CN207260198U - A kind of precast frame for the installation of urban road Sewage well cover - Google Patents

A kind of precast frame for the installation of urban road Sewage well cover Download PDF

Info

Publication number
CN207260198U
CN207260198U CN201721237790.0U CN201721237790U CN207260198U CN 207260198 U CN207260198 U CN 207260198U CN 201721237790 U CN201721237790 U CN 201721237790U CN 207260198 U CN207260198 U CN 207260198U
Authority
CN
China
Prior art keywords
installation
groove
well cover
hanging ring
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721237790.0U
Other languages
Chinese (zh)
Inventor
刘长祥
周英勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Longjie Municipal Track Traffic Engineering Co Ltd
Original Assignee
Heilongjiang Longjie Municipal Track Traffic Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang Longjie Municipal Track Traffic Engineering Co Ltd filed Critical Heilongjiang Longjie Municipal Track Traffic Engineering Co Ltd
Priority to CN201721237790.0U priority Critical patent/CN207260198U/en
Application granted granted Critical
Publication of CN207260198U publication Critical patent/CN207260198U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

A kind of precast frame for the installation of urban road Sewage well cover, it the utility model is related to a kind of precast frame of Sewage well cover installation, the utility model is grown to solve preserving period needed for inspection shaft strengthening construction in the prior art, duration is influenced big, repair road occupying time length, and easily damaged to having reinforced inspection shaft, it includes preset frame, multiple hanging ring components and multiple fixing bolts, preset frame is rectangle framework, the upper surface processing of rectangle framework is fluted, groove slot bottom end face is machined with through hole, groove is connected with through hole, multiple hanging ring components are uniformly arranged on the upper surface of rectangle framework, multiple fixing bolts are radially uniformly on the slot bottom of groove, each fixing bolt is vertically arranged, each fixing bolt is equipped with a fixing nut, the utility model is used for municipal field of environment engineering.

Description

A kind of precast frame for the installation of urban road Sewage well cover
Technical field
A kind of precast frame of Sewage well cover installation is the utility model is related to, is used for water under urban road more particularly to one kind The precast frame of well lid installation.
Background technology
In Municipal Road Engineering construction, existing inspection shaft reinforcement construction technology is commonly cast-in-place method construction, mainly Before base layer construction completion back layer paves, checking well head laying reinforcing bar and casting concrete, applied again after reaching desired strength Work surface layer, therefore required preserving period is grown, and the duration is influenced greatly, particularly when city traffic pressure is big, maintenance road occupying time length. In construction, when the surface layer that paves is to inspection shaft position, paver need to be lifted crosses inspection shaft and be further continued for paving, around inspection shaft only It can manually pave, and easily be damaged to having reinforced inspection shaft, it is necessary to which second consolidation but effect is bad, absolute altitude is also difficult With control.
Utility model content
The utility model is grown to solve preserving period needed for inspection shaft strengthening construction in the prior art, the duration is influenced greatly, Road occupying time length is repaired, and is easily damaged to having reinforced inspection shaft, and then needs offer one kind to be used for urban road The precast frame of Sewage well cover installation.
The utility model is for the technical solution used that solves the above problems:
It includes preset frame, multiple hanging ring components and multiple fixing bolts, and preset frame is rectangle framework, rectangle framework Upper surface processing it is fluted, groove slot bottom end face is machined with through hole, and groove is connected with through hole, and multiple hanging ring components are uniformly arranged On the upper surface of rectangle framework, multiple fixing bolts are radially uniformly installed on the slot bottom of groove, each fixed Bolt is vertically arranged, and each fixing bolt is equipped with a fixing nut.
The beneficial effects of the utility model are:
1st, precast frame good integrity, intensity is big, and technique it is advanced, it is easy for installation, do not influence road normal construction;Apply Working medium amount is secure, is hardly damaged, sturdy and durable, service life length, driving more safety and comfort;Later period maintenance is convenient, component It is readily replaceable, it is small to traffic impact;Service life is long, easy for installation, has saved manpower, improves efficiency, thus saved into This, improves economic benefit and social benefit, while be conducive to environmental protection.
2 is more entirely different than construction technology and process with cast-in-place reinforcement technique, this prefabricated section can be concentrated to be processed in advance outside the venue, is applied Man-hour directly carries out lifting construction, and next process construction can be directly carried out after installation is complete, it is not necessary to which health, shortens construction Cycle.
3rd, the utility model is mainly the concrete strength design requirement reinforced according to road inspection well, and use is prefabricated outside the venue And health, it is solid on prefabricated section groove 4 according to the diameter of the construction of existing inspection shaft well lid and road inspection well come prefabricated Determine bolt 3, which is used for fixing and adjusting well lid absolute altitude, and in the pre-buried hanging ring of prefabricated section four corners, to construct when holds Easy handling installation.
Brief description of the drawings
Fig. 1 is the utility model overall structure front view.
Fig. 2 is the top view of Fig. 1.
Embodiment
Embodiment one:Illustrate present embodiment with reference to Fig. 1-Fig. 2, one kind described in present embodiment is used for city road The precast frame of road Sewage well cover installation, it includes preset frame 1, multiple hanging ring components 2 and multiple fixing bolts 3, and preset frame 1 is Rectangle framework, the upper surface processing fluted 4 of rectangle framework, 4 slot bottom end face of groove is machined with through hole 5, groove 4 and through hole 5 connections, multiple hanging ring components 2 are uniformly arranged on the upper surface of rectangle framework, and multiple fixing bolts 3 are radially uniformly distributed On the slot bottom of groove 4, each fixing bolt 3 is vertically arranged, and each fixing bolt 3 is equipped with a fixing nut.
Embodiment two:Illustrate present embodiment with reference to Fig. 1-Fig. 2, one kind described in present embodiment is used for city road The precast frame of road Sewage well cover installation, the number of hanging ring component 2 is four, and each angle of rectangle framework is provided with one and hangs Ring assemblies 2 are other identical with embodiment one.
Embodiment three:Illustrate present embodiment with reference to Fig. 1-Fig. 2, one kind described in present embodiment is used for city road The precast frame of road Sewage well cover installation, two hanging ring components 2 include eyenut 6, lifting bolt 7 and hanging ring 8, eyenut 6 are installed on preset frame 1, and the bottom of lifting bolt 7 is threadedly coupled with eyenut 6, and hanging ring 8 is installed on the top of lifting bolt 7 It is other identical with embodiment two on end.
Embodiment four:Illustrate present embodiment with reference to Fig. 1-Fig. 2, one kind described in present embodiment is used for city road The precast frame of road Sewage well cover installation, preset frame 1 is the preset frame made of armored concrete.Other and embodiment One is identical.
Embodiment five:Illustrate present embodiment with reference to Fig. 1-Fig. 2, one kind described in present embodiment is used for city road The precast frame of road Sewage well cover installation, groove 4 is circular groove, and through hole 5 is circular through hole, and the upper surface of rectangle framework is Square, the center line of rectangle framework vertically are overlapped with the center line of groove 4 and the center line of through hole 5.It is other with Embodiment one is identical.
Embodiment six:Illustrate present embodiment with reference to Fig. 1-Fig. 2, one kind described in present embodiment is used for city road The precast frame of road Sewage well cover installation, the number of fixing bolt 3 is four to six.It is other with one phase of embodiment Together.
Operation principle
Preset frame 1 is placed on adjustment above lower well by lifting the hanging ring 8 of hanging ring component 2 during utility model works The lifting bolt 7 on each eyenut 6 and hanging ring 8 are removed behind complete position, for installing preset frame 1 later when uses, so Sewage well cover is placed on preset frame 1 afterwards, and the circular hole on well cover is corresponded into the fixing bolt 3 on preset frame 1 and is set, Sewage well cover is fixed by the fixing nut on fixing bolt 3.

Claims (6)

  1. A kind of 1. precast frame for the installation of urban road Sewage well cover, it is characterised in that:It includes preset frame (1), multiple Hanging ring component (2) and multiple fixing bolts (3), preset frame (1) are rectangle framework, and the upper surface of rectangle framework is machined with recessed Groove (4), groove (4) slot bottom end face are machined with through hole (5), and groove (4) is connected with through hole (5), and multiple hanging ring components (2) are laid To put on the upper surface of rectangle framework, multiple fixing bolts (3) are radially uniformly installed on the slot bottom of groove (4), Each fixing bolt (3) is vertically arranged, and each fixing bolt (3) is equipped with a fixing nut.
  2. A kind of 2. precast frame for the installation of urban road Sewage well cover according to claim 1, it is characterised in that:Hanging ring The number of component (2) is four, and each angle of rectangle framework is provided with a hanging ring component (2).
  3. A kind of 3. precast frame for the installation of urban road Sewage well cover according to claim 2, it is characterised in that:Two Hanging ring component (2) includes eyenut (6), lifting bolt (7) and hanging ring (8), and eyenut (6) is installed on preset frame (1), The bottom of lifting bolt (7) is threadedly coupled with eyenut (6), and hanging ring (8) is installed on the top of lifting bolt (7).
  4. A kind of 4. precast frame for the installation of urban road Sewage well cover according to claim 1, it is characterised in that:It is preset Frame (1) is the preset frame made of armored concrete.
  5. A kind of 5. precast frame for the installation of urban road Sewage well cover according to claim 1, it is characterised in that:Groove (4) it is circular groove, through hole (5) is circular through hole, and the upper surface of rectangle framework is square, and rectangle framework edge is vertical square To center line overlapped with the center line of groove (4) and the center line of through hole (5).
  6. A kind of 6. precast frame for the installation of urban road Sewage well cover according to claim 1, it is characterised in that:It is fixed The number of bolt (3) is four to six.
CN201721237790.0U 2017-09-25 2017-09-25 A kind of precast frame for the installation of urban road Sewage well cover Active CN207260198U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721237790.0U CN207260198U (en) 2017-09-25 2017-09-25 A kind of precast frame for the installation of urban road Sewage well cover

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721237790.0U CN207260198U (en) 2017-09-25 2017-09-25 A kind of precast frame for the installation of urban road Sewage well cover

Publications (1)

Publication Number Publication Date
CN207260198U true CN207260198U (en) 2018-04-20

Family

ID=61918757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721237790.0U Active CN207260198U (en) 2017-09-25 2017-09-25 A kind of precast frame for the installation of urban road Sewage well cover

Country Status (1)

Country Link
CN (1) CN207260198U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952180A (en) * 2018-07-26 2018-12-07 陕西铁路工程职业技术学院 A kind of recycled concrete component

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108952180A (en) * 2018-07-26 2018-12-07 陕西铁路工程职业技术学院 A kind of recycled concrete component

Similar Documents

Publication Publication Date Title
CN104234385B (en) Construction method of installation after a kind of terrace heavy steel plate built-in fitting
CN105484157B (en) Positioning device and construction method of capping beam of prefabricated bridge
CN105133655A (en) Construction method of well lid of road surface inspection well and auxiliary installation device
CN104631512A (en) Post-cast strip beam and slab construction method adopting formwork hanging method
CN104562906A (en) Device and method for repairing manhole cover
CN108005401A (en) A kind of support and change method of the column of existing frame structure base isolation reinforcement
KR101067003B1 (en) A manhole repairing apparutus
CN207260198U (en) A kind of precast frame for the installation of urban road Sewage well cover
CN109162204B (en) Construction method for transverse block rapid assembling of bridge substructure
CN103741597A (en) Bridge expansion joint device without transition section concrete and mounting method of bridge expansion joint device
CN203768800U (en) Non-transition-section concrete bridge expansion joint device
CN202450423U (en) Milling-planing machine for maintenance of manholes
CN203462754U (en) Free-disassembly suspension template
CN210288480U (en) Inspection well head reinforcing apparatus in town road pipe network engineering
CN204715148U (en) A kind of Simple mounting temporary construction steel plate pavement system
CN207176527U (en) Bridge Crack bracing means
CN116677061A (en) Municipal rainwater and sewage inspection well integrated prefabricated installation device and construction method thereof
CN206784437U (en) A kind of urban road inspection shaft
CN202447878U (en) Simple aligning line rack for installation centre line of detachable equipment
CN205062844U (en) Supplementary installation device of well lid construction of road surface inspection shaft
CN109098395A (en) A kind of installation method of the prefabricated piping lane of assembly concrete
CN203650687U (en) Integral cast filter plate mould
CN109680572B (en) Construction method of integrated comprehensive pipeline of concrete side mould of road bed
CN203700899U (en) Steel tool-type temporary construction road
CN203429528U (en) Bridge-type precast-reinforced-concrete-trough-plate wear-resistant pavement structure system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant