CN207228106U - A kind of footing excavation device for casting - Google Patents

A kind of footing excavation device for casting Download PDF

Info

Publication number
CN207228106U
CN207228106U CN201720067251.0U CN201720067251U CN207228106U CN 207228106 U CN207228106 U CN 207228106U CN 201720067251 U CN201720067251 U CN 201720067251U CN 207228106 U CN207228106 U CN 207228106U
Authority
CN
China
Prior art keywords
chain
concrete
lower device
intermediate stand
chain knife
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720067251.0U
Other languages
Chinese (zh)
Inventor
王燏斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720067251.0U priority Critical patent/CN207228106U/en
Application granted granted Critical
Publication of CN207228106U publication Critical patent/CN207228106U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The utility model proposes a kind of footing excavation device for casting, footing excavation device for casting is made of chain type excavating gear, concrete filling device, mud device, lower device and intermediate stand;Chain type excavating gear is made of chain knife, sprocket wheel and driving device;Chain knife is made of chain and the cutter being fixed on chain;Track equipped with the operation of chain knife in intermediate stand, the top of intermediate stand is connected with upper unit;The driving device and tensioning apparatus of chain knife are installed on upper unit, and the chain of dress chain knife is connected through intermediate stand with the chain of lower device bottom, forms closing.Advantage:, can be to decline when excavating basic infrastructure device since foundation bottom carries excavating gear, concrete declines through the full lower device of concrete spray head perfusion and the cavity of formation, construction is simple, short construction period, cost are low.

Description

A kind of footing excavation device for casting
Technical field
The present invention relates to a kind of footing excavation device for casting, belongs to civil engineering foundation construction technical field.
Background technology
Existing large-scale single-pile foundation technology is using overall excavation construction mode, and long construction period, labor intensity is big, building ring Border degree of safety is poor.
Existing well foundation technology, it is to cut the earth in well, overcomes wall friction resistance to sink to by self gravitation and sets The basis that back cover forms is carried out after meter absolute altitude;Its major defect:Long construction period cost is high, and correction is difficult, meets the barrier such as shaft bottom boulder When hindering thing, cutting shoe, which is difficult to overcome, easily there is prominent heavy, accident-proneness etc.
The content of the invention
Proposed by the present invention is a kind of footing excavation device for casting, its purpose is intended to overcome defect existing in the prior art. Its major advantage:Foundation bottom carries excavating gear, can be to decline when excavating basic infrastructure device, and concrete is sprayed through concrete The cavity that the full lower device of mouth perfusion declines and formed, construction is simple, short construction period, cost are low.
The technical solution of the present invention:Footing excavation device for casting is by chain type excavating gear, concrete filling device, mud Sizing device, lower device and intermediate stand composition;Chain type excavating gear is made of chain knife, sprocket wheel and driving device;Chain knife is by chain Bar and the cutter composition being fixed on chain;The bottom of lower device is equipped with the track of chain knife operation, is set at the top of lower device There is the nozzle of concrete filling device, the bottom of lower device is equipped with the nozzle of mud device;The top view of lower device is exactly The perspective view on basis, the bottom of intermediate stand are connected with lower device, and intermediate stand is logistics and walkway, i.e. the sixth of the twelve Earthly Branches excavates Ground, concrete and mud are come in and gone out by intermediate stand, and driving device drive chain knife during construction, chain knife is run along track, Chain knife in lower device base track excavates ground, and the ground excavated is sent to top, concrete warp through intermediate stand The nozzle of concrete filling device fills the space that lower device declines and formed, and the pressure of concrete pumping plant is acted on through concrete In the top of lower device, make lower device is vertical down to carry out grooving movement, the chain knife and lower device of lower device bottom Decline together.
Footing excavation device for casting is equipped with upper unit, and the track of chain knife operation is equipped with intermediate stand, intermediate stand Top is connected with upper unit;The driving device and tensioning apparatus of chain knife are installed on upper unit, fill the chain of chain knife through centre Rack is connected with the chain of lower device bottom, forms closing.
Advantages of the present invention:Since foundation bottom carries excavating gear, it is possible under when excavating basic infrastructure device Drop, concrete irrigate full lower device through concrete spray head and decline and the cavity of formation, construction is simple, short construction period, cost It is low.
Brief description of the drawings
Fig. 1 is that the schematic diagram of chain type excavating gear 1 is installed on ground, and the structural representation of the adverse construction method method of a word stake Figure, and the structure diagram during excavation foundation bottom ground of chain type excavating gear 1, and the drive of composition chain type excavating gear 1 The structure diagram of dynamic device 1-1, sprocket wheel 1-2 and chain knife 7;
Fig. 2 is the ground that chain knife 7 excavates lower device bottom, is sent through ground conveying device to top, lower device is therewith Decline, concrete irrigates the structure diagram in the space that full lower device declines and formed through concrete spray head 2-1;
Fig. 3 is the A direction views of Fig. 2, a word stake contour structure schematic diagram;
Fig. 4 is the B-B views of Fig. 2, and ground, the filling concrete on top are excavated in 7 side of chain knife on lower device 4 The schematic diagram of the nozzle 2-1 sides air placed concrete of device 2, and concrete pipeline 4-1 and mud channel 4-2 are in lower device 4 In structural plan;
Fig. 5 is the C-C views of Fig. 2, and the knot of concrete pipeline 5-1 and mud channel 5-2 are arranged in intermediate stand 5 Structure schematic diagram;
Fig. 6 is the structure diagram of chain knife 7,(a)It is the structure diagram of chain 7-1 and cutter 7-2, and by A crosses Save the structure diagram of the crossed joint of the chain 7-1 of 7-1-1 and B crossed joints 7-1-2 compositions;And chain 7-1 realizes that space is curved Bent structure diagram.(b)It is the structure diagram that chain knife 7 is made of flexible-belt 7-1B and cutter 7-2B;And flexible-belt 7- The structure diagram of 1B and cutter 7-2B;
Fig. 7 is that the driving device 1-1 and sprocket wheel 1-2 of excavating gear 1 are installed in lower device 4, is in 4 shape of lower device Into the structure diagram of enclosure space;
Fig. 8 is the A direction views of Fig. 7, and concrete pipeline 5-1, mud channel 5-2 and vertical spiral shell in intermediate stand 5 Revolve the structure diagram of conveyer 8-3;
Fig. 9 is that chain knife 7 on the B direction views of Fig. 7, and 4 base track of lower device cuts ground, and by the rock of excavation Soil is sent to the schematic diagram of upper unit 6 by ground conveying device 8 through intermediate stand 5;
Figure 10 is that the driving device 1-1 and sprocket wheel 1-2 of excavating gear 1 are installed in lower device 4, the top of lower device 4 Portion is equipped with the structure diagram of steel wire rope arrangement apparatus 10, and the structure diagram of the sleiding form 9 of concrete perfusion;
Figure 11 is the A direction views of Figure 10, and the structural representation in the middle construction hole formed by the sleiding form 9 of concrete Figure;
Figure 12 is the structure diagram on reverse construction intersecting parallels basis in water;
Figure 13 is the A direction views of Figure 12, and in water during reverse construction, first installs upper unit on intermediate stand 5 6, then the structure diagram that 1 formation base of chain type excavating gear excavates device for casting is installed on upper unit 6;
Figure 14 is the bottom chain knife track of chain type excavating gear 1 and the structure diagram of side chain knife track, the class of track Type includes totally 5 kinds of A1, A2, B, C and D, and wherein A1, A2 is concave, and B is plane, and C is convex;
Figure 15 is that D staggers into tapered structure diagram for the multiple rows of track in longitudinal direction;
Figure 16 is the D types track of chain type excavating gear 1 and the structure diagram of more row chain knives.
1 in figure is the chain type excavating gear of footing excavation device for casting, by driving device 1-1, sprocket wheel 1-2 and chain knife 7 Composition;1-1 is the driving device of chain type excavating gear 1;1-2 is the sprocket wheel of chain type excavating gear 1;2 be footing excavation perfusion dress The concrete filling device put;2-1 is the nozzle of concrete filling device;3 be the mud device of footing excavation device for casting;3- 1 is the swivel of mud device 3;4 be the lower device of footing excavation device for casting;4-1 is the pipe of concrete of lower device 4 Road;4-2 is the mud channel of lower device 4;5 be the intermediate stand of footing excavation device for casting;5-1 is on intermediate stand 5 Concrete pipeline;5-2 is the mud channel on intermediate stand 5;6 be the upper unit of footing excavation device for casting or Permanent building on ground;7 be the chain knife for forming chain type excavating gear 1;7-1 is the chain for forming chain knife 7, including crawler belt, rope Rope and flexible-belt;7-1-1 is the A crossed joints for forming chain crossed joint;7-1-2 is the B crossed joints for forming chain crossed joint;7-1B It is the flexible-belt for forming chain knife 7;7-2 is integrally fixed at the cutter of the excavation ground on chain 7-1;7-2B is integrally fixed at flexible-belt 7- The cutter of excavation ground on 1B;8 are mounted in the ground conveyer on intermediate stand 5;8-1 is vertical chain type conveyer;8-2 It is horizontal chain conveyer;8-3 is vertical screw type conveyer;8-4 is horizontal screw conveyer;9 be the slip of concrete perfusion Template;10 be the steel wire rope arrangement apparatus at the top of lower device 4.
Embodiment
A kind of footing excavation device for casting by chain type excavating gear, concrete filling device, mud device, lower device and Intermediate stand forms;Chain type excavating gear is made of chain knife, sprocket wheel and driving device;Chain knife is by chain and is fixed on chain Cutter forms;The bottom of lower device is equipped with the track of chain knife operation, and the top of lower device is equipped with concrete filling device Nozzle, the bottom of lower device are equipped with the nozzle of mud device;The top view of lower device be exactly basis perspective view, middle machine The bottom of frame is connected with lower device, and intermediate stand is logistics and walkway, i.e., ground, concrete and the mud that the sixth of the twelve Earthly Branches excavates are equal Come in and gone out by intermediate stand, driving device drive chain knife during construction, chain knife is run along track, in lower device base track Chain knife excavates ground, and the ground excavated is sent to top, nozzle of the concrete through concrete filling device through intermediate stand The space that lower device declines and formed is filled, the pressure of concrete pumping plant acts on the top of lower device through concrete, makes Lower device is vertical down to carry out grooving movement, and the chain knife and lower device of lower device bottom decline together.
The footing excavation device for casting is equipped with upper unit, and the track run in intermediate stand equipped with chain knife is middle The top of rack is connected with upper unit;The driving device and tensioning apparatus of chain knife are installed on upper unit, fill the chain of chain knife It is connected through intermediate stand with the chain of lower device bottom, forms closing.
The driving device and tensioning apparatus of the excavating gear are installed in lower device, are formed in lower device Enclosure space;The intermediate stand is construction hole.
Ground conveying device is installed in the construction hole, the ground that the chain knife in lower device base track excavates by Ground conveying device is sent to upper unit.
The construction hole is the sleiding form of concrete perfusion.
The concrete filling device and the pumping plant of mud device are installed on upper unit or ground.
The vertical ground conveying device is vertical screw type conveyer, its entrance is located at bottom or chain knife in the middle part of chain knife End, vertical screw type conveyer is located at the side of chain knife or the centre of more row chain knives.
The base track of the lower device has difference in height, easy to operation of the bottom excavating gear in intersection.
The top of the lower device is equipped with steel wire rope arrangement apparatus, i.e., contains steel wire rope in concrete.
The upper unit is building.
Technical scheme is further described below in conjunction with the accompanying drawings:
As shown in Figure 1 and Figure 2, the adverse construction method method step of footing excavation device for casting is as follows:
1)Clear up smooth location;
2)Chain type footing excavation device for casting is installed;
3)The pumping plant of concrete filling device mud device is installed;
4)Drive chain 7-1, chain knife 7 excavate the ground of lower device bottom, are sent through vertical chain type conveyer 8-1 supreme Side, lower device 4 decline therewith, and concrete irrigates the space that completely lower device 4 declines and formed through concrete spray head 2-1;
5)Projected depth is dropped to, is in the milk again after removing chain knife.
As shown in Fig. 1~Fig. 6, footing excavation device for casting is filled by chain type excavating gear 1, concrete filling device 2, mud Put 3, lower device 4, intermediate stand 5 and upper unit 6 to form, chain type excavating gear 1 is by driving device 1-1, sprocket wheel 1-2 and chain Knife 7 forms;Chain knife 7 is made of chain 7-1 and the cutter 7-2 being fixed on chain 7-1;The bottom of lower device 4 is equipped with chain knife 7 The track of operation, the pipeline 4-2 of concrete filling device pipeline 4-1 and mud device, lower part dress are respectively equipped with lower device The top for putting 4 is equipped with concrete spray head 2-1, and bottom is equipped with swivel 3-1, and bottom and the lower device 4 of intermediate stand 5 connect Connect, the top of intermediate stand 5 is connected with upper unit 6.Driving device 1-1 drive chain 7-1 during construction, chain 7-1 band moving knife Tool 7-2 is run along track, and the chain knife 7 in 4 base track of lower device cuts ground, will when chain knife 7 is run bottom-up The ground excavated is sent to upper unit 6 through intermediate stand 5, vertical down to carry out grooving movement, bottom chain knife 7 and lower device 4 decline together, and concrete irrigates full lower device through concrete spray head 2-1 and declines and the cavity of formation.
As shown in Fig. 7~Fig. 9, the driving device 1-1 and sprocket wheel 1-2 of excavating gear 1 are in lower part in lower device 4 Device 4 forms enclosure space, and intermediate stand 5 is provided with ground conveying device 8, including vertical screw type conveyer 8-3 and horizontal spiral shell Revolve conveyer 8-4.Driving device 1-1 drive chain 7-1 during construction, chain 7-1 band cutter 7-2 are run along track, lower part Chain knife 7 in 4 base track of device cuts ground, and the ground of excavation is sent by ground conveying device 8 through intermediate stand 5 supreme Part device 6, vertical down to carry out grooving movement, bottom chain knife 7 and lower device 4 decline together, and concrete is through concrete spray head The cavity that the full lower device 4 of 2-1 perfusions declines and formed.
As shown in Figure 10~Figure 11, the top of lower device 4 is equipped with the nozzle 2-1 and steel wire rope cloth of concrete filling device Device 10 is put, i.e., contains vertical steel wire rope in concrete;The sleiding form 9 of concrete perfusion is fixed on the top of lower device 4 Portion centre position, bottom chain knife 7, lower device 4 and sleiding form 9 decline together, and concrete filling device 2 is filled through nozzle 2-1 Concrete is noted, middle construction hole is formed because of sleiding form 9, and concrete conveying pipe and ground conveying device are all applied in centre In work hole.
As shown in Figure 12~Figure 13, reverse construction intersecting parallels basis in water, first installs upper unit on intermediate stand 5 6, then 1 formation base excavation device for casting of chain type excavating gear is installed on upper unit 6, in 4 base track of lower device Chain knife 7 cuts ground, and bottom chain knife 7 and lower device 4 decline together, and concrete irrigates full lower part through concrete spray head 2-1 and fills The cavity put 4 declines and formed.

Claims (10)

  1. A kind of 1. footing excavation device for casting, it is characterized in that footing excavation device for casting is by chain type excavating gear, filling concrete Device, mud device, lower device and intermediate stand composition;Chain type excavating gear is made of chain knife, sprocket wheel and driving device;Chain Knife is made of chain and the cutter being fixed on chain;The bottom of lower device is equipped with the track of chain knife operation, lower device Top is equipped with the nozzle of concrete filling device, and the bottom of lower device is equipped with the nozzle of mud device;The vertical view of lower device Figure is exactly the perspective view on basis, and the bottom of intermediate stand is connected with lower device, and intermediate stand is logistics and walkway, i.e. the sixth of the twelve Earthly Branches Ground, concrete and the mud of excavation are come in and gone out by intermediate stand, driving device drive chain knife during construction, and chain knife is along track Run, the chain knife in lower device base track excavates ground, and the ground excavated is sent to top, coagulation through intermediate stand The native nozzle through concrete filling device fills the space that lower device declines and formed, and the pressure of concrete pumping plant is through concrete The top of lower device is acted on, makes lower device is vertical down to carry out grooving movement, the chain knife of lower device bottom and lower part Device declines together.
  2. A kind of 2. footing excavation device for casting according to claim 1, it is characterized in that the footing excavation device for casting Equipped with upper unit, the track of chain knife operation is equipped with intermediate stand, the top of intermediate stand is connected with upper unit;Chain knife Driving device and tensioning apparatus are installed on upper unit, fill chain phase of the chain through intermediate stand with lower device bottom of chain knife Even, closing is formed.
  3. A kind of 3. footing excavation device for casting according to claim 1, it is characterized in that the driving dress of the excavating gear Put and be installed in tensioning apparatus in lower device, enclosure space is formed in lower device;The intermediate stand is to apply Work hole.
  4. A kind of 4. footing excavation device for casting according to claim 3, it is characterized in that being provided with rock in the construction hole Native conveying device, the ground that the chain knife in lower device base track excavates are sent to upper unit by ground conveying device.
  5. A kind of 5. footing excavation device for casting according to claim 3, it is characterized in that the construction hole is perfusion coagulation The sleiding form of soil.
  6. 6. a kind of footing excavation device for casting according to claim 1, it is characterized in that the concrete filling device and The pumping plant of mud device is installed on upper unit or ground.
  7. A kind of 7. footing excavation device for casting according to claim 4, it is characterized in that the ground conveying device is vertical Straight screw conveyor, its entrance are located at the bottom in the middle part of chain knife or the end of chain knife, and vertical screw type conveyer is located at the side of chain knife Face or the centre of more row chain knives.
  8. A kind of 8. footing excavation device for casting according to claim 1, it is characterized in that the bottom rail of the lower device There is difference in height in road, easy to operation of the bottom excavating gear in intersection.
  9. A kind of 9. footing excavation device for casting according to claim 1, it is characterized in that being set at the top of the lower device There is steel wire rope arrangement apparatus, i.e., contain steel wire rope in concrete.
  10. A kind of 10. footing excavation device for casting according to claim 2, it is characterized in that the upper unit is building Thing.
CN201720067251.0U 2017-01-18 2017-01-18 A kind of footing excavation device for casting Expired - Fee Related CN207228106U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720067251.0U CN207228106U (en) 2017-01-18 2017-01-18 A kind of footing excavation device for casting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720067251.0U CN207228106U (en) 2017-01-18 2017-01-18 A kind of footing excavation device for casting

Publications (1)

Publication Number Publication Date
CN207228106U true CN207228106U (en) 2018-04-13

Family

ID=61838142

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720067251.0U Expired - Fee Related CN207228106U (en) 2017-01-18 2017-01-18 A kind of footing excavation device for casting

Country Status (1)

Country Link
CN (1) CN207228106U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759287A (en) * 2017-01-18 2017-05-31 王燏斌 A kind of footing excavation device for casting and its adverse construction method method
WO2023066326A1 (en) * 2021-10-21 2023-04-27 王树生 Sunken wall foundation, and construction devices and method therefor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759287A (en) * 2017-01-18 2017-05-31 王燏斌 A kind of footing excavation device for casting and its adverse construction method method
WO2023066326A1 (en) * 2021-10-21 2023-04-27 王树生 Sunken wall foundation, and construction devices and method therefor

Similar Documents

Publication Publication Date Title
CN107059877A (en) Basis and its construction method of the bottom with chain knife during a kind of construction
WO2018133740A1 (en) Underground building and construction method for same
CN108343260A (en) Inclined building correcting and then reinforcing structure and its construction method
CN207228106U (en) A kind of footing excavation device for casting
CN106401598A (en) Remote tunneling control method of high pressure water jet flow automatic cutting
CN104712333A (en) Large-width one-step roadway formation roadway rapid excavation technology
CN206801460U (en) A kind of rectangle friction pile drilling construction device
CN106759464A (en) A kind of hypogee and its construction method
CN207047833U (en) A kind of groover for subterranean wall construction
CN106759287A (en) A kind of footing excavation device for casting and its adverse construction method method
WO2018133711A1 (en) Pier foundation and construction method therefor
WO2018133742A1 (en) Groove cutting apparatus used for underground wall construction, and construction method therefor
CN104747191A (en) Construction method for connecting structure of shaft and shaft station
CN106759486A (en) A kind of underground structure being made up of stake and wall and its construction method
CN110056003A (en) A kind of integral sinking construction method and its constructing device for basement
WO2018133744A1 (en) Trench-cutting device for underground construction and working method thereof
CN106836192A (en) A kind of assembled subterranean wall and its construction method
CN102619248B (en) Rock trenching machine and trenching method
CN204954021U (en) Double arm robot with shear work ability
CN105927237A (en) Chain tool device for undermining-method metro station assembling construction
CN207419572U (en) A kind of rotate excavates device for casting
CN207131408U (en) A kind of new TBM for possessing pipe roof construction ability
CN103334449A (en) Square hole girdling cutter and method for performing holing construction of deep cutting stab-pile wall by utilizing same
CN207228156U (en) A kind of underground structure being made of stake and wall
CN207047927U (en) A kind of groover for hypogee

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180413