CN206986933U CN201720577708.2U CN201720577708U CN206986933U CN 206986933 U CN206986933 U CN 206986933U CN 201720577708 U CN201720577708 U CN 201720577708U CN 206986933 U CN206986933 U CN 206986933U
Authority
CN
China
Prior art keywords
installing hole
pipe installing
sealing collar
prefabricated
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720577708.2U
Other languages
Chinese (zh)
Inventor
王伊立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Vocational College of Science and Technology
Original Assignee
Guangzhou Vocational College of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Vocational College of Science and Technology filed Critical Guangzhou Vocational College of Science and Technology
Priority to CN201720577708.2U priority Critical patent/CN206986933U/en
Application granted granted Critical
Publication of CN206986933U publication Critical patent/CN206986933U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses a kind of precast inspection well, including prefabricated well framework, the Pipe installing hole being arranged on the prefabricated well framework, the Pipe installing hole are used to connect pipe laying, and the sealing collar matched with the Pipe installing hole is additionally provided with the Pipe installing hole.By prefabricated inspection shaft described herein, brickwork construction intensity deficiency caused by efficiently solving site operation, easily produce and collapse;And manual site piles up, the problems such as site operation is complicated and difficulty is big, and the engineering time is longer.Secondly, by being improved to existing prefabricated inspection shaft, hollow sealing collar with certain elasticity is set in the Pipe installing hole of precast inspection well, what is used during the sealing for avoiding pipeline periphery artificial fill out slurry and smears seam, engineering time is grown, and operating efficiency is low, and interface caused by the hot shrinkage of pipeline or differential settlement releases after putting into operation, cause inspection shaft permeable, serious even causes the harmful effects such as flowing water.

Description

A kind of precast inspection well
Technical field
A kind of inspection shaft is the utility model is related to, it is particularly a kind of prefabricated in advance and can realize the pre- of live rapid construction Inspection shaft processed, belong to municipal works subdrainage, blowdown inspection shaft technical field of structures.
Background technology
Inspection shaft be the power supply for Urban Underground infrastructure, feedwater, draining, blowdown, communication, cable television, gas pipe, Public lighting circuit etc. repairs, easy for installation and setting.Be generally located at pipeline intersection, turning, caliber or gradient change, with And locate at a certain distance on straight line pipeline section, it is easy for inspecting periodically auxiliary construction.
Webmaster inspection shaft is formed using brick and concrete masonry units mostly under existing municipal works land used, and it has following master Want defect:1st, brickwork construction intensity deficiency, easily produce and collapse;2nd, because construction is mainly piled up with manual site, scene is applied Work is complicated and difficulty is big, and the engineering time is longer, and labor intensity is big, operating efficiency is low and construction quality is bad.
With the appearance of some precast inspection wells, gradually solve and build some technical problems existing for inspection shaft by laying bricks or stones, but together When bring some new puzzlements again, due to various prefabricated components according to routine shape and structure it is prefabricated in advance, assembled at the scene There is the problem of assembling constructional difficulties during construction.For example the conduit through bore that the well bore of inspection shaft opens up in advance is conventional circle Hole, need manually to align pipeline and conduit through bore when assembling with pipeline at the scene, aligning installation process wastes time and energy, Er Qieguan The sealing of road periphery, which fills out slurry and smears to stitch, needs space manually limited in well to be operated, and this is added to the workmen at scene Many amounts of labour, engineering time length, operating efficiency are low;Secondly, pipeline hole is reserved reserving hole and pipeline during construction Between gap be present and be not easy to block, the hot shrinkage of pipeline or differential settlement easily cause interface and released after putting into operation, cause to examine Look into that well is permeable, serious even causes flowing water phenomenon, brings and has a strong impact on to road.
Utility model content
For overcome the deficiencies in the prior art, the purpose of this utility model is to provide a kind of precast inspection well, on the one hand Solve in work progress at the scene, construction speed caused by piling up on the spot is slow, pollutes the problems such as big;Meanwhile also solve The problem of gap being present between reserving hole and pipeline that conventional precast inspection well occurs and being not easy to block.
The purpose of this utility model adopts the following technical scheme that realization:
A kind of precast inspection well, including prefabricated well framework, the Pipe installing hole being arranged on the prefabricated well framework, institute State Pipe installing hole to be used to connect pipe laying, be additionally provided with the Pipe installing hole and the Pipe installing hole The sealing collar matched somebody with somebody.
Further, the sealing collar is hollow sealing collar.
Further, the sealing collar is the sealing collar of elastic rubber material.
Further, the sealing collar is fixedly connected on the Pipe installing hole by building adhesive.
Further, the sealing collar is bolted to connection on the Pipe installing hole.
Further, in addition to pipeline, the pipeline are connected by the Pipe installing hole with the prefabricated well framework.
Further, the sealing collar internal diameter is more than the outer diameter tube.
Further, the prefabricated well framework is in square build, the prefabricated well framework two adjacent surfaces and/or opposing sides It is provided with the Pipe installing hole.
Compared with prior art, the beneficial effects of the utility model are:
(1) by the way that common is piled up into inspection shaft at the construction field (site), prefabricated inspection shaft described herein is substituted for, is had Brickwork construction intensity deficiency caused by effect solves site operation, easily produce and collapse;And manual site piles up, site operation The problem of complicated and difficulty is big, and the engineering time is longer, and labor intensity is big, operating efficiency is low and construction quality is bad.
(2) secondly, by being improved to existing prefabricated inspection shaft, in the Pipe installing hole of precast inspection well Sealing collar with certain elasticity is set, the artificial slurry of filling out used during the sealing for avoiding pipeline periphery smears seam, and the engineering time is grown, Operating efficiency is low, and interface caused by the hot shrinkage of pipeline or differential settlement releases after putting into operation, causes inspection shaft permeable, Serious even causes the harmful effects such as flowing water.
Brief description of the drawings
Fig. 1 is a kind of schematic diagram of precast inspection well pipe laying state described in the utility model;
Fig. 2 is a kind of prefabricated well block schematic illustration of precast inspection well described in the utility model.
In figure:1st, prefabricated well framework;11st, Pipe installing hole;2nd, sealing collar;3rd, pipeline.
Embodiment
Below, with reference to accompanying drawing and embodiment, the utility model is described further, it is necessary to explanation is, On the premise of not colliding, it can be formed in any combination between various embodiments described below or between each technical characteristic new Embodiment.
As shown in Figure 1-2, a kind of precast inspection well, including prefabricated well framework 1, the pipeline being arranged on prefabricated well framework 1 Hole 11 is installed, the sealing collar 2 matched with Pipe installing hole 11 is additionally provided with Pipe installing hole 11, the sealing collar 2 By building adhesive or bolt, it is fixed on the Pipe installing hole 11 on prefabricated well framework 1, is avoided because of pipeline 3 in advance , there is sealing collar 2 and shifts, influence sealing effectiveness in insertion;Pipeline 3 passes through the sealing collar 2 and Pipe installing hole 11, and prefabricated Crib frame 1 connects, and the internal diameter of sealing collar 2 is slightly larger than the external diameter of pipeline 3, when pipeline 3 inserts pipeline mounting hole 11 inside of hole, only Hydrosphere 2 plays sealing effectiveness between pipeline 3 and Pipe installing hole 11.Further, sealing collar 2 uses elastomeric material It is made, there is certain elasticity, simultaneously as the internal diameter of sealing collar 2 is slightly larger than the external diameter of pipeline 3, when installed, can be achieved Sealing.Further, sealing collar 2 uses hollow structure, increases the sealing space between pipeline 3 and Pipe installing hole 11, i.e., Pipeline 3 is not aligned completely with Pipe installing hole 11, flexible hollow sealing collar 2, and pipeline 3 can also be utilized The squeezing action between Pipe installing hole 11 realizes preferable sealing effectiveness in itself.
As the preferred embodiment of the application, the prefabricated well framework 1 is designed as square build, in prefabricated well framework 1 Two adjacent surfaces, or opposing sides, and the four sides of square are provided with Pipe installing hole 11, can be according to used field The selected quantity that Pipe installing hole 11 is set and the trend for corresponding to pipeline 3.
Above-mentioned embodiment is only preferred embodiment of the present utility model, it is impossible to is protected with this to limit the utility model Scope, the change of any unsubstantiality that those skilled in the art is done on the basis of the utility model and replacing belongs to In the utility model scope claimed.

Claims (7)

1. a kind of precast inspection well, including prefabricated well framework, the Pipe installing hole being arranged on the prefabricated well framework is described Pipe installing hole is used to connect pipe laying, it is characterised in that:It is additionally provided with the Pipe installing hole and the pipeline The sealing collar of hole matching is installed.
A kind of 2. precast inspection well according to claim 1, it is characterised in that:The sealing collar is hollow sealing collar.
A kind of 3. precast inspection well according to claim 2, it is characterised in that:The sealing collar is elastic rubber material Sealing collar.
A kind of 4. precast inspection well according to claim 1, it is characterised in that:The sealing collar is fixed by building adhesive to be connected It is connected on the Pipe installing hole.
A kind of 5. precast inspection well according to claim 1, it is characterised in that:The sealing collar is bolted to connection In on the Pipe installing hole.
A kind of 6. precast inspection well according to claim 1, it is characterised in that:The sealing collar internal diameter is more than the installation Outer diameter tube.
A kind of 7. precast inspection well according to claim 1, it is characterised in that:The prefabricated well framework is in square build, The prefabricated well framework two adjacent surfaces and/or opposing sides are provided with the Pipe installing hole.
CN201720577708.2U 2017-05-23 2017-05-23 A kind of precast inspection well Expired - Fee Related CN206986933U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720577708.2U CN206986933U (en) 2017-05-23 2017-05-23 A kind of precast inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720577708.2U CN206986933U (en) 2017-05-23 2017-05-23 A kind of precast inspection well

Publications (1)

Publication Number Publication Date
CN206986933U true CN206986933U (en) 2018-02-09

Family

ID=61390021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720577708.2U Expired - Fee Related CN206986933U (en) 2017-05-23 2017-05-23 A kind of precast inspection well

Country Status (1)

Country Link
CN (1) CN206986933U (en)

Similar Documents

Publication Publication Date Title
CN108166486B (en) Deep buried pipe type prefabricated energy pipe pile and construction process thereof
CN202170515U (en) Prefabricated assembling composite pipe line with U-shaped section
CN206189455U (en) Piping lane
CN105780808A (en) Assembly type precast comprehensive pipe gallery
CN204040062U (en) Prefabricated wedge shape flexible interface assembling piping lane
CN113107018A (en) Method for treating leakage water of underground structure crack
CN103939669A (en) Anti-seepage underground pipeline structure in soft soil matrix and construction technology of anti-seepage underground pipeline structure
CN105604163B (en) Grouting construction method outside inside sewage pipeline leak stopping
CN102619521B (en) Construction method for vertical shaft bedrock section wall structure
CN207761667U (en) A kind of supporting construction for tunnel reconstruction and extension project
CN207878505U (en) A kind of prefabricated piping lane of assembly concrete
CN105735353A (en) Prefabricated comprehensive pipe gallery
CN204551532U (en) Assembling cable shaft
CN206986933U (en) A kind of precast inspection well
CN1546842A (en) Construction method of leakage waterstop for shield tunnel concrete structure segments
CN110117959B (en) Construction method for foundation pit support near river
CN206090623U (en) Prefabricated inspection shaft of construction efficient
CN207260191U (en) A kind of class rectangle pipe gallery section of jurisdiction connection structure
CN207525779U (en) A kind of assembly type pipe gallery pattern foundation pit supporting structure of recycling and structure external mold composite structure
CN206189456U (en) Three cabin piping lanes
CN205714225U (en) A kind of railway culvert, tunnel defect wavy metal culvert pipe liner bracing means
CN205205863U (en) Prefabricated inspection shaft
CN204098067U (en) Side's culvert formula underground pipe gallery
CN204691791U (en) The waterproof construction of rectangular top pipe
CN203145011U (en) Anchor rod structure with anti-floating capacity

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180209