A kind of foundation structure in digging-free assembled stereoscopic garage
Technical field
It the utility model is related to foundation structure, more particularly to a kind of basis knot in digging-free assembled stereoscopic garage
Structure.
Background technology
After reform and opening-up, China shoots up as the third-largest automobile production state in the world and second largest automobile consumption state,
And the demand in parking lot also gradually increases.The thing followed also has the parking problems such as the few, parking difficulty of car multidigit, and parking stall shortage can
See one spot.Intelligent parking garage is as can concentrate the parking difficulty for solving people and being run into docking process, look for that car is difficult, passage rate
Moderate, the problems such as pay charge way is single, fully meet the modern parking lot of the practical demand of people, being capable of managing parking field well
Order, is effectively facilitated the raising of the limited parking stall utilization rate in parking lot, stopping at release problem, therefore, the demand of intelligent parking garage
Rise constantly.
At present, existing building type of foundation mainly has following several:(1) isolated footing, in the isolated footing individually excavated
Middle pouring reinforcement concrete, uneven soil property is constructed, construction is uncomplicated;But when upper load is larger, using independence
Basis relatively wastes, and when soil property is uneven, isolated footing settlement difference is larger.(2) strip footing, bending rigidity is big, will
Top load is converted into uniform load, makes basic stress more uniform;It is more unrestrained but strip footing construction is complex
Take, scene uses cast-type operation, and construction period is longer.(3) raft foundation, the compressive load per unit area of foundation soil can be reduced, carried
High foundation bearing capacity, and strengthen the integral rigidity on basis;But raft foundation volume is larger, casting concrete amount during construction
Greatly, construct more complicated, economy is poor.(4) pile foundation, has higher bearing capacity, and antidumping and sidesway to building have very
High guarantee;But cost is higher.
As can be seen here, traditional infrastructure form all inevitably needs excavation and construction.But in some large- and-medium size cities
In the case that housing-group is intensive, underground utilities are intricate, excavation of foundation pit is carried out, inevitably to Adjacent Buildings, pipeline
And the security of other underground installations constitutes a threat to.When especially excavation of foundation pit frontier distance existing building is close, foundation ditch
Additional shearing and moment of flexure can be applied to close to buildings and its basis by excavating soil body movement caused by off-load, and even more serious
Be so that the foundation soil of settlement stability due to settling again already, and particularly the mixed old building of brick is to uneven heavy
Drop very sensitive.
Therefore, it is significant to design a kind of foundation structure in digging-free assembled stereoscopic garage.
Utility model content
Technical problem to be solved in the utility model is the provision of one kind and does not need excavation and construction, suitable for flatness
Inconsistent ground, and dismount the foundation structure in convenient digging-free assembled stereoscopic garage.
The utility model is that solve above-mentioned technical problem by the following technical programs:A kind of digging-free assembled stereoscopic car
The foundation structure in storehouse, the foundation structure include girder steel, ground, and the girder steel includes primary and secondary girder steel, the primary and secondary girder steel peace
Loaded on radially along column direction, the girder steel is prefabricated construction, is from top to bottom set successively between the girder steel and ground
Have rubber layer, a sand stone layer, the girder steel upper surface is equipped with precast rc slab, the suspension column of the column by bolt with
Armoured concrete slab, the connection of main girder steel top flange.
As the technical scheme of optimization, it is bolted between the armoured concrete slab and girder steel.
As the technical scheme of optimization, the girder steel top flange and armoured concrete slab are provided with bolt hole.
As the technical scheme of optimization, bolted end-plate connection is used between the main girder steel.
As the technical scheme of optimization, the main girder steel uses high strength exploitation with time girder steel.
As the technical scheme of optimization, the main girder steel sectional dimension is HM400 × 300 × 10 × 16, addresses time steel
Beam section size is HM300 × 200 × 8 × 12.
As the technical scheme of optimization, the steel that the girder steel element of the foundation structure uses are H profile steels.
As the technical scheme of optimization, reinforcement is equipped with the H profile steel, the reinforcement is located at the H profile steel
Inner side, and one end of the reinforcement is connected with the top of the H profile steel, the other end of the reinforcement and the H profile steel
Bottom connects.
The utility model has advantages below compared with prior art:
1st, digging-free:Steel structure base is resolved into some girder steel elements, after the completion of processing and manufacturing, work is transported to by lorry
Journey scene, then on-site hoisting and splicing are implemented by large crane, steel structure base is assembled to form, is then laid on girder steel fixed pre-
Armoured concrete slab processed, avoid the security of the underground installation such as excavation and construction, protection surrounding building, pipeline.
2nd, steel foundation settlement is avoided:Certain thickness sand-gravel cushion is laid on ground, the bearing capacity on ground can be improved, and is kept away
Exempt from steel foundation uneven settlement;Layer rubber layer is first laid on sand bed course, avoids the endurance issues such as girder steel corrosion.
3rd, dismounting facility:All components of foundation structure can be divided into some units and carry out prefabricated, Zhi Houxian in factory
Field is assembled using full bolt, easy disassembly, short construction period.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model embodiment;
Fig. 2 is suspension column and girder steel junction enlarged diagram in the utility model embodiment;
Fig. 3 is precast slab and girder steel junction enlarged diagram in the utility model embodiment.
Wherein, 1, suspension column;2nd, armoured concrete slab;3rd, girder steel;4th, bolt;5th, Bolted End-plate;6th, bolt hole;7th, rubber
Layer;8th, sand stone layer;9th, ground.
Embodiment
Embodiment of the present utility model is elaborated below, the present embodiment using technical solutions of the utility model before
Put and implemented, give detailed embodiment and specific operating process, but the scope of protection of the utility model is unlimited
In following embodiments.
Refer to simultaneously shown in Fig. 1, Fig. 2 and Fig. 3, the foundation structure in the present embodiment digging-free assembled stereoscopic garage, including
Girder steel 3, ground 9, the girder steel 3 include primary and secondary girder steel, and the primary and secondary steel girder erection is in radially along column direction, the girder steel
3 be prefabricated construction, and rubber layer 7, sand stone layer 8, the steel are from top to bottom sequentially provided between the girder steel 3 and ground 9
The upper surface of beam 1 is equipped with precast rc slab 2, and the suspension column 1 of the column passes through bolt 4 and armoured concrete slab 2, main steel
Beam top flange connects;Connected between the armoured concrete slab 2 and girder steel 3 by bolt 4;The top flange of girder steel 3 and reinforcing bar
Concrete slab 2 is provided with bolt hole 6;Connected between the main girder steel using Bolted End-plate 5;The main girder steel is adopted with time girder steel
Connected with high-strength bolt 4;The main girder steel sectional dimension is HM400 × 300 × 10 × 16, addresses time girder steel sectional dimension
For HM300 × 200 × 8 × 12;The steel that the girder steel element of the foundation structure uses are H profile steels;It is equipped with the H profile steel
Reinforcement, the reinforcement is located at the inner side of the H profile steel, and one end of the reinforcement is connected with the top of the H profile steel,
The other end of the reinforcement is connected with the bottom of the H profile steel.
In the present embodiment, by prefabricated components after factory is transported to job site, first place rammed earth is flattened, built
In the range of ground on completely spread one layer of sandy soils 8, to increase bearing capacity, uneven settlement of foundation is avoided, in order to avoid girder steel is rotten
The endurance issues such as erosion, first lay layer rubber layer 7 on sandy soils 8, so as to the digging-free of optimized integration.
Specifically, basic engineering is resolved into some standardization H profile steel beams, girder steel element is by Gang Gou enterprises according to figure
Paper conversion manufacture is completed, and engineering site is transported to by lorry, then implements on-site hoisting and splicing primary and secondary girder steel by large crane, according to
It is secondary that external diameter after first internal diameter installs radial direction girder first according to outer shroud after first inner ring, the positioning of radial direction girder complete after according to by
It is interior to arrive outer gradually assembled ring girder, secondary beam is finally installed, is finally assembled to form steel structure base.It is it should be noted that whole
Installation process is connected using bolt 4.
Then precast rc slab 2 is laid on foundation structure girder steel 3, by bolt 4 by prefabricated reinforced concrete
Plate 2 is fixed with girder steel 3, realizes full assembling, so as to form the basis of design and road, after installation, in steel table
Face whitewashing once improves the durability on basis.
The transport of prefabricated components is each to basis according to lorry specification using domestic long 9.6m, wide 2.5m lorry
Component carries out fractionation design.With reference to haulage vehicle requirement, first inner ring girder is divided into 3 sections and is processed, the second inner ring girder
It is divided into 12 sections to be processed;3rd inner ring girder is divided into 16 sections and is processed;Outer ring girder is divided into 16 sections and is processed.It is specific every
Section size is as shown in table 1.Girder, in order to construct conveniently, should avoid being arranged in steel column and basic junction with girder junction.Its
Remaining secondary beam transports to scene after each physical length is processed again according to its.Each girder nearly weighs greatly 1 ton, and live crane needs
Meet lifting requirements.
The material table of table 1
Due to the concentrated force that base steel plinth is transmitted by upper box trestle, therefore in the direction radially along pillar, main girder steel is set
(HM400*300*10*16) and secondary girder steel (HM300*200*8*12), in base steel plinth and the node of supporting frame post connecting portion
Strengthened using outer ring plate and welding ribbed stiffener in domain.
In addition, the road that a wide 6m is built on the outside of the supporting frame post of outer ring is used to meet vehicle traveling and supporting road
Requirement, road is also to be made up of precast slab.
By by the component of foundation structure be divided into some components factory carry out it is prefabricated, then at the scene using full bolt connect
The mode connect, Site Welding operation is avoided, reduces existing workload, not only facilitates raising packaging efficiency, realized quick
Multi-storied garage is built, while avoids deformation and other quality problems caused by welding operation etc..In addition, each component is pre- in factory
Make, reduce the workload of Site Welding or splicing, it is possible to achieve fast assembling-disassembling, also, the one integral piece disassembled can weigh
It is multiple to utilize, energy-conserving and environment-protective.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model
All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model
Protection domain within.