CN206959224U - A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM - Google Patents
A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM Download PDFInfo
- Publication number
- CN206959224U CN206959224U CN201720780811.7U CN201720780811U CN206959224U CN 206959224 U CN206959224 U CN 206959224U CN 201720780811 U CN201720780811 U CN 201720780811U CN 206959224 U CN206959224 U CN 206959224U
- Authority
- CN
- China
- Prior art keywords
- air
- water
- race
- integrated
- conditioning facilities
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004378 air conditioning Methods 0.000 title claims abstract description 42
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 63
- JEGUKCSWCFPDGT-UHFFFAOYSA-N h2o hydrate Chemical compound O.O JEGUKCSWCFPDGT-UHFFFAOYSA-N 0.000 claims description 59
- 238000004891 communication Methods 0.000 claims description 6
- 238000011084 recovery Methods 0.000 claims description 5
- 238000009434 installation Methods 0.000 claims 1
- 238000013461 design Methods 0.000 abstract description 4
- 238000000034 method Methods 0.000 abstract description 4
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000001514 detection method Methods 0.000 abstract description 2
- 238000005516 engineering process Methods 0.000 abstract description 2
- 238000012545 processing Methods 0.000 abstract description 2
- 230000003247 decreasing effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 5
- 238000007664 blowing Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 230000003068 static effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 238000013508 migration Methods 0.000 description 1
- 230000005012 migration Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
- 239000003643 water by type Substances 0.000 description 1
Landscapes
- Central Air Conditioning (AREA)
Abstract
The utility model provides a kind of Air Conditioning Facilities based on the integrated race's blocks of BIM, belongs to Air Conditioning Facilities manufacture processing technique field, by with BIM technology, carrying out integral modularized design.Air Conditioning Facilities include multiple integrated air-conditioner set races, multiple integrated Fresh air handling units races and the pipeline without conduit fittings, equipment supporter or equipment hanger, support of pipelines or pipeline elevator and pipe insulating layer thereon;Integrated air-conditioner set race, integrated Fresh air handling units race include equipment body, airduct and water pipe, can be required according to the structure of equipment, air-supply and pipe-line layout realize collision detection and prefabricated customized and guide site operation.This Air Conditioning Facilities is completed using method for integrated designing, and workload can be greatly decreased in its utilization, is improved and is drawn efficiency, and increases the flexibility of arrangement, versatility.
Description
Technical field
The utility model belongs to Air Conditioning Facilities manufacture processing technique field, and the integrated races of BIM are based on more particularly to one kind
The Air Conditioning Facilities of block.
Background technology
BIM BIMs (Building Information Modeling) or architecture information management
(Building Information Management) be based on every relevant information data of construction-engineering project,
The BUILDINGS MODELS of three-dimensional is set up, by real information possessed by digital information analogue simulation building, has information complete
Property, information relevance, consistency on messaging, visualization, harmony, simulation, optimization property and the features such as figure can be gone out, given birth to improving
Production efficiency, played a significant role in terms of the cost-effective and shortening duration.
Utility model content
The purpose of this utility model is to provide a kind of Air Conditioning Facilities based on the integrated race's blocks of BIM, by using BIM skills
Art, carries out integral modularized design, establishment becomes more meticulous, by parameter regulation, realize Fast Drawing, realize collision detection, refer to
Cannula member is prefabricated, instructs the refrigerating plant room BIM models of site operation.
The technical solution of the utility model:
A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM, including multiple integrated air-conditioner set races 1 and multiple integrated
Fresh air handling units race 2, the two includes equipment body 11, airduct and water pipe;
It is close that described airduct includes ajutage 3, backwind tube 4, exhaust duct 5, split multi-clack control valve 7, fire resisting damper 8, fresh air
Valve closing 9, canvas are soft to connect 10, fresh air air grille 11, air supply plenum chamber 13, return air plenum chamber 14;
Described water pipe include rubber soft joint 15, transverse tube 16, chilled water water inlet adapter 17, chilled water water outlet pipe 18,
Hot water water inlet adapter 19 and hot water effluent's adapter 20, condensate pipe 21, gate valve 22, y-type filter 23, magnetic valve 24, thermometer
25 and pressure gauge 26;
The upper surface of the equipment body 12 of described integrated air-conditioner set race 1 connects air supply plenum chamber 13 and return air side by side
Plenum chamber 14, ajutage 3 is connected on air supply plenum chamber 13, be sequentially connected that canvas is soft to connect 10, split multi-clack control valve on ajutage 3
7 and fire resisting damper 8, and then computer room wall is passed through, connect the ajutage in air-conditioned room;Backwind tube 4 is connected on return air plenum chamber 14
With exhaust duct 5, backwind tube 4 divides for two-way, and fire resisting damper 8 is respectively connected with two-way return air branch pipe, and then passes through computer room wall, connects
Backwind tube in air-conditioned room;Be connected with turn on exhaust duct 5 split multi-clack control valve 7, canvas it is soft connect 10, exhaust fan 27,
Air grille 11, through Air Conditioning Facilities wall, outside communication chamber;Connect in the side wall of the equipment body 12 of integrated air-conditioner set race 1
Fresh wind tube 6, split multi-clack control valve 7, fresh air airtight valve 9 and air grille 11 are passed sequentially through on fresh wind tube 6 and passes through Air Conditioning Facilities
Wall, outside communication chamber;
One side wall of the equipment body 12 of described integrated air-conditioner set race 1 passes sequentially through rubber soft joint 15, horizontal stroke
Pipe 16 and bend pipe are separately installed with chilled water water inlet adapter 17, chilled water water outlet pipe 18, hot water water inlet adapter 19 and hot water and gone out
Water adapter 20;One side wall of the equipment body 12 of described integrated air-conditioner set race 1 is provided with condensate pipe 21;Chilled water
The intake upper end of adapter 19 and hot water effluent's adapter 20 of water inlet adapter 17, chilled water water outlet pipe 18, hot water is mounted on gate valve
22nd, thermometer 25 and pressure gauge 26;Close bend pipe position in chilled water water inlet adapter 17 and hot water water inlet adapter 19, from bottom to up
It is further fitted with magnetic valve 24 and y-type filter 23;Chilled water water inlet adapter 17 and chilled water water outlet pipe 18 connect respectively
Chilled water in Air Conditioning Facilities supplies, return riser, and hot water water inlet adapter 19 and hot water effluent's adapter 20 connect Air Conditioning Facilities respectively
Interior hot water supplies, return riser, and condensate pipe 21 connects the condensed water centralized recovery standpipe in Air Conditioning Facilities;
The upper surface connection air supply plenum chamber 13 of the equipment body 12 of described integrated Fresh air handling units race 2, static pressure of blowing
The layout connected mode of case 13 and the layout connected mode phase on the air supply plenum chamber 13 of described integrated air-conditioner set race 1
Together;Connect fresh wind tube 6 in the side wall of the equipment body 12 of integrated air-conditioner set race 1, the layout connected mode of fresh wind tube 6 with it is described
Integrated air-conditioner set race 1 fresh wind tube 6 layout connected mode it is identical;
One side wall of the equipment body 12 of described integrated Fresh air handling units race 2 passes sequentially through rubber soft joint 15, horizontal stroke
Pipe 16 and bend pipe are separately installed with chilled water water inlet adapter 17, chilled water water outlet pipe 18, hot water water inlet adapter 19 and hot water and gone out
Water adapter 20;One side wall of the equipment body 12 of described integrated air-conditioner set race 1 is provided with condensate pipe 21;Chilled water
The intake upper end of adapter 19 and hot water effluent's adapter 20 of water inlet adapter 17, chilled water water outlet pipe 18, hot water is mounted on gate valve
22nd, thermometer 25 and pressure gauge 26;Close bend pipe position in chilled water water inlet adapter 17 and hot water water inlet adapter 19, from bottom to up
It is further fitted with magnetic valve 24 and y-type filter 23;Chilled water water inlet adapter 17 and chilled water water outlet pipe 18 connect respectively
Chilled water in Air Conditioning Facilities supplies, return riser, and hot water water inlet adapter 19 and hot water effluent's adapter 20 connect Air Conditioning Facilities respectively
Interior hot water supplies, return riser, and condensate pipe 21 connects the condensed water centralized recovery standpipe in Air Conditioning Facilities.
The beneficial effects of the utility model:
1. the utility model is by integrated thought, by equipment, pipe fitting, conduit fittings in Air Conditioning Facilities according to design need
Will, Revit races block is integrated into, as an overall race.Remaining pipeline and a small amount of pipe fitting need to only be matched i.e. in application
System entirety can be completed, so as to which workload be greatly reduced, improves efficiency.
2. by the parametrization to integrated Air Conditioning Facilities race block, its all elements dimension adjustable, and energy are realized
Enough realize pipe fitting with caliber change automatically adjust, Auto-matching, so as to improve its application flexibility.In system creation process
In, it modify, need to be only changed in family parameter to adapter caliber if need to be taken over to equipment, without changing pipeline fittings,
So as to which modification time also be greatly reduced.
3. race's root tuber is drawn according to full size, the race's block characteristic of itself makes it easy to import and used, and has versatility
With flexible modulability, different design requirements can be tackled, at the same be easy to direct use of race's block between different engineering projects,
Migration and modification.
Brief description of the drawings
Fig. 1 is a kind of schematic diagram of the Air Conditioning Facilities based on the integrated race's blocks of BIM.
Fig. 2 is the airduct connection diagram of integrated air-conditioner set group race.
Fig. 3 is the water pipe connection diagram of integrated air-conditioner set group race.
Fig. 4 is the airduct connection diagram of the integrated Fresh air handling units race in position.
Fig. 5 is the water pipe connection diagram of the integrated Fresh air handling units race in position.
In figure:1 integrated air-conditioner set race;2 integrated Fresh air handling units races;3 ajutages;4 backwind tubes;5 exhaust ducts;6 is new
Airduct;7 split multi-clack control valves;8 fire resisting dampers;9 fresh air airtight valves;10 canvas are soft to be connect;11 air grilles;12 equipment bodies;13
Air supply plenum chamber;14 return air plenum chambers;15 rubber soft joints;16 transverse tubes;The water inlet adapter of 17 chilled waters;18 chilled water water outlets connect
Pipe;The water inlet adapter of 19 hot water;20 hot water effluents take over;21 condensate pipes;22 gate valves;23Y type filters;24 magnetic valves;25 temperature
Degree meter;26 pressure gauges;27 exhaust fans.
Embodiment
Below in conjunction with accompanying drawing and technical scheme, specific embodiment of the present utility model is further illustrated.
A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM, including multiple integrated air-conditioner set races 1 and multiple integrated
Fresh air handling units race 2, the two includes equipment body 11, airduct and water pipe;
It is close that described airduct includes ajutage 3, backwind tube 4, exhaust duct 5, split multi-clack control valve 7, fire resisting damper 8, fresh air
Valve closing 9, canvas are soft to connect 10, fresh air air grille 11, air supply plenum chamber 13, return air plenum chamber 14;
Described water pipe include rubber soft joint 15, transverse tube 16, chilled water water inlet adapter 17, chilled water water outlet pipe 18,
Hot water water inlet adapter 19 and hot water effluent's adapter 20, condensate pipe 21, gate valve 22, y-type filter 23, magnetic valve 24, thermometer
25 and pressure gauge 26;
The upper surface of the equipment body 12 of described integrated air-conditioner set race 1 connects air supply plenum chamber 13 and return air side by side
Plenum chamber 14, ajutage 3 is connected on air supply plenum chamber 13, be sequentially connected that canvas is soft to connect 10, split multi-clack control valve on ajutage 3
7 and fire resisting damper 8, and then computer room wall is passed through, connect the ajutage in air-conditioned room;Backwind tube 4 is connected on return air plenum chamber 14
With exhaust duct 5, backwind tube 4 divides for two-way, and fire resisting damper 8 is respectively connected with two-way return air branch pipe, and then passes through computer room wall, connects
Backwind tube in air-conditioned room;Be connected with turn on exhaust duct 5 split multi-clack control valve 7, canvas it is soft connect 10, exhaust fan 27,
Air grille 11, through Air Conditioning Facilities wall, outside communication chamber;Connect in the side wall of the equipment body 12 of integrated air-conditioner set race 1
Fresh wind tube 6, split multi-clack control valve 7, fresh air airtight valve 9 and air grille 11 are passed sequentially through on fresh wind tube 6 and passes through Air Conditioning Facilities
Wall, outside communication chamber;
One side wall of the equipment body 12 of described integrated air-conditioner set race 1 passes sequentially through rubber soft joint 15, horizontal stroke
Pipe 16 and bend pipe are separately installed with chilled water water inlet adapter 17, chilled water water outlet pipe 18, hot water water inlet adapter 19 and hot water and gone out
Water adapter 20;One side wall of the equipment body 12 of described integrated air-conditioner set race 1 is provided with condensate pipe 21;Chilled water
The intake upper end of adapter 19 and hot water effluent's adapter 20 of water inlet adapter 17, chilled water water outlet pipe 18, hot water is mounted on gate valve
22nd, thermometer 25 and pressure gauge 26;Close bend pipe position in chilled water water inlet adapter 17 and hot water water inlet adapter 19, from bottom to up
It is further fitted with magnetic valve 24 and y-type filter 23;Chilled water water inlet adapter 17 and chilled water water outlet pipe 18 connect respectively
Chilled water in Air Conditioning Facilities supplies, return riser, and hot water water inlet adapter 19 and hot water effluent's adapter 20 connect Air Conditioning Facilities respectively
Interior hot water supplies, return riser, and condensate pipe 21 connects the condensed water centralized recovery standpipe in Air Conditioning Facilities;
The upper surface connection air supply plenum chamber 13 of the equipment body 12 of described integrated Fresh air handling units race 2, static pressure of blowing
The layout connected mode of case 13 and the layout connected mode phase on the air supply plenum chamber 13 of described integrated air-conditioner set race 1
Together;Connect fresh wind tube 6 in the side wall of the equipment body 12 of integrated air-conditioner set race 1, the layout connected mode of fresh wind tube 6 with it is described
Integrated air-conditioner set race 1 fresh wind tube 6 layout connected mode it is identical;
One side wall of the equipment body 12 of described integrated Fresh air handling units race 2 passes sequentially through rubber soft joint 15, horizontal stroke
Pipe 16 and bend pipe are separately installed with chilled water water inlet adapter 17, chilled water water outlet pipe 18, hot water water inlet adapter 19 and hot water and gone out
Water adapter 20;One side wall of the equipment body 12 of described integrated air-conditioner set race 1 is provided with condensate pipe 21;Chilled water
The intake upper end of adapter 19 and hot water effluent's adapter 20 of water inlet adapter 17, chilled water water outlet pipe 18, hot water is mounted on gate valve
22nd, thermometer 25 and pressure gauge 26;Close bend pipe position in chilled water water inlet adapter 17 and hot water water inlet adapter 19, from bottom to up
It is further fitted with magnetic valve 24 and y-type filter 23;Chilled water water inlet adapter 17 and chilled water water outlet pipe 18 connect respectively
Chilled water in Air Conditioning Facilities supplies, return riser, and hot water water inlet adapter 19 and hot water effluent's adapter 20 connect Air Conditioning Facilities respectively
Interior hot water supplies, return riser, and condensate pipe 21 connects the condensed water centralized recovery standpipe in Air Conditioning Facilities;
A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM also include appendage, are equipment supporter or equipment hanger, pipe
Road support or pipeline elevator, described appendage are used for arrying main body structure;
A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM, according to demand, set up measuring instrumentss, sensor, valve, soft
Connect, filter etc..
Claims (3)
1. a kind of Air Conditioning Facilities based on the integrated race's blocks of BIM, it is characterised in that described Air Conditioning Facilities include multiple integrated
Air-conditioner set race (1) and multiple integrated Fresh air handling units races (2), the two includes equipment body (12), airduct and water pipe;
Described airduct include ajutage (3), backwind tube (4), exhaust duct (5), split multi-clack control valve (7), fire resisting damper (8),
Fresh air airtight valve (9), canvas are soft to connect (10), fresh air air grille (11), air supply plenum chamber (13) and return air plenum chamber (14);
Described water pipe includes rubber soft joint (15), transverse tube (16), chilled water water inlet adapter (17), chilled water water outlet pipe
(18), hot water water inlet adapter (19) and hot water effluent adapter (20), condensate pipe (21), gate valve (22), y-type filter (23),
Magnetic valve (24), thermometer (25) and pressure gauge (26);
The upper surface of the equipment body (12) of described integrated air-conditioner set race (1) connects air supply plenum chamber (13) and returned side by side
Wind plenum chamber (14), ajutage (3) is connected on air supply plenum chamber (13), soft connect (10), right of canvas are sequentially connected on ajutage (3)
Multi-clack control valve (7) and fire resisting damper (8) are opened, and then passes through computer room wall, connects the ajutage in air-conditioned room;Return air plenum chamber
(14) connect backwind tube (4) on and exhaust duct (5), backwind tube (4) are divided into two-way, fire resisting damper are respectively connected with two-way return air branch pipe
(8), and then computer room wall is passed through, connects the backwind tube in air-conditioned room;It is connected with split leafy regulation on exhaust duct (5) in turn
Valve (7), canvas are soft to connect (10), exhaust fan (27), air grille (11), through Air Conditioning Facilities wall, outside communication chamber;It is integrated
Fresh wind tube (6) is connect in the side wall of the equipment body (12) of air-conditioner set race (1), split leafy tune is passed sequentially through on fresh wind tube (6)
Section valve (7), fresh air airtight valve (9) and air grille (11) pass through Air Conditioning Facilities wall, outside communication chamber;
One side wall of the equipment body (12) of described integrated air-conditioner set race (1) pass sequentially through rubber soft joint (15),
Transverse tube (16) and bend pipe are separately installed with chilled water water inlet adapter (17), chilled water water outlet pipe (18), hot water water inlet adapter
(19) and hot water effluent takes over (20);The side wall installation of the equipment body (12) of described integrated air-conditioner set race (1)
There is condensate pipe (21);Chilled water water inlet adapter (17), chilled water water outlet pipe (18), hot water water inlet adapter (19) and hot water go out
The upper end of water adapter (20) is mounted on gate valve (22), thermometer (25) and pressure gauge (26);Chilled water water inlet adapter (17) and
Close to bend pipe position in hot water water inlet adapter (19), magnetic valve (24) and y-type filter (23) are further fitted with from bottom to up;
Chilled water water inlet adapter (17) and chilled water water outlet pipe (18) connect the chilled water water supply standpipe in Air Conditioning Facilities and returned respectively
Water standpipe, hot water water inlet adapter (19) and hot water effluent take over (20) and connect the hot water water supply standpipe in Air Conditioning Facilities respectively and return
Water standpipe, condensate pipe (21) connect the condensed water centralized recovery standpipe in Air Conditioning Facilities;
The upper surface connection air supply plenum chamber (13) of the equipment body (12) of described integrated Fresh air handling units race (2), air-supply are quiet
The layout connected mode of pressure case (13) is connected with the layout on the air supply plenum chamber (13) of described integrated air-conditioner set race (1)
Mode is identical;Fresh wind tube (6), the layout of fresh wind tube (6) are connect in the side wall of the equipment body (12) of integrated air-conditioner set race (1)
Connected mode is identical with the layout connected mode of the fresh wind tube (6) of described integrated air-conditioner set race (1).
A kind of 2. Air Conditioning Facilities based on the integrated race's blocks of BIM according to claim 1, it is characterised in that described collection
Also include appendage into the Air Conditioning Facilities for changing race's block, it is described for equipment supporter or equipment hanger, support of pipelines or pipeline elevator
Appendage be used for arrying main body structure.
3. a kind of Air Conditioning Facilities based on the integrated race's blocks of BIM according to claim 1 or 2, it is characterised in that according to need
Ask, set up measuring instrumentss, sensor, valve, soft connect and/or filter.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720780811.7U CN206959224U (en) | 2017-06-30 | 2017-06-30 | A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720780811.7U CN206959224U (en) | 2017-06-30 | 2017-06-30 | A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206959224U true CN206959224U (en) | 2018-02-02 |
Family
ID=61386586
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720780811.7U Active CN206959224U (en) | 2017-06-30 | 2017-06-30 | A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206959224U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109408850A (en) * | 2018-08-28 | 2019-03-01 | 中建八局第建设有限公司 | A kind of equipment machine room forward design method based on BIM |
-
2017
- 2017-06-30 CN CN201720780811.7U patent/CN206959224U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109408850A (en) * | 2018-08-28 | 2019-03-01 | 中建八局第建设有限公司 | A kind of equipment machine room forward design method based on BIM |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105593648B (en) | Fluid control and measure device | |
CN107895091B (en) | Module intelligent cold and hot station installation system and BIM model prefabrication construction method thereof | |
CN107218739B (en) | A kind of refrigerating plant room based on the integrated race of BIM | |
CN102519703B (en) | Air terminal air volume balance detection analog device and analog detecting method thereof | |
CN105047058A (en) | Full-scale central air-conditioning and centralized heating integration experiment platform and control method therefor | |
CN110765522A (en) | BIM forward design method of heating ventilation air conditioner | |
CN204946458U (en) | A kind of full size central air-conditioning and central heating synthesis experiment platform | |
CN116108605B (en) | Optimization design method of limited space air duct system considering total life cycle cost | |
CN206959224U (en) | A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM | |
Shopayeva et al. | CFD-modeling of flow in confluence nodes of ventilation units of multi-storey buildings | |
CN107270449A (en) | A kind of Air Conditioning Facilities based on the integrated race's blocks of BIM | |
CN207335216U (en) | A kind of refrigerating plant room based on the integrated races of BIM | |
CN107401784A (en) | Air conditioning system with variable and design method based on genetic algorithm | |
CN108386983B (en) | Low-resistance shunt three-way component for ventilation air conditioner air pipe | |
CN206234546U (en) | A kind of exhaust structure in the air-conditioning waterpipe installed in low pressure | |
CN211060293U (en) | Novel vertical same-stroke water system | |
CN115164352B (en) | Whole-process debugging method for large-space air conditioner | |
CN113175718A (en) | Multi-branch air quantity distribution method of environment control system and environment control system | |
CN105718631A (en) | Numerical value simulation-based ventilation duct smoke purification system | |
CN102374622A (en) | Ventilating duct system | |
CN106446342B (en) | Method for obtaining blade installation angle of axial flow fan | |
CN201731586U (en) | Air conduit system | |
CN204006492U (en) | A kind of domestic air is processed pipeline | |
CN113343378B (en) | Pneumatic characteristic calculation method and system for air pipeline system of high-altitude platform | |
CN214541155U (en) | Environment control system of aviation simulator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |