected in manned platform edge, the L-shaped
Handrail 10 is provided with backplate;The guide sleeve 11 that cooperation is slided up and down with guide rod is provided with the back side of the L-shaped backplate
With the thread bush 12 coordinated with leading screw, and the matching thread between leading screw and thread bush is self-locking thread.
The bottom of the top plate is provided with fluted roller shaft 13, and the sheave 14 being rotatably assorted with it, institute are set on the fluted roller shaft
State and steel cable 15 is provided with sheave, one end of the steel cable is connected with L-shaped backplate, and the other end of the steel cable is provided with clump weight
16。
The wind-power tower of the energy saving climbing mechanism of the present embodiment band, it is manned flat to lift that it uses motor driving leading screw to rotate
Platform, the cooperation between leading screw and thread bush use self-locking thread engagement so that when elevator breaks down, manned platform can pacify
Stop at entirely on leading screw, manned platform will not freely fall at a high speed so that elevator it is safe.And match somebody with somebody due to being provided with
Pouring weight, the weight of clump weight sets suitable with the gross weight of manned platform, L-shaped backplate and service personnel three, such servo
The weight that motor is actually needed driving lifting just greatly reduces, the energy consumption of solution lifting that can be very big.At the same time using on elevator
Lower tower so that upper and lower tower is faster, avoids and climbs the problem of time-consuming and laborious existing for tower up and down using cat ladder.
As the improvement to the present embodiment, often save in tower pipeline section and be additionally provided with cat ladder 17, the cat ladder is arranged on manned
The side of platform.When elevator breaks down, due to the Open architecture of L-shaped backplate, staff can be directly from manned flat
Platform is gone on cat ladder, is dropped to by cat ladder on half space so that upper and lower tower security higher.
Finally illustrate, above example is merely intended for describing the technical solutions of the present application, but not for limiting the present application, although ginseng
The utility model is described in detail according to preferred embodiment, it will be understood by those of ordinary skill in the art that, can be to this
The technical solution technical scheme is modified or replaced equivalently of utility model, without departing from the objective and model of technical solutions of the utility model
Enclose, it should all cover among the right of the utility model.
Claims (2)
1. a kind of wind-power tower of the energy saving climbing mechanism of band, including some sections often save tower by the tower pipeline section of flanged joint
The lower end of pipeline section is both provided with half space, it is characterised in that:Often save in tower pipeline section and be both provided with elevator;
The elevator includes the guide rod and screw axially in parallel with tower, and the lower end of guide rod and screw is vertically fixed on not
Cease on platform, the upper end of guide rod and screw is extend into a section tower pipeline section, and is set on the tube wall of upper section tower pipeline section
The top plate of left and right fixed guide pole and leading screw, is provided with the retarder being connected with leading screw on the top plate and is connected with retarder
Servomotor;
The elevator further includes manned platform and the L-shaped backplate being fixedly connected in manned platform edge, on the L-shaped backplate
It is provided with handrail;It is provided with the back side of the L-shaped backplate and slides up and down the guide sleeve of cooperation with guide rod and match somebody with somebody with leading screw
The thread bush of conjunction, and the matching thread between leading screw and thread bush is self-locking thread;
The bottom of the top plate is provided with fluted roller shaft, sets the sheave being rotatably assorted with it on the fluted roller shaft, in the sheave
Steel cable is provided with, one end of the steel cable is connected with L-shaped backplate, and the other end of the steel cable is provided with clump weight.
2. the wind-power tower of the energy saving climbing mechanism of band according to claim 1, it is characterised in that:Often save in tower pipeline section also
Cat ladder is provided with, the cat ladder is arranged on the side of manned platform.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721380099.8U CN207275957U (en) | 2017-10-24 | 2017-10-24 | Wind-power tower with energy saving climbing mechanism |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721380099.8U CN207275957U (en) | 2017-10-24 | 2017-10-24 | Wind-power tower with energy saving climbing mechanism |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207275957U true CN207275957U (en) | 2018-04-27 |
Family
ID=61978406
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721380099.8U Expired - Fee Related CN207275957U (en) | 2017-10-24 | 2017-10-24 | Wind-power tower with energy saving climbing mechanism |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207275957U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112591014A (en) * | 2020-12-25 | 2021-04-02 | 三峡大学 | Lifting device and method for scientific investigation lifting fin plate with anti-collision function |
-
2017
- 2017-10-24 CN CN201721380099.8U patent/CN207275957U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112591014A (en) * | 2020-12-25 | 2021-04-02 | 三峡大学 | Lifting device and method for scientific investigation lifting fin plate with anti-collision function |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201729557U (en) | Device with elevator and ladder stand arranged in tower tube of wind generating set | |
CN103939299B (en) | The split type mounting process of a kind of offshore wind turbine | |
CN209561867U (en) | Electric lifting lightning rod | |
CN202217968U (en) | Lifting type paying-off tackle for wires in power distribution lines | |
CN104627911B (en) | Method for replacing hoisting steel wire rope of vertical loop | |
CN207275957U (en) | Wind-power tower with energy saving climbing mechanism | |
CN203998746U (en) | Portable suspension installation | |
CN102606112B (en) | Oil pumping unit | |
CN204299768U (en) | A kind of huge waterwheel | |
CN204140032U (en) | A kind of intelligent oil pumping machine of twin-well operation | |
CN210620063U (en) | Hoisting device for transporting goods from fan cabin | |
CN205001130U (en) | Directly drive two thing access structure that hang in aerogenerator cabin | |
CN209129791U (en) | A kind of wind power generating set rain-proof sheet covering device | |
CN208986510U (en) | The antifouling improvement construction cable of water environment is buried support device | |
CN202390812U (en) | Self-adjusting gate | |
CN207891005U (en) | A kind of reservoir dykes and dams cat ladder | |
CN207645621U (en) | A kind of large scale electrical power unit installation lifting framework | |
CN206821466U (en) | A kind of slip lid greenhouse slip lid at the uniform velocity fall-back device | |
CN207375669U (en) | The electronic lifting bracket of cable tunnel inner column formula cable | |
CN205687455U (en) | A kind of lifting device | |
CN203079518U (en) | Device for lifting large component inside wind wheel of wind generator set | |
CN202990839U (en) | Crawling assisting device | |
CN204921258U (en) | Wind power generation base tubular pile righting device | |
CN204691984U (en) | A kind of wind power generating set of withstand strong wind environment | |
CN202967989U (en) | Mounting slide bar for multifunctional and intelligentized overhauling and detecting platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180427 Termination date: 20191024 |