CN207267833U CN201721009212.1U CN201721009212U CN207267833U CN 207267833 U CN207267833 U CN 207267833U CN 201721009212 U CN201721009212 U CN 201721009212U CN 207267833 U CN207267833 U CN 207267833U
Authority
CN
China
Prior art keywords
rose box
water
reaction chamber
middle position
chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721009212.1U
Other languages
Chinese (zh)
Inventor
杜英莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201721009212.1U priority Critical patent/CN207267833U/en
Application granted granted Critical
Publication of CN207267833U publication Critical patent/CN207267833U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat Treatment Of Water, Waste Water Or Sewage (AREA)

Abstract

The utility model discloses a kind of industrial sewage-treatment plant;Including base, reaction chamber, evaporating chamber and Rose Box;Side above the base is provided with Rose Box, and the middle position of Rose Box front bottom is provided with cleaning lid, the middle position at Rose Box front top is provided with microcontroller, Rose Box front below the microcontroller is provided with indicator light, the middle position of the Rose Box interior side is provided with water quality sensor, and water pump is provided with by water pump mounting bracket at the interposition at the top of the Rose Box.The utility model can be detected water quality, coordinate the device to carry out heating distillation to sewage at the same time and add the multiprocessings such as medicament, classification processing can be carried out to sewage according to the situation of detection, use scope is more extensive, more reasonably all sewage is handled, while can effectively avoid unnecessary energy waste.

Description

A kind of industrial sewage-treatment plant
Technical field
It the utility model is related to technical field of sewage treatment equipment;Specially a kind of industrial sewage-treatment plant.
Background technology
With the development of modern society, the raising of industrial productivity, environmental pollution caused by industrial production is also more and more tighter Weight, can discharge substantial amounts of sewage in industrial processes, currently the standby function without classification processing of processing installing to sewage, right The processing mode of polluted-water is more single, water quality can not be detected according to the situation of water pollution, and can not be according to water The pollution condition selectivity of body handle, and the energy cannot be preferably utilized in processing procedure, causes great energy wave Take.
Utility model content
The purpose of this utility model is to provide a kind of industrial sewage-treatment plant;To solve to carry in above-mentioned background technology The problem of going out.
To achieve the above object;The utility model provides following technical solution:A kind of industrial sewage-treatment plant;Including Base, reaction chamber, evaporating chamber and Rose Box, the side above the base are provided with Rose Box, and Rose Box front bottom Middle position is provided with cleaning lid, and Rose Box water inlet, the Rose Box front are provided with the top of the Rose Box side The middle position at top is provided with microcontroller, and the Rose Box front below microcontroller is provided with indicator light, the Rose Box The middle position of interior side is provided with water quality sensor, is pacified at the interposition at the top of the Rose Box by water pump mounting bracket Equipped with water pump, the input terminal of the water pump is provided with the second conduit for being extended to the over filter box inner bottom, and the output terminal of water pump First drainpipe is installed, the described one end of first drainpipe away from water pump is provided with threeway, and the upper and lower ends difference of threeway First water valve and the second water valve are installed, the side away from Rose Box is provided with reaction chamber above the base, and reaction chamber is just The bottom in face is provided with reaction chamber water outlet, and middle position of the reaction chamber away from one side bottom of Rose Box is provided with water outlet Valve, the middle position inside the reaction chamber is provided with reaction warehouse, and reaction warehouse passes through water at the top of Rose Box side Pipe is connected with the output terminal of the second water valve, and the outside inside the reaction chamber is provided with vacuum heat-insulating layer, and reaction warehouse and vacuum Reaction chamber between thermal insulation layer has been internally provided with heating cabinet, and the steaming being looped around on the outside of reaction warehouse is provided with inside the heating cabinet Tracheae, and one end of steam pipe is connected by conduit outlet valve input terminal, the middle position at the top of the reaction chamber is provided with Motor, and the output terminal of motor is provided with the rotating bar extended to inside reaction chamber, and four groups are provided with above the reaction chamber Supporting rod, and evaporating chamber is installed above supporting rod, the evaporating chamber passes through water pipe and close to the top of Rose Box side The output terminal connection of one water valve, the evaporating chamber front is provided with evaporating chamber water outlet close to the bottom of Rose Box side, described The middle position installation having heaters of evaporating chamber bottom, and the bottom inside evaporating chamber is provided with heat-conducting plate, the heat-conducting plate Bottom and the output terminal of heater connect, the side away from Rose Box is provided with air guide storehouse, and air guide inside the evaporating chamber Storehouse is provided with air hole at the top of Rose Box side, and the bottom inside the air guide storehouse is provided with wind turbine, and air guide storehouse Bottom is connected by guide valve with the one end of steam pipe away from outlet valve, the output terminal of the water quality sensor and microcontroller it is defeated Enter end to be electrically connected, the output terminal of the microcontroller is electrically connected by the input terminal of conducting wire and indicator light.
Preferably;The middle position at reaction chamber front top is provided with filling opening, and the top of filling opening is set There is sealing cover.
Preferably;The middle position of evaporating chamber front bottom is provided with thermometer.
Preferably;Row's heat conducting pipe is evenly arranged with above the heat-conducting plate, and heat conducting pipe is all in several fonts.
Preferably;Two rows of paddles are uniformly installed, and the distance between paddle is on the side wall of the rotating bar 20cm, the paddle is in the shape of a spiral.
Preferably;The described one end of second conduit away from water pump is provided with water absorption cover, and the inlet of water absorption cover is arranged with Filtering screen.
Compared with prior art;The beneficial effects of the utility model are:The industrial sewage-treatment plant can be to water quality It is detected, while coordinates the device to carry out heating distillation to sewage and add the multiprocessings such as medicament, can be according to detection Situation classification processing is carried out to sewage, use scope is more extensive, and more reasonably all sewage is handled, while can Effectively to avoid unnecessary energy waste, steam pipe is coordinated to be carried out by the steam that distillation is handled to needs anti- The sewage heating answered, can not only improve the speed of devaporation Cheng Shui, and can improve the efficiency of sewage reaction, not only can be with Effective to improve the work efficiency of steam, while can preferably save the energy, which passes through water absorption cover and filtering screen Structure design can filter water, so that the cluster tool is reacted, distills and filtered in one, feature is stronger, It is more diversified to the processing mode of water.
Brief description of the drawings
Fig. 1 is the external structure schematic diagram of the utility model;
Fig. 2 is the internal structure schematic diagram of the utility model;
Fig. 3 is the heating portion structure schematic diagram of the utility model;
Fig. 4 is the reaction chamber outside schematic diagram of the utility model.
In figure:1st, base;2nd, reaction chamber water outlet;3rd, outlet valve;4th, reaction chamber;5th, filling opening;6th, guide valve;7th, it is electric Machine;8th, supporting rod;9th, heater;10th, thermometer;11st, evaporating chamber;12nd, evaporating chamber water outlet;13rd, the first water valve;14th, three It is logical;15th, the second water valve;16th, the first drainpipe;17th, water pump;18th, the second conduit;19th, microcontroller;20th, indicator light;21st, filter Case;22- cleaning lids;23rd, air guide storehouse;24th, heat conducting pipe;25- wind turbines;26- heat-conducting plates;27th, heating cabinet;28th, reaction warehouse;29、 Steam pipe;30th, paddle;31st, rotating bar;32nd, water quality sensor;33- water absorption covers;34, filtering screen;35- air holes;36- Rose Box water inlet.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model;The technical scheme in the embodiment of the utility model is carried out Clearly and completely describe;Obviously;The described embodiments are only a part of the embodiments of the utility model;Rather than whole Embodiment.Based on the embodiment in the utility model;Those of ordinary skill in the art are without making creative work All other embodiments obtained;It shall fall within the protection scope of the present invention.
Please refer to Fig.1-4;A kind of embodiment provided by the utility model:A kind of industrial sewage-treatment plant;The bottom of including Seat 1, reaction chamber 4, evaporating chamber 11 and Rose Box 21, the side of the top of base 1 are provided with Rose Box 21, and the positive bottom of Rose Box 21 The middle position in portion is provided with cleaning lid 22, and Rose Box water inlet 36, Rose Box 21 are provided with the top of 21 side of Rose Box The middle position at positive top is provided with microcontroller 19, the model HT66F017 of microcontroller 19, the mistake of the lower section of microcontroller 19 21 front of filter box is provided with indicator light 20, and the middle position of 21 interior side of Rose Box is provided with water quality sensor 32, water quality The model SXXXC of sensor 32, is provided with water pump 17, water pump 17 at the interposition at the top of Rose Box 21 by water pump mounting bracket Model ISGD, the input terminal of water pump 17 is provided with the second conduit 18 for being extended to the over 21 inner bottom of filter box, and water pump 17 Output terminal the first drainpipe 16 is installed, first one end of drainpipe 16 away from water pump 17 is provided with threeway 14, and threeway 14 Upper and lower ends be separately installed with the first water valve 13 and the second water valve 15, side of the top of base 1 away from Rose Box 21 is provided with Reaction chamber 4, and 4 positive bottom of reaction chamber is provided with reaction chamber water outlet 2, reaction chamber 4 is away from 21 1 side bottom of Rose Box Middle position is provided with outlet valve 3, and the middle position inside reaction chamber 4 is provided with reaction warehouse 28, and reaction warehouse 28 is close The top of 21 side of Rose Box is connected by water pipe with the output terminal of the second water valve 15, and the outside inside reaction chamber 4 is provided with very Empty thermal insulation layer, and the reaction chamber 4 between reaction warehouse 28 and vacuum heat-insulating layer has been internally provided with heating cabinet 27, inside heating cabinet 27 The steam pipe 29 for being looped around the outside of reaction warehouse 28 is installed, and one end of steam pipe 29 is connected by 3 input terminal of conduit outlet valve Logical, the middle position at the top of reaction chamber 4 is provided with the output terminal peace of motor 7, the model Y90S-2 of motor 7, and motor 7 Equipped with the rotating bar 31 extended to inside reaction chamber 4, the top of reaction chamber 4 is provided with four groups of supporting rods 8, and supporting rod 8 is upper Side is provided with evaporating chamber 11, and evaporating chamber 11 passes through water pipe and the output terminal of the first water valve 13 close to the top of 21 side of Rose Box Connection, the front of evaporating chamber 11 are provided with evaporating chamber water outlet 12 close to the bottom of 21 side of Rose Box, in 11 bottom of evaporating chamber Between having heaters 9 is installed at position, and the bottom inside evaporating chamber 11 is provided with heat-conducting plate 26, the bottom of heat-conducting plate 26 and heating The output terminal connection of device 9, side of the inside of evaporating chamber 11 away from Rose Box 21 is provided with air guide storehouse 23, and air guide storehouse 23 is close It is provided with air hole 35 at the top of 21 side of Rose Box, the bottom inside air guide storehouse 23 is provided with wind turbine 25, and air guide storehouse 23 Bottom is connected by guide valve 6 with the one end of steam pipe 29 away from outlet valve 3, output terminal and the microcontroller 19 of water quality sensor 32 Input terminal be electrically connected, the input terminal that the output terminal of microcontroller 19 passes through conducting wire and indicator light 20 is electrically connected.
In this embodiment;The middle position at the front of reaction chamber 4 top is provided with filling opening 5, and the top of filling opening 5 Sealing cover is provided with, easy to add thimerosal and catalytic fluid, the middle position of the positive bottom of evaporating chamber 11 is provided with temperature Table 10, the top of heat-conducting plate 26 is evenly arranged with row's heat conducting pipe 24, and heat conducting pipe 24 is all in several fonts, improves the efficiency of heating surface, Two rows of paddles 30 are uniformly installed on the side wall of rotating bar 31, and the distance between paddle 30 is 20cm, paddle 30 is in Helical form, improves stirring efficiency, second one end of conduit 18 away from water pump 17 is provided with water absorption cover 33, and the entrance of water absorption cover 33 Place is arranged with filtering screen 34, the pump drainage easy to water pump 17 to water, while can effectively filter out the impurity in water.
Operation principle:Device is powered on first during use, is entered by 36 sewage of Rose Box water inlet in water filtering tank 21, The quality of water is detected by water quality sensor 32, the quality condition of the prompting water of indicator light 20 is controlled by microcontroller 19, according to water The quality selection processing mode of matter, the first water valve 13 is made when water quality is poor sewage is extracted into evaporating chamber 16, pass through heating Device 9, heat-conducting plate 26 and heat conducting pipe 24 carry out heating distillation to sewage, when polluting not serious, can open the second water valve 15, will Sewage is extracted into inside the reaction warehouse 28 in reaction chamber 4, during drawing water can by filtering screen 34 can to sewage into The advance filtering of row, adds catalyst and disinfectant to reaction warehouse inside by filling opening 5, passes through the rotating bar 31 of 7 band of motor Sewage is stirred with paddle 30, promotes the progress of reaction, while steam is imported by air guide storehouse 23 and wind turbine 25 and is steamed The inside of tracheae 29, heats reaction warehouse 28, from promote reaction progress, by outlet valve 3 to steam condensation into water It is collected, finally can be by clearing up lid 22 to being filtered inside Rose Box 21.
To those skilled in the art;Obvious the utility model is not limited to the details of above-mentioned one exemplary embodiment;And And in the case of the spirit or essential attributes without departing substantially from the utility model;It can realize that this practicality is new in other specific forms Type.Therefore;No matter from what point of view;The embodiments should be taken as exemplary;And it is non-limiting;This practicality is new The scope of type is indicated by the appended claims rather than the foregoing description;It is intended that the equivalency fallen in claim is contained All changes in justice and scope are embraced therein.Any reference numeral in claim should not be considered as limitation Involved claim.

Claims (6)

  1. A kind of 1. industrial sewage-treatment plant;Including base (1), reaction chamber (4), evaporating chamber (11) and Rose Box (21);Its It is characterized in that:Side above the base (1) is provided with Rose Box (21), and the centre position of the positive bottom of Rose Box (21) Place is provided with cleaning lid (22), and Rose Box water inlet (36), the Rose Box are provided with the top of Rose Box (21) side (21) middle position at front top is provided with microcontroller (19), and Rose Box (21) the front installation below microcontroller (19) There is indicator light (20), the middle position of Rose Box (21) interior side is provided with water quality sensor (32), the filtering Water pump (17) is provided with by water pump mounting bracket at interposition at the top of case (21), the input terminal of the water pump (17), which is provided with, to be prolonged Second conduit (18) of Rose Box (21) inner bottom is extended, and the output terminal of water pump (17) is provided with the first drainpipe (16), The one end of first drainpipe (16) away from water pump (17) is provided with threeway (14), and the upper and lower ends of threeway (14) are pacified respectively Equipped with the first water valve (13) and the second water valve (15), the side away from Rose Box (21) is provided with reaction above the base (1) Case (4), and reaction chamber (4) positive bottom is provided with reaction chamber water outlet (2), the reaction chamber (4) is away from Rose Box (21) The middle position of one side bottom is provided with outlet valve (3), and the internal middle position of the reaction chamber (4) is provided with reaction warehouse (28), and reaction warehouse (28) is connected close to the top of Rose Box (21) side by water pipe with the output terminal of the second water valve (15), The internal outside of the reaction chamber (4) is provided with vacuum heat-insulating layer, and reaction chamber of the reaction warehouse (28) between vacuum heat-insulating layer (4) heating cabinet (27) has been internally provided with, the steam being looped around on the outside of reaction warehouse (28) is installed inside the heating cabinet (27) Manage (29), and one end of steam pipe (29) is connected by conduit outlet valve (3) input terminal, the centre at the top of the reaction chamber (4) Motor (7) is installed, and the output terminal of motor (7) is provided with and extends to the internal rotating bar (31) of reaction chamber (4), institute at position State and four groups of supporting rods (8) are installed above reaction chamber (4), and evaporating chamber (11), the steaming are installed above supporting rod (8) Hair storehouse (11) is connected close to the top of Rose Box (21) side by water pipe with the output terminal of the first water valve (13), the evaporating chamber (11) front is provided with evaporating chamber water outlet (12) close to the bottom of Rose Box (21) side, in evaporating chamber (11) bottom Between having heaters (9) is installed at position, and the internal bottom of evaporating chamber (11) is provided with heat-conducting plate (26), the heat-conducting plate (26) Bottom be connected with the output terminal of heater (9), the internal side away from Rose Box (21) of the evaporating chamber (11), which is provided with, leads Gas storehouse (23), and air guide storehouse (23) are provided with air hole (35), the air guide storehouse (23) at the top of Rose Box (21) side Internal bottom is provided with wind turbine (25), and the bottom of air guide storehouse (23) passes through guide valve (6) and the remote water outlet of steam pipe (29) One end connection of valve (3), the output terminal of the water quality sensor (32) are electrically connected with the input terminal of microcontroller (19), the list The output terminal of piece machine (19) is electrically connected by the input terminal of conducting wire and indicator light (20).
  2. A kind of 2. industrial sewage-treatment plant according to claim 1;It is characterized in that:Reaction chamber (4) front The middle position at top is provided with filling opening (5), and is provided with sealing cover at the top of filling opening (5).
  3. A kind of 3. industrial sewage-treatment plant according to claim 1;It is characterized in that:Evaporating chamber (11) front The middle position of bottom is provided with thermometer (10).
  4. A kind of 4. industrial sewage-treatment plant according to claim 1;It is characterized in that:The heat-conducting plate (26) it is upper Side is evenly arranged with row's heat conducting pipe (24), and heat conducting pipe (24) is all in several fonts.
  5. A kind of 5. industrial sewage-treatment plant according to claim 1;It is characterized in that:The side of the rotating bar (31) Two rows of paddles (30) are uniformly installed on wall, and the distance between paddle (30) is 20cm, the paddle (30) is in spiral shell Revolve shape.
  6. A kind of 6. industrial sewage-treatment plant according to claim 1;It is characterized in that:Second conduit (18) is remote One end from water pump (17) is provided with water absorption cover (33), and the inlet of water absorption cover (33) is arranged with filtering screen (34).
CN201721009212.1U 2017-08-14 2017-08-14 A kind of industrial sewage-treatment plant Expired - Fee Related CN207267833U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721009212.1U CN207267833U (en) 2017-08-14 2017-08-14 A kind of industrial sewage-treatment plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721009212.1U CN207267833U (en) 2017-08-14 2017-08-14 A kind of industrial sewage-treatment plant

Publications (1)

Publication Number Publication Date
CN207267833U true CN207267833U (en) 2018-04-24

Family

ID=61959924

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721009212.1U Expired - Fee Related CN207267833U (en) 2017-08-14 2017-08-14 A kind of industrial sewage-treatment plant

Country Status (1)

Country Link
CN (1) CN207267833U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108793548A (en) * 2018-05-31 2018-11-13 江苏天航水处理有限公司 Multi-stage sewage treatment device
CN109553239A (en) * 2019-01-05 2019-04-02 洁源环境(深圳)有限公司 A kind of waste water vacuum distillation purification device and its purification method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108793548A (en) * 2018-05-31 2018-11-13 江苏天航水处理有限公司 Multi-stage sewage treatment device
CN109553239A (en) * 2019-01-05 2019-04-02 洁源环境(深圳)有限公司 A kind of waste water vacuum distillation purification device and its purification method

Similar Documents

Publication Publication Date Title
CN207267833U (en) A kind of industrial sewage-treatment plant
CN103981052A (en) Brewing machine
CN207101521U (en) A kind of energy-saving efficient Chinese medicine steaming device
CN203440351U (en) Pomace brewing distiller
CN203041907U (en) Vacuum thermal-insulation hot tank assembly for water dispenser
CN210434505U (en) Sealed heating reaction device of lithium hydride reaction kettle
CN211513459U (en) Solvent recovery device
CN202590798U (en) Outer coiled pipe reaction kettle for synthetic resin
CN201908087U (en) Integrated distillation boiler and pot
CN203878133U (en) Wine brewing machine
CN210079461U (en) Vacuum condensation reaction kettle
CN204901730U (en) Device is recycled to workshop hot water heat energy
CN204841593U (en) Alcohol evaporation reation kettle
CN210057796U (en) Steam recovery device
CN206989757U (en) Water vapour reuse means
CN203461834U (en) Alkali fusion sintering production equipment for zircon sand
CN205990435U (en) A kind of heat treatment device for aluminum alloy hub
CN206799168U (en) A kind of cubic boron nitride powder purifying processing device
CN205619552U (en) Multifunctional electric water heater
CN206476776U (en) A kind of water still of the convenient control of energy-saving safety
CN201678880U (en) Steam ironing machine
CN212746407U (en) Steam generator device
CN203893143U (en) Steam generation device with steam waste heat recovery device
CN103214046A (en) Energy-saving household water distiller
CN205878558U (en) High -efficient recovery system of solid epoxy resin steam waste heat

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee