CN206956733U - Slope Supporting of Deep Excavation structure - Google Patents

Slope Supporting of Deep Excavation structure Download PDF

Info

Publication number
CN206956733U
CN206956733U CN201720336190.3U CN201720336190U CN206956733U CN 206956733 U CN206956733 U CN 206956733U CN 201720336190 U CN201720336190 U CN 201720336190U CN 206956733 U CN206956733 U CN 206956733U
Authority
CN
China
Prior art keywords
side slope
slope
anchoring pile
steel pipe
anchoring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720336190.3U
Other languages
Chinese (zh)
Inventor
杨新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaya Metallurgical Construction Group Co. Ltd.
Original Assignee
Hubei Huaya Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Huaya Construction Engineering Co Ltd filed Critical Hubei Huaya Construction Engineering Co Ltd
Priority to CN201720336190.3U priority Critical patent/CN206956733U/en
Application granted granted Critical
Publication of CN206956733U publication Critical patent/CN206956733U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a kind of Slope Supporting of Deep Excavation structure, including:Horizontally disposed steel pipe and some anchoring piles connected with steel pipe, anchoring pile is evenly distributed on steel pipe, and in the side slope bottom injection soil layer of the lower end edge foundation ditch of anchoring pile, the top of anchoring pile is provided with a pin, and a sealing plate is provided between two adjacent pins, cured layer is filled between sealing plate and the inclined-plane of side slope.The utility model in the bottom position of deep foundation pit slope by setting steel pipe and the multiple anchoring piles connected with steel pipe, in anchoring pile injection side slope soil layer, to improve the coupling force between supporting construction and side slope, simultaneously, coordinate and pin is set at the top of anchoring pile, utilize one host cavity of formation between the sealing plate between pin and side slope, by filling cured layer in host cavity, to realize its side slope surface cure, and the angle formed using sealing plate and anchoring pile, it not only can effectively ensure the flatness on side slope surface, and the also gradient of fixed slope.

Description

Slope Supporting of Deep Excavation structure
Technical field
Technical field of buildings is the utility model is related to, more particularly, to a kind of Slope Supporting of Deep Excavation structure.
Background technology
The substantial amounts of deep-foundation pit engineering of nearly state is started from the 1980s, developing rapidly due to urban skyscraper, underground The various needs such as parking lot, skyscraper buried depth, people's air defense, skyscraper need to build certain basement.In recent years, due to city Develop rapidly subway station, local section open cut etc. of city's subway engineering are directed to substantial amounts of base pit engineering, intersect in two-wire Subway station, foundation ditch is as deep as 20-30m.There is also underground power house, the Excavation problems of underground pump house for water conservancy, electric power.
The either deep-foundation pit engineering of skyscraper or subway, due to being excavated in city, around foundation ditch The various structures such as traffic main artery, built construction or pipeline generally be present, this relate to one of excavation of foundation pit it is critically important in Hold, to protect the safe handling of its periphery structures.And the excavation supporting of foundation ditch is a comprehensive Geotechnical Engineering problem, Pattern foundation pit supporting structure is interim measure in most cases, and the safety stock of supporting construction is smaller, and risk is also big, and the economy of base pit engineering refers to Mark is harsh, strict to surrounding environment requirement, and the contradiction of the provisional and economy of base pit engineering is more prominent, along with foundation ditch work The regional differences of journey are big, and it is various informative to also result in base pit engineering supporting construction.
And in current slope support engineering, to prevent slope failure, more anchor poles, dowels are typically set in side slope Beam etc., and fill up cement mortar between anchor pole, dowel beam and bolthole, it is ensured that anchor pole, dowel beam and the discrete rock mass in periphery Or native stone consolidation is chained together, at the same time, steel fibre reinforced concrete is sprayed in side slope surface to reach the purpose of stability of slope.So And for soil-slope, slip unstability, mudstone flow phenomenon are easily produced because the soil body is soft, after meeting rainwater, takes anchor Bar, dowel beam and spray steel fibre reinforced concrete are difficult to prevent domatic slip, if setting retaining wall in side slope toe, only can ensure that side slope Toe bottom is not slided, and can not still be prevented top from producing landslide phenomenon, be had a strong impact on slope project safe operation.In summary, Current slope retaining is passive protecting pattern.
Utility model content
A kind of technique of the utility model offer is simple, can effectively prevent slope failure from triggering security incident and can ensure that side slope The Slope Supporting of Deep Excavation structure of gradient, to solve, upper existing optical depth excavation slope reliability is not high easily to produce initiation of caving in The technical problem of security incident.
According to one side of the present utility model, there is provided a kind of Slope Supporting of Deep Excavation structure, including:Horizontally disposed steel Pipe and some anchoring piles connected with the steel pipe, the anchoring pile is evenly distributed on the steel pipe, and the lower end edge of the anchoring pile In the side slope bottom injection soil layer of foundation ditch, extended upwardly at the top of the anchoring pile outside the side slope bottom solum of foundation ditch, the anchor The top of stake is provided with a pin, and the inclined-plane compartment of the pin and side slope be arranged in parallel, and between two adjacent pins Provided with a sealing plate, cured layer is filled between the sealing plate and the inclined-plane of side slope.
On the basis of such scheme preferably, the sealing plate is bent plate, and its both ends is welded on the pin of both sides, its Bottom is welded on the steel pipe, the sealing plate and the inclined-plane of side slope is enclosed and is set as a host cavity, the cured layer with it is described Host cavity is adapted.
On the basis of such scheme preferably, the cured layer is that multiple sand bags stack the sand stone layer formed.
On the basis of such scheme preferably, the cured layer is soil cement mixed layer.
On the basis of such scheme preferably, the anchoring pile bottom is opening-like, and provided with more on the periphery of the anchoring pile Individual grout hole.
On the basis of such scheme preferably, some helicla flutes are additionally provided with the periphery of the anchoring pile, the helicla flute with The grout hole is corresponding, and is arranged on the underface of the grout hole.
A kind of Slope Supporting of Deep Excavation structure of the utility model, by deep foundation pit slope bottom position set steel pipe and The multiple anchoring piles connected with steel pipe, by anchoring pile injection side slope soil layer, being made with improving the connection between supporting construction and side slope Firmly, meanwhile, coordinate and pin is set at the top of anchoring pile, housed using forming one between the sealing plate between pin and side slope Chamber, by filling cured layer in host cavity, to realize its side slope surface cure, and formed using sealing plate and anchoring pile Angle, it not only can effectively ensure the flatness on side slope surface, and the also gradient of fixed slope.
Meanwhile anchoring pile of the present utility model is connected with steel pipe, in use, injecting water into anchoring pile simultaneously using steel pipe Mud, its is simple to operate, can effectively reduce its cost, and inject cement to side slope bottom by anchoring pile and can further improve supporting knot The stability of structure, to prevent slope failure from influenceing its security performance.
Brief description of the drawings
Fig. 1 is a kind of schematic cross-section of Slope Supporting of Deep Excavation structure of the present utility model;
Fig. 2 is a kind of overlooking the structure diagram of Slope Supporting of Deep Excavation structure of the present utility model.
Embodiment
With reference to the accompanying drawings and examples, specific embodiment of the present utility model is described in further detail.Below Embodiment is used to illustrate the utility model, but is not limited to the scope of the utility model.
Referring to Fig. 1, and with reference to shown in Fig. 2, the utility model provides a kind of Slope Supporting of Deep Excavation structure, including: Horizontally disposed steel pipe 20 and some anchoring piles 10 connected with the steel pipe 20, anchoring pile 10 is evenly distributed on steel pipe 20, and anchor In the side slope bottom injection soil layer of the lower end edge foundation ditch of stake 10, the top of the anchoring pile 10 extends upwardly to the side slope bottom of foundation ditch Outside soil layer, the top of the anchoring pile 10 is provided with a pin 30, and the pin 30 and the inclined-plane compartment of side slope be arranged in parallel, and institute State and be provided with a sealing plate 40 between two adjacent pins 30, cured layer is filled between the sealing plate 40 and the inclined-plane of side slope 41。
In order to further illustrate detailed description the technical solution of the utility model, please continue to refer to shown in Fig. 2, this practicality New sealing plate 40 is bent plate, and the both ends of bent plate are welded on the pin 30 of both sides, and the bottom surface of bent plate is welded on steel pipe 20 On, sealing plate 40 and the inclined-plane of side slope is enclosed and is set as a host cavity 42, cured layer 41 is adapted with host cavity 42.It is preferred that this reality Can stack the sand stone layer formed for multiple sand bags with new cured layer 41.And the cured layer 41 can also be soil cement Mixed layer.
The bottom of anchoring pile 10 of the present utility model is opening-like, and multiple grout holes are provided with the periphery of the anchoring pile 10. Cement is injected to anchoring pile 10 using steel pipe 20 is unified, cement crosses grout hole and the bottom of anchoring pile 10 and forms one with side slope all, So as to improve its stability, slope failure is prevented, influences its safety in utilization.Further, on the periphery of the anchoring pile 10 also Provided with some helicla flutes, helicla flute is corresponding with grout hole, and is arranged on the underface of the grout hole, i.e., is played using helicla flute The effect of guiding so that mud flows downward along helicla flute, so as to further improve the company between anchoring pile 10 and side slope soil Connect fastness.
A kind of Slope Supporting of Deep Excavation structure of the utility model, steel pipe 20 is set by the bottom position in deep foundation pit slope And the multiple anchoring piles 10 connected with steel pipe 20, by the injection side slope soil layer of anchoring pile 10, to improve between supporting construction and side slope Coupling force, meanwhile, coordinate anchoring pile 10 top set pin 30, utilize the sealing plate 40 and side slope between pin 30 Between form a host cavity 42, by the filling cured layer 41 in the host cavity 42, to realize its side slope surface cure, and profit It the angle formed with sealing plate 40 and anchoring pile 10, not only can effectively ensure the flatness on side slope surface, and also have and fix The gradient of side slope.
Meanwhile anchoring pile 10 of the present utility model is connected with steel pipe 20, in use, using steel pipe 20 simultaneously to anchoring pile 10 Interior injection cement, its is simple to operate, can effectively reduce its cost, and can be further to side slope bottom injection cement by anchoring pile 10 The stability of supporting construction is improved, to prevent slope failure from influenceing its security performance.
Finally, the present processes are only preferable embodiment, are not intended to limit the scope of protection of the utility model. All any modification, equivalent substitution and improvements within the spirit and principles of the utility model, made etc., should be included in this reality Within new protection domain.

Claims (6)

  1. A kind of 1. Slope Supporting of Deep Excavation structure, it is characterised in that including:Horizontally disposed steel pipe and connect with the steel pipe Some anchoring piles, the anchoring pile are evenly distributed on the steel pipe, and the side slope bottom injection soil of the lower end edge foundation ditch of the anchoring pile In layer, extended upwardly at the top of the anchoring pile outside the side slope bottom solum of foundation ditch, the top of the anchoring pile is provided with a pin, institute The inclined-plane compartment for stating pin and side slope is be arranged in parallel, and a sealing plate, the sealing are provided between two adjacent pins Cured layer is filled between plate and the inclined-plane of side slope.
  2. A kind of 2. Slope Supporting of Deep Excavation structure as claimed in claim 1, it is characterised in that the sealing plate is bent plate, its Both ends are welded on the pin of both sides, and its bottom is welded on the steel pipe, enclose the inclined-plane of the sealing plate and side slope A host cavity is set as, the cured layer is adapted with the host cavity.
  3. A kind of 3. Slope Supporting of Deep Excavation structure as claimed in claim 1 or 2, it is characterised in that:The cured layer is multiple Sand bag stacks the sand stone layer formed.
  4. A kind of 4. Slope Supporting of Deep Excavation structure as claimed in claim 1 or 2, it is characterised in that:The cured layer is cement Native mixed layer.
  5. A kind of 5. Slope Supporting of Deep Excavation structure as claimed in claim 1, it is characterised in that:The anchoring pile bottom is in opening Shape, and multiple grout holes are provided with the periphery of the anchoring pile.
  6. A kind of 6. Slope Supporting of Deep Excavation structure as claimed in claim 5, it is characterised in that:On the periphery of the anchoring pile also Provided with some helicla flutes, the helicla flute is corresponding with the grout hole, and is arranged on the underface of the grout hole.
CN201720336190.3U 2017-04-01 2017-04-01 Slope Supporting of Deep Excavation structure Expired - Fee Related CN206956733U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720336190.3U CN206956733U (en) 2017-04-01 2017-04-01 Slope Supporting of Deep Excavation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720336190.3U CN206956733U (en) 2017-04-01 2017-04-01 Slope Supporting of Deep Excavation structure

Publications (1)

Publication Number Publication Date
CN206956733U true CN206956733U (en) 2018-02-02

Family

ID=61372453

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720336190.3U Expired - Fee Related CN206956733U (en) 2017-04-01 2017-04-01 Slope Supporting of Deep Excavation structure

Country Status (1)

Country Link
CN (1) CN206956733U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183811A (en) * 2018-10-27 2019-01-11 江苏中煤地质工程研究院有限公司 A kind of foundation pit supporting construction and its construction method of resistance to deformation
CN110761300A (en) * 2019-11-08 2020-02-07 中国十七冶集团有限公司 Construction method for supporting impervious soft soil body on side slope of deep foundation pit of high-rise building through micro-expansion

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183811A (en) * 2018-10-27 2019-01-11 江苏中煤地质工程研究院有限公司 A kind of foundation pit supporting construction and its construction method of resistance to deformation
CN110761300A (en) * 2019-11-08 2020-02-07 中国十七冶集团有限公司 Construction method for supporting impervious soft soil body on side slope of deep foundation pit of high-rise building through micro-expansion
CN110761300B (en) * 2019-11-08 2021-04-09 中国十七冶集团有限公司 Construction method for supporting impervious soft soil body on side slope of deep foundation pit of high-rise building through micro-expansion

Similar Documents

Publication Publication Date Title
CN102392458B (en) Piling beam cofferdam construction method used for bare rock foundation construction in water
CN110118090A (en) For preventing tunnel grouting reinforcing from causing the safeguard structure of surface uplift
CN207987960U (en) A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN110004919B (en) Foundation pit enclosure construction method used in pipeline influence range
CN201407053Y (en) Support and waterproof structure for metro tunnel of tunnel boring machine construction
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN101967983A (en) Method for over-dredging, anchoring, backfilling and controlling deep well rock roadway floor heave
CN105484266B (en) The grouting equipment and its construction method of a kind of multifunctional information
CN203594035U (en) Multilevel combined protection structure for shallow hole blasting excavation bridge foundation pit construction
CN207646746U (en) A kind of arch interlocking pile formula foundation pit supporting construction
CN206956733U (en) Slope Supporting of Deep Excavation structure
CN207278276U (en) Cross the shallow-depth-excavation tunnel supporting construction of ground fissure crushed zone
CN208594560U (en) A kind of foundation pit stope support structure
CN207176700U (en) A kind of solid matter perfusion inner support of pile foundation ditch permanent support structure under complex environment
CN107178088B (en) A kind of basement waterproofing foundation pit structure and its construction method
CN202323960U (en) Shallow foundation pit forming construction structure capable of ensuring slope stability
CN204311456U (en) Foundation ditch strengthening structure
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN205576957U (en) Stake end pilework
CN102220764A (en) Deep foundation pit bracing system and construction method thereof
CN204000836U (en) A kind of structure for the ground stabilization of shield end well surrounding building
CN103821140B (en) A kind of construction method of reinforcing soft foundation
KR101403997B1 (en) Concrete caisson hollow part reinforcement structure and method by using grouting device
RU121275U1 (en) REINFORCED GROUND-CEMENT WALL FOR PROTECTION OF BUILDINGS AND STRUCTURES FROM THE DIGGED NEAR THE CROWDED
CN102678127B (en) Method for constructing weakly consolidated non-stratified sandstone tunnel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 430080 Peace Avenue, Qingshan District, Wuhan, Hubei Province, No. 1250

Patentee after: Huaya Metallurgical Construction Group Co. Ltd.

Address before: 430080 Peace Avenue, Qingshan District, Wuhan, Hubei Province, No. 1250

Patentee before: Hubei Huaya Construction Engineering Co. Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180202