Prior art keywords
abutment
cave type
parados
abutment body
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720284618.4U
Other languages
Chinese (zh)
Inventor
张辉青
周宁
李卫斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Ankang Highway Administration
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201720284618.4U priority Critical patent/CN206873278U/en
Application granted granted Critical
Publication of CN206873278U publication Critical patent/CN206873278U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pharmaceuticals Containing Other Organic And Inorganic Compounds (AREA)

Abstract

A kind of cave type u abutment construction, including basis, abutment body, abutment platform cap, parados and aileron;Wherein, on the basis of abutment body is arranged on, abutment platform cap and parados are set at the top of abutment body, on the basis of be also vertically arranged with two parallel ailerons, abutment body, parados are in contact with aileron;Some cave type constructions are offered on abutment body.The deadweight of abutment will mitigate significantly in the utility model, and the requirement to substrate also greatly reduces, so as to reduce the dosage of the materials such as reinforcing bar, concrete.Abutment steadily of centre of gravity described in the utility model, rational in infrastructure, stress performance is good, while abutment stability is ensured, can solve existing u abutment from the defects of great, material usage is more.

Description

A kind of cave type u abutment construction
Technical field
It the utility model is related to technical field of bridge construction, more particularly to a kind of cave type u abutment construction.
Background technology
U abutment is widely used in science of bridge building, and it is slightly larger in below 8-11m or span to be especially adapted for use in the depth of fill Bridge, but the abutment body whole casting concrete in work progress, this can cause the volume of abutment and conduct oneself with dignity it is larger, to substrate Bearing capacity require it is very high, it is therefore necessary to provide a kind of abutment low to pedestal requirement for bearing capacity.
Utility model content
The purpose of this utility model is exactly to overcome defect present in above-mentioned prior art, there is provided a kind of structure is closed The u abutment construction for the cave type that reason, stress performance are good, save material, mitigate deadweight.
To achieve the above object, the technical solution adopted in the utility model is:
A kind of cave type u abutment construction, including basis, abutment body, abutment platform cap, parados and aileron;Wherein, abutment body is set On the basis of, abutment platform cap and parados are set at the top of abutment body, on the basis of be also vertically arranged with two parallel ailerons, abutment body, Parados is in contact with aileron;Some cave type constructions are offered on abutment body.
The utility model, which further improves, to be, the top of cave type construction is provided with arch ring, and the abutment body back side is provided with Arch ring for constructing closing to cave type blocks.
The utility model, which further improves, to be, the front end face of abutment body is ramped shaped.
The utility model, which further improves, to be, the gradient of the front end face of abutment body is 10:1.
The utility model, which further improves, to be, bridge block, bridge block side and the back of the body are provided with abutment platform cap Wall spacing is 5cm.
The utility model, which further improves, to be, basis uses rigid Extended chemotherapy, and the size expanded per side is minimum 0.2~0.5m.
Compared with prior art, the utility model has the advantages that:Due to some using being offered on abutment body Cave type is constructed, and can save material, and the materials such as reinforcing bar, concrete can be greatly reduced by pouring the cave type construction reserved during abutment body The dosage of material.Simultaneously so that from heavy and light, reduce requirement of the abutment to base bearing capacity.Cave type construction is adopted in the utility model Take the mode of vault to ensure that the steadiness of abutment, the bulky abutment of script is seemed slim and graceful attractive in appearance again, enhance bridge Landscape effect.It can be seen that the utility model mitigate dead load, reduce base bearing capacity requirement, steadily of centre of gravity, it is rational in infrastructure, by Power is functional, handsome in appearance.While abutment stability is ensured, can solve existing u abutment heaviness, from great, material The defects of dosage is more.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is that cave type u abutment of the present utility model constructs front view.
Fig. 3 is cave type u abutment structural side view of the present utility model.
Fig. 4 is that cave type u abutment of the present utility model constructs top view.
Fig. 5 is abutment body structural map of the present utility model.
Fig. 6 is cave dwelling of the present utility model and arch ring structural map.
In figure,
1-basis;2-abutment body;2-1-cave type construction;
2-2-arch ring;2-3-arch ring end-blocking;3-abutment platform cap;
4-parados;5-aileron;6-bridge block.
Embodiment
Below by drawings and examples, the technical solution of the utility model is described in further detail.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5 and Fig. 6, the utility model includes:Basis 1, abutment body 2, abutment platform cap 3, Parados 4, aileron 5 and bridge block 6.Wherein, basis 1 uses the construction of Extended chemotherapy, specifically, basis 1 is expanded using rigidity Basis, the minimum 0.2~0.5m of size expanded per side.
Abutment body 2 is arranged on basis 1, and the top of abutment body 2 sets abutment platform cap 3 and parados 4, and bridge is provided with abutment platform cap 3 Beam block 6, the side of bridge block 6 is with parados 4 at a distance of 5cm.Two parallel ailerons 5, abutment body are also vertically arranged with basis 1 2 back sides, parados 4 are in contact with aileron 5, and aileron 5 and the top surface of abutment body 2 are planar u-shaped;Offered on abutment body 2 some Cave type constructs 2-1, is provided with arch ring 2-2 at the top of cave type construction 2-1, the back side of abutment body 2 is provided with for cave type structure The arch ring end-blocking 2-3 of 2-1 closings is made, i.e. abutment body 2 uses back-end closure, the form of front opening.In work progress, abutment body 2 is carried on the back Face side needs the reserved reinforcing bar being connected with arch ring end-blocking 2-3, is needed after the completion of abutment body 2 pours to the reverse side of abutment body 2 Carry out dabbing processing.In addition, the front end face of abutment body 2 is ramped shaped, the gradient desirable 10 on slope:1, or determined according to actual conditions It is fixed.
Abutment material usage of the present utility model is few, and from heavy and light, the requirement to substrate is small.
As shown in Figure 5, Figure 6, when the utility model is constructed, abutment body 2 and aileron 5 is poured in basic 1 higher slice, is specifically: First layer template is first placed, abutment body 2 is reserved the construction 2-1 of cave type, cave type construction 2-1 makes in casting concrete Reserved with template, its quantity and concrete shape are determined by actual conditions.Second layer template is placed again, pours arch ring 2-2, is encircleed Circle 2-2 bottoms are connected with cave type construction 2-1, and the back side of abutment body 2 is connected with arch ring end-blocking 2-3.In abutment body back side piece Stone concrete is sealed, formed arch ring end-blocking 2-3, then pour abutment platform cap 3 and parados 4 successively, finally construct block 6 and Other constructions.
The utility model can reserve arch to reduce abutment deadweight during abutment body concreting in lifts Cave type constructs, as cave type u abutment.Constructed using the u abutment of cave type, the platform back of the body can be made to reserve hole, saved Volume and the deadweight of bridge abutment structure are substantially reduced while material saving.Meanwhile Urban Bridge meet it is safe, practical, economical While, also of a relatively high to requirement attractive in appearance, the construction of cave type plays very big excellent in terms of the landscape effect of enhancing bridge Gesture.

Claims (6)

1. a kind of cave type u abutment construction, it is characterised in that including basic (1), abutment body (2), abutment platform cap (3), parados And aileron (5) (4);Wherein, abutment body (2) is arranged on basic (1), and abutment platform cap (3) and parados (4) are set at the top of abutment body (2), Two parallel ailerons (5) are also vertically arranged with basic (1), abutment body (2), parados (4) are in contact with aileron (5);Platform Some cave type constructions (2-1) are offered on body (2).
A kind of 2. cave type u abutment construction according to claim 1, it is characterised in that the top of cave type construction (2-1) Portion is provided with arch ring (2-2), and abutment body (2) back side is provided with for blocking (2-3) to the arch ring of cave type construction (2-1) closing.
3. a kind of cave type u abutment construction according to claim 1, it is characterised in that the front end face of abutment body (2) is oblique Ramp shaped.
A kind of 4. cave type u abutment construction according to claim 1 or 3, it is characterised in that the front end face of abutment body (2) The gradient be 10:1.
5. a kind of cave type u abutment construction according to claim 1, it is characterised in that be provided with abutment platform cap (3) Bridge block (6), bridge block (6) side and parados (4) spacing are 5cm.
6. a kind of cave type u abutment construction according to claim 1, it is characterised in that basic (1) is expanded using rigidity Basis, the minimum 0.2m of size expanded per side.
CN201720284618.4U 2017-03-22 2017-03-22 A kind of cave type u abutment construction Expired - Fee Related CN206873278U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720284618.4U CN206873278U (en) 2017-03-22 2017-03-22 A kind of cave type u abutment construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720284618.4U CN206873278U (en) 2017-03-22 2017-03-22 A kind of cave type u abutment construction

Publications (1)

Publication Number Publication Date
CN206873278U true CN206873278U (en) 2018-01-12

Family

ID=61327202

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720284618.4U Expired - Fee Related CN206873278U (en) 2017-03-22 2017-03-22 A kind of cave type u abutment construction

Country Status (1)

Country Link
CN (1) CN206873278U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110438914A (en) * 2019-07-01 2019-11-12 中国葛洲坝集团第一工程有限公司 Water tank culvert and its construction method are crossed on soft soil foundation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110438914A (en) * 2019-07-01 2019-11-12 中国葛洲坝集团第一工程有限公司 Water tank culvert and its construction method are crossed on soft soil foundation
CN110438914B (en) * 2019-07-01 2021-04-30 中国葛洲坝集团第一工程有限公司 Water passing box culvert on soft soil foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN203412167U (en) Novel ribbed mould-blocking building block
CN203569579U (en) Building foundation
CN206873278U (en) A kind of cave type u abutment construction
CN203603261U (en) Connecting structure for balcony slab and superposed beam
CN107327061A (en) A kind of prefabricated composite stalk fiber concrete hollow board
CN201125487Y (en) Hollow building block for enhancing anti-vibration and heat preserving energy-saving effects
CN201593261U (en) Wall body module
CN103362123A (en) Reverse Y-shaped filling pile and construction method thereof
CN201679136U (en) Hollow block for building
CN205046743U (en) Building block of wall crown wedge
CN204326351U (en) A kind of hollow brick for building
CN203654454U (en) Upper-lower-layer prefabricated balcony slabs, and support connecting structures therebetween and beams
CN203669209U (en) Novel square beam column
CN207160256U (en) A kind of sandwich thermal insulated block
CN206681265U (en) Combination constraint rectangular steel-tube concrete column structure
CN202596006U (en) Special-shaped combined building block
CN201605678U (en) Splice structure of vehicle-passing cast-in-place floor plate in electrolytic plant
CN208235939U (en) A kind of contrary sequence method guarantees the formwork structure of concrete density
CN104631388A (en) Ramp slope protection brick
CN205591415U (en) Non - standard building block
CN203531201U (en) Novel open-web floor system box
CN204626708U (en) The dark skeleton solid-walled structure of a kind of self-heat conserving
CN207633622U (en) Open-core type building structure
CN203320792U (en) High-intensity energy-saving heat-preservation load-bearing building block
CN105780664A (en) Novel bridge pier construction process

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180413

Address after: No. 101, Bashan Road, Ankang City, Shaanxi Province, Shaanxi

Patentee after: Shaanxi Ankang Highway Administration

Address before: 710064 Shaanxi province Xi'an Beilin District South Second Ring Road No. 33 in the middle

Patentee before: Changan Univ.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180112

Termination date: 20200322

CF01 Termination of patent right due to non-payment of annual fee