CN206941614U - A kind of slope reinforcement structure - Google Patents

A kind of slope reinforcement structure Download PDF

Info

Publication number
CN206941614U
CN206941614U CN201720519089.1U CN201720519089U CN206941614U CN 206941614 U CN206941614 U CN 206941614U CN 201720519089 U CN201720519089 U CN 201720519089U CN 206941614 U CN206941614 U CN 206941614U
Authority
CN
China
Prior art keywords
stone
retaining wall
reinforcement structure
packing layer
slope reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720519089.1U
Other languages
Chinese (zh)
Inventor
熊勃
郑亚琴
陈位洪
甄宏志
李骏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Architectural Design and Research Institute of Guangdong Province
Original Assignee
Architectural Design and Research Institute of Guangdong Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Architectural Design and Research Institute of Guangdong Province filed Critical Architectural Design and Research Institute of Guangdong Province
Priority to CN201720519089.1U priority Critical patent/CN206941614U/en
Application granted granted Critical
Publication of CN206941614U publication Critical patent/CN206941614U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model discloses a kind of slope reinforcement structure, including old slopes, the domatic upper heap of old slopes is filled with the forced ramming reinforcing matrix that compactness is more than 80%, reinforces on the outside of matrix and is provided with geo-grid reinforcement body, the construction land utilization rate allowed in red line greatly promotes.The utility model is used for the embankment slope project of large area and big height.

Description

A kind of slope reinforcement structure
Technical field
It the utility model is related to a kind of slope reinforcement structure.
Background technology
Landfill, thermal power generation factory etc. have the project necessarily polluted, and government often delimit in remote area Red line, these environment sanitation facilities are arranged far to the place in urban district.These local geological conditions are often more severe, and its surrounding Substantially all it is mountain region, in order to obtain smooth construction land as much as possible on mountain region, generally requires to carry out mountain region side slope Processing, eminence is excavated by certain ratio of slope slope, and lower is backfilled by certain ratio of slope.Wherein, what difficulty was larger is to backfilling side The consolidation process on slope, according to traditional reinforcing mode, it is necessary to carry out slope by certain ratio of slope to embankment side slope, but due to having The limitation of land red-line, it is impossible to which unconfined slope is carried out to slopes, it should which supporting and retaining system measure is set at red line.This patent is A kind of slopes ruggedized construction being arranged near deep embankment side slope red line.
Utility model content
The technical problems to be solved in the utility model is:A kind of very firm and small quantities slope reinforcement knot is provided Structure.
The solution that the utility model solves its technical problem is:
A kind of slope reinforcement structure, including old slopes, the domatic upper heaps of old slopes be filled with compactness be more than 80% plus Gu matrix, the gradient for reinforcing matrix is more than the gradient of old slopes, reinforces on the outside of matrix and is provided with reinforcing body, the reinforcing body includes more Individual back-up coat, adjacent back-up coat GSZ or geotextiles separate, and the bottom of reinforcing body is provided with stone packing layer, the stone The compactness of block packing layer is more than 85%, and the outside of stone packing layer is provided with retaining wall, the lower section of stone packing layer by it is interior extremely Outer compartment of terrain is provided with several CFG stakes.
As the further improvement of such scheme, stone packing layer includes multiple rock layers, is set between adjacent rock layer There is GSZ.
As the further improvement of such scheme, rock layer includes multiple stones being closely packed together mutually, the stone Intensity be more than MU15.
As the further improvement of such scheme, retaining wall is counterfort wall, and shingle nail and the stone of retaining wall are filled out The bed of material abuts, and the wall heel of retaining wall is located at the lower section of stone packing layer.
As the further improvement of such scheme, Percussion Piles are connected with below retaining wall, the stake end of the Percussion Piles is entered At least one meter of weathered rock formation in a subtle way.
As the further improvement of such scheme, Percussion Piles, effective stake of the Percussion Piles are connected with below retaining wall It is long at least ten meters.
As the further improvement of such scheme, retaining wall is slabstone concrete guard wall, and the slabstone intensity in retaining wall is not Less than MU20.
As the further improvement of such scheme, in addition to canal case, retaining wall is slabstone concrete guard wall, and canal case is located at gear The lower section of cob wall and/or stone packing layer.
As the further improvement of such scheme, compartment of terrain is provided with several CFG stakes from the inside to the outside for the lower section of canal case.
As the further improvement of such scheme, the top outer of canal case is provided with sand stone layer, the compactness of the sand stone layer For more than 90%.
The beneficial effects of the utility model are:A kind of slope reinforcement structure, including old slopes, the domatic upper landfill of old slopes The reinforcing matrix for having compactness to be more than 80%, the gradient for reinforcing matrix are more than the gradient of old slopes, reinforce on the outside of matrix and be provided with Reinforcing body, the reinforcing body include multiple back-up coats, and adjacent back-up coat GSZ or geotextiles separate, such reinforcing The combination of matrix and reinforcing body, the larger gradient can be not only built, the utilization rate allowed in red line greatly promotes, due to reinforcing base Body need not set GSZ, therefore can greatly reduce quantities and material cost.The bottom of reinforcing body is provided with stone packing layer, institute The compactness for stating stone packing layer is more than 85%, and the outside of stone packing layer is provided with retaining wall, the lower section of stone packing layer by Interior to outer compartment of terrain is provided with several CFG stakes.By the use of stone packing layer as reinforcing body substrate, equivalent to artificially producing one The very high lithosphere of bearing capacity, Just because of this, so need not the far distance of slope outward, alleviate the pressure of expropriation of land While, it can also greatly reduce quantities.And compactness is very good for the globality of high stone packing layer, to avoid entirety Sedimentation, if so being provided with individual CFG stakes in the lower section of stone packing layer, CFG stakes can be given outside the enough support forces of stone packing layer, also The quantities excavated can be reduced.Furthermore stone packing layer also has hydrophobic effect so that the side slope after reinforcing does not integrally fear heavy rain Wash away and soak.The utility model is used for the embankment slope project of large area and big height.
Brief description of the drawings
, below will be to needed for embodiment description in order to illustrate more clearly of the technical scheme in the embodiment of the utility model The accompanying drawing to be used is briefly described.Obviously, described accompanying drawing is part of the embodiment of the present utility model, rather than entirely Portion's embodiment, those skilled in the art on the premise of not paying creative work, can also obtain it according to these accompanying drawings His design and accompanying drawing.
Fig. 1 is the a1 structural representations of the utility model embodiment;
Fig. 2 is the a1 structure partial enlarged diagrams of the utility model embodiment;
Fig. 3 is the utility model embodiment a2 structural representations;
Fig. 4 is the utility model embodiment a2 structure partial enlarged diagrams.
Embodiment
Design, concrete structure and caused technique effect of the present utility model are carried out below with reference to embodiment and accompanying drawing Clearly and completely describe, to be completely understood by the purpose of this utility model, feature and effect.Obviously, described embodiment It is part of the embodiment of the present utility model, rather than whole embodiments, based on embodiment of the present utility model, the skill of this area The other embodiment that art personnel are obtained on the premise of not paying creative work, belong to the model of the utility model protection Enclose.In addition, all connection/annexations being previously mentioned in text, not singly refer to component and directly connect, and refer to can be according to specific reality Situation is applied, by adding or reducing couple auxiliary, to form more excellent draw bail.Each technology in the utility model creation Feature, can be with combination of interactions on the premise of not conflicting conflict.
Referring to Figures 1 and 2, this is embodiment a1 of the present utility model, specifically:
A kind of slope reinforcement structure, including old slopes, former domatic the 11 of old slopes and land red-line 13 as illustrated, in original Domatic upper strong rammer to compactness be 90%, then by it is counter dig to be formed it is stair-stepping it is domatic so as to formed reinforce matrix 10, reinforce The gradient of matrix 10 is more than the gradient of old slopes, reinforces the outside of matrix 10 and is provided with reinforcing body, the outer slope for reinforcing matrix is rammed into rank Scalariform, the reinforcing body include multiple back-up coats, and adjacent back-up coat GSZ or geotextiles separate, such reinforcing base The combination of body 10 and reinforcing body, the larger gradient can be not only built, the utilization rate allowed in red line greatly promotes, due to reinforcing base Body 10 need not set GSZ, therefore can greatly reduce quantities and material cost.The bottom of reinforcing body is provided with stone packing layer, The compactness of the stone packing layer is more than 92%, and the outside of stone packing layer is provided with retaining wall, the lower section of stone packing layer Compartment of terrain is provided with several CFG stakes from the inside to the outside.By the use of stone packing layer as reinforcing body substrate, equivalent to artificially producing one The very high lithosphere of individual bearing capacity, Just because of this, so need not the far distance of slope outward, alleviate the pressure of expropriation of land While power, it can also greatly reduce quantities.It is whole to avoid and compactness is very good for the globality of high stone packing layer Body is settled, if so being provided with individual CFG stakes in the lower section of stone packing layer, CFG stakes can be given outside the enough support forces of stone packing layer, The quantities of excavation can also be reduced.Furthermore stone packing layer also has hydrophobic effect so that the side slope after reinforcing is not feared integrally big Rain washes away and soaked.
In order to make consolidation effect more preferable, so the present embodiment is built using the method for compaction in layers to stone packing layer Make, it is stacked by multiple rock layers 1 and formed, and GSZ 2 is provided between adjacent rock layer.The setting of multilayer, it can also improve The stability and intensity of stone packing layer.
And due to being provided with GSZ in embankment Slope body, the shearing strength of side slope is enhanced, therefore side slope is not required to Will the far distance of slope outward, alleviate the pressure of expropriation of land.By the use of stone packing layer as reinforcing body substrate, due to its intensity Height, compactness is high, good integrity, can effectively reduce the sedimentation of whole embankment side slope, and stone packing layer also has hydrophobic work With underground water that can effectively in guide side slope.Some CFG stakes are provided with below stone packing layer, whole side slope can be given to provide Enough support forces, ensure the stability of whole side slope.
The rock layer 1 of the present embodiment includes multiple stones being closely packed together mutually, the intensity of the stone for MU20 or More than MU20.
In order to further improve the antiskid slope ability of the present embodiment, retaining wall 3 is counterfort wall, the wall of retaining wall 3 Panel abuts with stone packing layer, and the wall heel of retaining wall 3 is located at the lower section of stone packing layer.Thus equivalent to there is one piece of megalith Push down wall heel so that retaining wall is not in rotation situation about turning up, resist landslide power when, only can integrally be displaced outwardly.
Similarly, in order to which retaining wall 3 will not be sunk, the lower section of retaining wall 3 is connected with Percussion Piles 4, the Percussion Piles 4 Stake end enters at least one meter of micro- weathered rock formation.And at least ten meters of the effective length of the Percussion Piles 4.
Reference picture 3 and Fig. 4, this is embodiment a2 of the present utility model, specifically:
The difference for implementing a2 and embodiment a1 is that retaining wall 3 is slabstone concrete guard wall, the slabstone in retaining wall 3 Intensity is not less than MU20.
Because generally require to set canal case 5 in stone packing layer, therefore the present embodiment also includes canal case 5, retaining wall 3 is Slabstone concrete guard wall, canal case 5 are located at the lower section of retaining wall 3 and stone packing layer.
In order to provide enough support forces to canal case, compartment of terrain is provided with several CFG stakes from the inside to the outside for the lower section of canal case 5.
Because the intensity of canal case 5 is weaker, for hydrophobic and energy-absorbing, the top outer of canal case 5 is provided with sand stone layer 6.The energy of sand stone layer 6 Allow the top uniform force of canal case 5.Simultaneously as canal case 5 is reinforced concrete structure, stone directly bears against that will have thereon can Structure can be caused to damage, therefore the top outer in canal case 5 is provided with sand stone layer 6, the compactness of sand stone layer is more than 95%, is being filled out When building stone 1, sand stone layer 6 can effectively protect the structure of canal case 5 not damaged by block stone.
Canal case 5 is located in box cut, and the lateral surface of the box cut is inclined-plane, the lateral surface of the lower end of retaining wall 3 and institute Inclined-plane is stated to abutting, the region that the lower surface of retaining wall 3, the inclined-plane, the lateral surface of canal case are formed is filled with sandstone, so Can improves the anti-slide performance of retaining wall.
The retaining wall of the present embodiment is just provided with subsiding crack at interval of a segment distance, and subsiding crack is filled with flax silk is leached, along wall It is inside and outside, top three sides filling.
Better embodiment of the present utility model is illustrated above, but the utility model is created and is not limited to The embodiment, those skilled in the art can also make a variety of etc. on the premise of without prejudice to the utility model spirit With modification or replacement, these equivalent modifications or replacement are all contained in the application claim limited range.

Claims (10)

1. a kind of slope reinforcement structure, including old slopes, it is characterised in that:The domatic upper heap of old slopes is filled with compactness as 80% More than reinforcing matrix (10), the gradient for reinforcing matrix (10) is more than the gradient of old slopes, reinforce on the outside of matrix (10) be provided with plus Solid, the reinforcing body include multiple back-up coats, and adjacent back-up coat is separated with GSZ (2) or geotextiles, reinforcing body Bottom is provided with stone packing layer, and the compactness of the stone packing layer is more than 85%, and the outside of stone packing layer is provided with earth-retaining Wall (3), compartment of terrain is provided with several CFG stakes from the inside to the outside for the lower section of stone packing layer.
A kind of 2. slope reinforcement structure according to claim 1, it is characterised in that:Stone packing layer includes multiple rock layers (1) GSZ (2), is provided between adjacent rock layer.
A kind of 3. slope reinforcement structure according to claim 2, it is characterised in that:Rock layer (1) includes multiple tight mutually The stone being close together, the intensity of the stone is more than MU15.
A kind of 4. slope reinforcement structure according to claim 1, it is characterised in that:Retaining wall (3) is counterfort wall, The shingle nail of retaining wall (3) abuts with stone packing layer, and the wall heel of retaining wall (3) is located at the lower section of stone packing layer.
A kind of 5. slope reinforcement structure according to claim 4, it is characterised in that:Retaining wall is connected with punching below (3) Hole stake (4), the stake end of the Percussion Piles (4) enter at least one meter of micro- weathered rock formation.
A kind of 6. slope reinforcement structure according to claim 4, it is characterised in that:Retaining wall is connected with punching below (3) Hole stake (4), at least ten meters of the effective length of the Percussion Piles (4).
A kind of 7. slope reinforcement structure according to claim 1, it is characterised in that:Retaining wall (3) keeps off for piece stone concrete Wall, the slabstone intensity in retaining wall (3) are not less than MU20.
A kind of 8. slope reinforcement structure according to claim 1, it is characterised in that:Also include canal case (5), retaining wall (3) For slabstone concrete guard wall, canal case (5) is located at the lower section of retaining wall (3) and/or stone packing layer.
A kind of 9. slope reinforcement structure according to claim 8, it is characterised in that:The lower section of canal case (5) from the inside to the outside between Several CFG stakes are provided with every ground.
A kind of 10. slope reinforcement structure according to claim 8, it is characterised in that:The top outer of canal case (5) is provided with sand Rock layers (6), the compactness of the sand stone layer (6) is more than 90%.
CN201720519089.1U 2017-05-10 2017-05-10 A kind of slope reinforcement structure Expired - Fee Related CN206941614U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720519089.1U CN206941614U (en) 2017-05-10 2017-05-10 A kind of slope reinforcement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720519089.1U CN206941614U (en) 2017-05-10 2017-05-10 A kind of slope reinforcement structure

Publications (1)

Publication Number Publication Date
CN206941614U true CN206941614U (en) 2018-01-30

Family

ID=61361584

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720519089.1U Expired - Fee Related CN206941614U (en) 2017-05-10 2017-05-10 A kind of slope reinforcement structure

Country Status (1)

Country Link
CN (1) CN206941614U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236269A (en) * 2020-01-21 2020-06-05 山西机械化建设集团有限公司 Layered laying and combining reinforcement method for geotechnical material in airport high slope area

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236269A (en) * 2020-01-21 2020-06-05 山西机械化建设集团有限公司 Layered laying and combining reinforcement method for geotechnical material in airport high slope area
CN111236269B (en) * 2020-01-21 2021-11-02 山西机械化建设集团有限公司 Layered laying and combining reinforcement method for geotechnical material in airport high slope area

Similar Documents

Publication Publication Date Title
CN203308470U (en) Cover arch structure suitable for large-section unsymmetrical loading tunnel portal section
CN103882884B (en) A kind of anchor cable geo-grid retaining structure and construction method thereof
CN105887889B (en) A kind of ultra-wide hyposmosis mud method of excavation of deep foundation pit
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN105178327A (en) Composite retaining structure of foundation pit project and construction method thereof
CN103410152B (en) A kind of construction method for long and narrow deep foundation pit earthwork digging
CN104895111B (en) The construction method of integrated pipe canal in weak soil ground
CN109778868A (en) A kind of clad steel sheet pile combined enclosure structure and its construction method
CN204940298U (en) A kind of Composite Enclosure Structure of base pit engineering
CN205348221U (en) Merogenesis formula prefabricated barricade building block and retaining wall structure on an empty stomach
CN102966109A (en) Method for constructing zonal deep foundation pit bottom sealing of soft soil foundation
CN101591906A (en) The method for processing foundation of intubate, multipass vacuum well-point dewatering dynamic consolidation
CN206941614U (en) A kind of slope reinforcement structure
CN105696701A (en) Along-slope shear wall building development platform and construction method thereof
CN109083442A (en) The construction method of dynamic load bearing structure when existing building is docked with newly-built basis
CN109763513A (en) A kind of anchor cable lattice and the compound retaining structure of Modified soil retaining wall and its construction method
CN115506382A (en) Construction method for pile plate wall of island building platform
CN108570979A (en) A kind of construction method for building antiseepage composite foundation on dolomite stratigraph
CN204608701U (en) A kind of gravity type quay being applicable to roadbed of alluvial silt
CN103866788A (en) Retaining wall reformation method for column type bridge abutment foreslope
CN111441794B (en) Underground excavation construction method and structure for rebuilding existing tunnel into double-layer tunnel
CN102535485B (en) Concentric-circle-shaped reinforced rib geotechnological supporting structure for soft soil cutting excavation slope and top-down method of concentric-circle-shaped reinforced rib geotechnological supporting structure
CN206646513U (en) A kind of excavation and filling combines the earth material field slag field composite construction of construction
CN107460866B (en) A kind of big mud sump original position step curing processing method of depth
CN103981841B (en) Banket damming structure and method in the peat swamps evolution of waters

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180130