CN206957742U - A kind of long span under soft rock tunnel excavation support structure - Google Patents

A kind of long span under soft rock tunnel excavation support structure Download PDF

Info

Publication number
CN206957742U
CN206957742U CN201720265959.7U CN201720265959U CN206957742U CN 206957742 U CN206957742 U CN 206957742U CN 201720265959 U CN201720265959 U CN 201720265959U CN 206957742 U CN206957742 U CN 206957742U
Authority
CN
China
Prior art keywords
steelframe
supporting
joist
support structure
tunnel excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720265959.7U
Other languages
Chinese (zh)
Inventor
郭永发
丁文云
剧仲林
殷洪波
张甫
罗胜利
罗云飞
刘正初
肖勇刚
李贵民
伍容兵
杨进京
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Kunming Survey Design and Research Co Ltd
Original Assignee
CREEC Kunming Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Kunming Survey Design and Research Co Ltd filed Critical CREEC Kunming Survey Design and Research Co Ltd
Priority to CN201720265959.7U priority Critical patent/CN206957742U/en
Application granted granted Critical
Publication of CN206957742U publication Critical patent/CN206957742U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

It the utility model is related to a kind of long span under soft rock tunnel excavation support structure, including preliminary bracing body and secondary lining body, the preliminary bracing body includes some supporting steelframe rings, some supporting steelframe central spacers are set, and connected by the joist located at supporting steelframe ring both sides, the supporting steelframe ring includes spaced steelframe web and longitudinally connected muscle, and longitudinally connected muscle is trapezoidal layout, on steelframe web, joist is installed simultaneously with longitudinally connected muscle;Secondary lining body week in preliminary bracing body.Tunnel vault position sets the double-deck solid matter advanced tubules of Φ 42;Tunnel side wall sets the grouting rock bolts of Φ 22;Also include horizontal false stull steelframe supporting;Tunnel side wall scope Support Steel Holder joint position sets Φ 42 to lock pin anchor tube, and anchor tube connection ring plate consolidates itself and supporting steelframe weld anchor.Compared to currently used measure method, the set supporting construction supporting effect more preferably, can largely save engineering material, and economic benefit of engineering and social benefit are notable.

Description

A kind of long span under soft rock tunnel excavation support structure
Technical field
It the utility model is related to a kind of tunnel excavation support structure, and in particular to a kind of long span under soft rock tunnel excavation support knot Structure, belong to Tunnel Engineering technical field.
Background technology
With greatly developing for railway construction, Tunnel Engineering construction condition is increasingly sophisticated, Tunnel Engineering design and construction skill Art faces a severe challenge further.For the big across railway tunnel, its digging process of the poor location of country rock physical and mechanical parameter index In typically deform larger, the common liner supporting structure using " preliminary bracing structure+secondary liner structure " is difficult to be effectively ensured Tunnel engineering resistance to overturning, technical measures are slightly improper easily to cause engineering accident.Most long span under soft rock tunnel at present Generally use strengthening supporting steelframe model, thicken the mode of secondary lining thickness to solve above-mentioned problem, this measure construction costs compared with Height, economic benefit and social benefit are low.Therefore, for long span under soft rock tunnel, it is badly in need of a kind of long span under soft rock tunnel rational in infrastructure Road excavation supporting structure.
The content of the invention
Based on the above situation, the purpose of this utility model is to solve railway tunnel excavation supporting structure across soft rock greatly at present Ineffective engineering problem, and propose a kind of effective excavation supporting structure.
The utility model proposes a kind of long span under soft rock tunnel excavation support structure, a kind of tunnel excavation support structure, bag Include preliminary bracing body and secondary lining body, it is characterised in that:The preliminary bracing body includes some supporting steelframe rings, some supportings Steelframe central spacer is set, and is connected by the joist located at supporting steelframe ring both sides, and the supporting steelframe ring includes being arranged at intervals Steelframe web and longitudinally connected muscle, on facade, longitudinally connected muscle is trapezoidal layout, on steelframe web, joist and longitudinal direction Dowel is installed simultaneously;Secondary lining body week in preliminary bracing body.Further, in addition to stull steelframe, stull Steelframe termination is connected with both sides joist.It is mainly used in the support of excavation face ring, is set laterally according to excavating sequences in digging process False stull steelframe supporting.
Further, in addition to lock pin anchor tube, the lock pin anchor tube are located at Support Steel Holder joint position, are in along steelframe both sides Certain angle is alternately arranged, and is locked and is fixed between pin anchor tube and steelframe by anchor tube connection ring plate, anchor tube connection ring plate is located at supporting For steelframe close to the side wing edge outer panel face of country rock one, the plate face is provided with lock pin anchor tube perforation lanes.All anchor tubes are all in compression shape State, anchor tube is connected with steelframe should meet by pressure request.
Further, in addition to support anchor rod, the support anchor rod are located in the tunnel side wall of supporting steelframe ring both sides.
Further, the joist respectively sets three in left and right sides abutment wall, is connected respectively with supporting steelframe, and joist is set In upper or middle step steelframe footing position, joist is installed simultaneously with longitudinally connected muscle.
Further, joist is monolithic reinforced concrete structure, and cover to reinforcement is not less than 30mm, and joist section is square Shape, the long side of rectangle are set close to country rock side.
Further, in addition to advanced tubule, the advanced tubule are located at tunnel vault at an angle, and bilayer is close Arrangement is put, two rows ductule ring interlaced arrangement, and ductule longitudinal pitch is set by two Pin steelframes.Any one tunnel is horizontal There is two layers of ductule in section.
The beneficial effects of the utility model are as follows:
The utility model adds part construction measure based on conventional lining supporting construction, can effectively ensure that long span under soft rock Resistance to overturning during tunnel excavation.Compared to currently used measure method, the set supporting construction supporting effect more preferably, energy A large amount of to save engineering material, economic benefit of engineering and social benefit are notable.
Brief description of the drawings
Fig. 1 is the utility model long span under soft rock tunnel excavation support structural composite lining section figure;
Fig. 2 is the structural representation of supporting steelframe of the present utility model;
Fig. 3 is the facade structures schematic diagram that steelframe dowel of the present utility model is connected with steelframe web;
Fig. 4 is the planar structure schematic diagram that steelframe dowel of the present utility model is connected with steelframe web;
Fig. 5 is the facade structures schematic diagram that lock pin anchor tube of the present utility model is connected with steelframe;
Fig. 6 is Fig. 5 A-A sectional views;
Fig. 7 is Fig. 6 B-B sectional views;
Fig. 8 is the structural representation that anchor tube connects ring plate;
Fig. 9 is the structural representation of support anchor rod of the present utility model;
Figure 10 is the vertical face structural representation of double-deck solid matter advanced tubule of the present utility model;
Figure 11 is the positive structure schematic of double-deck solid matter advanced tubule of the present utility model;
Figure 12 is the vertical structure schematic diagram of reinforced concrete supporting beam of the present utility model;
Figure 13 is Figure 12 A-A sectional views;
Figure 14 is Figure 12 B-B sectional views;
In figure respectively marked as:1- solid matter advanced tubules;2- preliminary bracing bodies;3- support anchor rods;4- secondary lining bodies;5- Supporting steelframe;6- joists;7- stull steelframes;8- steelframe dowels;9- locks pin anchor tube;10- anchor tubes connect ring plate.
Embodiment
The utility model is described in further detail below by drawings and examples, but protection model of the present utility model Enclose and be not limited to the content.
As Figure 1-4, a kind of long span under soft rock tunnel excavation support structure of the present embodiment, including the He of preliminary bracing body 2 Secondary lining body 4, preliminary bracing body include some supporting steelframe rings 5, and some supporting steelframe central spacers are set, and by located at branch The joist 6 of shield steelframe ring both sides connects, and the supporting steelframe ring includes spaced steelframe web and longitudinally connected muscle 8, indulges It is trapezoidal layout to dowel, on steelframe web, joist is installed simultaneously with longitudinally connected muscle;Secondary lining body is located at initial stage Prop inner circumferential, in addition to solid matter advanced tubule 1 and support anchor rod 3.
Preliminary bracing body tunnel excavation face loopful set, in addition to C25 gunite concretes andBar-mat reinforcement, just spray is mixed The solidifying thick 40mm of soil, multiple pneumatically placed concrete thickness 30mm.Secondary liner structure 4 is monolithic reinforced concrete structure, the specific root of lining thickness Determined according to tunnel excavation cross dimensions and Analysis of Field Geotechnical Parameters checking computations.The supporting steelframe 5 of abutment wall uses I22 or I25 profile steel frames, specifically Determine that steelframe is according to excavated section size segmentation prefabricating and assembly according to tunnel excavation cross dimensions and Analysis of Field Geotechnical Parameters checking computations.Support Beam 6 is monolithic reinforced concrete structure, and reinforced concrete supporting beam muscle 8 longitudinally connected with steelframe is installed simultaneously, is welded with steelframe web Connect in succession, weld bead height is not less than 10mm.The longitudinally connected muscle of steelframe can use HRB400 reinforcing bars, a diameter of 20-22mm, use The U-shaped trapezoidal arrangement connection of connection reinforcing bar, is welded on steelframe web.
As shown in Fig. 2 the horizontal supporting of false stull steelframe 7, stull steelframe two are set according to excavating sequences in digging process End termination is connected with both sides joist 6, is mainly used in the support of excavation face ring, its model and structure type and supporting steelframe 5 is consistent, Selectively set according to Specific construction operating mode and process in work progress.
As viewed in figures 5-8, the present embodiment also includes lock pin anchor tube 9, locks a diameter of 42mm of pin anchor tube, is arranged at abutment wall scope Support Steel Holder joint position, is alternately arranged along steelframe both sides, and being connected the full weld of ring plate 10 by anchor tube with steelframe welds, full seam height Not less than 10mm;All anchor tubes are all in pressured state, and anchor tube is connected with steelframe should meet by pressure request;Lock pin anchor tube 9 has been constructed Cheng Hou, it is connected ring plate 10 with anchor tube and welded.Anchor tube connection ring plate 10 is made of shaped steel steel disc, and plane is rectangle, size For length × wide=180mm × 110mm;The reserved perforation lanes of lock pin anchor tube 9 of plate face, channel diameter 42mm;Anchor tube connects ring plate 10 it is pre-formed after be welded in supporting steelframe 5 in advance close to the side wing edge outer panel face of country rock one.
As shown in figure 9, the support anchor rod 3 of the present embodiment is in the tunnel side wall of supporting steelframe ring both sides.Support anchor rod is adopted With grouting rock bolt, a diameter of 22mm or 25mm, length 3-5m.
As shown in figs. 10-11, the seamless steel floral tube of double-deck solid matter advanced tubule 1 use of the present embodiment, a diameter of 42mm, Wall thickness is 3.5mm, and length 2.4-3.6m, ring spacing is 30cm;There is two layers of ductule in any one tunnel cross section, And two rows ductule ring interlaced arrangement;Ductule longitudinal pitch is set by two Pin steelframes, is installed first close to face Ductule locating steel frame, then apply ductule, another Pin steelframes be finally installed, so that the outer limb of ductule is minimum, reduce Backbreak.
As shown in figs. 12-14, the cover to reinforcement of steelframe joist cannot be less than 30mm, rectangular cross section size for it is long × wide= 250mm × 210mm, long side are set close to country rock side;Reinforced concrete supporting beam 6 coordinate benching tunnelling method excavate, be arranged at or in Step steelframe footing position.
Supporting construction is considered as deformation allowance design, after being closed in construction according to preliminary bracing, the knot after adjoining rock stability Fruit adjusts;Pay special attention to deformation allowance mainly to consider to construct accident error and reserve, site operation should be to control country rock to become Shape is target.
The utility model is as follows using step:
(1) in the tunnel tunnel face keystone construction double-deck solid matter advanced tubule advance support structures of Φ 42, and opening Dig abutment wall scope and the grouting rock bolts of Φ 22 are set.
(2) merogenesis construction loopful supporting steelframe, longitudinally connected muscle is arranged circumferentially along steelframe between adjacent supporting steelframe and is connected, edge Circuit longitudinal direction sets three reinforced concrete supporting beams to connect in left and right sides abutment wall scope, and supporting steelframe is arranged circumferentially steelframe connection Muscle connects.
(3) horizontal false stull steelframe supporting is set according to Specific construction operating mode and process, selectivity.
(4) in digging process, Φ 42 is set to lock pin anchor tube in tunnel side wall scope Support Steel Holder joint position, and utilize anchor Pipe connection ring plate consolidates itself and supporting steelframe weld anchor.
(5) construction secondary liner structure.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc., the utility model should be included in Protection domain within.

Claims (7)

1. a kind of tunnel excavation support structure, including preliminary bracing body and secondary lining body, it is characterised in that:The preliminary bracing Body includes some supporting steelframe rings, and some supporting steelframe central spacers are set, and is connected by the joist located at supporting steelframe ring both sides Connecing, the supporting steelframe ring includes spaced steelframe web and longitudinally connected muscle, on facade, the longitudinally connected trapezoidal cloth of muscle Put, on steelframe web, joist is installed simultaneously with longitudinally connected muscle;Secondary lining body week in preliminary bracing body.
A kind of 2. tunnel excavation support structure according to claim 1, it is characterised in that:Also include stull steelframe, stull Steelframe termination is connected with both sides joist.
A kind of 3. tunnel excavation support structure according to claim 1, it is characterised in that:Also include lock pin anchor tube, it is described Lock pin anchor tube is located at Support Steel Holder joint position, is alternately arranged at an angle along steelframe both sides, locks between pin anchor tube and steelframe Ring plate is connected by anchor tube to fix, anchor tube connection ring plate is located at supporting steelframe close to the side wing edge outer panel face of country rock one, the plate Face is provided with lock pin anchor tube perforation lanes.
A kind of 4. tunnel excavation support structure according to one of claim 1-3, it is characterised in that:Also include supporting anchor Bar, the support anchor rod is in the tunnel side wall of supporting steelframe ring both sides.
A kind of 5. tunnel excavation support structure according to one of claim 1-3, it is characterised in that:The joist is in left and right Two side walls respectively set three, are connected respectively with supporting steelframe, joist is arranged at or middle step steelframe footing position.
A kind of 6. tunnel excavation support structure according to claim 5, it is characterised in that:The joist mixes for cast in place reinforced bar Xtah Crude Clay structure, cover to reinforcement are not less than 30mm, and joist section is rectangle, and the long side of rectangle is set close to country rock side.
A kind of 7. tunnel excavation support structure according to one of claim 1-3, it is characterised in that:Also include small in advance lead Pipe, the advanced tubule be located at tunnel vault at an angle, and double-deck solid matter is arranged, two rows ductule ring interlocks cloth Put, ductule longitudinal pitch is set by two Pin steelframes.
CN201720265959.7U 2017-03-17 2017-03-17 A kind of long span under soft rock tunnel excavation support structure Active CN206957742U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720265959.7U CN206957742U (en) 2017-03-17 2017-03-17 A kind of long span under soft rock tunnel excavation support structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720265959.7U CN206957742U (en) 2017-03-17 2017-03-17 A kind of long span under soft rock tunnel excavation support structure

Publications (1)

Publication Number Publication Date
CN206957742U true CN206957742U (en) 2018-02-02

Family

ID=61377383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720265959.7U Active CN206957742U (en) 2017-03-17 2017-03-17 A kind of long span under soft rock tunnel excavation support structure

Country Status (1)

Country Link
CN (1) CN206957742U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756948A (en) * 2018-06-15 2018-11-06 中铁工程设计咨询集团有限公司 A kind of longspan tunnel prestressed anchor net branch shell is from carrying supporting construction
CN112814715A (en) * 2021-01-07 2021-05-18 中铁十六局集团第三工程有限公司 Novel locking anchor pipe construction fixing device and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756948A (en) * 2018-06-15 2018-11-06 中铁工程设计咨询集团有限公司 A kind of longspan tunnel prestressed anchor net branch shell is from carrying supporting construction
CN108756948B (en) * 2018-06-15 2023-06-20 中铁工程设计咨询集团有限公司 Self-bearing supporting structure for large-span tunnel prestress anchor net supporting rock shell
CN112814715A (en) * 2021-01-07 2021-05-18 中铁十六局集团第三工程有限公司 Novel locking anchor pipe construction fixing device and construction method thereof

Similar Documents

Publication Publication Date Title
CN106761810B (en) A kind of large-deformation tunnel in soft rock supporting structure system and its construction method
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN102587924A (en) Construction method for shallow-buried high-water-content clayed soil tunnel
CN111677520B (en) Construction method for excavating station structure by tunnel-first station-later station pipe curtain hole-pile method
CN103362513A (en) Transformation and construction method for existing cavity in underground excavation region
CN105736017A (en) Asymmetric unit forwardly-reversely arranged arch structure for primary supporting of tunnel
CN103244143B (en) A kind of underground construction excavating construction method and underground station
CN111828053A (en) Steel pipe concrete and sprayed concrete rigid combined structure tunnel supporting system and construction method
CN112796763A (en) Deep underground tunnel ventilation shaft supporting construction
CN206957742U (en) A kind of long span under soft rock tunnel excavation support structure
CN204851266U (en) Secretly dig shaft structure directly over station
CN113062750A (en) Construction method of tunnel structure with underground structure uplift pile penetrating downwards
WO2024027772A1 (en) Composite support structure combining bag-based backfill grouting and high-strength support frame, and construction method
US20230349291A1 (en) System and construction method of single-layer lining tunnel structure based on mine-tunnelling method
CN218439399U (en) Auxiliary supporting device for tunnel inverted arch construction
CN110359471B (en) Anti-seepage damage structure of strong water-permeable sandy soil layer of underwater tunnel and construction method
CN107780942A (en) The new prefabricated assembled pipe canopy and its manufacture craft of a kind of soft soil tunnel pre-reinforcement
CN104594358A (en) Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit
CN111734450A (en) Safe and rapid tunneling and supporting method for water-rich fault zone tunnel
CN216894442U (en) Multi-guide-hole combined excavation steel frame connecting device
CN105113513A (en) Anti-seepage foundation pit supporting structure and construction method
CN115839251A (en) Up-down overlapping tunnel construction method based on advanced pre-reinforcement
CN212202065U (en) Tunnel structure suitable for composite stratum with upper soft layer and lower hard layer
CN112664205B (en) Tunnel excavation supporting method for cross intersection
CN212270961U (en) Deep foundation pit supporting structure under ultra-wide pipeline

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant