CN206969989U - Pile foundation steel reinforcement cage lifting device - Google Patents

Pile foundation steel reinforcement cage lifting device Download PDF

Info

Publication number
CN206969989U
CN206969989U CN201720832852.6U CN201720832852U CN206969989U CN 206969989 U CN206969989 U CN 206969989U CN 201720832852 U CN201720832852 U CN 201720832852U CN 206969989 U CN206969989 U CN 206969989U
Authority
CN
China
Prior art keywords
pile foundation
reinforcement cage
hoisting equipment
vertical
foundation reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720832852.6U
Other languages
Chinese (zh)
Inventor
王利平
高登峰
杨玉吉
李金星
白铭宇
沈强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN201720832852.6U priority Critical patent/CN206969989U/en
Application granted granted Critical
Publication of CN206969989U publication Critical patent/CN206969989U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses the technique relates to building engineering technical field specifically is a pile foundation steel reinforcement cage lifting device. Pile foundation steel reinforcement cage lifting device includes: the transverse supporting ribs are arranged at intervals; the two vertical fixing plates are respectively positioned at two ends of the transverse supporting rib and are perpendicular to the transverse supporting rib, through holes are respectively formed in the two vertical fixing plates, and vertical reserved steel bars of the pile foundation steel bar cage penetrate through the through holes; the fastening device is used for fixing the vertical reserved steel bars penetrating through the through holes on the hoisting equipment; each vertical fixing plate is provided with a hanging ring, and the hanging rings are positioned on two sides of the through hole. The hoisting equipment can be used for hoisting the pile foundation reinforcement cage quickly and safely, the hoisting efficiency of the pile foundation reinforcement cage can be greatly improved, the position of the pile foundation reinforcement cage in the pile casing can be flexibly adjusted, and the pile position accuracy is improved.

Description

A kind of pile foundation reinforcement cage hoisting equipment
Technical field
The utility model technology is related to construction engineering technical field, specially a kind of pile foundation reinforcement cage hoisting equipment.
Background technology
In the prior art, it is general directly to sling pile foundation steel bar cage using crane.But directly slinging pile foundation using crane During steel reinforcement cage, perpendicularity, less stable when steel reinforcement cage is sling, easily to rock, security is poor, and nor Often inconvenient, the versatility of crane is poor, and the accuracy for putting steel reinforcement cage is poor.
Based on above description, a kind of pile foundation reinforcement cage hoisting equipment is needed badly, to solve steel reinforcement cage present in prior art Perpendicularity, less stable when slinging, are easily rocked, and security is poor, and also very inconvenient, the versatility of crane It is poor, put steel reinforcement cage accuracy it is poor the problem of.
Utility model content
To solve the problems, such as the above, the purpose of this utility model is to provide a kind of pile foundation reinforcement cage hoisting equipment, uses The hanging device can quickly, the lifting pile foundation steel bar cage of safety, can increase substantially pile foundation reinforcement cage hoisting efficiency, and can spirit Regulation pile foundation steel bar cage position in casing living, improves stake position precision.
To achieve the above object, the utility model adopts the following technical scheme that:
A kind of pile foundation reinforcement cage hoisting equipment, including:
Some transverse support ribs, transverse support ribs are arranged at intervals;
Two vertical fixed plates, two vertical fixed plates are located at the both ends of transverse support ribs, and and transverse support ribs respectively It is vertically arranged, through hole is respectively arranged with two vertical fixed plates, the vertical reserved steel bar of pile foundation steel bar cage passes through through hole;
Fastener, the vertical reserved steel bar through through hole is fixed on hanging device;
Suspension ring are provided with every vertical fixed plate, and suspension ring are located at the both sides of through hole.
As preferred, all transverse support ribs are evenly distributed.
As preferred, two through holes are respectively arranged with each vertical fixed plate.
Preferably, be provided with two pairs of suspension ring in every vertical fixed plate, two pairs of suspension ring are respectively positioned at two through holes Both sides.
Preferably, described be vertically provided with pad between fixed plate and fastener, the pad reserves steel from vertical The upper end of muscle passes through, and fastener is fixed on pad upper end.
As preferred, the pad is steel plate washer.
As preferred, the fastener is nut or sleeve.
As preferred, the transverse support ribs are made using 2-18a I-steel.
As preferred, the vertical fixed plate is made using 2cm steel plates.
As preferred, the transverse support ribs both ends pass through welding manner respectively and corresponding vertical fixed plate is fixed and connected Connect.
Compared with prior art, the pile foundation reinforcement cage hoisting equipment that the application provides has the characteristics that and beneficial effect:
The pile foundation reinforcement cage hoisting equipment that the application provides is suitably applied high-volume pile foundation steel bar cage fast hoisting, uses The method of welding produces pile foundation reinforcement cage hoisting equipment, the vertical reserved steel bar of pile foundation steel bar cage is connected with hanging device, so Suspender and steel reinforcement cage are sling and be accurately placed in casing by crane afterwards.The hanging device have safely, conveniently, versatility By force, the advantages that steel reinforcement cage is accurate is put.
Brief description of the drawings
Fig. 1 is the top view of hanging device provided by the utility model;
Fig. 2 is the vertical reserved steel bar and hanging device installation diagram of pile foundation steel bar cage provided by the utility model.
Reference,
1- transverse support ribs;The vertical fixed plates of 2-;21- through holes;3- fasteners;The vertical reserved steel bars of 4-;5- suspension ring;6- Pad.
Embodiment
The utility model is described in further detail below by specific examples of the implementation combination accompanying drawing.
As shown in Figure 1 to Figure 2, a kind of pile foundation reinforcement cage hoisting equipment provided by the utility model, including:
Some transverse support ribs 1, transverse support ribs 1 are arranged at intervals;
Two vertical fixed plates 2, two vertical fixed plates 2 are located at the both ends of transverse support ribs 1, and and cross-brace respectively Rib 1 is vertically arranged, and through hole is respectively arranged with two vertical fixed plates 2, and the vertical reserved steel bar 4 of pile foundation steel bar cage, which passes through, to be led to Hole;
Fastener 3, the vertical reserved steel bar 4 through through hole is fixed on hanging device;
Suspension ring 5 are provided with every vertical fixed plate 2, and suspension ring 5 are located at the both sides of through hole.
Using the hanging device can quickly, safety lifting pile foundation steel bar cage, pile foundation steel bar cage can be increased substantially and hung Efficiency, and energy flexible modulation pile foundation steel bar cage position in casing are filled, improves stake position precision.
In the present embodiment, preferably, all transverse support ribs 1 are evenly distributed.And the transverse support ribs 1 Number be preferably 4, but be not limited thereto.
In the present embodiment, preferably, two through holes are respectively arranged with each vertical fixed plate 2, but It is not limited thereto.
In the present embodiment, preferably, two pairs of suspension ring 5, two pairs of suspension ring are provided with every vertical fixed plate 2 5 respectively positioned at the both sides of two through holes.
It is preferably, described that pad 6 is vertically provided between fixed plate 2 and fastener 3 in the present embodiment, The pad 6 passes through from the upper end of vertical reserved steel bar 4, and fastener 3 is fixed on the upper end of pad 6.
In the present embodiment, preferably, the pad 6 is steel plate washer, but is not limited thereto.
In the present embodiment, preferably, the fastener 3 is nut or sleeve, but is not limited thereto.
In the present embodiment, preferably, the transverse support ribs 1 are made using 2-18a I-steel, but simultaneously It is not limited to this material.
In the present embodiment, preferably, the vertical fixed plate 2 is made using 2cm steel plates, but not It is confined to this material.
In the present embodiment, preferably, the both ends of transverse support ribs 1 respectively by welding manner with it is corresponding Vertical fixed plate 2 is fixedly connected.
The idiographic flow for making and using for pile foundation steel bar cage below:
(1)According to pile foundation steel bar cage size welding hanging device.
Pile foundation steel bar cage drawing is first looked at, determines the hanging device of suitable dimension.
(2)Connect hanging device, pile foundation steel bar cage
4 steel reinforcement cage vertical reinforcements are passed through into hanging device reserved through hole and pad, using nut or sleeve by reinforcing bar with Steel plate washer is fixed.
(3)Put pile foundation steel bar cage
Pile foundation steel bar cage is sling, the position of pile foundation steel bar cage is adjusted while pile foundation steel bar cage is placed, to ensure stake Level is true.
Another advantage of this programme is that pile foundation reinforcement cage hoisting is quick, safe, and certain modification can be applied to difference The steel reinforcement cage in stake footpath.
In the present embodiment, when selection is connected reinforcing bar with hanging device, to ensure that steel reinforcement cage can firmly, surely when slinging It is fixed, every two of 4 reinforcing bars must be selected mutually on steel reinforcement cage diameter symmetry, and be vertically optimal with normal between any two.
Preferred embodiment of the present utility model is the foregoing is only, is not limited to the utility model, for this For the technical staff in field, the utility model can have various modifications and variations.It is all in the spirit and principles of the utility model Within, any modification, equivalent substitution and improvements made etc., it should be included within the scope of protection of the utility model.

Claims (10)

  1. A kind of 1. pile foundation reinforcement cage hoisting equipment, it is characterised in that including:Some transverse support ribs, cross-brace rib space Set;Two vertical fixed plates, two vertical fixed plates are located at the both ends of transverse support ribs respectively, and are hung down with transverse support ribs It is straight to set, through hole is respectively arranged with two vertical fixed plates, the vertical reserved steel bar of pile foundation steel bar cage passes through through hole;Fastening dress Put, the vertical reserved steel bar through through hole is fixed on hanging device;Suspension ring are provided with every vertical fixed plate, and are hung Ring is located at the both sides of through hole.
  2. 2. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that all transverse support ribs are in uniform point Cloth.
  3. 3. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that divide in each vertical fixed plate Two through holes are not provided with.
  4. 4. pile foundation reinforcement cage hoisting equipment according to claim 3, it is characterised in that be respectively provided with every vertical fixed plate There are two pairs of suspension ring, two pairs of suspension ring are respectively positioned at the both sides of two through holes.
  5. 5. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the vertical fixed plate fills with fastening Pad is provided between putting, the pad passes through from the upper end of vertical reserved steel bar, and fastener is fixed on pad upper end.
  6. 6. pile foundation reinforcement cage hoisting equipment according to claim 5, it is characterised in that the pad is steel plate washer.
  7. 7. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the fastener is nut or set Cylinder.
  8. 8. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the transverse support ribs use 2- 18a I-steel is made.
  9. 9. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the vertical fixed plate uses 2cm Steel plate is made.
  10. 10. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the transverse support ribs both ends point It is not fixedly connected by welding manner with corresponding vertical fixed plate.
CN201720832852.6U 2017-07-11 2017-07-11 Pile foundation steel reinforcement cage lifting device Expired - Fee Related CN206969989U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720832852.6U CN206969989U (en) 2017-07-11 2017-07-11 Pile foundation steel reinforcement cage lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720832852.6U CN206969989U (en) 2017-07-11 2017-07-11 Pile foundation steel reinforcement cage lifting device

Publications (1)

Publication Number Publication Date
CN206969989U true CN206969989U (en) 2018-02-06

Family

ID=61402482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720832852.6U Expired - Fee Related CN206969989U (en) 2017-07-11 2017-07-11 Pile foundation steel reinforcement cage lifting device

Country Status (1)

Country Link
CN (1) CN206969989U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111705664A (en) * 2020-06-08 2020-09-25 中铁北京工程局集团第一工程有限公司 Hoisting process of prefabricated pier stud of assembled bridge
CN113734954A (en) * 2021-08-12 2021-12-03 广东地山基础工程有限公司 Bored concrete pile steel reinforcement cage hoist and mount auxiliary device of stress point can quick adjustment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111705664A (en) * 2020-06-08 2020-09-25 中铁北京工程局集团第一工程有限公司 Hoisting process of prefabricated pier stud of assembled bridge
CN113734954A (en) * 2021-08-12 2021-12-03 广东地山基础工程有限公司 Bored concrete pile steel reinforcement cage hoist and mount auxiliary device of stress point can quick adjustment
CN113734954B (en) * 2021-08-12 2023-05-16 广东地山基础工程有限公司 Cast-in-place pile reinforcement cage hoisting auxiliary device capable of quickly adjusting stress point

Similar Documents

Publication Publication Date Title
CN105129602B (en) Grow up vertical reinforcement monoblock type raising suspender
CN207294093U (en) A kind of large span steel truss integral lifting apparatus
CN206969989U (en) Pile foundation steel reinforcement cage lifting device
CN206267139U (en) A kind of pile foundation steel bar cage positioning and concrete pouring support
CN105464456B (en) Go straight up to method and suspender that unit founds UHV transmission steel tower
CN209455933U (en) A kind of superimposed sheet lifting appliance for hoisting
CN206665952U (en) A kind of novel hanging tool
CN204038849U (en) A kind of cable drum lifting device
CN212608990U (en) But reuse's steel reinforcement cage hanging device
CN206693061U (en) A kind of hoisting device for main cable saddle of suspension bridge lifting
CN206971084U (en) The supporting construction of bridge coping template
CN104499706A (en) Elevator well template platform and construction method thereof
CN202785257U (en) Control device used for hoisting and positioning steel reinforcement cage of manual hole digging piles
CN108516454A (en) A kind of hanging apparatus of prefabricated components
CN208265608U (en) Large-tonnage hoisting device for reinforcement cage
CN208814490U (en) A kind of novel drainage ditch cover plate hanging apparatus
CN109577323B (en) Tubular pile reinforcing method
CN110171766B (en) Steel bar transportation lifting appliance
CN203889880U (en) Lifting and clamping appliances for lowering large-diameter super-long pile reinforcement cage
CN208219546U (en) A kind of pile cover integral inverted hangs bottom system
CN207685827U (en) The punching piling machine for square hole pile foundation of constructing
CN205976550U (en) Cluster hangs instrument of girder steel
CN202830787U (en) Duplex beam for bridge construction
CN207176698U (en) A kind of concrete purlin and the general attachment structure gone along with sb. to guard him
CN206735623U (en) Framework of steel reinforcement hanging apparatus

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180206