CN207211169U - A kind of beach cofferdam construction device - Google Patents

A kind of beach cofferdam construction device Download PDF

Info

Publication number
CN207211169U
CN207211169U CN201720860207.5U CN201720860207U CN207211169U CN 207211169 U CN207211169 U CN 207211169U CN 201720860207 U CN201720860207 U CN 201720860207U CN 207211169 U CN207211169 U CN 207211169U
Authority
CN
China
Prior art keywords
pylon
cofferdam
float member
truss
beach
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720860207.5U
Other languages
Chinese (zh)
Inventor
余健
郑绍刚
杜洪涛
袁绍轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Stecol Corp
Original Assignee
Sinohydro Tianjin Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Tianjin Engineering Co Ltd filed Critical Sinohydro Tianjin Engineering Co Ltd
Priority to CN201720860207.5U priority Critical patent/CN207211169U/en
Application granted granted Critical
Publication of CN207211169U publication Critical patent/CN207211169U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

It the utility model is related to a kind of beach cofferdam construction device, it is characterised in that:The first float member and the second float member including being placed on beach upper surface;First float member and the second float member are arranged on the both sides in borrow areas, and the first pylon is installed with above the first float member, the second pylon is installed with above the second float member, truss is provided between the first pylon and the second pylon;Truss one end extends to the top in cofferdam region from the first pylon side;The horizontal slide rail laid along truss length direction is installed on truss, walking dolly is installed on slide rail, elevator unit, drive device, the steel wire cable connection grab bucket of elevator unit are installed on walking dolly.The utility model solves the problems, such as that traditional cofferdam such as construction technology such as sand pocket cofferdam, earth rock cofferdam is more difficult, improves working environment, improves operating efficiency, reduces construction cost.

Description

A kind of beach cofferdam construction device
Technical field
The utility model belongs to beach cofferdam technical field, more particularly to a kind of beach cofferdam construction device.
Background technology
At present, this equipment is used for beach cofferdam construction, and under beach construction environment, coffered foundation is under water or moisture content High mud, traditional cofferdam such as construction technology such as sand pocket cofferdam, earth rock cofferdam is more difficult, suits measures to local conditions simultaneously, with reference to Zhejiang Jiang Taizhou market prices, traditional cofferdam construction cost is higher, 150 yuan/m of sand pocket cofferdam construction cost unit price3, earth rock cofferdam takes nearby 30~40 yuan/m of soil application work cost unit price3;And the present apparatus carries out cofferdam construction using soil on the outside of cofferdam, construction cost unit price is about 10 yuan/m3, greatly reduce construction cost;But simultaneously because of soil less stable, it is necessary to necessarily consolidate the phase, cofferdam can not be once Property fills completion, so needing successively to increase cofferdam.
The content of the invention
The utility model for solve technical problem present in known technology provide it is a kind of simple in construction, easy for construction, The beach cofferdam construction device that construction cost is low, operating efficiency is high.
The utility model is adopted the technical scheme that to solve technical problem present in known technology:
A kind of beach cofferdam construction device, it is characterised in that:Two float members including being placed on beach upper surface, point Wei not be close to the first float member of cofferdam side, the second float member away from cofferdam;First float member and the second floating body structure Part is arranged on the both sides in borrow areas, and the first pylon is installed with above the first float member, and the second float member top is solid Dingan County is equipped with the second pylon, and truss is provided between the first pylon and the second pylon;
Described truss one end extends to the top in cofferdam region from the first pylon side, and the other end of truss is from the second pylon side Extend identical length;
Second float member, the second pylon and/or truss are provided with control cabinet away from cofferdam end;
The horizontal slide rail laid along truss length direction is installed on the truss, walking is installed small on the slide rail Car, elevator unit, the steel wire cable connection grab bucket of the elevator unit are installed on the walking dolly;
Driving walking dolly is installed along the reciprocating drive device of horizontal slide rail on the truss.
The utility model can also use following technical measures:
The float member uses body structure, and supporting plate is fixedly mounted with the upper surface of casing, and the top of the supporting plate is consolidated Determine erection tower.
It is additionally provided with above the supporting plate towards the manhole in casing.
The structure of first pylon and the second pylon is identical, including two lower bracing frames and a upper support frame, institute State the bottom of two lower bracing frames to be fixedly connected with the upper surface of float member, the top centre position of two lower bracing frames is upward Upper support frame is fixedly mounted, upper support frame is connected pre- guy tightening between the lower bracing frame of both sides respectively;Two lower bracing frames and One triangle supporting construction of upper support frame.
Cofferdam method comprises the following steps:
1), coffered foundation being filled using the hanged underwater clay of purlin digging below water level, using cofferdam outside on the spot Fetch earth;Beach cofferdam construction device is laid on the outside of cofferdam, more than 15m position is taken using grab bucket on the outside of away from coffered foundation Soil, the distance range that fetches earth are 15m~125m, and the depth that fetches earth is not less than 3m;Under the drive of drive device, soil is transported to and enclosed Weir;The whole process about 2min that moves in circles, purlin, which is dug, is hung in same position operation, and the time of continuously fetching earth must not exceed 1h, set every time It is standby to be fetched earth using hoist engine movement apart from preferably 5m~8m;
2), fill after cofferdam is higher by 0.5 meter of the water surface and carry out, usage mining machine carries out leveling and rolled, then successively fills Weir body is rolled, every layer of virtual resurfacing thickness is no more than 30cm, and flood usage mining machine carries out grinding compacting after the completion of every layer of paving soil, does not stay Section seam;
3), cofferdam, which is filled, takes staged and layered construction method, and section is filled by 200 meters long conduct one, that is, each when filling Soil layer is filled by 200 meters of long controls;
4), purlin is dug the pit that fetched earth when hanged underwater clay or excavator fetch earth and must not continuously penetrated, according to live actual The low bank of earth between fields of 3 meters or so of a width is stayed every 15 meters or so distances, as underwater cofferdam base support.
The utility model has the advantages and positive effects of:Because the utility model uses above-mentioned technical proposal, solve The problem of for example construction technology such as sand pocket cofferdam, earth rock cofferdam is more difficult in traditional cofferdam, in addition, the utility model utilizes cofferdam Outside soil carries out cofferdam construction, and realization is gathered materials on the spot, and greatly reduces construction cost;But simultaneously because of soil less stable, Certain consolidation phase is needed, therefore cofferdam can not disposably fill completion, so needing successively to increase cofferdam.Other the utility model Also have it is rational in infrastructure, install conveniently moving, improve working environment, improve operating efficiency, it is safe and reliable the advantages that.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the first pylon structure schematic diagram;
Fig. 3 is the utility model Construction Principle figure.
In figure:1-1, the first float member;1-10, the first pylon;1-11, lower bracing frame;1-12, upper support frame; 1- 13rd, pre- guy tightening;1-2, the second float member;1-20, the second pylon;1-3, truss;1-30, horizontal slide rail;1-31, walking are small Car;1-32, grab bucket;1-4, supporting plate;1-40, manhole;1-20, the second pylon;2nd, borrow areas;3rd, cofferdam region
Embodiment
For invention, features and effects of the present utility model can be further appreciated that, following examples are hereby enumerated, and coordinate Accompanying drawing describes in detail as follows:
Fig. 1 to Fig. 3, a kind of beach cofferdam construction device are referred to, including is placed on two floating body structures of beach upper surface Part, it is respectively the first float member 1-1 close to cofferdam side, the second float member 1-2 away from cofferdam;First float member and Second float member is arranged on the both sides in borrow areas 2, is installed with the first pylon 1-10 above the first float member, and second The second pylon 1-20 is installed with above float member 1-2, purlin is installed between the first pylon 1-10 and the second pylon 1-20 Frame 1-3;Described truss one end extends to the top in cofferdam region 3 from the first pylon 1-10 sides, and the truss 1-3 other end is from second Pylon side extends identical length;The second float member 1-2, the second pylon 1-20 and/or truss 1-3 are away from cofferdam end Control cabinet is installed;The horizontal slide rail 1-30 laid along truss length direction is installed on the truss 1-3, pacified on the slide rail Equipped with walking dolly 1-31, elevator unit, the steel wire cable connection grab bucket of the elevator unit are installed on the walking dolly 1-32;Driving walking dolly is installed along the reciprocating drive device of horizontal slide rail on the truss.
The utility model can also use following technical measures:
In order to increase the stability of float member, the float member uses body structure, is fixedly mounted with the upper surface of casing Pylon is fixedly mounted in supporting plate 1-4, the top of the supporting plate.
For the ease of maintenance box operating personnel rest, it is additionally provided with above the supporting plate 1-4 towards the people in casing Hole 1-40, of short duration rest can be carried out in casing for operating personnel.
The structure of first pylon and the second pylon is identical, including two lower bracing frame 1-11 and a upper support frame 1-12, the bottom of described two lower bracing frames are fixedly connected with the upper surface of float member, among the top of two lower bracing frames Upper support frame 1-12 is fixedly mounted in position upwards, and upper support frame is connected pre- guy tightening 1- between the lower bracing frame of both sides respectively 13;Two lower bracing frames and a triangle supporting construction of upper support frame, this structure make use of the stability of triangular form, carry Its high fastness.
Cofferdam method based on above-mentioned beach cofferdam construction device comprises the following steps:
1), coffered foundation being filled using the hanged underwater clay of purlin digging below water level, using cofferdam outside on the spot Fetch earth;Beach cofferdam construction device is laid on the outside of cofferdam, more than 15m position is taken using grab bucket on the outside of away from coffered foundation Soil, the distance range that fetches earth are 15m~125m, and the depth that fetches earth is not less than 3m;Under the drive of drive device, soil is transported to and enclosed Weir;The whole process about 2min that moves in circles, purlin, which is dug, is hung in same position operation, and the time of continuously fetching earth must not exceed 1h, set every time It is standby to be fetched earth using hoist engine movement apart from preferably 5m~8m;
2), fill after cofferdam is higher by 0.5 meter of the water surface and carry out, usage mining machine carries out leveling and rolled, then successively fills Weir body is rolled, every layer of virtual resurfacing thickness is no more than 30cm, and flood usage mining machine carries out grinding compacting after the completion of every layer of paving soil, does not stay Section seam;
3), cofferdam, which is filled, takes staged and layered construction method, and section is filled by 200 meters long conduct one, that is, each when filling Soil layer is filled by 200 meters of long controls;
4), purlin is dug the pit that fetched earth when hanged underwater clay or excavator fetch earth and must not continuously penetrated, according to live actual The low bank of earth between fields of 3 meters or so of a width is stayed every 15 meters or so distances, as underwater cofferdam base support.
Described above is only to preferred embodiment of the present utility model, not the utility model is made any formal Limitation, it is every according to the technical essence of the utility model to any simple modification made for any of the above embodiments, equivalent variations with Modification, is belonged in the range of technical solutions of the utility model.

Claims (4)

  1. A kind of 1. beach cofferdam construction device, it is characterised in that:Two float members including being placed on beach upper surface, respectively For close to the first float member of cofferdam side, second float member in remote cofferdam;First float member and the second float member The both sides in borrow areas are arranged on, the first pylon is installed with above the first float member, is fixed above the second float member Second pylon is installed, truss is installed between the first pylon and the second pylon;
    Described truss one end extends to the top in cofferdam region from the first pylon side, and the other end of truss extends from the second pylon side Identical length;
    Second float member, the second pylon and/or truss are provided with control cabinet away from cofferdam end;
    The horizontal slide rail laid along truss length direction is installed on the truss, walking dolly is installed on the slide rail, institute State and elevator unit is installed on walking dolly, the steel wire cable connection grab bucket of the elevator unit;
    Driving walking dolly is installed along the reciprocating drive device of horizontal slide rail on the truss.
  2. 2. beach cofferdam construction device according to claim 1, it is characterised in that:The float member uses casing knot Structure, supporting plate is fixedly mounted with the upper surface of casing, and pylon is fixedly mounted in the top of the supporting plate.
  3. 3. beach cofferdam construction device according to claim 2, it is characterised in that:It is additionally provided with above the supporting plate logical Toward the manhole in casing.
  4. 4. beach cofferdam construction device according to claim 1, it is characterised in that:First pylon and the second pylon Structure is identical, including two lower bracing frames and a upper support frame, the bottoms of described two lower bracing frames and float member Upper surface is fixedly connected, and the top centre positions of two lower bracing frames is fixedly mounted upper support frame upwards, upper support frame respectively with Pre- guy tightening is connected between the lower bracing frame of both sides;Two lower bracing frames and a triangle supporting construction of upper support frame.
CN201720860207.5U 2017-07-14 2017-07-14 A kind of beach cofferdam construction device Active CN207211169U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720860207.5U CN207211169U (en) 2017-07-14 2017-07-14 A kind of beach cofferdam construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720860207.5U CN207211169U (en) 2017-07-14 2017-07-14 A kind of beach cofferdam construction device

Publications (1)

Publication Number Publication Date
CN207211169U true CN207211169U (en) 2018-04-10

Family

ID=61813165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720860207.5U Active CN207211169U (en) 2017-07-14 2017-07-14 A kind of beach cofferdam construction device

Country Status (1)

Country Link
CN (1) CN207211169U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338802A (en) * 2017-07-14 2017-11-10 中国水利水电第十三工程局有限公司 A kind of beach cofferdam construction device and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338802A (en) * 2017-07-14 2017-11-10 中国水利水电第十三工程局有限公司 A kind of beach cofferdam construction device and construction method

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104343455B (en) Long-distance curved jacking pipe and pipe roof construction technique
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN105133627B (en) Construction under single wall steel sheet-pile cofferdam flowing water state
CN103510551A (en) Three-directional static and dynamic loading model test platform for deep water foundations of bridges
CN106950070A (en) Experimental rig for rectangular top pipe jacking construction Whole Process Simulation
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN107869144A (en) A kind of pre- slotting ring seal Double-Wall Steel Boxed Cofferdam deep water foundation comprehensive construction method
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN107338802A (en) A kind of beach cofferdam construction device and construction method
CN106436788A (en) Foundation reinforcement and inclination correction method for friction piles of high-rise building
CN105064381A (en) High-low cutting edge double-wall steel cofferdam reinforced concrete once bottom sealing construction method
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN107386453B (en) High-rise House on stilts construction method
Ma et al. The influence of shallow buried double-line parallel rectangular pipe jacking construction on ground settlement deformation
CN207211169U (en) A kind of beach cofferdam construction device
CN103147435A (en) Method for treating construction engineering foundation in gob
CN205975646U (en) Shallow water territory steel pipe pile holder fortifield village weir structure
CN106592598A (en) Same-layer double-beam large-diameter steel pipe support and deep foundation pit combined inner support formed thereby
CN207943803U (en) Diaphram wall steel reinforcement cage lifting device under overpass
CN103614999B (en) A kind of method of clump of piles deep hole construction under complex geological condition
CN207436961U (en) A kind of full circle swinging all casing drill main body and full circle swinging all casing drill
CN206408631U (en) Anchored Sheet Pile Wall for Excavation system for closing on existing underground structure
CN110258521A (en) Ground-connecting-wall encloses well construction
CN105089084B (en) Transmission line of electricity screw pile resistance to plucking static test special equipment and test method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 300384 Tianjin Binhai New Area High-tech Zone Huayuan Industrial Area No. 2, 4-2101

Patentee after: China Construction Municipal Construction Group Co., Ltd.

Address before: 300384 No. 2, 4-2101 Rongyuan Road, Huayuan Industrial Area, Binhai New Area, Tianjin

Patentee before: Sinohydro Tianjin Engineering Co.,Ltd.