CN206969985U - The lifting auxiliary balance instrument of multi-segmental precast beam - Google Patents

The lifting auxiliary balance instrument of multi-segmental precast beam Download PDF

Info

Publication number
CN206969985U
CN206969985U CN201720591812.7U CN201720591812U CN206969985U CN 206969985 U CN206969985 U CN 206969985U CN 201720591812 U CN201720591812 U CN 201720591812U CN 206969985 U CN206969985 U CN 206969985U
Authority
CN
China
Prior art keywords
precast beam
auxiliary balance
lifting auxiliary
support bar
prefabricated girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720591812.7U
Other languages
Chinese (zh)
Inventor
牛辉
孙长超
郭志鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201720591812.7U priority Critical patent/CN206969985U/en
Application granted granted Critical
Publication of CN206969985U publication Critical patent/CN206969985U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of lifting auxiliary balance instrument of multi-segmental precast beam is the utility model is related to, wherein being linked together between two adjacent prefabricated girder segments by bottom reinforcement bars, and is set between adjacent two prefabricated girder segments in certain intervals, the lifting auxiliary balance instrument includes:It is supported between the prefabricated girder segment of adjacent two and the support bar of adjustable in length, the support bar is by length adjustment to adapt to the intersegmental interval of two precast beams;And the fastener of the support boom end is fixedly arranged on, the fastener button is located at the top external corner of corresponding prefabricated girder segment.Pressure suffered by top at the space that interval is formed is born by the lifting auxiliary balance instrument, ensure that the precast beam of each section in hoisting process is in stability, ensure the structural stability of precast beam, solve the problems, such as that each prefabricated girder segment is in the easy unstability of non-equilibrium state during existing multi-segmental precast beam lifting.

Description

The lifting auxiliary balance instrument of multi-segmental precast beam
Technical field
The realm of building construction is the utility model is related to, refers in particular to a kind of lifting auxiliary balance instrument of multi-segmental precast beam.
Background technology
Concrete component precasting process is that the concrete section of making building or structures is pre-machined in factory or building site The technique of part.Prefabricated construction is carried out using precast concrete, is had and is saved labour, overcome seasonal effect, be easy to often The advantages that year construction.Precast concrete is promoted the use of, is to realize one of important channel of building industrialization.
The kind of precast concrete is various, there is the pillar for industrial building, foundation beam, crane girder, roofing Beam, truss, roof boarding, gutter, skylight frame, wallboard, the ledger beam of multi storied factory building and floor etc.;There is the base for civil buildings Stake, floor, lintel, balcony, stair, inside and outside wall board, frame beam column, roofing eave plate, finishing part etc..As shown in Figure 1, it is shown that A kind of multi-segmental precast beam of the prior art, the precast beam are used as girder, are connected with the secondary beam of other direction in the structure.For Primary-secondary beam is formed entirety, using primary and secondary beam nodes region as cast-in-place concrete section when girder is prefabricated so that girder into For multi-segmental beam, including at least two prefabricated girder segments for being arranged at intervals and linking into an integrated entity, Fig. 1 shown is to include three The precast beam structure of prefabricated girder segment, the precast beam 10 include the first prefabricated girder segment 101, the second prefabricated girder segment more than individual The 102 and n-th prefabricated girder segment 10n, certain interval is installed with as primary-secondary beam section between adjacent two prefabricated girder segments Point cast-in-place concrete section, the first prefabricated girder segment 101 therein, the second prefabricated 102 and n-th prefabricated girder segment of girder segment 10n can be linked together by bottom reinforcement bars 11, form an entirety.When being subsequently assembled to form structural beams, by the multi-segmental Precast beam 10 lift in place, then secondary beam is installed in the space between two adjacent prefabricated girder segments and pour node area Concrete and overlapping layer concrete.During precast beam 10 lifts, precast beam 10 produces moment of flexure at the space at interval, if Suspension centre is set in two sides of precast beam 10 in the way of common lifting components, moment of flexure will only between each section in hoisting process Undertaken by bottom reinforcement bars, bottom reinforcement bars flexural deformation will be caused, so as to influence the structural stability of precast beam 10.It is prefabricated to ensure Beam 10 hoisting process structural stability, it is necessary to be respectively provided with multiple suspension centres for each prefabricated girder segment, it is each prefabricated to cause Girder segment is at self-balancing state in lifting, but such lifting mode causes hanging device to set multiple hang again Rope so that hoisting process is cumbersome, it has not been convenient to.
Utility model content
A kind of the defects of the purpose of this utility model is to overcome prior art, there is provided the lifting auxiliary of multi-segmental precast beam Poising tool, solve in the prior art lift multi-segmental precast beam when each prefabricated girder segment be in the easy unstability of non-equilibrium state so that Influence the structural stability of precast beam and make it that hoisting process is cumbersome not using multiple suspension centres are respectively provided with every prefabricated girder segment The problem of facilitating.
Realizing the technical scheme of above-mentioned purpose is:
The utility model provides a kind of lifting auxiliary balance instrument of multi-segmental precast beam, wherein two adjacent precast beams Linked together by bottom reinforcement bars between section, and set between adjacent two prefabricated girder segments in certain intervals, the lifting is auxiliary Poising tool is helped to include:
It is supported between the prefabricated girder segment of adjacent two and the support bar of adjustable in length, the support bar passes through length Adjust to adapt to the intersegmental interval of two precast beams;And
The fastener of the support boom end is fixedly arranged on, the fastener button is located at the top external corner of corresponding prefabricated girder segment Place.
Lifting auxiliary balance instrument provided by the utility model is used for the interval formation for being supported on two stage precast beams Top at space, the pressure suffered by the top at the space that interval is formed is born by the lifting auxiliary balance instrument, should The pulling force that bottom is subject to is born by bottom reinforcement bars so that multi-segmental precast beam can be by the way of common lifting components in lifting Suspension centre is set in two sides of precast beam, it becomes possible to ensure that the precast beam of each section in hoisting process is in stable equilibrium State, it is ensured that the structural stability of precast beam, also simplify lifting construction so that lifting is convenient and easy.It is of the present utility model to hang It is volatile to be in non-equilibrium state for each prefabricated girder segment when dress auxiliary balance instrument solves existing multi-segmental precast beam lifting The problem of steady.
The utility model multi-segmental precast beam lifting auxiliary balance instrument further improvement is that, the fastener and institute State and be installed with elastomeric pad on the binding face that prefabricated girder segment is affixed.
The utility model multi-segmental precast beam lifting auxiliary balance instrument further improvement is that, the elastomeric pad For rubber sheet gasket.
The utility model multi-segmental precast beam lifting auxiliary balance instrument further improvement is that, the fastener is L Type part, including the transverse slat and riser being mutually connected vertically, the transverse slat is attached at the top surface of corresponding prefabricated girder segment, described perpendicular Plate is attached at the side of corresponding prefabricated girder segment, and the riser is fixedly connected with the support bar.
The utility model multi-segmental precast beam lifting auxiliary balance instrument further improvement is that, the support bar bag Left-handed screw, right handed screw and the two-way bolt being screwed together with the left-handed screw and the right handed screw are included, passes through rotation Turn the two-way bolt to adjust the length of the support bar.
The utility model multi-segmental precast beam lifting auxiliary balance instrument further improvement is that, the support bar bag Include the first pole, the second pole and shore the hydraulic system being connected between first pole and second pole, lead to Overregulate the flexible of the hydraulic system and adjust the length of the support bar.
The utility model multi-segmental precast beam lifting auxiliary balance instrument further improvement is that, the hydraulic system Both ends be fastenedly connected by lock nut with corresponding first pole and second pole.
The utility model multi-segmental precast beam lifting auxiliary balance instrument further improvement is that, the hydraulic system For hydraulic cylinder or hydraulic jack.
Brief description of the drawings
Fig. 1 is the structural representation of multi-segmental precast beam in the prior art.
Fig. 2 is that the lifting auxiliary balance instrument of the utility model multi-segmental precast beam is applied to the structure of multi-segmental precast beam Schematic diagram.
Fig. 3 is the structural representation of the first embodiment of the lifting auxiliary balance instrument of the utility model multi-segmental precast beam Figure.
Fig. 4 is the structural representation of the second embodiment of the lifting auxiliary balance instrument of the utility model multi-segmental precast beam Figure.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 2, the utility model provides a kind of lifting auxiliary balance instrument of multi-segmental precast beam, suitable for including The hoisting of the multi-segmental precast beam of at least two prefabricated girder segments, in hoisting process, by the lifting auxiliary balance instrument Interval between two adjacent stage concretes, the lifting auxiliary balance instrument are prefabricated in two by they sup-port Between girder segment, and the adjustable length of the support bar, the multi-segmental precast beam that can be adapted to different interval size is hung Dress, support bar is shored between two prefabricated girder segments, and has fastener in the end set of support bar, be located in pair by fastener At the top external corner for the stage concrete answered, so as to serve position-limiting action to lifting auxiliary balance instrument, and cause lifting auxiliary Poising tool can bear the pressure on the top in the interval space, ensure that structure of the multi-segmental precast beam in hoisting process Stability.The lifting auxiliary balance instrument to the utility model multistage precast beam illustrates below in conjunction with the accompanying drawings.
As shown in Fig. 2 the lifting auxiliary balance instrument 31 of multi-segmental precast beam provided by the utility model is used for multi-segmental On precast beam 21, the multi-segmental precast beam 21 includes at least two prefabricated girder segments, wherein leading between two adjacent prefabricated girder segments Cross bottom reinforcement bars 22 to link together, form an entirety, and set between adjacent two prefabricated girder segments in certain intervals.Fig. 2 The shown state being applied to for lifting auxiliary balance instrument 31 on the multi-segmental precast beam 21 with two prefabricated girder segments, this is more Precast segment beam 21 includes the first prefabricated girder segment 211 and second stage concrete 212 set in certain intervals, prefabricated first The interval of 211 and second prefabricated girder segment 212 of girder segment is flat formed with space 213, lifting auxiliary provided by the utility model Weighing apparatus instrument 31 includes being supported between the prefabricated girder segment of adjacent two and the support bar 311 of adjustable in length and is fixedly arranged on support bar The fastener 312 of 311 ends, the support bar 311 are supported between the first prefabricated 211 and second prefabricated girder segment 212 of girder segment, branch Strut 311, to adapt to the interval between the first prefabricated 211 and second prefabricated girder segment 212 of girder segment, is being pacified by length adjustment During dress, 311 intervals being located between the first prefabricated 211 and second prefabricated girder segment 212 of girder segment of support bar are formed In space 213, the support bar 311 is horizontal to be supported between the first prefabricated 211 and second prefabricated girder segment 212 of girder segment. The fastener 312 for being installed in the end of support bar 311 be located at the top external corner of corresponding prefabricated girder segment, positioned at the first precast beam Fastener 312 at section 211 be located in the first prefabricated girder segment 211 and be located at the top external corner of interval, pre- positioned at second Fastener 312 at girder segment 212 processed be located in the second prefabricated girder segment 212 and be located at the top external corner of interval, pass through two The fastener 312 of end be located on corresponding prefabricated girder segment so that what the lifting auxiliary balance instrument 31 can be stablized installs It is pre- lifting auxiliary balance instrument 31 is located at into first between the first prefabricated 211 and second prefabricated girder segment 212 of girder segment When between 211 and second prefabricated girder segment 212 of girder segment processed, by the length for adjusting support bar 311 so that the support bar 311 Stay between the first prefabricated 211 and second prefabricated girder segment 212 of girder segment, so as to be born by lifting auxiliary balance instrument 31 The pressure suffered by the top of space 213 that the interval is formed, and the pulling force that the bottom of space 213 is subject to by bottom reinforcement bars 22 come Bear, realize and set by lifting auxiliary balance instrument 31, ensure that the structural stability of multi-segmental precast beam 21, it is ensured that The adjacent intersegmental Stability Analysis of Structures of two precast beams so that, can be according to common prefabricated components when lifting multi-segmental precast beam 21 Mode suspension centre is set and uses common hanging device, without using balance hanging beam and being set on each prefabricated girder segment Multiple suspension centres are put to make each prefabricated girder segment be in self-balancing state in hoisting process so that lifting is convenient and easy.
As shown in Figure 3, it is shown that the structure of the first embodiment of the utility model lifting auxiliary balance instrument 31, first It is fixed flexible on the binding face that the fastener 312 of the lifting auxiliary balance instrument 31 fits with prefabricated girder segment in embodiment Pad 3121, elastomeric pad 3121 is set on the binding face of fastener 312, for preventing the damage to prefabricated girder segment, to pre- Girder segment processed serves protective effect.It is preferred that the elastomeric pad 3121 is rubber sheet gasket.In a better embodiment, card Part 312 is L-type part, including the transverse slat 3122 and riser 3123 being mutually connected vertically, transverse slat 3122 therein are sticked corresponding The top surface of prefabricated girder segment, riser 3123 is sticked to be fixed in the side of corresponding prefabricated girder segment, riser 3123 with support bar 311 Connection.With reference to shown in Fig. 2, the transverse slat 3122 of the fastener 312 at the first prefabricated girder segment 211 is attached at the first precast beam section On the top surface 2111 of section 211, the elastomeric pad that is provided with the transverse slat 3122 between transverse slat 3122 and top surface 2111 3121, riser 3123 is sticked on the side 2112 of the first prefabricated girder segment 211, is provided with the riser 3123 positioned at riser Elastomeric pad 3121 between 3123 and side 2112, the back side of riser 3123 are fixedly connected with the end of support bar 311.It is located at The transverse slat 3122 of fastener 312 at second prefabricated girder segment 212 is sticked on the top surface 2121 of the second prefabricated girder segment 212, The elastomeric pad 3121 being provided with the transverse slat 3122 between transverse slat 3122 and top surface 2121, riser 3123 is sticked second On the side 2122 of prefabricated girder segment 212, the elasticity that is provided with riser 3123 between riser 3123 and side 2122 Pad 3121, the back side of riser 3123 are fixedly connected with the end of support bar 311.
Further, in the first embodiment, support bar 311 include left-handed screw 3111, right handed screw 3112 and with The two-way bolt 3113 that left-handed screw 3111 and right handed screw 3112 connect, one end of the two-way bolt 3113 and left-handed screw 3111 are screwed, and the other end is screwed with right handed screw 3112, and the length of support bar 311 is adjusted by rotating two-way bolt 3113 Degree.When rotating forward two-way bolt 3113, left-handed screw 3111 and right handed screw 3112 to the two-way inside precession of bolt 3113, So that the length of support bar 311 diminishes;When reversely rotating two-way bolt 3113, left-handed screw 3111 and right handed screw 3112 from The inside of two-way bolt 3113 outwards screws out so that the length of support bar 311 becomes big.Lifting auxiliary of the present utility model is being installed During poising tool, between the lifting auxiliary balance instrument branch is located at into two prefabricated girder segments, then rotates two-way bolt and cause The length of support bar 311, the fastener button until both ends set and pressed closer untill the side of corresponding prefabricated girder segment.
As shown in Figure 4, it is shown that the structure of the second embodiment of the utility model lifting auxiliary balance instrument 31, second In embodiment, it is that the structure of support bar 311 is different from the difference of first embodiment, support bar in a second embodiment 311 include the first pole 3114, the second pole 3115 and shore to be connected between the first pole 3114 and the second pole 3115 Hydraulic system 3116, adjust the length of support bar 311 by adjusting the flexible of hydraulic system 3116.Hydraulic system 3116 is Micro hydraulic system, it is telescopically adjustable structure.The both ends of hydraulic system 3116 by lock nut 3117 with it is corresponding First pole 3114 and the second pole 3115 are fastenedly connected.It is preferred that the hydraulic system 3116 is hydraulic cylinder or hydraulic jack. When installing lifting auxiliary balance instrument of the present utility model, the lifting auxiliary balance instrument branch is located at two prefabricated girder segments Between, then stretching for regulation hydraulic system 3116 causes the length of support bar 311, until the fastener button at both ends is set simultaneously tightly Untill the side of prefabricated girder segment corresponding to withstanding on.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to described above.Thus, some details in embodiment should not be formed to this practicality New restriction, the utility model will be used as the scope of protection of the utility model using the scope that appended claims define.

Claims (8)

  1. A kind of 1. lifting auxiliary balance instrument of multi-segmental precast beam, wherein passing through bottom reinforcement bars between two adjacent prefabricated girder segments Link together, and set between adjacent two prefabricated girder segments in certain intervals, it is characterised in that the lifting auxiliary balance work Tool includes:
    It is supported between the prefabricated girder segment of adjacent two and the support bar of adjustable in length, the support bar passes through length adjustment To adapt to the intersegmental interval of two precast beams;And
    The fastener of the support boom end is fixedly arranged on, the fastener button is located at the top external corner of corresponding prefabricated girder segment.
  2. 2. the lifting auxiliary balance instrument of multi-segmental precast beam as claimed in claim 1, it is characterised in that the fastener and institute State and be installed with elastomeric pad on the binding face that prefabricated girder segment is affixed.
  3. 3. the lifting auxiliary balance instrument of multi-segmental precast beam as claimed in claim 2, it is characterised in that the elastomeric pad For rubber sheet gasket.
  4. 4. the lifting auxiliary balance instrument of multi-segmental precast beam as claimed in claim 1, it is characterised in that the fastener is L Type part, including the transverse slat and riser being mutually connected vertically, the transverse slat is attached at the top surface of corresponding prefabricated girder segment, described perpendicular Plate is attached at the side of corresponding prefabricated girder segment, and the riser is fixedly connected with the support bar.
  5. 5. the lifting auxiliary balance instrument of multi-segmental precast beam as claimed in claim 1, it is characterised in that the support bar bag Left-handed screw, right handed screw and the two-way bolt being screwed together with the left-handed screw and the right handed screw are included, passes through rotation Turn the two-way bolt to adjust the length of the support bar.
  6. 6. the lifting auxiliary balance instrument of multi-segmental precast beam as claimed in claim 1, it is characterised in that the support bar bag Include the first pole, the second pole and shore the hydraulic system being connected between first pole and second pole, lead to Overregulate the flexible of the hydraulic system and adjust the length of the support bar.
  7. 7. the lifting auxiliary balance instrument of multi-segmental precast beam as claimed in claim 6, it is characterised in that the hydraulic system Both ends be fastenedly connected by lock nut with corresponding first pole and second pole.
  8. 8. the lifting auxiliary balance instrument of multi-segmental precast beam as claimed in claim 6, it is characterised in that the hydraulic system For hydraulic cylinder or hydraulic jack.
CN201720591812.7U 2017-05-25 2017-05-25 The lifting auxiliary balance instrument of multi-segmental precast beam Expired - Fee Related CN206969985U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720591812.7U CN206969985U (en) 2017-05-25 2017-05-25 The lifting auxiliary balance instrument of multi-segmental precast beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720591812.7U CN206969985U (en) 2017-05-25 2017-05-25 The lifting auxiliary balance instrument of multi-segmental precast beam

Publications (1)

Publication Number Publication Date
CN206969985U true CN206969985U (en) 2018-02-06

Family

ID=61410702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720591812.7U Expired - Fee Related CN206969985U (en) 2017-05-25 2017-05-25 The lifting auxiliary balance instrument of multi-segmental precast beam

Country Status (1)

Country Link
CN (1) CN206969985U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258629A (en) * 2019-06-12 2019-09-20 中国建筑第八工程局有限公司 The assembled equipment and its assembling method of prefabricated components
CN110626933A (en) * 2019-08-01 2019-12-31 中铁十六局集团第四工程有限公司 Segmental beam hanger

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258629A (en) * 2019-06-12 2019-09-20 中国建筑第八工程局有限公司 The assembled equipment and its assembling method of prefabricated components
CN110626933A (en) * 2019-08-01 2019-12-31 中铁十六局集团第四工程有限公司 Segmental beam hanger

Similar Documents

Publication Publication Date Title
CN105604334B (en) A kind of rapid constructing method for large span steel truss integral installation
CN107663951A (en) The support system and construction technology of superimposed sheet and wallboard formed by integrally casting
CN103276893A (en) Novel composite structure for supporting rigid building template and construction method
CN104712141A (en) Construction method of cast-in-place reinforced concrete dense ribbed beam floor
CN206969985U (en) The lifting auxiliary balance instrument of multi-segmental precast beam
US5012627A (en) Construction process for multiple-story concrete building
CN104775606A (en) Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof
CN202882446U (en) Horse stool suspended by steel bars
US3292313A (en) Tensile system of building construction
JP7041463B2 (en) How to build a building
CN105370027A (en) Construction method for integrally lifted and supported steel platform structure in high-rise suspended structure
JPH0571225A (en) Temporarily set roof of complete weather type
CN104878942B (en) A kind of high accuracy lifted for prefabricated structural element is with regard to positioning auxiliary device and method
CN206530037U (en) A kind of elevating platform assembly for Construction of Silo
CN211143319U (en) Building structure composed of beam column framework for multi-layer steel structure building
CN112443052A (en) Indoor wall frame connection structure of assembly type building
US3435583A (en) Method of forming buildings
JPH0833032B2 (en) Construction method of building frame
CN220789460U (en) Small box girder adjusting jacking frame
CN214220081U (en) Indoor wall frame connection structure of assembly type building
CN109723237A (en) Portable support system and construction method based on assembled floor
JP2004052455A (en) External scaffolding device and construction method therefor
CN215714679U (en) Steel purlin arched bridge side span unstressed construction equipment
CN217326382U (en) Lifting elevator derrick suitable for elevator shaft with side wall
CN219586575U (en) Construction structure of segment prefabricated single-box single-chamber variable-height prestressed concrete box girder

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180206