CN207161119U - A kind of symmetrical trouble hole supporting construction - Google Patents

A kind of symmetrical trouble hole supporting construction Download PDF

Info

Publication number
CN207161119U
CN207161119U CN201721098562.XU CN201721098562U CN207161119U CN 207161119 U CN207161119 U CN 207161119U CN 201721098562 U CN201721098562 U CN 201721098562U CN 207161119 U CN207161119 U CN 207161119U
Authority
CN
China
Prior art keywords
shaped steel
hole
arch
steel arch
pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721098562.XU
Other languages
Chinese (zh)
Inventor
胡旺兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Zhongnan Engineering Corp Ltd
Original Assignee
PowerChina Zhongnan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Zhongnan Engineering Corp Ltd filed Critical PowerChina Zhongnan Engineering Corp Ltd
Priority to CN201721098562.XU priority Critical patent/CN207161119U/en
Application granted granted Critical
Publication of CN207161119U publication Critical patent/CN207161119U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a kind of symmetrical trouble hole supporting construction, including main hole, first hole and second hole, the shaped steel arch of semi-arched first is provided with first hole, the shaped steel arch of semi-arched second is provided with second hole;The every Pin and the second shaped steel arch of first shaped steel arch every Pin are in one-to-one relation, and correspond docking and fix, and form the shaped steel arch of complete arch door shape;The setting area of first shaped steel arch and the second shaped steel arch from first hole, second hole and main hole connection to Cha Dong Cha Dangchu.The symmetrical trouble hole supporting construction of the utility model design so that excavate Cha Dong in the location of features as poor geologic condition and be possibly realized.Using the form of shaped steel arch supporting, arrangement is simple, easy for construction, has reached good supporting effect.

Description

A kind of symmetrical trouble hole supporting construction
Technical field
The utility model belongs to underground engineering construction field, and in particular to a kind of symmetrical trouble hole supporting construction.
Background technology
During current tunnel engineering is built, symmetrical Cha Dong is excavated if needed, can typically select the good location of geological conditions Excavated, get around the location of features as poor geologic condition as far as possible, in favor of ensureing Stability of Excavation Surrounding.Opened in the good location of geological conditions Wa Cha holes, typically only need to take combined bolting and shotcrete to maintain adjoining rock stability.
But inevitably existing in Practical Project needs to excavate Cha Dong feelings in the position of features as poor geologic condition Condition, in this case traditional bolt-spary supports be difficult to ensure that adjoining rock stability, the actual requirement of engineering can not be met, it is therefore desirable to one Kind can excavate the structure that symmetrical Cha Dong carries out supporting to the location of features as poor geologic condition.
Utility model content
In view of the above-mentioned problems, the utility model aim to provide it is a kind of the location of features as poor geologic condition can be excavated it is symmetrical Cha Dong carries out the structure of supporting.
The utility model solve problem technical scheme be:A kind of symmetrical trouble hole supporting construction, including main hole and main hole connect Logical first hole and second hole, and first hole and second hole are symmetrical along main hole axis, and half is provided with first hole The shaped steel arch of arch first, the shaped steel arch of semi-arched second is provided with second hole;
In first hole, the non-top arch abutment of every shaped steel archs of a Pin first is fixed on the bottom plate in first hole, each The top of the shaped steel archs of Pin first is fixedly connected by anchor pole with country rock;
In second hole, the non-top arch abutment of every shaped steel archs of a Pin second is fixed on the bottom plate in second hole, each The top of the shaped steel archs of Pin second is fixedly connected by anchor pole with country rock;
The every Pin and the second shaped steel arch of first shaped steel arch every Pin are in one-to-one relation, and are corresponded Docking is fixed, and forms the shaped steel arch of complete arch door shape;
The setting area of first shaped steel arch and the second shaped steel arch connects from first hole, second hole with main hole Place is refuted to Cha Dong Cha Dangchu.
The form that such scheme is connected using the first shaped steel arch and the second shaped steel arch, overcome main hole and branch hole and intersect The problem of mouth supporting so that set symmetrical Cha Dong to be possibly realized in the location of features as poor geologic condition.
Further, it is sprayed with concrete between first shaped steel arch, the top of the second shaped steel arch and country rock.
Specifically, the shaped steel used in first shaped steel arch, the second shaped steel arch is I-steel, the anchor pole lower end folding L-shaped is curved, horizontal component and the I-steel bottom flange of the bending of anchor pole lower end weld.
The end of every the first shaped steel archs of Pin free end is equipped with the first connecting plate, and every shaped steel archs of a Pin second are free The end at end is equipped with the second connecting plate, the first connecting plate and the second connecting plate bolt connection, so that the first shaped steel arch Fixation is docked with every Pin of the second shaped steel arch, forms the shaped steel arch of complete arch door shape.
Preferably, the every shaped steel archs of a Pin first and the second shaped steel arch be each perpendicular to Cha Dong fork angle angular bisector set Put.It is that structure is most simple using this arrangement, the shaped steel arch arrangement form for most convenient of constructing.
For the stability of the first shaped steel arch of increase and Second-Type steel arch support, first shaped steel arch and Second-Type The non-top arch abutment of steel arch-shelf is equipped with base, is fixed on by base support on bottom plate.
The utility model design symmetrical trouble hole supporting construction so that features as poor geologic condition location excavate Cha Dong turn into can Energy.Using the form of shaped steel arch supporting, arrangement is simple, easy for construction, has reached good supporting effect.
Brief description of the drawings
The utility model is described in further detail below in conjunction with the accompanying drawings.
Fig. 1 is symmetrical trouble hole shaped steel arch horizontal layout schematic diagram.
Fig. 2 is shaped steel arch profile.
Fig. 3 is shaped steel arch joint detail drawing.
In figure:The shaped steel archs of 1- first, 2- Cha Dong forks angle, the main holes of 3-, first hole of 4-, second hole of 5-, 6- second Shaped steel arch, 7- anchor poles, 8- trouble crotch, 9- concrete, the 10- edges of a wing, the connecting plates of 11- first, the connecting plates of 61- second.
Embodiment
As shown in Figures 1 to 3, a kind of symmetrical trouble hole supporting construction, including main hole 3, first hole 4 being connected with main hole 3 and Second hole 5, and first hole 4 and second hole 5 are along the main axisymmetrical of hole 3.
The first shaped steel arch of semi-arched 1 is provided with first hole 4, the shaped steel of semi-arched second is provided with second hole 5 Bow member 6.
In first hole 4, the non-top arch abutment of every the first shaped steel archs of a Pin 1 is fixed on the bottom plate in first hole 4, often The top of one the first shaped steel archs of Pin 1 is fixedly connected by anchor pole 7 with country rock.
In second hole 5, the non-top arch abutment of every the second shaped steel archs of a Pin 6 is fixed on the bottom plate in second hole 5, often The top of one the second shaped steel archs of Pin 6 is fixedly connected by anchor pole 7 with country rock.
Every Pin of first shaped steel arch 1 and every Pin of the second shaped steel arch 6 is in one-to-one relation, and one a pair Fixation should be docked, forms the shaped steel arch of complete arch door shape.
The setting area of the shaped steel arch 6 of first shaped steel arch 1 and second is from first 4, second, hole hole 5 and main hole At 3 connection to Cha Dong trouble crotch 8.
Concrete 9 is sprayed between first shaped steel arch 1, the top of the second shaped steel arch 6 and country rock.
Shaped steel used in first shaped steel arch 1, the second shaped steel arch 6 is I-steel, and the lower end of anchor pole 7 is bent into L-shaped, the horizontal component of the lower end bending of anchor pole 7 weld with I-steel bottom flange 10.
The end of every free end of the first shaped steel archs of a Pin 1 is equipped with the first connecting plate 11, every the second shaped steel archs of a Pin 6 The end of free end is equipped with the second connecting plate 61, the first connecting plate 11 and the bolt connection of the second connecting plate 61, so that the One shaped steel arch 1 docks fixation with every Pin of the second shaped steel arch 6, forms the shaped steel arch of complete arch door shape Frame.
The angular bisector that every a Pin the first shaped steel archs 1 and the second shaped steel arch 6 are each perpendicular to Cha Dong forks angle 2 is set.
The non-top arch abutment of the shaped steel arch 6 of first shaped steel arch 1 and second is equipped with base, is supported and fixed by base In on bottom plate.
Construction procedure is as follows:
(a)Excavated from main hole 3 to first hole 4, linked network and first shotcrete support are done after excavating shaping.
(b)At connection to Cha Dong trouble crotch 8 from first 4, second, hole hole 5 with main hole 3, by the first shaped steel arch 1 non-top arch abutment is fixed on the bottom plate in first hole 4.Coagulation is sprayed again between the first shaped steel arch 1 and first hole wall of hole 4 Soil, then by the more one end of L-shaped anchor pole 7 insertions, country rock is fixed, the other end is bent into horizontal part and the bottom of the first shaped steel arch 1 Weld on the portion edge of a wing 10.
(c)Second hole 5 of opposite side is excavated, linked network and first shotcrete support are done after excavating shaping.
(d)The non-top arch abutment of second shaped steel arch 6 is fixed on to the bottom plate in second hole 5, by the every of the second shaped steel arch 6 One Pin docks fixation with every Pin of the first shaped steel arch 1, forms the shaped steel arch of complete arch door shape.Second Multiple pneumatically placed concrete between shaped steel arch 6 and second hole wall of hole 5, then, country rock is inserted into more one end of L-shaped anchor pole 7 and fixed, separately One end is bent into horizontal part and welded with the bottom flange 10 of the second shaped steel arch 6.
The angular bisector that every a Pin the first shaped steel archs 1 and the second shaped steel arch 6 are each perpendicular to Cha Dong forks angle 2 is set.
The non-top arch abutment of the shaped steel arch 6 of first shaped steel arch 1 and second is welded with base, is supported by base solid Due on bottom plate.

Claims (6)

1. a kind of symmetrical trouble hole supporting construction, including main hole(3)And main hole(3)First hole of connection(4)With second hole (5), and first hole(4)With second hole(5)Along main hole(3)Axisymmetrical, it is characterised in that:In first hole(4)Inside set There is the shaped steel arch of semi-arched first(1), in second hole(5)It is interior to be provided with the shaped steel arch of semi-arched second(6);
In first hole(4)It is interior, every shaped steel archs of a Pin first(1)Non-top arch abutment be fixed on first hole(4)Bottom plate on, Every shaped steel archs of a Pin first(1)Top pass through anchor pole(7)It is fixedly connected with country rock;
In second hole(5)It is interior, every shaped steel archs of a Pin second(6)Non-top arch abutment be fixed on second hole(5)Bottom plate on, Every shaped steel archs of a Pin second(6)Top pass through anchor pole(7)It is fixedly connected with country rock;
First shaped steel arch(1)Every a Pin and the second shaped steel arch(6)Every Pin be in one-to-one relation, and one a pair Fixation should be docked, forms the shaped steel arch of complete arch door shape;
First shaped steel arch(1)With the second shaped steel arch(6)Setting area from first hole(4), second hole(5)With Main hole(3)Connection to Cha Dong trouble crotch(8)Place.
2. symmetrical trouble hole supporting construction according to claim 1, it is characterised in that:First shaped steel arch(1), second Shaped steel arch(6)Top and country rock between be sprayed with concrete(9).
3. symmetrical trouble hole supporting construction according to claim 2, it is characterised in that:First shaped steel arch(1), second Shaped steel arch(6)Shaped steel used is I-steel, the anchor pole(7)Lower end bending is L-shaped, anchor pole(7)The level of lower end bending Part and I-steel bottom flange(10)Welding.
4. symmetrical trouble hole supporting construction according to claim 3, it is characterised in that:Every shaped steel archs of a Pin first(1)From First connecting plate is equipped with by the end held(11), every shaped steel archs of a Pin second(6)The end of free end is equipped with the second company Fishplate bar(61), the first connecting plate(11)With the second connecting plate(61)Bolt connection, so that the first shaped steel arch(1)With second Shaped steel arch(6)Every Pin correspond docking and fix, form the shaped steel arch of complete arch door shape.
5. symmetrical trouble hole supporting construction according to claim 1, it is characterised in that:Every shaped steel archs of a Pin first(1)With Second shaped steel arch(6)It is each perpendicular to Cha Dong forks angle(2)Angular bisector set.
6. symmetrical trouble hole supporting construction according to claim 1, it is characterised in that:First shaped steel arch(1)With Two shaped steel archs(6)Non-top arch abutment be equipped with base, by base support be fixed on bottom plate.
CN201721098562.XU 2017-08-30 2017-08-30 A kind of symmetrical trouble hole supporting construction Active CN207161119U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721098562.XU CN207161119U (en) 2017-08-30 2017-08-30 A kind of symmetrical trouble hole supporting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721098562.XU CN207161119U (en) 2017-08-30 2017-08-30 A kind of symmetrical trouble hole supporting construction

Publications (1)

Publication Number Publication Date
CN207161119U true CN207161119U (en) 2018-03-30

Family

ID=61719658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721098562.XU Active CN207161119U (en) 2017-08-30 2017-08-30 A kind of symmetrical trouble hole supporting construction

Country Status (1)

Country Link
CN (1) CN207161119U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313790A (en) * 2017-08-30 2017-11-03 中国电建集团中南勘测设计研究院有限公司 A kind of symmetrical trouble hole supporting construction and its construction method
CN109853494A (en) * 2019-03-12 2019-06-07 中国电建集团中南勘测设计研究院有限公司 Cha Dong and surge-chamber integral structure and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107313790A (en) * 2017-08-30 2017-11-03 中国电建集团中南勘测设计研究院有限公司 A kind of symmetrical trouble hole supporting construction and its construction method
CN109853494A (en) * 2019-03-12 2019-06-07 中国电建集团中南勘测设计研究院有限公司 Cha Dong and surge-chamber integral structure and its construction method

Similar Documents

Publication Publication Date Title
CN108278116B (en) Shallow-buried large-span pipe curtain supporting system and construction method thereof
CN103603679B (en) For arch crown steel frame and the method for tunnel construction of arch, supporting tunnel
CN104775832A (en) Primary support structure of corrugated steel tunnel
CN205171549U (en) Piping lane prefab and prefabricated formula utility tunnel
CN207161119U (en) A kind of symmetrical trouble hole supporting construction
CN210460706U (en) Underground roadway supporting device for coal mining
CN107313790A (en) A kind of symmetrical trouble hole supporting construction and its construction method
CN105822329B (en) A kind of construction method of support bracket, supporting construction and supporting construction
CN206668287U (en) A kind of combined steel pipe concrete bow member for supporting
CN206816278U (en) Novel recoverable supporting steel arch frame for excavating transverse channel
CN107387131A (en) A kind of asymmetric trouble hole supporting construction and its construction method
CN207093102U (en) A kind of asymmetric trouble hole supporting construction
CN205154191U (en) Tunnel preliminary bracing steel pipe concrete steelframe
CN207892630U (en) A kind of steel arch-shelf quickly assembled
CN204646267U (en) A kind of corrugated steel Tunnel structure
CN105804084A (en) Excavation construction method of small foundation pit near excavated deep foundation pit
CN205400759U (en) Special U shaped steel support of city subway construction
CN203905008U (en) Diagonal brace supporting structure for superior angle of foundation pit
CN209925009U (en) Connecting block in tunnel invert steelframe gap
CN210459181U (en) New and old ground is wall T joint design node even
CN209875183U (en) Tunnel IV-level surrounding rock full-circle excavation inverted arch longitudinal water stop fixing device
CN206957743U (en) A kind of rectangular steel pipe curtain foot attachment structure
CN215715362U (en) Steel encloses purlin connecting device
CN216077147U (en) Soft rock frame canopy tunnel reinforcing bar backplate
CN219570092U (en) TBM detachable temporary supporting device for coal mine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant