CN207177459U - A kind of construction protection column - Google Patents

A kind of construction protection column Download PDF

Info

Publication number
CN207177459U
CN207177459U CN201721210916.5U CN201721210916U CN207177459U CN 207177459 U CN207177459 U CN 207177459U CN 201721210916 U CN201721210916 U CN 201721210916U CN 207177459 U CN207177459 U CN 207177459U
Authority
CN
China
Prior art keywords
construction protection
protection column
slide
fixed
mounting hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721210916.5U
Other languages
Chinese (zh)
Inventor
于娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing City Construction Great Wall Building Decoration Engineering Co Ltd
Original Assignee
Beijing City Construction Great Wall Building Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing City Construction Great Wall Building Decoration Engineering Co Ltd filed Critical Beijing City Construction Great Wall Building Decoration Engineering Co Ltd
Priority to CN201721210916.5U priority Critical patent/CN207177459U/en
Application granted granted Critical
Publication of CN207177459U publication Critical patent/CN207177459U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of construction protection column, including firm banking, the railing on firm banking and the connection component for connecting adjacent guard rail, the firm banking includes support base and the slide assemblies being fixed in support base;The firm banking by provided with connector connect into required length;Construction protection column is slidably connected on slide assemblies for being transmitted installation, saves the process that workmen carries construction protection column, more convenient when mounted, reduces the workload of staff.

Description

A kind of construction protection column
Technical field
A kind of construction safeguard is the utility model is related to, more specifically, it relates to a kind of construction protection column.
Background technology
Construction protection column, can be extensively in urban road mainly as separating, separating or make spacer use during accident treatment The place such as construction, building engineering construction, scene of the accident uses.
When being constructed in large-scale place, the quantity of required placement guard rail is more.Existing construction protection column mostly needs Specific position is manually transported to, then carries out the installation connection on construction protection column, the quantity on construction protection column is manually removed when more It is shipped to the inconvenience that workmen brings.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of construction protection column, saves and apply Worker person carries the process on construction protection column, more convenient when mounted, reduces the workload of staff.
Above-mentioned technical purpose of the present utility model technical scheme is that:
A kind of construction protection column, including firm banking, the railing on firm banking and the adjacent protection of connection The connection component on column, the firm banking include support base and the slide assemblies being fixed in support base;The fixation Base by provided with connector connect into required length;Construction protection column be slidably connected on slide assemblies for Transmitted installation.
Pass through above-mentioned technical proposal, when being constructed in large-scale place, the required quantity for placing guard rail is also particularly It is huge, inconvenience is carried, by increasing slide assemblies in base, construction protection column is slided into finger by slide assemblies after mounting Fixed position, then be fixed.
Preferably, the slide assemblies include being fixed on the upside of support base and the cylinder slide rail of inner hollow is with sliding The sliding shoe being socketed on slide rail.
Pass through above-mentioned technical proposal, sliding block socket are slided on slide rail, and construction protection column is arranged on sliding block and passes through cunning Road is transmitted, and facilitates operating personnel to be carried and installed.
Preferably, the upper surface of the sliding shoe offers the fixing hole for connecting the railing.
Pass through above-mentioned technical proposal, mounting hole is opened up on sliding block, construction protection column is fixed on square sliding block upper surface.
Preferably, the connector includes the connecting rod of the connection slide rail and consolidating for the support base that is connected Determine part.
Pass through above-mentioned technical proposal, firm banking is lengthened by connector, the utility model is useful in difference Construction site.
Preferably, the fixture is the installation sheet being fixed in two section support bases.
Two adjacent supports bases are fixed together by Pass through above-mentioned technical proposal, installation sheet, realize two firm bankings Splicing lengthen.
Preferably, the connecting rod includes being arranged on the slide connecting part of centre and is arranged on slide connecting part axial direction both ends to connect The connecting portion of slide rail is held, the diameter of the connecting portion is less than slide connecting part, and the diameter of the slide connecting part is identical with slide rail.
Two adjacent slide rails are stitched together by Pass through above-mentioned technical proposal, connecting rod, the slide connecting part among connecting rod It is identical with the diameter of slide rail, realize that the splicing of two firm bankings lengthens.
Preferably, the connection component includes mounting hole and is fixedly connected with adjacent two with the mounting hole and constructs to prevent The fixation kit of guardrail;The fixation kit includes the inserted link for being fixed on the fixed cylinder of side and being connected in fixed cylinder;Institute State that mounting hole is located at the both sides on construction protection column with fixation kit and the top of mounting hole and the end of fixed cylinder are neat when being connected It is flat;During two construction protection column connections, the inserted link is connected between fixed cylinder and mounting hole, is applied on the inserted link upward Active force, its upward transport power until depart from mounting hole.
Pass through above-mentioned technical proposal, connector by the inserted link on a construction protection column by being plugged into another construction protection Two construction protection columns are linked together in the mounting hole on column.
In summary, the utility model has the advantages that:
1st, by increasing slide assemblies in base, construction protection column is made to slide into what is specified by slide assemblies after mounting Position, then be fixed;
2nd, firm banking is lengthened by connector, required length can be connected into, be useful in different occasions and apply The installation of work guard rail.
Brief description of the drawings
Fig. 1 is the structural representation on construction protection column;
Fig. 2 is the structural representation of construction protection column connecting rod;
Fig. 3 is the structural representation of construction protection column railing;
Fig. 4 is the structural representation of construction protection column fixation kit;
Fig. 5 is the view after the installation of construction protection column.
Reference:1st, railing;11st, branch bar;111st, straight-bar;112nd, bent rod;113rd, mounting rod;12nd, fixture;121、 Three muzzle pipes;122nd, four muzzle pipe;2nd, firm banking;21st, support base;22nd, slide assemblies;221st, slide rail;222nd, sliding shoe; 2221st, fixing hole;23rd, connector;231st, connecting rod;2311st, slide connecting part;2312nd, connecting portion;232nd, fixture;3rd, connection group Part;31st, mounting hole;32nd, fixation kit;321st, fixed cylinder;3211st, top cover;3212nd, through hole;3213rd, sideboard;322nd, bullet Property component;3221st, inserted link;3222nd, elastic component;3223rd, catch;3224th, handle;4th, warning sign.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
A kind of construction protection column, referring to Fig. 1 and Fig. 2, including firm banking 2, the railing that is slidably connected on firm banking 2 1 and the adjacent construction protection column of connection with the connection component 3 of shape needed for multiple construction protection columns are connected into.Construction protection column It is slidably connected on firm banking 2, when installing multiple construction protection columns, saves the handling time of staff.
Railing 1 has a branch bar 11, limb 11 mainly by multistage straight-bar 111, be arranged on the bent rod 112 and peace of frame Formed mounted in base and screwed mounting rod 113.Connected between pole 11 by fixture 12, wherein fixture includes being in Same plane and three muzzle pipes 121 with vertical relation and it is in same plane and the four muzzle pipes with vertical relation 122.The railing 1 on construction protection column is spliced on corresponding more muzzle pipes by the way that pole 11 is plugged on.
One piece of warning sign 4 is fixed with the centre position of railing 1, prompts non-operator away from construction area.
Referring to Fig. 1 and Fig. 3, firm banking 2 includes being supported on the support base 21 on ground and is fixed on support base 21 On slide assemblies 22.Slide assemblies 22 include being fixed on the slide rail 221 of support base 21 and are slidably socketed on slide rail 221 Sliding shoe 222.Slide rail 221 is hollow cylinder track body, and its bottom is fixed in support base 21.Sliding shoe 222 is upper table Face offers the square sliding block of bolt fixing hole 2221, and the bottom of sliding shoe 222 offers circular groove, and it is embedded in slide rail 221 Enterprising line slip.
The length of firm banking 2 can by provided with connector 23 connect into required length.Wherein connector 23 wraps Include the fixture 232 of the connecting rod 231 of connecting sliding rail 221 and the multistage support base 21 that is connected.Connecting rod 231 includes setting Put centre slide connecting part 2311 and be arranged on 2311 axial both ends of slide connecting part with the connecting portion 2312 of connection end slide rail 221, The diameter of connecting portion 2312 is less than slide connecting part 2311, and the diameter of slide connecting part 2311 is identical with slide rail 221.The company of both sides in connection Socket part 2312 is embedded into slide rail 221, and middle slide connecting part 2311 serves as a part for part slide rail 221.
Fixture 232 is rectangle aluminium alloy installation sheet, and the support base 21 of both sides is fixedly connected by it by bolt.Apply Work guard rail is slidably connected on the sliding shoe 222 of slide assemblies 22, is slided after installation by slide rail 221 multiple in sliding shoe Construction protection column on 222, send it to specific installation site.
Referring to Fig. 4, connection component 3 is fixed on two sides of railing 1, and it includes the mounting hole 31 for being welded on railing side And it is welded on the fixation kit 32 of another side.Fixation kit 32 have be fixed on fixed cylinder 321 on railing side and The elastic parts 322 being arranged in the fixed cylinder.Wherein, the bottom of fixed cylinder 321 of fixation kit 32 and the top of mounting hole 31 Flush, and two groups of identical connection components 3 are provided with the top and bottom of each construction protection column side, make two constructions anti- What guardrail can be stablized links together.
Fixed cylinder 321 is penetrating cylinder and is fixed on vertically on the side of railing 1, and its top spiral is fixed with top cover 3211, the through hole 3212 through elastic parts 322 is offered on top cover 3211.
Elastic parts 322, which has the inserted link 3221 being vertically arranged in fixed cylinder 321 and is arranged, to be on inserted link 3221 Elastic component 3222.3221 vertical profile of inserted link is cylinder stock and bottom is welded with rounded tabs 3223, and its top is fixed There is the spheroidal handle 3224 that cross-sectional area is more than the area of through hole 3212 on top cover 3211, the inserted link 3221 in fixation kit 322 Because handle 3224 is connected on top cover 3211.
Be provided with the lower end of top cover 3211 circle sideboard 3213, inserted link 3221 be inserted through sideboard 3213 with Through hole 3212.The one end of elastic component 3222 being socketed on inserted link 3221 is connected to the lower surface of sideboard 3213, and the other end abuts On the catch 3223 of inserted link 3221, wherein elastic component 3222 is spring.
Inserted link 3221 is slotting in fixed cylinder 321, outer and its length is not more than fixed cylinder 321 at its bottom in the case of by external force Being moved up to when bar 3221 is by external force in fixed cylinder 321, inserted link 3221 is had the trend for the motion that keeps down by compressing all the time, Mounting hole 31 and the vertical direction of fixed cylinder 321 are alignd, discharge the active force to inserted link 3221, inserted link 3221 is because of elastic component 3222 Effect resilience abut mounting hole 31, two construction protection columns are linked together.
Installation process:Referring to Fig. 1 and Fig. 5, multistage firm banking 2 is first spliced into needs by workmen by connector 23 Length, then multiple sliding shoes 222 are sliding fixed on slide rail 221, the railing 1 assembled is threadably secured to sliding shoe 222 On, then the railing 1 on sliding shoe 222 slided into specified location, finally two adjacent construction protection columns are fixed, most Complete the assembling on all construction protection columns according to demand afterwards.
The utility model makes workmen when installing multiple construction protection columns, and railing 1 is fixed on sliding shoe 222 and led to Cross slide rail 221 and be sent to specified location and be fixed again, reduce staff and construction protection column is carried at a distance.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but As long as all protected in right of the present utility model by Patent Law.

Claims (7)

1. a kind of construction protection column, including firm banking(2), installed in firm banking(2)On railing(1)And connection is adjacent Guard rail connection component(3), it is characterized in that:
The firm banking(2)Support base including being supported on ground(21)And it is fixed on support base(21)On slip Component(22);The firm banking(2)By provided with connector(23)Connect into required length;Slide on construction protection column It is dynamic to be connected to slide assemblies(22)On for transmitted installation.
2. construction protection column according to claim 1, it is characterized in that:The slide assemblies(22)Including being fixed on support bottom Seat(21)Upside and the cylinder slide rail of inner hollow(221)With being slidably socketed in slide rail(221)On sliding shoe(222).
3. construction protection column according to claim 2, it is characterized in that:The sliding shoe(222)Upper surface offer company Connect the railing(1)Fixing hole(2221).
4. the construction protection column according to Claims 2 or 3, it is characterized in that:The connector(23)Including connecting the cunning Rail(221)Connecting rod(231)And the support base that is connected(21)Fixture(232).
5. construction protection column according to claim 4, it is characterized in that:The fixture(232)To be fixed on the support of two sections Base(21)On installation sheet.
6. construction protection column according to claim 5, it is characterized in that:The connecting rod(231)Including being arranged on centre Slide connecting part(2311)And it is arranged on slide connecting part(2311)Axial both ends are with connection end slide rail(221)Connecting portion(2312), institute State connecting portion(2312)Diameter be less than slide connecting part(2311), the slide connecting part(2311)Diameter and slide rail(221)It is identical.
7. construction protection column according to claim 1, it is characterized in that:The connection component(3)Including mounting hole(31)With And with the mounting hole(31)It is fixedly connected with the fixation kit on two adjacent construction protection columns(32);The fixation kit(32) Fixed cylinder including being fixed on side(321)And it is connected to fixed cylinder(321)Interior inserted link(3221);The mounting hole(31) With fixation kit(32)Positioned at the both sides on construction protection column and connection when mounting hole(31)Top and fixed cylinder(321)End End flushes;During two construction protection column connections, the inserted link(3221)It is connected to fixed cylinder(321)With mounting hole(31)Between, In the inserted link(3221)Upper to apply upward active force, its upward transport power is until departing from mounting hole(31).
CN201721210916.5U 2017-09-19 2017-09-19 A kind of construction protection column Expired - Fee Related CN207177459U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721210916.5U CN207177459U (en) 2017-09-19 2017-09-19 A kind of construction protection column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721210916.5U CN207177459U (en) 2017-09-19 2017-09-19 A kind of construction protection column

Publications (1)

Publication Number Publication Date
CN207177459U true CN207177459U (en) 2018-04-03

Family

ID=61748839

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721210916.5U Expired - Fee Related CN207177459U (en) 2017-09-19 2017-09-19 A kind of construction protection column

Country Status (1)

Country Link
CN (1) CN207177459U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235326A (en) * 2018-09-13 2019-01-18 北京城建十六建筑工程有限责任公司 A kind of assembled branch turnout track of traveling construction fence sytsem
TWI656297B (en) * 2018-05-11 2019-04-11 景發鋁業有限公司 Aluminum frame fence module
CN111021826A (en) * 2019-10-08 2020-04-17 宁波市城市排水有限公司北区污水处理厂 Safety protective guard for water pump operation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI656297B (en) * 2018-05-11 2019-04-11 景發鋁業有限公司 Aluminum frame fence module
CN109235326A (en) * 2018-09-13 2019-01-18 北京城建十六建筑工程有限责任公司 A kind of assembled branch turnout track of traveling construction fence sytsem
CN109235326B (en) * 2018-09-13 2021-03-26 北京城建十六建筑工程有限责任公司 Assembled shunt turnout track of walking construction guardrail system
CN111021826A (en) * 2019-10-08 2020-04-17 宁波市城市排水有限公司北区污水处理厂 Safety protective guard for water pump operation

Similar Documents

Publication Publication Date Title
CN207177459U (en) A kind of construction protection column
CN204901062U (en) A three -dimensional antidetonation gallows
CN103835387B (en) Assembling frame structure node frcition damper
CN207177458U (en) Construction protection column
CN108930337A (en) A kind of steel-structure factory building mounting rack
CN213439564U (en) Civil engineering pipe fitting placing equipment
CN207620502U (en) A kind of municipal construction guardrail being easily installed folding
CN105672677A (en) Support tool used for fabricated building wallboard installation and use method of support tool
KR101121054B1 (en) Round logs within reinforcement pipe
CN102361252A (en) Folding rotary insulating platform
CN108180319A (en) A kind of new and effective locking single tube antidetonation branch device for hoisting
CN108547503A (en) Easy-to-dismount construction safety guardrail
CN106504674A (en) Billboard
CN206607504U (en) A kind of support platform for building
CN108223924B (en) Assembled shaft air pipe joint support
CN109356299A (en) A kind of novel buckling restrained brace stage by stage
CN207228774U (en) A kind of high municipal administration guardrail of protective
CN105804418A (en) Prefabricated wallboard fixed supporting system and construction method
CN213271380U (en) Door type unilateral bidirectional anti-seismic support hanger
CN108150724A (en) A kind of New anti-loose single tube antidetonation branch device for hoisting
CN104088297A (en) Corrugated tube installation rack used for culvert construction and application thereof
CN210003009U (en) construction adjustable rail guard is built in room
CN209538640U (en) A kind of supporting leg of pylon
CN209397711U (en) A kind of steel-structure factory building mounting rack
CN203571233U (en) Large-span X-shaped spatial arch pipeline support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180403

Termination date: 20200919

CF01 Termination of patent right due to non-payment of annual fee