CN206859241U - Double ground-connecting-wall cofferdam structure - Google Patents
Double ground-connecting-wall cofferdam structure Download PDFInfo
- Publication number
- CN206859241U CN206859241U CN201720599581.4U CN201720599581U CN206859241U CN 206859241 U CN206859241 U CN 206859241U CN 201720599581 U CN201720599581 U CN 201720599581U CN 206859241 U CN206859241 U CN 206859241U
- Authority
- CN
- China
- Prior art keywords
- wall
- rigid plate
- rear wall
- front vertical
- foundation ditch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000000463 material Substances 0.000 claims abstract description 10
- 239000011150 reinforced concrete Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 8
- 239000004567 concrete Substances 0.000 description 3
- 239000011435 rock Substances 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 230000008521 reorganization Effects 0.000 description 1
Landscapes
- Retaining Walls (AREA)
Abstract
It the utility model is related to a kind of double ground-connecting-wall cofferdam structure, including rigid plate, the rigid plate top is provided with front vertical wall and rear wall, backfill material is provided between front vertical wall and rear wall, front vertical wall bottom is provided with drainpipe, and front vertical wall is arranged on foundation ditch side, wall is arranged on the outside of foundation ditch afterwards, the rigid plate bottom is provided with front wall and rear wall, and front wall is arranged on foundation ditch side, and rear wall is arranged on the outside of foundation ditch.The utility model saves space, reduces influence of the construction to Adjacent Buildings.
Description
Technical field
Cofferdam structure is the utility model is related to, more specifically to a kind of double ground-connecting-wall cofferdam structure.
Background technology
Because economic development is rapid, inland river transport rapid growth, the handling capacity and the volume of goods transported of many original ship lock need
Ask incompatible, be badly in need of the original ship lock of upgrading or enlarging second-line shiplock, reorganization and expansion construction often require that do not influence it is existing
The normal operation of ship lock.Lock construction generally requires cofferdam to ensure dry ground condition.
Traditional cofferdam mainly has two kinds, and one kind is earth rock cofferdam, and one kind is concrete cofferdam.Earth rock cofferdam weir crest width one
As be 4~12m, foundation ditch side slope ratio is 1:1.5~1:2.0, the outer side slope ratio of foundation ditch is 1:2.0~1:2.5, cause weir bottom width degree past
It is past very big.Earth rock cofferdam applies in general to the unrestricted engineering of plane figure.Concrete cofferdam typically requires to be laid in carrying
On the preferable ground of power, weir crest width is 3~7m, it is domatic can be vertical, space-consuming is little.But concrete cofferdam construction is in itself
Need to build Temporary Cofferdam, to provide dry ground condition.Temporary Cofferdam can typically take larger space.Traditional cofferdam or it is long-term or
Larger space can be all taken in short term, this may hinder the normal operation of a line ship lock, in some instances it may even be possible to cause a line ship lock to be stopped navigation.
Utility model content
The technical problems to be solved in the utility model is, there is provided one kind saves space, reduces to surrounding constructure influence
Double ground-connecting-wall cofferdam structure.
Technical scheme is used by the utility model solves its technical problem:Construct a kind of double ground-connecting-wall cofferdam knot
Structure, including rigid plate, the rigid plate top are provided with front vertical wall and rear wall, backfill are provided between front vertical wall and rear wall
Material, front vertical wall bottom are provided with drainpipe, and front vertical wall is arranged on the inside of foundation ditch, and rear wall is arranged on the outside of foundation ditch, the rigidity
Plate bottom is provided with front wall and rear wall, and front wall is arranged on the inside of foundation ditch, and rear wall is arranged on the outside of foundation ditch.
By such scheme, the front vertical wall and rear wall are arranged on the top of rigid plate, and front vertical wall is fixed with rigid plate to be connected
Connect, rear wall is fixedly connected with rigid plate.
By such scheme, after the front wall and rear wall is arranged on the bottom of rigid plate, and front wall is fixedly connected with rigid plate, after
Wall is fixedly connected with rigid plate.
By such scheme, the front wall and rear wall are arranged on underground, are underground structure.
By such scheme, the front wall, rear wall, front vertical wall, rear wall and rigid plate are reinforced concrete structure.
Implement double ground-connecting-wall cofferdam structure of the present utility model, have the advantages that:
1st, space needed for double ground-connecting-wall cofferdam structure of the present utility model is smaller, it is not necessary to heavy excavation, to surrounding buildingses
The safety of thing and the influence used are smaller;
2nd, the rigid plate in the utility model can completely cut off the transmission of backfill material weight stress, reduce front wall, the soil pressure of rear wall
Power, reduce front wall, the thickness or reinforcement ratio of rear wall, cost saving;
3rd, the front vertical wall lower end in the utility model is disposed with osculum, drains ponding in backfill material, reduces backfill material pair
The pressure of front vertical wall, rear wall, reduce front vertical wall, the thickness or reinforcement ratio of rear wall, cost saving;
4th, the backfill charge level layer in the utility model can lay pavement structure, be passed through for Construction traffic, public vehicles;
5th, the cofferdam structure in the utility model can be used as dash soil-baffling structure, at the same can also also serve as guide wall, every
Flow the permanent structures such as wall.
Brief description of the drawings
Below in conjunction with drawings and Examples, the utility model is described in further detail, in accompanying drawing:
Fig. 1 is a kind of floor map of double ground-connecting-wall cofferdam structure of the utility model;
Fig. 2 is A-A directions cross section in Fig. 1;
Fig. 3 is B-B directions vertical section in Fig. 1;
Fig. 4 is C-C directions vertical section in Fig. 1.
Embodiment
In order to which the technical characteristics of the utility model, purpose and effect are more clearly understood, it is detailed now to compare accompanying drawing
Illustrate specific embodiment of the present utility model.
As Figure 1-4, double ground-connecting-wall cofferdam structure of the present utility model includes rigid plate 1.
The top of rigid plate 1 is provided with front vertical wall 2 and rear wall 3, and backfill material 4 is provided between front vertical wall 2 and rear wall 3,
The bottom of front vertical wall 2 is provided with drainpipe 5, and drainpipe 5 is distributed along cofferdam axis by certain length.Front vertical wall 2 and rear wall 3
The top of rigid plate 1 is arranged on, front vertical wall 2 is fixedly connected with rigid plate 1, and rear wall 3 is fixedly connected with rigid plate 1, front vertical wall 2
It is arranged on 6 on the inside of foundation ditch, rear wall 3 is arranged on 7 on the outside of foundation ditch.The bottom of rigid plate 1 is provided with front wall 8 and rear wall 9, and front wall 8 is set
Put 6 on the inside of foundation ditch, rear wall 9 is arranged on 7 on the outside of foundation ditch, and front wall 8 is fixedly connected with rigid plate 1, and rear wall 9 is fixed with rigid plate 1
Connection.Front vertical wall 2, rear wall 3, rigid plate 1, front wall 8 and rear wall 9 are reinforced concrete structure.Front wall 8 and rear wall 9 are set
It is underground structure in underground, seepage proof curtain can be also served as, 10 is ground wherein in figure.
Space is smaller needed for the utility model, serves not only as foundation pit supporting construction, while also serves as the ground of Adjacent Buildings
Lower supporting construction, the influence to Adjacent Buildings are also smaller.Rigid plate 1 connects front wall 8, rear wall 9, front vertical wall 2 and stood afterwards respectively
While wall 3, the weight stress transmission of backfill material 4 is completely cut off, has reduced front wall 8, the soil pressure of rear wall 9.The bottom of front vertical wall 2 is set
The drainpipe 5 put, the ponding in backfill material 4 can be drained, the pressure of front vertical wall 2 and rear wall 3 can be reduced.Backfill material 4 can
Pavement structure is laid, is passed through for Construction traffic, public vehicles.The cofferdam structure, avoid traditional cofferdam structure space-consuming very
The shortcomings that big.To occupy little space, it is small to surrounding constructure influence the characteristics of, realize the functions such as dash, earth-retaining, antiseepage, supporting.
Meanwhile cofferdam structure can also serve as the permanent buildings such as guide wall, flow blocking wall, cost saving
Embodiment of the present utility model is described above in conjunction with accompanying drawing, but the utility model is not limited to
The embodiment stated, above-mentioned embodiment is only schematical, rather than restricted, this area it is common
Technical staff is not departing from the utility model aims and scope of the claimed protection situation under enlightenment of the present utility model
Under, many forms can be also made, these are belonged within protection of the present utility model.
Claims (5)
1. a kind of double ground-connecting-wall cofferdam structure, it is characterised in that including rigid plate, the rigid plate top is provided with front vertical wall
With rear wall, backfill material is provided between front vertical wall and rear wall, front vertical wall bottom is provided with drainpipe, and front vertical wall is arranged on base
Hole inner side, rear wall are arranged on the outside of foundation ditch, and the rigid plate bottom is provided with front wall and rear wall, and front wall is arranged in foundation ditch
Side, rear wall are arranged on the outside of foundation ditch.
2. double ground-connecting-wall cofferdam structure according to claim 1, it is characterised in that the front vertical wall and rear wall are set
On the top of rigid plate, front vertical wall is fixedly connected with rigid plate, and rear wall is fixedly connected with rigid plate.
3. double ground-connecting-wall cofferdam structure according to claim 1, it is characterised in that be arranged on after the front wall with rear wall
The bottom of rigid plate, front wall are fixedly connected with rigid plate, and rear wall is fixedly connected with rigid plate.
4. double ground-connecting-wall cofferdam structure according to claim 3, it is characterised in that the front wall and rear wall are arranged on ground
Under, it is underground structure.
5. double ground-connecting-wall cofferdam structure according to claim 1, it is characterised in that the front wall, rear wall, front vertical wall,
Wall and rigid plate are reinforced concrete structure afterwards.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720599581.4U CN206859241U (en) | 2017-05-26 | 2017-05-26 | Double ground-connecting-wall cofferdam structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720599581.4U CN206859241U (en) | 2017-05-26 | 2017-05-26 | Double ground-connecting-wall cofferdam structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206859241U true CN206859241U (en) | 2018-01-09 |
Family
ID=60825067
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720599581.4U Expired - Fee Related CN206859241U (en) | 2017-05-26 | 2017-05-26 | Double ground-connecting-wall cofferdam structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206859241U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111424627A (en) * | 2020-05-18 | 2020-07-17 | 湖南省交通规划勘察设计院有限公司 | Ship lock extension supporting structure and ship lock extension method |
-
2017
- 2017-05-26 CN CN201720599581.4U patent/CN206859241U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111424627A (en) * | 2020-05-18 | 2020-07-17 | 湖南省交通规划勘察设计院有限公司 | Ship lock extension supporting structure and ship lock extension method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201962688U (en) | Diaphram wall wharf pile foundation structure | |
CN103669398B (en) | A kind of monoblock type cutting retaining wall | |
CN103510528B (en) | For the blind drainage structure of underground structure anti-floating | |
CN106761768B (en) | A kind of steel pipe curtain structure support system and its construction method | |
CN202194148U (en) | Waterproof curtain | |
CN102286981A (en) | Waterproof curtain and construction method thereof | |
CN102535408B (en) | Semi-assembly type ecological debris flow check dam, and construction method thereof | |
CN107083771A (en) | A kind of drilling construction method of artificial digging pile | |
CN102277874A (en) | Assembled retaining wall and construction method thereof | |
CN202194149U (en) | Water-proof curtain | |
CN105239578A (en) | Water-rich sand layer deep foundation pit underwater construction method | |
CN207003421U (en) | A kind of steel plate pilework for being seated hard rock top surface | |
CN201746843U (en) | High slope supporting and road retaining wall integrated structure | |
CN104652444A (en) | Construction method for overall reverse operation of ultra-large type deep foundation pit center island type alternative earth excavation | |
CN102174803B (en) | Assembled drainage canal of debris flows and construction method thereof | |
CN204940298U (en) | A kind of Composite Enclosure Structure of base pit engineering | |
CN206859241U (en) | Double ground-connecting-wall cofferdam structure | |
CN104196046B (en) | Reduce the water proof drainage system of underground hydrostatic water table | |
CN106884431A (en) | One kind building pit foundation construction safety supporting construction | |
CN204551510U (en) | A kind of filled-up ground catchments pressure reduction well drop and drainage structure | |
CN102943480B (en) | Loess foundation pit supporting method | |
CN209760299U (en) | light and shade of avoiding house to tear open and move is dug and is combined subway station structure | |
CN204703189U (en) | A kind of cutting barricade being applicable to crevice water, diving growth | |
CN101793027A (en) | Core-grouted static pressure anchor rod pile | |
CN205382942U (en) | Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||