CN207017097U - Deep super embankment on soft soil - Google Patents

Deep super embankment on soft soil Download PDF

Info

Publication number
CN207017097U
CN207017097U CN201720936830.4U CN201720936830U CN207017097U CN 207017097 U CN207017097 U CN 207017097U CN 201720936830 U CN201720936830 U CN 201720936830U CN 207017097 U CN207017097 U CN 207017097U
Authority
CN
China
Prior art keywords
embankment
prefabricated
soft soil
diameter
sheet pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720936830.4U
Other languages
Chinese (zh)
Inventor
王新泉
李肖
李栋樑
崔允亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201720936830.4U priority Critical patent/CN207017097U/en
Application granted granted Critical
Publication of CN207017097U publication Critical patent/CN207017097U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

A kind of deep super embankment on soft soil is the utility model is related to, including:Embankment, soil cement divider wall, stabilization zone solidification soil cement, transition region solidification soil cement, drainage blanket, the prefabricated node of cross, isolation geotextiles, reinforced concrete box plate, the prefabricated node of a word, sheet pile with ribbing and quick grouting equipment;The sheet pile with ribbing reaches ultra-soft soil layer through stabilization zone solidification soil cement, and sheet pile with ribbing carries circular hole in prefabricated sheet pile foundation on principal rod of the fixed position using vertical dowel B bendings as rib, its middle rib;It is overall to be respectively used to provided with rectangle anchor plate, circular anchor plate by vertical dowel A, vertical dowel B anchoring.The beneficial effects of the utility model are:Stabilization zone solidification soil cement, transition region solidification soil cement, rigid pile, reinforced concrete sash plate, enhance the overall stress of roadbed, greatly reduce the differential settlement of ground, vertical drainage body, drainage blanket efficiently solve work groundwork drainage problem.

Description

Deep super embankment on soft soil
Technical field
Expressway works and foundation treatment technology field are the utility model is related to, refers specifically to deep super embankment on soft soil.
Background technology
Over nearly more than 40 years, deep super soft ground Embankment Subsidence and stable problem are interesting.Due to the complex nature of the problem, It is to perplex the difficult problems that engineering is smoothly implemented that rational Ground Treatment Schemes how are formulated in process of construction.Corniche road Dike is mostly deep soft soil foundation, and ground is weak and does not almost have crust layer, and native microstructure and genesis mechanism are complicated and changeable, thing Reason model and its parameter have heterogencity, anisotropy and uncertainty.Highway is a kind of linear banding engineering, Binhai Highway Often pass through different geomorphic units.The engineering-environment complicated in face of Coastal Area in Zhejiang Province, for without crust layer, high-moisture (ω >=60~100%), high void ratio (e >=1.8~2.0), shearing strength are low, high sensitivity, infiltration coefficient very little, thickness The deformation characteristic of the stream plasticity mud of (H0 >=40~60m) greatly, still has very in terms of technical data and project data accumulation at present It is more insufficient.Due to the complexity of engineering-environment and the uncertainty of ground character, deep super soft ground embankment construction is faced with Many technical barriers, wherein most importantly overcoming the differential settlement of highway.
Before the utility model, Chinese invention " sheet pile combined structure " (patent No.:CN101298776A one) is provided Kind sheet pile combined structure, it is characterised in that by Prefabricated reinforced concrete pile tube, Prefabricated reinforced concrete baffle plate, reinforced concrete longitudinal beam and transverse beam Composition, the globality and stability of the structure are good, rigidity is big.It is uneven heavy but to still suffer from embankment lateral displacement big for the technology The problem of drop is still notable, and do not account for draining, embankment periphery mound Load Problems after work.
Utility model content
The purpose of this utility model seeks to the deficiency for solving above-mentioned background technology, there is provided a kind of deep super embankment on soft soil.
In order to realize above-mentioned technical purpose, the utility model employs following technical scheme:
Deep super embankment on soft soil, including embankment, soil cement divider wall, stabilization zone solidification soil cement, transition region solidification cement The prefabricated node of soil, drainage blanket, cross, isolation geotextiles, reinforced concrete box plate, the prefabricated node of a word, sheet pile with ribbing and Quick grouting equipment;The sheet pile with ribbing reaches ultra-soft soil layer through stabilization zone solidification soil cement, and sheet pile with ribbing is in prefabricated sheet pile On the basis of vertical dowel B bent in fixed position principal rod as rib, carry circular hole on its middle rib;Anchored provided with rectangle Steel plate, circular anchor plate be respectively used to be by vertical dowel A, vertical dowel B anchoring it is overall, circular anchor plate it is straight The length of side of footpath and rectangle anchor plate is respectively less than anchor slot diameter;The prefabricated intra-node of cross forms transverse direction provided with deformed bar Dowel A;The prefabricated node of cross leaves bottom embedded groove and top anchor groove in longitudinal and transverse intersection, and top is top anchor Groove, bottom are bottom embedded groove, and the diameter of groove is wider than the diameter of back cover pile tube with holes, and intersection leaves vertical dowel through hole A, the diameter in hole are more than the vertical dowel A of stake diameter;The prefabricated node of cross is provided with drainpipe, connection step in end, in advance The lateral connection muscle A of node processed stretches out certain length at step.
The back cover pile tube with holes uses back cover drainage type pile tube, fills core with sand or rubble, using pervious concrete or sets Permeable hole, slurry outlet is set in pile body.
The isolation geotextiles are covered in above drainage blanket, for isolating the concrete of top construction.
The length that each 1/4 section of the prefabricated node of cross is 2.2~2.4m top anchor 30~50mm of groove depth, bottom embedded groove Deep 30~50mm.
The length of each 1/2 section of the prefabricated node of one word is 2.2~2.4m, and inside forms transverse direction provided with deformed bar Dowel B, vertical dowel through hole B, the diameter in hole are more than the vertical dowel B of stake diameter.
The quick grouting equipment includes:Slip casting pipeline section not with holes, slip casting pipeline section, upper spacer, lower clapboard and foam with holes Bed course;The upper spacer, lower clapboard and Grouting Pipe weld together.
The beneficial effects of the utility model are:The ground that divider wall solves work rear perimeter edge mound and WATER LEVEL CHANGES is brought Base destabilization problems, stabilization zone solidification soil cement, transition region solidification soil cement, rigid pile, reinforced concrete sash plate, enhance roadbed Overall stress, greatly reduces the differential settlement of ground, and vertical drainage body, drainage blanket efficiently solve work groundwork draining Problem.
Brief description of the drawings
Fig. 1 is the structure section figure of the deep super embankment on soft soil of the utility model and construction method;
Fig. 2 is the prefabricated node schematic diagram of cross;
Fig. 3 is the prefabricated node A-A diagrammatic cross-sections of cross;
Fig. 4 is sheet pile schematic diagram with ribbing;
Fig. 5 is sheet pile B-B diagrammatic cross-sections with ribbing;
Fig. 6 is the prefabricated node schematic diagram of a word;
Fig. 7 is rectangle anchor plate schematic diagram;
Fig. 8 is circular anchor plate schematic diagram;
Fig. 9 is quick grouting equipment schematic diagram;
Figure 10 is construction flow chart.
In figure:1-embankment, 2-ultra-soft soil layer, 3-Soft Soil Layer, 4-stabilization zone solidification soil cement, the solidification of 5-transition region Soil cement, 9-back cover pile tube with holes, 10-slurry outlet, 11-slip casting around pile area, 12-drainage blanket, the prefabricated section of 13-cross Point, 14-vertical dowel A, 15-bottom embedded groove, 16-top anchor groove, 17-vertical dowel through hole A, 18- Fill at the top of anchor slot core, 19-rear fill slightly expanded concrete A, 20-rectangle anchor plate, 21-circular anchor plate, 22-anchor Gu steel plate through hole, 23-connection step A, 24-lateral connection muscle A, 25-drainpipe, 26-isolation geotextiles, 27-side Ditch, 28-lateral row water hole, 29-backfill planting soil, 30-reinforced concrete box plate, the prefabricated node of 31-one word, 32-shield Column, 33-sheet pile with ribbing, 34-vertical dowel B, 35-vertical dowel through hole B, 36-are rear fill slightly expanded concrete B, 37-connection step B, 38-lateral connection muscle B, 39-quick grouting equipment, 40-slip casting pipeline section not with holes, 41-note with holes Starch pipeline section, 42-upper spacer, 43-lower clapboard, 44-foam carpet, 45-anchor bolt, 46-prefabricated bent cap.
Embodiment
Specific embodiment of the utility model is elaborated below in conjunction with the accompanying drawings.
Fig. 1 is the structure section figure of the deep super embankment on soft soil of the utility model and construction method;Fig. 2 is the prefabricated node of cross Schematic diagram;Fig. 4 is sheet pile schematic diagram with ribbing;Fig. 6 is the prefabricated node schematic diagram of a word.Shown deep super embankment on soft soil and construction party Method, the deep super embankment on soft soil and construction method mainly include embankment 1, stabilization zone solidification soil cement 4, transition region solidification water Soil 5, back cover pile tube 9 with holes, drainage blanket 12, the prefabricated node 13 of cross, isolation geotextiles 26, reinforced concrete box plate 30th, the prefabricated node 31 of a word, sheet pile with ribbing 33, quick grouting equipment 39;The divider wall 6 is prefabricated using prefabricated sheet pile, top Bent cap 46 is linked as entirety.
The deep super embankment on soft soil of the present embodiment, including embankment 1, soil cement divider wall 6, stabilization zone solidification soil cement 4, mistake Cross area's solidification soil cement 5, drainage blanket 12, the prefabricated node 13 of cross, isolation geotextiles 26, reinforced concrete box plate 30, one The prefabricated node 31 of word, sheet pile with ribbing 33 and quick grouting equipment 39;The sheet pile with ribbing 33 solidifies soil cement 4 through stabilization zone Ultra-soft soil layer 2 is reached, sheet pile 33 with ribbing is bent vertical dowel B34 as rib in fixed position in prefabricated sheet pile foundation Principal rod, circular hole is carried on its middle rib;It is respectively used to provided with rectangle anchor plate 20, circular anchor plate 21 by vertical dowel To be overall, the diameter of circular anchor plate 21 and the length of side of rectangle anchor plate 20 are respectively less than for A14, vertical dowel B34 anchoring Anchor slot diameter;The prefabricated inside of node 13 of cross is provided with deformed bar and forms lateral connection muscle A24;The prefabricated node 13 of cross exists Longitudinal and transverse intersection leaves bottom embedded groove 15 and top anchor groove 16, and top is top anchor groove, and bottom is bottom embedded groove, The diameter of groove is wider than the diameter of back cover pile tube 9 with holes, and intersection leaves vertical dowel through hole A17, and the diameter in hole is more than stake Vertical dowel A14 diameter;The prefabricated node of cross is provided with drainpipe 25, connection step 23, the horizontal stroke of prefabricated node in end Certain length is stretched out at step to dowel A24.
The back cover pile tube 9 with holes uses back cover drainage type pile tube, fills core with sand or rubble, using pervious concrete or sets Permeable hole, slurry outlet 10 is set in pile body.
The isolation geotextiles 26 are covered in above drainage blanket, for isolating the concrete of top construction.
The length of 13 each 1/4 sections of the prefabricated node of cross is 2.2~2.4m top anchor 30~50mm of groove depth, and bottom is embedded in 30~50mm of groove depth.
The length of prefabricated 31 each 1/2 sections of the node of one word is 2.2~2.4m, and inside forms horizontal stroke provided with deformed bar To dowel B38, vertical dowel through hole B35, the diameter in hole is more than the vertical dowel B34 of stake diameter.
The quick grouting equipment 39 includes:Slip casting pipeline section 40 not with holes, slip casting pipeline section 41 with holes, upper spacer 42, under every Plate 43 and foam carpet 44;The upper spacer 42, lower clapboard 43 weld together with Grouting Pipe.
Above-mentioned deep super embankment on soft soil and construction method work progress mainly include the following steps that:
1st, site clearing, in the range of the width that should satisfy the need, ground top layer fertile soil, table soil, turf etc. cleared up;
2nd, partition wall construction:Sheet pile 33 with ribbing is squeezed into ultra-soft soil layer 2, Soft Soil Layer 3, the prefabricated node 31 of a word is installed, adopted The anchoring of vertical dowel B34 anchor bolts 45 is linked as entirety with rectangle anchor plate 20.Slightly expanded concrete B36 is filled after Sealing of hole.Groove is excavated according to the prefabricated size of bent cap 46 lateral connection muscle B colligations are linked to be formed with some strength and overall knot The prefabricated bent cap 46 of structure forms entirety, to resist soil lateral pressure caused by the mound of periphery;
3rd, solidification soil cement in stabilization zone is constructed and pushed ahead, and utilizes a series of caused things between curing agent and ultra-soft soil Physicochemical reacts, and makes weak soil scleroma into the high-quality ground with globality, water stability and some strength;
4th, transition region solidification soil cement 5, stabilization zone solidification soil cement 4 are constructed and pushed ahead, and utilize curing agent and ultra-soft Caused a series of physical chemical reaction makes weak soil scleroma into the high-quality of globality, water stability and some strength between soil Ground;
5th, foundation pile construction:Back cover pile tube 9 with holes is squeezed into before cement solidification, after 48 hours, with quick grouting equipment Slip casting.The quick slip casting of grouting equipment 39 is inserted into back cover pile tube 9 with holes using machinery, slowly push belt arrival is specified inwards Stop insertion during 10 position of slurry outlet, cement mortar is injected slip casting pipeline section 40 not with holes and injected, due to upper spacer 42, lower clapboard 43rd, foam carpet 44 is bonded with the inwall of back cover pile tube 9 with holes, and cement mortar forms slip casting around pile from the pulp of slip casting pipeline section 41 with holes Area.Then above carry successively, stop above carrying when reaching next 10 position of slurry outlet, slip casting, operate successively.
6th, groove is excavated according to the size of reinforced concrete box plate 30;
7th, lay drainage blanket 12 and be compacted;
8th, it is native for isolating top in the top of drainage blanket 12 laying isolation geotextiles 26;
9th, the prefabricated node 13 of cross is filled, using circular anchor plate 20 by the vertical company of anchoring of dowel A14 anchor bolts 45 For entirety.Slightly expanded concrete A19 sealing of holes are filled after.Vertical dowel A14 anchorings are linked as entirety;
10th, with reinforcing bar colligation or lateral connection muscle A24 is welded to connect, pouring reinforcement concrete sash plate 30;
11st, after reinforced concrete box plate reaches the 70%~80% of design strength, progress embankment 1 fills and follow-up side Ditch 27, lateral row water hole 28, backfill planting soil 29, guardrail 32 are constructed.

Claims (6)

1. a kind of deep super embankment on soft soil, it is characterised in that including embankment (1), soil cement divider wall (6), stabilization zone solidification water Soil (4), transition region solidification soil cement (5), drainage blanket (12), the prefabricated node of cross (13), isolation geotextiles (26), reinforcing bar Concrete frame panel (30), the prefabricated node of a word (31), sheet pile with ribbing (33) and quick grouting equipment (39);The sheet pile with ribbing (33) ultra-soft soil layer (2) is reached through stabilization zone solidification soil cement (4), sheet pile (33) with ribbing is in prefabricated sheet pile foundation in fixation Position bends vertical dowel B (34) principal rod as rib, and circular hole is carried on its middle rib;Provided with rectangle anchor plate (20), circular anchor plate (21) is respectively used to vertical dowel A (14), vertical dowel B (34) anchorings to be overall, circular The diameter of anchor plate (21) and the length of side of rectangle anchor plate (20) are respectively less than anchor slot diameter;In the prefabricated node of cross (13) Portion is provided with deformed bar and forms lateral connection muscle A (24);The prefabricated node of cross (13) leaves bottom insertion in longitudinal and transverse intersection Groove (15) and top anchor groove (16), top are top anchor groove, and bottom is bottom embedded groove, and the diameter of groove is wider than back cover with holes The diameter of pile tube (9), intersection leave vertical dowel through hole A (17), and the diameter in hole is more than the vertical dowel A (14) of stake Diameter;The prefabricated node of cross is provided with drainpipe (25), connection step (23), the lateral connection muscle A of prefabricated node in end (24) certain length is stretched out at step.
2. deep super embankment on soft soil according to claim 1, it is characterised in that the back cover pile tube (9) with holes is using envelope Bottom drainage type pile tube, fills core with sand or rubble, using pervious concrete or sets permeable hole, and slurry outlet (10) is set in pile body.
3. deep super embankment on soft soil according to claim 1, it is characterised in that described isolation geotextiles (26) row of being covered in Above water subfill, for isolating the concrete of top construction.
4. deep super embankment on soft soil according to claim 1, it is characterised in that each 1/4 section of the prefabricated node of cross (13) Length be 2.2~2.4m top anchor 30~50mm of groove depth, bottom 30~50mm of insertion groove depth.
5. deep super embankment on soft soil according to claim 1, it is characterised in that the prefabricated node of a word (31) each 1/ 2 sections of length is 2.2~2.4m, and inside is provided with deformed bar and forms lateral connection muscle B (38), vertical dowel through hole B (35), the diameter in hole is more than the diameter of the vertical dowel B (34) of stake.
6. deep super embankment on soft soil according to claim 1, it is characterised in that the quick grouting equipment (39) includes: Slip casting pipeline section (40), slip casting pipeline section with holes (41), upper spacer (42), lower clapboard (43) and foam carpet (44) not with holes;It is described Upper spacer (42), lower clapboard (43) weld together with Grouting Pipe.
CN201720936830.4U 2017-07-31 2017-07-31 Deep super embankment on soft soil Active CN207017097U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720936830.4U CN207017097U (en) 2017-07-31 2017-07-31 Deep super embankment on soft soil

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720936830.4U CN207017097U (en) 2017-07-31 2017-07-31 Deep super embankment on soft soil

Publications (1)

Publication Number Publication Date
CN207017097U true CN207017097U (en) 2018-02-16

Family

ID=61481996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720936830.4U Active CN207017097U (en) 2017-07-31 2017-07-31 Deep super embankment on soft soil

Country Status (1)

Country Link
CN (1) CN207017097U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447613A (en) * 2017-07-31 2017-12-08 浙江大学城市学院 A kind of deep super embankment on soft soil and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107447613A (en) * 2017-07-31 2017-12-08 浙江大学城市学院 A kind of deep super embankment on soft soil and construction method

Similar Documents

Publication Publication Date Title
CN107447613A (en) A kind of deep super embankment on soft soil and construction method
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN103410167B (en) Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method
CN103334357B (en) Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
CN103924602B (en) Deep Thick Soft Ground foundation ditch construction method
CN204356594U (en) Non-fragment orbit expensive soil cutting-bedding construction
CN103774674B (en) A kind of steel pipe underpinned pile and anchor pole deep foundation pit supporting structure and construction method thereof
CN111778793B (en) Cavity collapse prevention and control structure and construction method
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN203429660U (en) Stereo stiffened rigid-flexible combined ecological retaining wall
CN109750571A (en) A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method
CN104480956B (en) A kind of minor diameter mold-bagged concrete pile composite foundation
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN113818300B (en) Sponge city ecological roadbed structure based on original road and construction method thereof
CN102330436A (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN108487234B (en) Construction method of cast-in-situ pile plate type platform wall
CN111622234B (en) Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN207017097U (en) Deep super embankment on soft soil
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
CN209723024U (en) Composite foundation reinforcement counterfort wall structure
CN210439090U (en) Structure for building or widening high embankment
CN207672344U (en) Railway bed karez location pin-connected panel foundation stabilization construction
CN216040465U (en) Ecological roadbed structure in sponge city based on original road
CN102561368B (en) Flexible supporting construction of pre-compaction reinforced soil piece

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant